HomeMy WebLinkAboutADMIN-34-95 DN:ADULT.REP THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
REPORT
Meeting: General Purpose and Administration Committee File # _� <, 6__7
Date: Monday, December 4, 1995 Res.
Report #: ADMIN .3a-95File #: By-law #
Subject: PROPOSAL CALL FOR OLDER ADULT CENTRE
1
Recommendations:
i
It is respectfully recommended that the General Purpose and Administration
Committee recommend to Council the following:
1. THAT Report ADMIN 34-95 be received;
2. THAT the selection committee be authorized to negotiate an agreement with
Vanstone Mill Inc. and to report back to Council.
1. BACKGROUND:
1.1 Council has earlier authorized the Chief Administrative Officer to proceed to
discuss with various property owners as to their interests in building an Older
Adult Centre for the Municipality. As a result, discussions were held with
representatives of Vanstone Mills Inc., Windleigh Development Inc. and Jourdan
(1100719 Ontario Limited). All three companies expressed an interest and all
requested the opportunity to bid on the project.
1.2 As a result, a proposal call document was drawn up by staff and all three parties
were invited to bid on the proposed Older Adult Centre,
2
1104
REPORT NO.: ADMIN 34-95 PAGE 2
1.3 The proposal call document is drawn up based on a "turn-key" project, ie. cash
for key and describes the objectives and requirements of the Municipality for the
Older Adult Centre. It provides the terms of reference under which the parties
were to prepare their submissions.
2. THE SUBMISSIONS:
2.1 All three parties submitted proposals. Copies of the proposal call document and
the three (3) submissions will be distributed to Members of Council under
separate cover.
3. THE EVALUATION COMMITTEE:
3.1 The Chief Administrative Officer has struck an adhoc Committee to evaluate the
proposals. Members of the committee are: Chief Administrative Officer, Director
of Planning and Development, Director of Community Services, and Facility
Manager. Representing the Older Adult Committee are Don Welsh and Annabel
Sissons.
4. THE EVALUATION:
4.1 The Evaluation Committee first met to determine the evaluation criteria and to
agree on a process that follows.
4.2 Eight criteria were considered pertinent and were ranked in the following order of
importance: cost, location, access, expansion potential, parking, building design,
site aesthetics and ownership. Numerical weighting factors were then assigned
to each criteria.
4.3 Next, each committee member was asked to assess the three proposals based
on the agreed to criteria and weights. The scores from each member were then
added to determine the total scores for each of the three proposals presented as
follows: 3
REPORT NO.: ADMIN 34-95 PAGE 3
OLDER ADULT CENTRE
PROPOSAL EVALUATION
COMPOSITE SCORES
CRITERIA JOURDAN VANSTONE WINDLEIGH
COST 176 200 56
LOCATION 168 119 133
PARKING 75 90 70
ACCESS 115 50 105
EXPANSION 75 115 85
BUILDING DESIGN 60 57 36
SITE AESTHETICS 14 46 30
LAND OWNERSHIP 8 24 22
TOTAL 691 701 53771
4.4 As part of the evaluation process, each party was given the opportunity to present
their proposals to the Committee as well as to answer questions.
5. STAFF COMMENTS:
5.1 Unlike a tendering process where bidders were asked to bid on a specific project
or product, and where the lowest bid price usually represents the most important
and often the only criterion for selection, evaluation of submissions to the
proposal call is somewhat different as other criteria are just as important as cost.
This therefore necessitated the ranking and weighting of various criteria as
described in Section 4.
5.2 In any event, the bid price (exclusive of G.S.T.) from the three (3) parties are as
follows: Jourdan $1,300,000.
Vanstone Mill $1,295,328.
Windleigh Developments $1,729,080.
4
1106
REPORT NO.: ADMIN 34-95 PACE 4
5.3 As a result of the evaluation and the resultant point scores, the Committee
unanimously recommend the Vanstone Mill proposal be given favourable
consideration.
5.4 Prior to committing to the Vanstone Mill proposal, it is imperative that the
Municipality can successfully negotiate an agreement with Vanstone Mill Inc..
Said agreement is necessary to address all details pertaining to the delivery of the
project.
5.5 Upon reaching an agreement, staff will bring forth a report for Council's
consideration and approval.
5.6 The Evaluation Committee is aware that Council has tabled Report CS-31-95
which deals with the renovation of the old Firehall/Court House building. We
suggest that this report should remain tabled until such time an agreement is
reached with Vanstone Mill Inc. and duly approved by Council.
Respectfully submitted,
W. H. Stockwell
Chief Administrative Officer
WHS*FW*jip
November 29, 1995
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
X
REPORT
Meeting: COUNCIL File# �C
Date: SEPTEMBER 11, 1995 Res. #
Report#: CS-31-95 File#: By-Law#
Subject: OLDER ADULT CENTRE/FORMER FIRE HALL RENOVATIONS
Recommendations:
It is respectfully recommended to Council the following:
1. THAT Report No. CS-31-95 be received;
2. THAT the revised project budget be established at $757,955.00;
3. THAT staff report back identifying a specific source for funding at such time when project
tenders have been received; and
4. THAT the Clarington Older Adult Association be advised of Council's decision.
1.0 BACKGROUND:
1.1 On July 10, 1995 staff was informed by the project architect that the new elevator shaft could
not be accommodated within the existing structure. The explanation given was the existing
plumbing system and heating, ventilation and air conditioning duct work system for the
second floor passes through the proposed elevator shaft.
1.2 The cost of modifying the existing duct work would exceed the cost allowed for this portion
of the project therefore, the Architect recommended relocating the elevator shaft to the
exterior of the building.
1.3 Staff was further advised that the increased cost of an exterior elevator shaft would be offset
by the following:
o Plumbing and mechanical savings;
o Renovations to the second floor would be less extensive;
o Modifications to the roof structure to provide elevators headroom clearance would
be eliminated; and
o Excavation cost would be reduced for an exterior shaft and pit.
../2
I
PPE9®NECYCLE � / I�
TH66E5i.f1EDWRECYCiID P/.�R '
REPORT CS-31-95 " 2 - SEPTEMBER 11, 1995
1.4 On August 3, 1995 staff was again contacted by the project architect and informed that an
increase to the budget is required due to the following:
o Need to move elevator shaft to the exterior;
o Increases in the construction industry; and
o Additional savings in the design could not be found.
2.0 COST ANALYSIS:
2.1 Since that time staff referred the project to an independent cost consultant to verify the
estimated project costs and confirm the amount of additional funds required to complete the
project.
2.2 Results of that undertaking have confirmed that the project will require a construction
budget of$688,400.00 (estimated).
3.0 PROJECT BUDGET;
3.1 The original budget for this project was estimated at $350,000.00 which was the amount
submitted when the Municipality made application for the Canada/Ontario Infrastructure
program.
3.2 On April 3, 1995 Council approved an increase of$239,995.00 to establish the project budget
at $589,995.00 as recommended by the project architect.
3.3 As a result, the current revised estimate for the project is as follows:
Construction Costs (Including Contingency) $688,000.00
Preliminary Studies - Soils Investigation $ 1,500.00
- Legal Survey $ 1,225.00
- Hazardous Substance $ 1,330.00
Hydro $ 9,350.00
Architect/Engineering Fees $ 51,800.00
TOTAL 753,205.00
G.S.T. $ 4,564.00
GRAND TOTAL $757,769.00
CURRENT BUDGET $589,955.00
ADDITIONAL FUNDING REQUIRED $167,814.00
3.4 Through discussions with the Chief Administrative Officer and the Treasurer, alternative
sources of funding could be accessed for the additional funds to supplement this project.
3.5 Should Council approve the revised budget,staff will report back identifying a recommended
source of financing at such time that a recommendation to award the tender is made.
../3
1109
REPORT CS-31-95 - 3 " SEPTEMBER 11, 1995
Respectfully submitted, Reviewed by,
Jos P. Caruana, Director W. H. gt6ckwell,
Co munity Services'Department Chief Administrative Officer
JPC:sa
I
� Sol l g6k6
rnc,V,L�ar o �-1 ce X13
Lit { R40- �Wb
G •e.rur-i C�cr��rS
� c
Con c v�c�-� -zC �
::;,� aob
Doy" mk&k O m C 3-�j C�
-tt(.e 4q5 -7
�P( inc�
-Tb ou�,d l l b01 l �`4rutc,a 1 n C ,
Cl W064 awn �e�
Toroh. (), .
Ct ko -0�6