HomeMy WebLinkAboutADMIN-12-88 REPORT #3
TOWN OF NEWCASTLE
S
REPORT File # t
Res. # . . `
__---- By-Law #
MNG: COUNCIL
DATE: JULY 11 1988
REPORT #: ADMIN. 12-88 FILE #:
SUB,ECT:
WATERMAIN TO SERVICE NEW ARENA FACILITY
RECOMMENDATIONS:
It is respectfully recommended to Council:
1. That the increase in cost of $105,900 required to install
the watermain to service the New Arena Facility be approved;
2. That the additional funding be drawn from the Arena
Reserve Fund Account; and
3. That the Region of Durham be requested to proceed with the
installation of the watermain service to the new Arena Facility
in accordance with Attachment #1 to Report ADMIN. 12-88.
REPORT:
At its meeting of November 16 1987, the Town Council approved Report #CS-37-87
wherein an expenditure of $470,000 was included regarding the construction of
a watermain (excluding booster pumping station) to the New Arena Facility at
Highway #2 and Regional Road #57. The Region of Durham was advised accordingly
and requested to initiate the necessary work in this regard.
ADMIN. 12'- 88 PAGE 2
As a result of its detailed investigations, design work, and tendering of
this project, the Regional Works Department has provided its results in this
regard (refer to Attachment #1) . In short, Attachment #1 indicates that the
original cost estimate of $470,000 provided by the Region regarding the subject
watermain will require an additional expenditure of $105,900. This can be
attributed largely to an increase in the length of the watermain associated
with a minor revised alignment due to technical difficulties. In addition,
costs related to land acquisition, engineering investigations, and contingency
aspects which are based on slightly higher costs to construct the facility than
expected are included in this increase. It should be noted, however, that actual
costs could in fact be less and if this is the case the Town would be
reimbursed accordingly.
Furthermore, it should be indicated that the installation of the watermain to
the general area of Highway #2 and Regional Road #57 will assist in the development
of other lands than those owned by the Town. Staff is presently negotiating
with prospective developers in this general area to cost share in the provision
of this facility. It is expected that a substantial portion of the total cost of the
watermain will be recouperated by the Town over a period of time.
Funds are available in the Arena Reserve Fund Account to cover
this increased expenditure. In addition, approval must be given to the Region
I
as soon as possible in order not to jeopardize the opening of the facility in
I
October of this year.
All the above is respectfully submitted for Council's consideration and approval.
I
Recommended for presentation
to Council
John Blanchard,
Treasurer
Walter A. Evans, Lawrence E. Ko,seff,
Director of Public Works Chief Admi ist tive Officer
ATTACHMENT #1 TO
REPORT ADMIN 12-88
DURHAM June 29, 1988
The Regional
Municipality
of Durham
Works Department
Mr. L. Kotseff
Box 623 Chief Administrative Officer
105 Consumers Dr.
Whitby, Ontario Town of Newcastle
Canada.L1N6A3 40 Temperance St.
(416)668-7721
Bowmanvi 1 le, Ontario
L1C 3A6
W.A.TWELVETREES,P.Eng.
Commissioner of Works Dear Sir:
Please quote our ref:
Re: Watermain to Service New Arena Facility, Bowmanville
As discussed, tenders have now closed for our Contract D88-18 for
WAT-N-1-1 the construction of the above watermain. A summary of the
tenders received is enclosed.
The tenders have been checked and it is recommended that the low
tender of VISP Construction Co. be accepted for Contract D88-18
for the bid price of $464,541.00. This tender results in a total
project cost as summarized below.
Contract D88-18
Tender Price $ 464,541
Land Purchase (Easements) 7,000
Sundry Work by Region 10,000
(Including the Supply of 6 Fire Hydrants)
Engineering 91,859
Contingency 14,000
$ 587.400
An analysis of this contract has resulted in the following
breakdown of the respective shares.
Town of Newcastle $ 575,900
Region - Oversizing 10,700
- Preinstalled Connection 800
$ 587,400
JUN 10 1988
TOitYN OF NI:KASTLE
' - 2 -
We have prepared a tender report for this project which presently
requires confirmation of the award by the Town. This report was
originally planned to be submitted to Works Committee on July 5,
1988, and would then proceed to Council on July 13, 1988, for
approval . It would then be necessary to await the Town 's
confirmation of the award prior to proceeding with the work.
It has been suggested that it may be appropriate to delay the
report until the July 19th Works Committee meeting in order to
give the Town the opportunity to deal with the project prior to
the Region. This is deemed to be appropriate since the Town's
share is the bulk of the project.
It would be appreciated if you would schedule this matter for the
attention of your Council at an early date. Contrary to our
Report 17-88 dated January 19, 1988, we are prepared to accept a
purchasee order for the Town's share. If this is acceptable to
the Town, please arrange to forward this purchase order as soon
as practical so that we may order the contractor to commence work
upon receipt of Council approval .
Please feel free to contact the writer should there be any
questions.
Yours truly,
c
J. Ba er
Manager of Administrative Services
/rd
cc: J. Johnson
R.W. Price, P. Eng.
i
i
i
i
i
i
i
i
CONTRACT 088-18
COST APPORTIONMENT
TOTAL TOWN OF REGION WATER
COST NEWCASTLE OVERSIZING CONNECTION
Tender Section 3 425,041.00 416,448.50 8,010.00 582.00
Section 4 9,500.00 9,308.00 179.00 13.00
Section 5 30,000.00 29,394.00 564.00 42.00
Total Tender 464,541.00 455,150.50 8,753.50 637.00
Land Purchase 7 ,000.00 7,000.00 - -
Sundry Work by Region 10,000.00 10,000.00 - -
Engineering 91 ,859.00 90,032.50 1,683.50 143.00
Contingency 14,000.00 13,717.00 263.00 20.00
Total Estimated Cost 587,400.00 575,900.00 10,700.00 800.00
I
i
i
i
I
1
THE ;ION ,L MUNICIPALITY OF DURHN1
TENDER SUMMARY
BOWMANVILLE
TATE TENDERS OPENED THURSDAY JUNE 23, 1988 CONTRACT D 88-18 WATERMAIN — fd= ^ASTLE
TENDERER ADDRESS TOTAL :_'::JER AMOUNT
VISP CONSTRUCTION CO. R.R. 1 BROCK ROAD N. , PICKERING $ 464,541.00
PACHINO CONSTRUCTION CO. LTD. P.O. BOX 27, GORMLEY 488,OJO.00
NOVACOR CONSTRUCTION LTD. P.O. BOX 199 QUEENSVILLE 505,389.00
WARDET LIMITED 345 WILSON AVE. , DOWNSVIEW 562,373.00
FERNVIEW CONSTRUCTION LIMITED P.O. BOX 33, BOLTON 567,029.00
HOLLINGWORTH CONSTRUCTION CO. 8161 KEELE STREET, CONCORD 569,910.00
BOYLE EXCAVATING LTD. R.R. # 5, BOWMANVILLE 578,671.00
PISA CONSTRUCTION CO. LTD. 2411 TESTON ROAD, MAPLE 619,605.00
RABITO SEWER AND WATERMAIN LTD. 71 SMITHY STREET, MARKHAM 624,640.00
i
V.J.R. CONTRACTORS 63 SMITHY STREET, MARKHAM 630,265.00
TIMBEL LIMITED 2610 WESTON ROAD, WESTON 728,523.00
WESTWOOD DRAIN COMPANY LTD. 1755 DREW ROAD, MISSISSAUGA 761,435.00