HomeMy WebLinkAboutWD-58-95 REPORT #3
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
REPORT
J
Meeting: COUNCIL File #
Date: DECEMBER 11, 1995 Res.
Report#:
WD-58-95 File#: Dy-Law# -
CANADA/ONTARIO INFRASTRUCTURE WORKS PROGRAM,
Subject: KING STREET STORM SEWERS,
ONTARIO STREET TO FRANK STREET, BOWMANVILLE
Recommendations:
It is respectfully recommended that the General Purpose and Administration
Committee recommend to Council the following:
1. THAT Report WD-58-95 be received;
2. THAT the application to the Ministry of Municipal Affairs for
Infrastructure Funding for King Street Storm Sewers, Ontario Street to
Frank Street, be revised and resubmitted to reflect the revised project
schedule; and
3. THAT additional funds, required over and above those approved under the
Infrastructure Program, be obtained by either requesting the Province to
reallocate any funds from other underspent Clarington Infrastructure
projects or from Public Works Lot Levy Reserve Fund.
REPORT
1.0 ATTACHMENTS
No. 1: Key Map
No. 2: Cost Summary
2.0 BACKGROUND
2.1 One of the projects approved under the Canada/Ontario Infrastructure Works
Program was for the upgrading of storm sewers on King Street, from Ontario
Street to Frank Street. Currently these sewers are at capacity and pose
a barrier for redevelopment along the roadway.
2.2 In January of 1995, the cost of upgrading the storm sewers was esti
Pg g mated
at $600,741. This estimate provided for the installation of storm sewers,
restoration of the disturbed road surface and some replacement of
deficient sidewalk and curb. No provision was made for the installation
nim rwrJim a�nmvc��o rpven i
REPORT NO.: WD-58-95 PAGE 2
of Regional services as of January, 1995. Construction was to be
completed in Summer 1995.
3.0 REVIEW AND COMMENT
3.1 After the storm sewer estimate was prepared and Infrastructure forms
completed, the Region of Durham approached the Municipality of Clarington
regarding sanitary sewer and watermain replacement on King Street. They
requested this work be undertaken in conjunction with the storm sewer
replacement project.
3.2 In addition, it was agreed by the Region and Clarington that improvements
were also required at the intersection of King and Liberty Streets.
Traffic congestion is occurring at peak hours and turning lanes are
required to improve traffic flow.
3.3 As a result of these additional works proposed by Durham Region, the
project schedule was revised to permit construction during the Summer of
1996, and the Municipality of Clarington Public Works Department now
proposes that King Street be fully reconstructed from Ontario Street to
Frank Street. Replacing the underground services to the extent proposed,
and only restoring disturbed areas of roadway, curb and sidewalk, would
result in a patchwork effect which would be unsightly and unacceptable to
the Public Works Department. The extent of the required restoration would
not be cost effective.
3.4 A revised cost estimate to provide for full restoration of the roadway is
provided on Attachment No. 2. In addition, cost estimates for Regional
Works are also provided. The Region has agreed to fund 100% of the
intersection improvements at King and Liberty Streets, if the Municipality
of Clarington funds the full road restoration costs for the remainder of
the project. In addition, the Region of Durham is financing the Costs to
replace the sanitary sewer and watermains, including associated services,
over the full length of the project.
I
3.5 The revised cost estimate (Attachment No. 2) includes for restoration of
sidewalk and boulevard areas with concrete and asphalt respectively. It
should be noted that interlocking brick and other special streetscape
amenities have been used recently on other high profile streets within
Bowmanville. Public input may result in the Municipality considering
similar treatment on this project. Cost of streetscape improvement is not
I
REPORT NO.: WD-58-95 PAGE 3
included herein and funding for this would have to be obtained from
another source.
4.0 CONCLUSIONS AND RECOMMENDATIONS
4.1 Should Council support the recommendation to proceed with this project,
they have two (2) options. Option one would be to revise the
Infrastructure Program Application Form, identifying the new construction
schedule and also requesting additional funding to cover the cost of full
reconstruction. This approach is very risky and could result in
considerable delay or even cancellation of the project. A costly
environmental study report would be required by the Infrastructure Program
as a result of new Federal Legislation and the revised project scope.
Public Works does not recommend this procedure.
4.2 The second option is to revise the Infrastructure forms by changing the
project schedule only. Cost for Clarington Works exceeding $600,741 would
have to be covered by the Municipality. This process should result in a
quick response by the Infrastructure Program and allow the project to
proceed in 1996. The estimated additional cost of $224,164, to fully
reconstruct the roadway, could be obtained either by a reallocation from
the underspent Clarington Infrastructure projects or from the
Municipality's Lot Levy Reserve. This is the option favoured by Public
Works.
Respectfully submitted, Reviewed by,
i
l
M Marano, H.BSc.,AMCT W. H. Stockwell
Treasurer Chief Administrative Officer
Stephed A. Vokes, P.Eng.
Director of Public Works
SAV*ph
December 7, 1995
Attachments
LEGEND: PROPOSE.D LIMITS OF
CONSTRUCTION
ST
oho
CHURCH ST.
ST. HIGHW
0QUEEN m
ui
ST.
NPS PRINCE ST.
KEY PLAN
N.T.S.
JUL
HWY.2
F
-3
flall
0 rP T�
13 HWa oY;
} ,F;^.
.... ......
000QO
�� �� Baa
TH
V!
BASED ElHL
wy., (
DRAWN BYL- I:BIDATE: DEC. 1995
ATTACHMENT NO, I
BOWMANVILLE KEY MAP WD- 58 -95
KING STREET RECONSTRUCTION COST APPORTIONMENT
AMOUNT ELIGIBLE
DESCRIPTION TOTAL OR CANADAIONTARI CANADA/ONTARIO MUNICIPALITY REGION
OF PROJECT INFRASTRUCTURE CONTRIBUTION OF OF
WORKS COST PROGRAM FUNDING 2/3 CLARINGTON DURHAM
SANITARY SEWERS $300,000.00 $300,000.00 $200,000.00 $100,000.00
STORM SEWERS and ROAD RECONSTRUCTION $824,905.00 $600,741.00 $400,494.00 $424,411 .00
77WATERMAI N $600,000.00 $600,000.00 $400,000.00 $200,000.00
L
INTERSECl10N IMPROVEMENTS $398,880.00 $398,880.00
[TOTAL $2,123,785.00 $1,500,741.00 $1,000,494.00 $424,411.00 $698,880.00
ATTACHMENT No. 2
ADDENDUM TO REPORT WD —58 —95