HomeMy WebLinkAboutWD-16-93 THE CORPORATION OF THE TOWN OF NEWCASTLE
REPORT
Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE File #
J1
9
Res, #,L-
Date: APRIL 5, 1993 �Ic)�1 _ �
By-Law#
Report#: File#: -RC-31-11A, B. 0 1. 0 9 .0 9
Subject: CONTRACT NW 92-28, ADDITIONAL WORK ON KING STREET EAST BETWEEN
KEARNS AVENUE AND HAINES ROAD, BOWMANVILLE
Recommendations:
It is respectfully recommended that the General Purpose and
Administration Committee recommend to Council the following:
1. THAT Report WD-16-93 be received;
2 . THAT the quotation from Novacor Construction Company Ltd. for
additional work on King Street East in the amount of
$88,425 .50 be accepted;
3 . THAT the additional cost of $4,478 . 10 over and above the funds
provided for in the approved 1993 Budget be obtained from the
Development Charge Fund; and
4 . THAT the attached By-law (Attachment No. 3) authorizing a
purchase order to be issued to Novacor Construction Ltd. be
approved.
REPORT
1.0 ATTACHMENTS
No. 1: Correspondence dated March 12, 1993, from Totten
Sims Hubicki Associates
No. 2 : Project Detail Sheet from the approved 1993 Capital
Budget
No. 3: Proposed By-law
REPORT NO. : WD-16-93 PAGE 2
2 . 0 BACKGROUND AND COMMENT
2 . 1 In 1992, the Town entered into a contract with Novacor
Construction Company Ltd. for the reconstruction of King
Street East from Simpson Avenue to the West Branch of the
Soper Creek and Mearns Avenue from King Street East to Orchard
Park Drive. The contract is a two year contract, with
completion in 1993.
2 .2 At a meeting held on March 23, 1992, Council passed Resolution
#C-118-92 and #C-119-92 as follows:
"THAT the correspondence received from Rev. Jake Binnema,
regarding several recommendations contained in the CAUSE
Report, be received for information and that it be
referred to the Director of Public Works for review and
preparation of a report back to the General Purpose and
Administration Committee regarding the possibility of the
installation of a sidewalk and/or path from the
Bowmanville Mall to the Marantha Christian Reformed
Church. "
2 .3 The Town's contract for the reconstruction of King Street East
terminated 95 meters west of the East Branch of Soper Creek.
The Ministry of Transportation's contract for the
.reconstruction of Highway 2 started at Haines Street and ended
at the west limit of Newcastle Village. This left a section
of King Street/Highway 2, which was not considered either by
the Town or the Ministry of Transportation for reconstruction
or resurfacing.
2 .4 During the discussion with the Ministry of Transportation
regarding the construction of a sidewalk on this section of
road (as requested by Reverend Jake Binnema) , the Ministry
asked the Town to extend our contract with Novacor
Construction Company Ltd. to resurface this section of
roadway. The items required for the construction of the
sidewalk and for the resurfacing of King Street East are
IJ90
REPORT NO. : WD-16-93 PAGE 3
listed on Attachment No. 1. The Town's share of this work is
$48,278 . 10.
2 .5 The prices quoted are the same as those in the original
contract, where applicable. The prices for the other items
were negotiated. Council may be concerned that we are not in
a very good position to negotiate prices with the contractor.
All contracts contain a provision to carry out extra work on
a time and material basis for those items for which a
reasonable price cannot be negotiated.
2 . 6 At the time of preparing the 1993 Budget, the estimated cost
of the project was $88,000 with a cost to the Town of $43,800.
The Town's share of the cost, based on prices from the
contractor, is $48,278. 10, a difference of $4,478. 10 . It is
recommended that the additional cost be financed from the
Development Charge Fund.
2 . 7 This report has been reviewed with the Treasurer, who concurs
with the recommendations.
Respectfully submitted, Recommended for presentation
to the Committee,
`Walter A. Evans, P.Eng. , Lawrence E. Kot `e, f,
Director of Public Works Chief Administrative Officer
WAE*ph
March 25, 1993
0
. I. .
1A KING STREET EAST, P.O. BOX 398, COBOURG
ONTARIO, CANADA K9A 41-1
totten sims hubicki associates (416)372-2121 FAX(416)372-3621
Mr. W.A. Evans, P.Eng., Director of Public Works
Corporation of the Town of Newcastle
Municipal Building, 40 Temperance Street
BOWMANVILLE, Ontario LiC 3A6
March 12, 1993
Dear Sir:
Re: Contract N«'92-28; King Street and Mearns Avenue, Bowmanville, Town of Newcastle
Further to our letter to Mr. Patterson of March 9th, we are now enclosing one copy of the Cost
Apportionment for the above additional work, based on the Contractor's bid prices.
With our letter to you dated November 24, 1992, we provided estimated costs for this work and we have
tabulated below, both estimated totals as then provided, and those based on the Contractor's pricing, to
include GST and all other allowances:
Based on
Original Estimate Contractor's Pricing
Total Project Cost $88,000.00 $88,425.50
MTO Share 44,189.46 40,147.40
Total Town Cost 43,810.54 48,278.10
We will be pleased to receive the Town's instructions before proceeding further with this work.
We have already received written approval from the Region of Durham on the sanitary and water works,
and construction has commenced on the watermain.
By copy of this letter and enclosures to Mr. Conforti, we also request his confirmation on connecting link
subsidy eligibility, on the basis of approval by the Town.
Yours very truly,
totten sims hubicki associates
H.D. Glennie
HDG/ag
sirzFJV2snan9ic ATTACHMENT NO. 1
encl. WD-16=93
PC: Mr. D. Patterson, Manager of Operations.
Mr. F. Conforti, MTO, Downsview
ENGINEERS ARCHITECTS AND PLANNERS ( l)
CONTRACT No NW 92-28 ADDITIONAL WORK BETWEEN MEARNS AVE. AND HAINES ROAD PROJ. i12-10229-01
MARCH 11,1993
CONNECTING LINK in the TOWN OF NEWCASTLE being _KING STREET (HWY. No 2) from
AND MEARNS AVENUE MEARNS AVENUE TO HAINES ROAD
ESTIMATED SHAREABLE SHAREABLE CHARGEABLE TO CHARGEABLE TO
DETAILS OF CONSTRUCTION GROSS COST UNDER EXPLANATION
UNDER PART X CORPORATION REGION OF
C.L. AGREEMENT OF THE ACT _ DURHAM
-- —
-- --- —
SECTION '1' ROADWORKS --- — —- --
1. Earth Excavation (Grading) $234.30
33 m3 @ $7.10 $234.30 FOR SIDEWALK
2. Earth Borrow $520.00
104 m3 @ $5.00 $520.00 FOR SIDEWALK
3• Hot Mix HL-1 $5,490.00 $5,490.00
120 t @ $45.75
4. Hot Mix HL-4 $1,465.80
42 t @ $34.90 $1,465.80
5. Granular 'A' $277.50 $277.50
30 t @ $9.25
6. Concrete Sidewalk $10,939.05
333 m2 @ $32.85 $10,939.05
7• Concrete Curb and Gutter $3,780.00 $3,780.00
All Types
126 m @ $30.00
8. 450mm CSP Storm Sewers, incl. $6,825.00 $6,825.00
Excavation, Type 2 Bedding and
Native Backfill
39 m @ $175.00
9. 600mm x 600mm Precast $2,600.00 $2,600.00
Catbasins, Type 'A'
(OPSD - 705.02 mod.)
2 ea. @ $1,300.00
10. Removal of Asphalt Pavement $228.00
228 m2 @ $1.00 $228.00 FOR SIDEWALK
11. Removal of Asphalt Pavement $102.50 $102.50
Partial Depth
50 m2 @ $2.05
CONTRACT No. NW 92-28 ADDITIONAL WORK BETWEEN MEARNS AVE. AND HAINES ROAD PRO.T- #12-10229-01
MARCH 11,1993
CONNECTING LINK in the TOWN OF NEWCASTLE being KING STREET (HWY. No. 2) from
MEARNS AVENUE TO HAINES ROAD
AND MEARNS AVENUE
ESTIMATED SHAREABLE SHAREABLE CHARGEABLE TO CHARGEABLE TO EXPLANATION
DETAILS OF CONSTRUCTION GROSS COST UNDER UNDER PART X CORPORATION
REGION OF
C.L. AGREEMENT OF THE ACT DURHAM
12. Removal of Concrete Curb $25.00 $25.00
and Gutter
10 m @ $2.50
13. Removal of Pipe Culvert $80.00 $80.00
16 m @ $5.00
14. Removal of Steel Beam Guide $155.00
Rail $155.00 FOR SIDEWALK
31 m @ $5.00
15. Riprap with Geotextile $92.50 $92.50
5 m2 @ $18.50
16. Steel Beam Guide Rail $1,922.00
31 m @ $62.00 $1,922.00 FOR SIDEWALK
17. Placing Topsoil (stockpiled) $200.00
20 m3 @ $10.00 $200.00 FOR SIDEWALK
18. Sodding (Nursery, Unstaked) $465.00
300 m2 @ $1.55 $465.00 FOR SIDEWALK
19. Water for Sod $55.00
10 m3 @ $5.50 $55.00 FOR SIDEWALK
SUB-TOTAL SECTION 1 $35,456.651 $20,738.30
$0.00 $14,718.35
$0.00
CONTRACT No. NW 92-28 ADDITIONAL WORK BETWEEN PRAT. #12-10229-01
MEARNS AVE. AND HAINES ROAD
MARCH 11,1993
CONNECTING LINK in the TOWN OF NEWCASTLE
being KING STREET (HWY. No 21
from MEARNS AVENUE TO HAINES ROAD
AND MEARNS AVENUE
DETAILS OF CONSTRUCTION ESTIMATED SHAREABLE SHAREABLE CHARGEABLE TO CHARGEABLE TO
GROSS COST UNDER UNDER PA EXPLANATION
PART X
CORPORATION REGION OF
C.L.
SECTION 12' AGREEMENT' OF THE ACT
DURHAM
SANITARY SEWERS AND APPURTENANCES
2.01.00 Pipe
2.01.01 MH # 11-F to MH # 11-G
83.5 m @ $148.00 $12.358.00
$12,358.00
2.01.02 MH # 11-G to MH # 11-H
$13,172.00
89 m @ $148.00 $13,172.00
2.03.00 Service Connections
2.03.01 100mm Diameter (2)
$1,890.00
(� 14 m @ $135.00 $1,890.00
2.04.00 Manholes
2_04.07 M-H_ #11-G
LUMPSUM $2,800.00
$2,800.00 $2,800.00
2.04.08 H.H. #11-H
LUMPSUM $2,800.00 $2,800.00
$2,800.00
2.04.09 M.H. #11.F1
LUMPSUM $2,800.00 $2x800.00
$2,800.00
SUB-TOTAL SECTION 2 $35,820.00
$35,820.00
CONTRACT No. NW 92-28 ADDITIONAL WORK BETWEEN MEARNS AVE. AND HAINES ROAD PROJ. #12-10229-01
MARCH 11,1993
CONNECTING LINK in the TOWN OF NEWCASTLE being KING STREET (HWY. No. 2) from MEARNS AVENUE TO HAINES ROAD
AND MEARNS AVENUE
ESTIMATED SHAREA REGION OF
SHAREABLE CHARGEABLE TO CHARGEABLE TO
DETAILS OF CONSTRUCTION GROSS COST UNDER UNDER PART X CORPORATION EXPLANATION
C.L. AGREEMENT OF THE ACT DURHAM
SECTION '3'
WATERMAINS AND APPURTENANCES
3.01.00 Pipe
3.01.03 200 mm PVC $50,115.00
257 m @ $195.00 $50,115.00
3.02.00 Extra over Item 3.01.00
3.02.03 Abandon Pipe Plugs $100.00
2 ea. @ $50.00 $100.00
-- 3.02.04 Remove Exist. Valve Box $50.00
lea. @ $50.00 $50.00
3.02.08 Install Plugs on $550.00
existing watermain $550.00
2 ea. @ $275.00
3.03.00 Valves c/w Valve Boxes
3.03.03 200 mm Gate $1,400.00
2 •a• @ $700.00 $1,400.00
3.04.00 Hydrants
3.04.02 New Hydrant with $6,200.00
Pump Nozzle - $6,200.00
2 ea. @ $3,100.00
3.04.05 Remove and Salvage $350.00
Existing Hydrant $350.00
1 ea. @ $350.00
3.05.00 Service Connections
3.05.01 19 mm Main Stop $1,100.00
- $1,100.00
PROD. #12-10229-01
CONTRACT No. NW 92-28 ADDITIONAL WORK BETWEEN MEARNS AVE. AND HAINES ROAD MARCH 11,1993
CONNECTING LINK in the TOWN OF NEWCASTLE being KING STREET (HWY. No. 2) from MEARNS AVENUE TO HAINES ROAD
AND MEARNS AVENUE
ESTIMATED SHAREABLE SHAREABLE CHARGEABLE TO CHARGEABLE TO EXPLANATION
DETAILS OF CONSTRUCTION GROSS COST UNDER UNDER PART X CORPORATION REGION OF
C.L. AGREEMENT OF THE ACT DURHAM
3.05.05 50 mm Main Stop $685.00 $685.00
lea. @ $685.00
3.05.06 19 mm Curb Stop and Box $370.00 $370.00
2 ea. @ $185.00
3.05.07 25 mm Curb Stop and Box $250.00 $250.00
lea. @ $250.00
3.05.10 50 mm Curb Stop and Box $300.00 $300.00
1 m @ $300.00
3.05.12 19 mm Copper Pipe $1,480.00 $1,480.00
74 m @ $20.00
3.05.15 50 mm Copper Pipe $710.00 $710.00
10 m @ $71.00
3.05.22 Connection to Existing $250.00 $250.00
Water Service
1 ea. @ $250.00
3.05.23 Remove 25mm Curb Stop $50.00 $50.00
lea. @ $50.00
3.05.24 Remove 50mm Curb Stop $50.00 $50.00
1 ea. @ $50.00
SUB-TOTAL SECTION 3 $64,010.00 $64,010.00
CONTRACT No. NW 92-28 ADDITIONAL WORK BETWEEN MEARNS AVE. AND HAINES ROAD PROJ. #12-10229-01
MARCH 11,1993
CONNECTING LINK in the TOWN OF NEWCASTLE being KING STREET (HWY. No. 2) from
MEARNS AVENUE TO HAINES ROAD
AND MEARNS AVENUE
ESTIMATED SHAREABLE SHAREABLE CHARGEABLE TO CHARGEABLE TO
DETAILS OF CONSTRUCTION GROSS COST UNDER UNDER PART X CORPORATION REGION OF EXPLANATION
C.L. AGREEMENT OF THE ACT DURHAM
SECTION '7.1'
STRUCTURES, SOPER CREEK
EAST BRIDGE WIDENING
1. Removal of Asphalt from $165.00 $165.00
Concrete Surface
11 m2 @ $15.00
2. Removal and Disposal of $3,500.00 $3,500.00
Existing Sturcture FOR SIDEWALK
LUMPSUM
$3,500.00
3. Scarifying $900.00 $900.00
18 m2 @ $50.00 FOR SIDEWALK
4. Removal of Concrete
$1,000.00 $1,000.00
2 mz a $soo_oo FOR SIDEWALK
5. Sandblasting $760.00 $760.00
38 m2 @ $20.00
6- Patch Repair South Parapet Wall $5,400.00 $5,400.00
40 1 @ $135.00
7. Modifications of Deck Drains $300.00 $300.00
3 ea @ $100.00 FOR SIDEWALK
8. Deck Drains $1,200.00
2 ea @ $600.00 $1,200.00 FOR SIDEWALK
9. Dowels into Concrete
a)Size 15 $551.00
58 ea @ $9.50 $551.00 FOR SIDEWALK
b)Size 25 $492.00
6 ea @ $82.00 $492.00 FOR SIDEWALK
10. Cncrete Overlay $600.00 $600.00
l m3 @ $600.00 FOR SIDEWALK
11. Concrete in Sidewalk Widening $5,400.00 I $540000
9m3 @ $600.00 $5,400.00 FOR SIDEWALK
C 0 R P 0 R A T I 0 N O F T H E T 0 W N O F N E W C A S T L E PAGE #: 31
1993 CAPITAL BUDGET AND FOUR YEAR FORECAST
I PROJECT DETAIL DEPARTMENT: I
I
DIV. PAGE REF.#: 3
L P R O J E C T / L O C A T I O N M A P
P R O J E C T C O S T / F I N A N C I N G I
I
I
C O S T
Division: A. ROADS AND STRUCTURES (RECONSTRUCTION)
Account #: 7205-89013-X
Account Name: KING STREET (HIGHWAY 42) I 1
I Description: ROAD WIDENING INCLUDING SIDEWALK I I
I I I I
Location: From 95 metres west of Soper Creek Drive east1to Haines Road.
1 (Bowmanville).
I I I I
I-Construction I 77,440
Details/Needs: Road widening (south side only) to an urban road standard including I
grading, granular base and sub-base, curb and gutter, hot mix asphalt I-Design and Construction Administration I 10,560 I
�I and the construction of a concrete sidewalk. 1
�I. I
I
Length: 249 m Cost Per Metre: $353 I TOTAL I $86,000 I
CRFFk
BO 174 N 17ILLE I I
^i H F I N A N L I N G
I > I I I
I. Account Name
I-Res./Res. Funds Development Charge I 18,834
I
King Street I I i
a �Ilo- I-other:
y
I rn 0
I-Subsidy I 44,200 '
I wy I I F
I-Debenture I
I I
o I
Iv (n '-Tax Levy I 24,966
QJ I
TOTAL I $88,000 1
THE CORPORATION OF THE TOWN OF NEWCASTLE
BY-LAW NUMBER 93-
Being a By-law to authorize the issuance of a
purchase order to Novacor Construction Company
Ltd. in respect to an addition to Contract NW
92-28 for the construction of curb and gutter,
sidewalks, hot mix paving and other related
work.
NOW THEREFORE, the Council of The Corporation of the Town of
Newcastle enacts as follows:
1. THAT the Purchasing and Supply Agent be authorized to issue a
Purchase Order to Novacor Construction Company Ltd. in the
amount of $88,425.50 for an extension to Contract NW 92-28.
2. THAT the Purchase Order to Novacor Construction Company Ltd. ,
attached hereto as Schedule "A", form part of this By-law.
BY-LAW read a first and second time this 13th day of April, 1993.
BY-LAW read a third time and finally passed this 13th day of April,
1993.
MAYOR
CLERK