REPORT
Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE File#
Date: DECEMBER 6, 1993 Res. #
By-Law#
Report#:__XD_-53_-93_ File #: -RU-.-LQM
Subject: STATUS OF PUBLIC WORKS DEPARTMENT CAPITAL WORKS PROJECTS
Recommendations:
It is respectfully recommended that the General Purpose and
Administration Committee recommend to Council the following:
1. THAT Report WD-53-93 be received for information.
REPORT
1.0 ATTACHMENTS
No. 1: Table showing status of Capital Works Projects
2.0 REVIEW AND COMMENT
Some of the projects on the Table (Attachment No. 1) require
an explanation.
2 . 1 Item 2: Traffic Signals, Bowmanville
The $20,000 was included in the 1993 budget to complete the
upgrading of the traffic signals on King Street. The cost was
paid in 1992 between the time the budget was prepared and the
accounts were closed out for 1992 .
2 .2 Item 4: Lakeshore Road Erosion Protection
This project is $105,000 over the budget amount of $485,000.
The reasons for this larger overrun are as follows:
REPORT NO. : WD-53-93 PAGE 2
a) Granular 'B' Type 1 in Shoreline Embankment
At the outset of construction the noticeable
increased rate of erosion and wave action
prompted a change in the material backfill to
the revetment stone (rock protection on the
slope) . It was agreed with the Contractor and
the Owner that a switch to crushed rock
material was required in order to ensure
stability of the revetment. Granular 'B' Type
1 material was too difficult to place, in
conditions where water levels fluctuated
almost daily and the material would have
washed out if the protective geotextile was
inadvertently ripped or punctured during
installation.
i
In addition to the increased cost of switching
to crushed rock material the quantity of
material required was considerably greater
than the estimated quantity in the tender.
This is directly attributable to the active
ongoing erosion which occurred in the three
months between tendering and commencement of
I
construction in which period an additional 750
m3 approximately was removed by wave action.
In addition, excavation in the shoreline
produced unexpectedly large volumes of topsoil
(in excess of 1000 m3) and other debris not
anticipated from the soils investigation
report or our own investigations. $ 69, 100
b) Supply Material and Construct Splash Pad
The revetment design, as approved by the
Ministry of Natural Resources, called for
U34
REPORT NO. : WD-53-93 PAGE 3
stone to be placed to the design elevation of
100 year storm plus wave uprush. In
subsequent discussion with the Municipality
and Ganaraska Region Conservation Authority,
it has been agreed that a splash pad should be
added to the construction to increase bank
protection and reduce the extent of future
maintenance. The splash pad has now been
constructed of 300 mm sized rock placed to a
depth of 600 mm and extending to an elevation
of 78.80 m. 11,332
c) Earth Borrow
This covers the use of material in
constructing the embankment above the
revetment and backfilling of sub-excavated
areas within the new roadway. Again, due to
erosion and excessive topsoil removal this
item required more material.
It is important to note that other than
surplus topsoil, we have not removed any
materials from the site which could be used j
for fill purposes. 15,000
d) Geotextile
The increased area of geotextile used under
this Item results primarily from the
introduction of the "splash pad" under Work
Order No. 2 . Estimated overrun is $9,000. 91000
TOTAL $104,432
1US
REPORT NO. : WD-53-93 PAGE 4
2 .3 Item 11: Williams Mill Road Bridge
The purpose of this item is for the removal of the bridge
after having passed the by-law to close the bridge. I will be
submitting a report on this item to the General Purpose and
Administration Committee early in the new year.
2 .4 Item 13: Unspecified Construction
The expenditure under this item was for drainage work on Fices
Road and for a survey at Middle Road and Concession Road 8.
2 .5 Item 22: Gravel Parking Lots
This item was included in the budget to provide additional
parking at the Hampton Depot in the event that students were
hired during the summer months. No students were hired;
therefore, the project was cancelled.
2 .6 Item 24: King Street Storm Sewer
This project was included in the budget to provide for the
possibility of supplemented funding being available from the
Ministry of Transportation. No supplementary funding was
available and the project did not proceed.
I
Council approved using $100,000 from this project to provide
funding for additional repair work on the roads.
I
2 . 7 Work in Subdivisions
Council will recall that we were forced to take over and
complete the work in three ( 3) subdivisions:
i
Newcastle Meadows - Bowmanville
Trulls Delbert - Courtice
Willowbrooke - Bowmanville
i
i
i
1 (J
3
REPORT NO. : WD-53-93 PAGE 5
All of the work scheduled for completion in 1993 has been
completed.
3.0 CONCLUSIONS
3. 1 Not including the construction of the King Street Storm
Sewers, which was cancelled, we are about 9.6% under budget
for the capital projects.
Respectfully submitted, Recommended for presentation
to the Committee,
I
Walter A. Evans, P.Eng. , Marie Marano, H.B.Sc. , AMCT
Director of Public Works Acting Chief
Administrative Officer
WAE*ph
November 29, 1993
Attachment
I
i
i
1 � � 7
PUBLIC WORKS DEPARTMENT
STATUS OF CAPITAL WORKS PROJECTS Page 1 of 3
ESTIMATED
ITEM EXPENDITURE ESTIMATED
NO. PROJECT DESCRIPTION 1993 BUDGET TO YEAR DIFF
END ERENCE COMPLETION DATE
1. King St./ Mearns Ave. 1,058,000 11041,000 17,000 Completed
2. Traffic Signals - Bowmanville 20,000 0 20,000 Completed
3. Phair Avenue 20,000 10,000 10 000 Completed
4. Lakeshore Road Erosion Protection 485,000 590,000 (105,000) Completed
5. Prince Street 355,000 301,500 53,500 Completed
6. Prestonvale Road (Land Purchase) 100,000 75,000 25,000 December 13
7. Road Resurfacing (Mill Street, Orono) 136,000 114,900 21,100 Completed
8. SURFACE COURSE ASPHALT
a Edward Street 68,500 38,133 30 367 Completed
b) Concession Street 110,000 117,960 (7,960) Completed
-� c Beaver/Robert Sts. 65,000 52,500 12P500 Completed
d) Prestonvale Road 50,000 32,230 17,770 Completed
e Rudell Road 50,000 42 290 7,710 Completed
f) Baseline Road 47,000 20,480 26,520 Completed
9. Concession Road 7 Culvert 50,000 50 000 0 December 15
10. Aggregate Development 50,000 37,000 13,000 December 15
11. Williams Mill Road Bridge 3,500 0 3,500 Note 3
12. Bus Shelter 3,500 3,500 0 December 21
cn 13. Uns ecifiied Const. 10,000 5,000 5,000
w n Note 4
14. Road Needs Study 40,000 40,000 0 =December
w M
15. Engineering Design 155,000 155,000 0 December 31
z
0
PUBLIC WORKS DEPARTMENT
STATUS OF CAPITAL WORKS PROJECTS Page 2 of 3
ESTIMATED
ITEM EXPENDITURE ESTIMATED
NO. PROJECT DESCRIPTION 1993 BUDGET TO YEAR END DIFFERENCE COMPLETION DATE
16. SIDEWALKS
a Hwy. 2 Courtice 200,000 192 000 8 000 Completed
b) Hwy. 2, Newtonville - Sidewalk 80,000 70,000 10,000 Completed
c Hwy. 2 Bowmanville - Sidewalk 250,000 235,000 15,000 Completed
17. STREET LIGHTING
a Fourth/Westmore/L nwood 14,000 6 420 71-5-80- Completed
b) Hart Ct./Sunset Blvd. 30,000 10,000 20,000 Completed
c Reg. Rd. -17/Hwy. 35 7,000 2 660 4 340 Completed
d) King Street 15,000 3,460 11,540 Completed
e Hwy. 2, Newtonville 70,000 66,500 3,500 Completed
f) Irwin & Winter Rd. 5,500 3,270 2,230 Completed
Street Smart Program - WD-57-92 645 307 451,200 194,107 Completed
18. EQUIPMENT
a) 1979 Ford Dump Replacement of 115,000 114,000 1 000 Ordered
b) 1983 Ford Dump, Replacement of 115,000 114,000 1,000 Ordered
c 1988 Champion Grader Replacement of 120,000 94 500 25,500 Ordered
d) 1977 IHC Tractor, Replacement of 60,000 60,000 0 December 31
e) Misc. Small Equipment 20,000 20 000 0 December 31
f) 2 Ton Truck/Boom (New) 70,000 70,000 0 December 31
g Lubreel S stem (New) 20,000 19,500 500 Completed
h) Fuel/Key Lock System (New) 30,000 30,900 (900) Completed
19. Hampton Yard Improvement Water Supply) 20,000 20,000 0 Completed
11, 20. Salt Shed/Orono 60,000 60,000 0 December 15
PUBLIC WORKS DEPARTMENT
STATUS OF CAPITAL WORKS PROJECTS Page 3 of 3
ESTIMATED
ITEM EXPENDITURE ESTIMATED
N0. PROJECT DESCRIPTION 1993 BUDGET TO YEAR END DIFFERENCE COMPLETION DATE
21. Sign Shed Improvement, Hampton Depot 10,000 10,000 0 December 31
22. Gravel Parking Lot 15,000 0 15,000 Deleted - not required -
Note 5
23. Depots/Doors Repair 8,000 8,000 0 December 31
SUB-TOTALS 4,856,307 4,387.903 46-8-140-4 9.6% under Budget
24. King Street Storm Sewer 540,000 100,000 440-10-0-0- Cancelled - Note 6
TOTALS 5 396,307 43487,903 908,404
December 6, 1993