HomeMy WebLinkAboutTM-48-80 n1-48-80 '10: Chaiin»an and Members of the Fi.nwice and Administration Committee MUM: A. C. Goiter, TWu Manager DAZE: October 7th, 1980 SUBJECT: Baseline Community Centre (proposed new construction) In a report to Committee on July 21st, 1980, we reported on a meeting held with the Baseline Ccxnnunity Centre Board on July 15th, 1980 and report 7M-33-80 outlined the proposed financing for the project. As the land transaction with Ontario hydro has now been completed the following is an ui-)-dated outline of the financing available for -this project together with staff comments and concerns re1ate'd to this project. REVENUE Sale of Exisi;ing property $ 85,000.00 Interest on Funds paid by Ontario Hydro to September 12th, 1980 26,768.44 Supplementary Agreement ##6 Ontario Hydro 35,000.00 C.R.C.A. Grants 44,125.00 $190.,893.44 EXPENDITURES Estimated cost of construction of building $139,500.00 Estimated cost of well 5,000.00 Professional Fees 11,000.00 Land Transfer and Survey 1,000.00 $156,500.00 In estimating the revenues for grant purposes the estimated value of the lands to be donated by East Woodbridge Developments Limited have been estimated at $20,000.00. This is done in accordance with policy set for C.R.C.A. grants, which allows the Town to add value for all donated lands, material and labour for purposes of grant calculations. V-48-80 In reviewing the progress of this project we note that Letters were sent from Mayor Rickard requesting that the land grant be increased to 31 acres and as a result of the meeting held on July 15th, 1980 an immediate request went to Last Woodbridge Developments Limited to convey two acres of land as set out in their letter dated October 2nd, 1979. On SepteNDer 16th, 1.980 we received the attached letter frmi Last Woodbridge Limited regarding the conveyance or lands and the conditions under which the conveyance would take place. Since this letter was received and further discussions were held with the Developer the attached telegram was received on October 6th, 1980 which in my interpretation assures this project of the necessary lands. In Report `IM--33-80 we outlined to Council the procedure required to carry on with this project noting the fact that staff feel this construction should not be undertaken until the Recreation Master Plan has been completed and the Master Plan indicates a need for such a facility at this location. If it is Council's intention to carry on with this project the follmling actions should be taken: 1 . Niflic Meeting be held by the Baseline Cannuni_ty Hall. Board Lo nscerktin .i f there is sufficient support for' such a facility to be built and if the hall Board is in a position to guarantee the maintenance casts of these facilities that it does not become a burden on the ta.xpavers of the Town or Newcastle. 2. Land Surveys and land transfers 3. Soil tests 4. Construction of Well 5. Authority for consultant to call tenders for construction of Recreation Centre. 1 AV✓®®f k 68.9 e Deve{Ql l��6�16J TELEPHONE (416) 669.4432 old 8481 KEELE STREET (at Langstaff Rd.) AND ASSOCIATES UNIT 11A P.O. 80X 5000 CONCORD,ONTARIO L4K 186 September 5, 1980 Corporation of the Town of Newcastle 40 Temperance Street Bowmanville, Ontario L1C 3A6 Attention: Mr. A. C. Cuiler. Town Manager Dear Sir: Re: Durham J.V. Baseline Community Centre The executive of the Durham J.V. have reviewed the letter from Mr. McIlroy dated July 31, 1980, and wish to advise that they will consider conveying the entire 22 acres for the purposes of constructing the Baseline Community Centre, subject to the convey- ance being calculated as part of the 5% park dedication for any future development as and when the plans of subdivision are regis- tered. Part of the above would be conveyed to the Municipality in the registration of the Rills of Liberty North in place of the two lots to be dedicated as the 5% park dedication. We would appreciate your position on the matter. Yours truly, EAST WOODBRIDGE DEVELOPMENTS LIMITED if Ivano A. Manias, M.C.I.P. IAM/sem i Y` OcLobot, GLh, 1080 Concord Ontario All'. (luiler: As requested by Cbnmittee on September 29th, 1980 Durhwn J. V. is confirming their intention to honour comnitmnt before Council at this time. It is �our understanding that said conmitment is the conveyance of two acre parcel for Baseline Community Centre. We felt offering entire twenty-too (22) acre parcel for negotiable parkland credits was more favourable to 'R)w1j, however, we axe prepared to proceed With conveyance i.n which ever way the Town wishes. Fast Woodbridge Developments Mutt Enterprises Chalk Farm Inc.