HomeMy WebLinkAboutTR-84-86 TOWN OF NEWCASTLE
u`s -
LO
REPORT File #
Res.
By-Law #
MEETING: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
DATE: October 20, 1986
REPORT #: TR-84-86 FILE #:
SUB.ECT: TENDER NO. T86-26, PRINCE STREET STORM SEWERS
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1 . That this report be received; and
2. That Elirpa Construction, Pickering, Ontario, with a bid in the amount
of $98, 197.84, being the lowest responsible bidder meeting all terms,
conditions and specifications of Tender T86-26, be awarded the contract
for the Prince Street Storm Sewers; and
3. That the funds be drawn from the 1986 Public Works Operating budget,
pending a further review of available funds.
BACKGROUND AND COMMENT:
Tender specifications were provided by G.M. Sernas and Associates Ltd. , for the Prince
Street Storm Sewers.
Initially, Tender T86-14 was issued in June 1986, and was subsequently advertised in
the local papers as well as the Daily Commercial News.
Page 2 -
TR-84-86
TENDER NO. T86-26, PRINCE STREET STORM SEWERS
Bids were received and tabulated as follows :
BIDDER BID AMOUNT
Boyle Excavating Limited $129,877.73
Bowmanville, Ontario
659928 Ontario Limited 0/A $139,213.00
V.J.R. Contractors
Markham, Ontario
After review of the bids by Public Works, Purchasing and the consultants G.M. Sernas and
Associates Ltd. , and upon the advice of the consultants, staff decided not to proceed with
Tender T86-14, for the following reasons:
1) Lack of bidders
2) Due to the extremely busy construction season, and the fact that the
timing was not convenient for most contractors, it was felt that the
prices tendered were inflated
3) At the time of this tender call there had been a strike in the
construction industry (operators) , which put contractors an additional
three (3) weeks behind schedule
4) All bids received were over budget.
After further analysis of the situation and again upon the advice of the consultants,
staff decided to re-tender in the fall of 1986. The contract terms were changed by
revising the required completion date of the project, thereby, making the project more
desirable to potential bidders.
Subsequently, Tender T86-26 was advErtised, and both contractors who had previously
submitted tenders, were invited to bid.
Bids were received and tabulated as follows:
BIDDER BID AMOUNT
Elirpa Construction $ 98,197.84
Pickering, Ontario
Boyle Excavating Limited $127,349.78
Bowmanville, Ontcri0
Harnden and King Construction $129,290.25
Cobourg , Ontario
The engineer' s estimate for the tendered work was $91 ,220.00. Initially $85,000.00 was
budgeted in working capital reserve as approved by Council in 1985. In addition to the
total bid price of $98, 197.84 is the contingencies allowance of $4,677. 16 and the
Engineering Supervision cost of $10,625.00. This brings the total estimated project cost
to $113,500.00. However, staff have now obtained M.T.C. approval for 50% of the total
Page - 3 -
TR-84-86
TENDER NO. T86-26, PRINCE STREET STORM SEWERS
cost which results in a net cost to the Town in the amount of $56,750.00. Staff is of
the opinion that the Town 's contribution can be funded from the 1986 Public Works
Operating budget and will advise Council accordingly at a later date.
After further review of the bids by Public Works, Purchasing and G.M. Sernas and
Associates Ltd. , it was mutually agreed the low bidder, Elirpa Construction, Pickering,
Ontario, be recommended for the contract award for the Prince Street Storm Sewers. A
letter from G.M. Sernas and Associates Ltd. , advising of their recommendations is attached,
marked Schedule "A" .
Respectfully submitted,
G
J.R. Blanchard,
Treasurer.
G.J. Ough, P. Eng. ,
Director of Public Works.
/hjm
Attachment
SCHEDULE "A"
PROFESSIONAL
CONSULTING
ENGINEERS October 15 , 1986
Town of Newcastle
Scugog Street r
Hampton , Ontario ` 1
LOB lJ0 �t��,� '?" �u. �(7
Attention: Mr . G. Ough, P. Eng. i
Dear Sir :
RE : PRINCE STREET STORM SEWER
TOWN OF NEWCASTLE CONTRACT T86-26
Tenders for Prince Street storm sewer, Town of
Newcastle Contract T86-26 were received and opened on Tuesday ,
October 14 , 1.986 , at 2 : 00 p ,m. The following is a summary of the
three (3) tenders received:
Total
Tenderer 'Tendered Amount
Elirpa Construction $ 98 , 197 .84
Boyle Excavating Limited $127 , 349 . 78
Harden & King Construction $129 , 290 . 25
The Engineer' s estimate for the tendered work was
$91 , 220 .00 . A copy of the low tender submission is attached for
your record.
We have examined the three (3) tender submissions and
found the same to be arithmetically correct and complete I complying
with the general tendering requirements .
Further, we have analyzed the unit prices tendered
by the two low tenderers and found that the unit prices bid to be
reasonable without evident of unbalancing of the tender bids .
Based upon the low tender received, Elirpa Construction
& Materials Limited , the following is our estimate and apportionment
of the total project cost :
2/
85 THE EAST MALL,SUITE I i I 185 RROCK ST NORTH,SU11 F 207
TORONTO,ONTARIO M075M WHITAY,ONTARIO LIN 4H3
TELEPHONE.(416)25 9-6323 TELEPHONE(416(6GB')?"
TORONTO LINE-683-5541
`:��}�9 Li C�.1:.1.�L1J;••L.J t3..!_I59 J tl:t:.1ENL.9 iLtPUJ.
Town of Newcastle
Mr . G. Ough, P . Eng.
October. 15 , 1986
P a S E_
Total Estimated Project Cost
Contract tendered amount (El.irpa Construction & Materials $ 98 , 197 . 84
Limited)
Contingencies $ 4 , 677 . 16
Engineering, & Resident Supervision $ 10 , 625 . 00
Total $113 , 500 . 00
A-pportionment of Estimated Total. Project Cost
Ministry of Transportation & Communications $ 56 , 750 . 00
Town of Newcastle $ 56 , 750 . 00
Total Estimated Project Cost $113 , 500 . 00
The contract work includes the installation of storm
sewers and road and boulevard restoration on Prince Street from
Simpson Street westerly 250 meters .
The contract is open for acceptance for a period of
30 days after the tender closing date of October 14 , 1986 . The contract
work is scheduled for completion- within eight (8) weeks after the
date of official. notification to commence work . The award of the
contract is subject to the approval of the Ministry of Transportation
and Communications .
We are satisfied that Eli.rpa Construction & Materials
Ltd. , is capable of completing this project to the terms of the contract ,
and therefore recommend acceptance of the low tender and award of
contract to Eli_rpa Construction & Materials I.td. , in the amount of
M:inety-Eight 'Thousand One Hundred acid Ninety--Seven Dollars and Eighty
Dour Cents ($98 , 197 .84) subject to the requisite approvals .
Upon receipt of your instructions , we will prepare
the contract documents for execution and make the necessary submission
to the Ministry of Transportation and Communications for approval of the
contract award. Please advise if you require additional information to
supplement the above .
3/
� � O V Sw".�L3,1
Town of Newcastle
Mr. G . Ough, P . Eng.
October 15 , 1986
Page 3 - --
Trusting that the above is sai_tsfactory, we remain
Yours very truly,
G. M. SERNAS & ASSOCIATES LTD.
N. Mensink, P. Eng.
NM: hm Associate , Project Manager
Encl.
cc : Town of Newcastle
Attn. Mrs . L . Burkett-
SUMMARY - PRINCE STREET STORM SEWER, TOWN OF NEWCASTLE
CLOSING - 2 ;00 P.M. , OCT. 14 , 1986
ROADWORK & STORM SEWER SERVICING
T80DCR 3UMMA8Y
CONTRACTOR It ROADWORKS 11 UNDERGROUND 11 TOTAL It REMARKS
======================================================================
0OV&C0R
CONSTRUCTION 11
11
______________________________________________________________________
DAVE B0YLB It 11 It 11 &TB
EXCAVATING 11 ¢36 , 642 . 10 11 $90 , 707 , 68 It $127 , 349 . 78 11 CC
LTD, It 11 it 1113 ,000 . 00
______________________________________________________________________
K&MLD ! l 11 ' 11 ll
'
CONSTRUCTION 11 11 ! l } !
LTD. 11 i !' It It
_-_--_--_--_-___--__--_-----__--____--_-_--___-___-----_--_-_--___-__-
8OLLINGW0BT8 ll it
CONSTRUCTION / 1 ll it ll
11 It
______________________________________________________________________
V.J .R . ! l ! l 11 if
CONTRACTORS 11
,_--____-_-__--_-_-_-_-_-_-___-_-__----__-__----_----_--_-_-__--_----__
HARDEN 6 KING 11 11 It
CONSTRUCTION 11 \ ! If 11 8T8
(ONTARIO) 11 $33 , 553 . 35 11 ¢96 ' 736 . 90 11 ¢139 , 890 . 25 11 CC
LIMITED 11 11 11 1113 , 500 . 00
----------------------------------------------------------------------
/ D&GM&B 11 11 11 11
CONSTRUCTION 11 It
LIMITED 11 If
______________________________________________________________________
8LIRP& 11 it It ! l &78
CONSTRUCTION & 11 $24 , 532 . 84 It ¢73 , 665 . 00 11 $98 , 197 . 84 / t CC
MATERIALS LTD. 11 11 11 1110 , 000 , 00
----------------------------------------------------------------------
! l 11 11 11
ENGINEER' S 11 ¢23 , 397 . 50 11 $67 , 822 . 50 11 ¢91' 320 .00 il
ESTIMATE 11 l ! it It
______________________________________________________________________
NOTES :
ATB - AGREEMENT TO BOND INCL .
B8 - BID BOND INCL .
CC - CERTIFIED CRDOUO INCL.
Q - QUALIFYING LETTER PROVIDED '
�