CORPORATION OF THE TOWN OF NEWCASTLE
TREASURY DEPARTMENT K. CAMPBELL, C.A.,TREASURER
40 TEMPERANCE STREET TEL.(416) 623-3379
BOWMANVILLE, ONTARIO
L 1 C 3A6
REPORT TO THE GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
MEETING OF DECEMBER 3, 1984
REPORT NO. : TR-94-84
SUBJECT: 1985 FIVE YEAR CAPITAL BUDGET (FIRST DRAFT)
RECOMMENDATION:
It is respectfully recommended that the General Purpose and
Administration Committee recommend to Council the following:
1. That this report be received, and
2. That the 1985 Five Year Capital Budget, which has been
distributed under separate cover, be received for
,review and consideration.
BACKGROUND AND COMMENT:
The demands on the Corporation for capital works in the next
five years are substantial with the proposals for a Baseline
Community Centre (1985) , a new town administration facility
(1986) , a new arena in the Bowmanville Urban Area (1987) ,
renovation of the main fire station (1988) and a Community
Services depot (1988) having major impacts. Lessor proposals
include the construction of a lunchroom and washrooms at the
Hampton Works Depot (1985) , construction of a storage/office
facility at the Bowmanville Cemetery (1985) , construction of
training facility for the fire department (1985) , updating
the change facilities at the Orono Pool (1988) and the
expansion of the Zamboni Room at the Darlington Sports Centre
(1989) . In addition to the aforementioned projects, the
r.
0
3(bI
- 2 -
TR-94-84
1985 FIVE YEAR CAPITAL BUDGET (FIRST DRAFT)
BACKGROUND AND COMMENT: continued
regular program of road construction, equipment replacement
and updating in all departments and the capital repairs to
facilities is ongoing.
The Baseline Community Centre project (1985) has received
approval of its grant request and with the monies available in
the reserve fund, this project should have no impact on the
tax levy.
The construction of a new municipal administrative facility
(1986) is shown as funded principally through a debenture
issue. Staff are investigating other means of funding the
provision of the facility through long term lease arrangement
and will report the results of that later in the budget
discussions.
The construction of an arena in the Bowmanville Urban Area
will be fully investigated in the feasibility study which is
slated for completion in the spring of 1985. That study wi l l
determine the size and type of facility required and provide
the Town with a better basis for the cost estimate. Council
has made a financial commi ttement to the project in the amount
of 25% of the project cost plus the carrying charges to fund
the project while the fundraising and grant monies are
collected.
The renovation of the main fire station (1988) will be funded
principally through the tax levy as no government funding is
available to offset these costs. If substantial residential
development takes place in the interim, there will be funds
avaliable in the Lot Levy Reserve Fund to help cushion the
impact on the tax levy.
3
- 3 -
TR-94-84
1985 FIVE YEAR CAPITAL BUDGET (FIRST DRAFT)
BACKGROUND AND COMMENT: continued
The Community Services' depot (1988) is shown as a debentured
project because the Town would not normally have $761 ,420
available to put towards such a project in one year.
Of the lessor proposals only the lunchroom/washroom project at
the Hampton Works Yard (1985) and the fire department training
facility have funding available from sources other than the
tax levy, being the Lot Levy Reserve Fund, the Ontario Hydro
Impact Funds and the Fire Department Reserve Account.
In 1984 the taxes levied for capital projects totalled
$596,175. In 1985, this draft capital budget proposes a tax
levy of $1 ,071 ,225, an increase of 80%. That increase results
from the administrative building levy, an increased road
construction program and the needs of the Community Services
Department. The Fire Department requirements for 1985 are
entirely funded from Ontario Hydro Impact Funds and existing
reserves.
If the Ministry of Transportation and Communications provides
a minimal increase in subsidy He: 4%-5%) the road
construction projects proposed wi l l have to be reduced to come
into line with -the available funding. A project on Nash Road
which is detailed on the attached sheets, was excluded in
error, and should also be considered with the 1985
construction. I
The Newcastle Library Board requirements were not available at
the time the budget was compiled, but will be forthcoming to
later discussions.
-r;-3�b1
- 4 -
TR-94-84
1985 FIVE YEAR CAPITAL BUDGET ( FIRST DRAFT)
BACKGROUND AND COMMENT: continued
Requests for capital projects from the local boards will not
be known until the grant requests have been reviewed early in
the new year by the Newcastle Community Services Planning
Board.
Respectfully submitted ,
C_
X. Kathryn A. Campbell , C.A. ,B.Comm.,
easurer.
*gf
Attachment given out under separate cover. ( 1985 Five Year
Capital Budget- First Draft)
Attachment - Nash Road 1985 Reconstruction Project Sheet.
TOWN OF NEWCASTLE
MEMORANDUM
TO: Kathryn A. Campbell , Treasurer
FROM: R.G. Dupuis, Director of Public Works
DATE: November 22, 1984.
SUBJECT: REVISIONS TO FOUR YEAR CAPITAL BUDGET FOR 1985
Further to our recent discussion, attached is a revised
summary and detail sheet to cover inclusion of
reconstruction of Nash Road in 1985. This project was
missed in the transfers of information from our rough draft
to the final summary sheets.
R.G4DuDPUi
RGD:j co
cc: D.S. Johnston
HI i
CORPORATION OF THE TOWN OF NEWCASTLE
1985 CAPITAL BUDGET AND FOUR YEAR FORECAST PUBLIC WORKS DEPARTMENT
Financing 1985
ROAD CONSTRUCTION Gross Other than Taxation Tax
Expenditure Other Debenture Levy
Concession St. - Lots 3&4 Darl . 150,000 MTC 75,000 75,000
Holt Road (Robinson/Drew) 10,000 MTC 5,000 5,000
Prestonvale Rd. - Design & Land 50,000 MTC 25,000 25,000
6th Conc. - Solina 150,000 MTC 75,000 75,000
Nash Road - Townline to
Darlington Blvd. 200,000 MTC 100,000 100,000
Scugog Rd./7th Conc. Intersection 10,000 MTC 5,000 5,000
Golf Course Road 100,000 MTC 50,000 50,000
Mosport Road (Salco) 50,000 MTC 25,000 25,000
Baseline Road - Liberty St. east
- Part X - design 30,000 MTC 15,000 15,000
- Supplementary-const. 300,000 MTC 150,000
Ind.Reserve 150,000
Baseline Road - Duke to Spry 360,000 MTC 180,000 180,000
Needs Study (Major Update) 15,000 MTC 7,500 7,500
Unspecified Road Construction
associated with development 100,000 MTC 50,000 50,000
TOTAL 1,525,000 912,500 612,500
i
i
CORPORATION OF THE TOWN OF NEWCASTLE DEPARTMENT: PUBLIC WORKS DEPARTMENT
1985 CAPITAL BUDGET ACCOUNT NUMBER: 7205
PROJECT DETAIL SHEET ACCOUNT DESCRIPTION: ROAD CONSTRUCTION
I . Project Number
4. Capital Costs
2. Project Location & Description
Land, Building & Major Improvement $
Nash Road Between the Oshawa/Newcastle Furniture & Equipment
Townline Road and Darlington Boulevard North
Construction Services:
Contractor 200,000
Regional
Engineering
3. Key Plan
A i Temporary Financing
o�
0
z
¢° a N
N
Qj TOTAL COSTS $ 200,000
r
W W
K H J
J
W �
u
5. Related Project
NASH RoAO This section of road is deficient in the Road Needs Study
and has had improvements petitioned by area residents.
With the development and road reconstruction proceeding
J �K in the vicinity it is now appropriate to schedule
Z Z o HiG HWAY N° 2 reconstruction to urban standards.
J_ J
C
Q�
4P °
a
W