HomeMy WebLinkAboutTR-47-91 TOWN OF NEWCASTLE
t REPORT
� File # `I-6
Res. #
By-Law #
hEETING: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
DATE: June 17, 1991
REPORT #: TR-47-91 FILE #:
SU&JECT: TENDER NW91-61 RECONSTRUCTION OF BEAVER STREET AND ROBERT
STREET
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and
Administration Committee recommend to Council the following:
1. That Report TR-47-91 be received;
2 . That Mar-King Construction Company Limited, Concord,
Ontario, with a total bid in the amount of $915,080 . 93
being the lowest responsible bidder meeting all terms,
conditions and specifications of Tender NW91-6, be
awarded the contract for the Reconstruction of Beaver
Street and Robert Street, as required by the Department
of Public Works;
3 . That the funds in the amount of $725,000 .00 be drawn
from the approved 1991 Public Works Capital budget,
account #7205-88014-0261; and
4 . That the additional funds required in an approximate
amount of $91,731.00 be drawn from Public Works Lot
Levies (total project cost $816,731.00 less budgeted
cost $725, 000 . 00 and the Ministry of Transportation
Supplementary Subsidy, as per Council Resolution
#GPA-318-91.
BACKGROUND AND COMMENT:
Tender specifications were provided by Totten Sims Hubicki
Associates for the reconstruction of Beaver Street and Robert
Street, as required by the Department of Public Works .
' � 2
Page - 2 -
TR-47-91
TENDER NW91-61 RECONSTRUCTION OF BEAVER STREET AND ROBERT STREET
Tenders were advertised in the local papers, as well as the Daily
Commercial News . Subsequently, tenders were received and
tabulated as per Schedule "A" attached.
The low bid of $915,080.93 is within the total budget allocation
of $1,225,000 . 00 ( $750,000 . 00 Capital Budget + $500,000 .00 as
approved by Council Resolution #GPA-318-91 (see copy, marked
Schedule "B" attached) . The engineer's estimate for the contract
was $1,324 . 660.00 . Other associated costs are estimated and
detailed as follows:
Contract (includes G.S.T. ) $ 915,080 .93
Contingencies $ 28,316 . 19
Design and Tendering Services $ 30,000 . 00
Construction Administration $ 70,000 . 00
Relocation of Utilities $ 40,000 . 00
Legal Surveys $ 2,000 .00
Land Appraisal $ 3,200 .00
Soils Investigation $ 5, 100.00
Land Acquisition $ 10,000 .00
G.S.T. (items 2 - 9) $ 13,203. 13
TOTAL $1,116,900 .25
Less Payable by Others (including G.S.T) $ 300, 169 .25
TOTAL FUNDS REQUIRED $ 816,731.00
It is proposed that funds in the amount of $725,000 .00 be drawn
from the approved 1991 Public Works Capital budget, account
#7205-88014-0261 and that the additional funds in an approximate
amount of $91,731. 00 be drawn from the Public Works Lot Levies
and the Ministry of Transportation Supplementary Subsidy as per
Council Resolution #GPA-318-91.
Although the low bidder has not previously performed for the Town
of Newcastle, their references have been outlined in the attached
letter from Totten Sims Hubicki Associates, marked Schedule "C" .
The Treasurer has reviewed the funding requirements and concurs
with the recommendation. Queries with respect to department
needs, specifications, etc . , should be referred to the Director
of Public Works .
13
Page - 3 -
TR-47-91
TENDER NW91-6, RECONSTRUCTION OF BEAVER STREET AND ROBERT STREET
After further review and analysis of the bids by Public Works,
Totten Sims Hubicki Associates and Purchasing, it was mutually
agreed that the low bidder, Mar-King Construction Company
Limited, Concord, Ontario, be recommended for the contract for
the Reconstruction of Beaver Street and Robert Street.
Respectfully submitted, Recommended for presentation
to the Committee,
r
Marne Marano, H.B.Sc. , AMCT. , Lawrenc Kotseff,
Treasurer. Chief 'nistrative Officer.
.A. Evans, P. Eng. ,
Director of Public Works.
LAB/hjl
Attachments
SCHEDULE "A"
BID SUMMARY
TENDER NW91-6
RECONSTRUCTION OF BEAVER STREET AND ROBERT STREET
Bidder Total Bid Amount
Mar-King Construction Company Limited $ 915,080 . 93
Concord, Ontario
Advice Contracting Limited $ 937,237 .88
Markham, Ontario
Dawn Enterprises Ltd. $ 948,237 .22 **
Concord, Ontario
Pilen Construction of Canada Limited $ 986,073 . 16
Brampton, Ontario
Novacor Construction Ltd. $1,013,000.04
Queensville, Ontario
Kamlu Construction Limited $1,022,977 .08 **
Sharon, Ontario
Elirpa Construction & Materials Limited $1,033,224 . 93
Pickering, Ontario
Ron Robinson Limited $1,036,298 .02
Oshawa, Ontario
Econo Excavating and Paving Co. Ltd. $1,039,201. 17 **
Concord, Ontario
Quadsons Construction Ltd. $1,040,006 .40 **
Concord, Ontario
Dagmar Construction Inc. $1,068,048 .81
Markham, Ontario
Fernview Construction Limited $1,084,755. 69 **
Bolton, Ontario
Duntri Construction $1,087,576 . 14
Oshawa, Ontario
P. Mancuso Construction Limited $1,239,912 . 90
Downsview, Ontario
** amended tenders due to extension errors
SCHEDULE
G.P.& A. Minutes - 10 - May 6, 1991
PUBLIC WORKS DEPARTMENT
Reconstruction of Resolution #GPA-318-91
Beaver Street,from
Edward Street to Moved by Councillor Hamre, seconded by Councillor Hooper
Highway 2,
Village of Newcastle THAT Report WD-42-91 be received;
T04.408.BE
THAT Council approve the reconstruction of Beaver Street from Edward
Street to Highway #2 in 1991; and
THAT the funding for the project be provided from $250,000
Supplementary Subsidy from the Ministry of Transportation and $250,000
from the Lot Levy Reserve Fund.
"CARRIED"
/ 16
SCHEDULE "C"
(31,TOTION S.Sc., P,Eng•
R,E,SIMS S A,Sc„ P.Eng,
J,M. HUSICKI S A$t.,OAA, P,Eng,
R.L.WINDOVER MSc,,P.Eng,
CONSULTANTS 1A SIMS HUDICKI ASSOCIATED(1041)UWYEO
1A K NO STRUM EAST P.O,BOX 3G9,COSOURG
ONTARIO,CANADA K4A 41.1
totten Sims hubicki associates (416)On-2121 FAX(416)372.3621
Mrs. Lott Ann 8irkett
Purchasing & Supply Agent
Corporation of the Town of Newcastle
Municipal Building, 40 Temperance Street
BOWMANVILLE, Ontario L1C 3A6
June 3, 1991
Dear Mrs. 8i.rkett:
Re; Contract No. NW91-6, Beaver St./Robert St./ Reconstruction, Newcastle,
Corporation of the Town of Newcastle
TSH Project No. 12-8025
Tenders for the above project were opened at the Municipal offices on
Friday, 31 May, 1991. The list of bids received are as follows:
Mancuso Construction Ltd. $1,239,912.90
Duntri Construction $1,087,576. 14
Fernview Construction Ltd. $1,084,755.69
Dagmar Construction Inc. $1'0 �
Quadsons Construction Ltd. $1> 40,006.40
Econo Excavating & paving $1,039,201. 17
Ron Robinson Ltd. $1,036,298.02
Elirpa Construction. & Materials Ltd. $1,033,224.93
Kamlu Construction Ltd. $1,022,977.08 *
Novacor Construction Ltd, $1 ,013,000,04
Filen Construction of Canada Ltd. $ 986,073.16
Dawn Enterprises Ltd. $ 948,237.22 *
Advice Contracting Ltd. $ 937.237.88
Mar-King Construction Ltd. $ 915,080.93
*corrected amount $1,324,660.00
Engineers Estimate:
We have checked the low bidders tender and wish to advise that all requirements
have been satisfactorily addressed. The Agreement to Bond has been executed and
a depostt cheque in the amount of $40,000 accompanied the 'fender.
Mar-King is a new Company formed with personnel from Craftwood Construction Ltd.
This is the new Company's first our
ho review
based on Craftwood and
17
ENGINEERS ARCHITECTS AND PLANNERS
Page 2
Contract No. NW91-6, Beaver St./Robert St./ Reconstruction, Newcastle,
Corporation of the Town Of Newcastle
TSH Project No. 12-8025
,dune 3, 1991
We have checked various references including contracts undertaken under the
supervision of our own personnel and have found performance to be satisfactory.
Craftwood has undertaken two contracts for our company within the past two years
in Port Hope and Cobourg and the projects were completed satisfactorily. Discussion
with Region of Durham staff Town of Helton Hills
1990.indicates satisfactory
performance on work carried out for
Craftwood Construction has recently split up and the principals of Mar-King are:
Mr. Frank Dipede, President
Mr. Domenic Baldesarra, Vice President
Mr. Peter Baldesarra, Treasurer
Mr. Steve Polsinelli, C.R.T. , Secretary
Mr. Frank Depede is still the President of Craftwood and the other personnel mentioned
held various positions with Craftwood.
All equipment to be used by Mar-King an this project is owned by the Company with
no financing On it. The Company is sound financially according to their Bank
Manager.
Based on our research we can recommend that the contract be awarded to Mar-King
Construction.
Based on the low bid the amount payable by the Town of Newcastle is estimated
as follows:
Roadworks -- Seotion 1
Tender $574�,�68 ��3C� •l `l
Contingencies
Design and Tendering Services 30,000.00
Constructions Administration 40,000.00
Relocation of Utilities 40,000-00
Legal Surveys ,200.00
Land Appraisal 3 3,100.00
Sails Investigation 5,100.00
000.00
Land acquisition
$763,300.00
,add G.S.T. $ 532431-00
Total Cost S$Z 6 731-10
of the total cost, sidewalks construction is not eligible for subsidy by the Ministry,
of Transportation. This cost amounts to approximately $38,000.00
. ./3 ,� totten sups hubicki associates
Page 3
Contract No. NW91-6, Beaver St. /Robert St./ Reconstruction) Newcastle,
Corporation of the Town of Newcastle
TSH Project No. 12-8025
June 3, 1991
A copy of the letter from Mar-King Construction is attached for your future information.
All deposit cheques other than the low and second low bids may now be released.
Yours very truly,
TOTTEN SXMS HIMCKX ASSOCIATES
�. 4'
Z.A. Kempton, P.Eng.
RAK/lld
Encl.
cc: Mr. W.A. Evans, P.Eng. , Director of Public Works
Mr. O. Patterson, Manager of Operations
Mir. A.S. Cannella, C.E.T. , Manager of Engineering
Ms. Kay Rand, Public Works
Ms. Lori Brown, Treasury Department
totten aims hubicki associates
Uf1c <+ 1 I Ut 1 1 = v.3 T S H . CCDURC F1= X 1I _ r 2 =G2 1 F' _ 'O:Z—
N3I UM NO. 2 To REPORT ON CONTRACT Flo. NW91-6
Estimated cost to Town is as follows:
Total Tender Bid (including G.S.T. ) $915,080.93
1. Contingencies 28,31$. 19
2. Design and Tndering Services 30,000.00
3. Construction. Administration 70,000.00
4. Relocation of Utilities 40,000.00
3. Legal Surveys 2,000.00
6. Land Appraisal 3,200.00
7. Soils Investigation 5,100.00
8. Land Acquisition 10,000.00
Goods and Services Tax (Items 1 ° 8) 13,203. 13
Total. $1 ,_1162900.25
Less Payable by Others (including G.S.T. ) 3000169.25
Total funds required $816,731.00
120 totteu sims hubicki. associatea
*7385496 MAR-KING 054 P02 JUN 03 '91 12.;37
Mar-King Construction Company Ltd.
176 Rlvermode Rd. Unit$
concord,Ontario L4K 3M9
agrrT�xoorr�Frr.,n. Tel,(416)738,4182 Fax(416)738,5496
June 3, 1991
Mr. R.A. KemPton
Totten Sims Hubicki AssoCiates
1A King Street East, P.b box 398
Cobourg, Ontario
KgA 4Lx
Re: ,Town of Newcastle
contract NW91-6
Reconstruction of Bearer ST.
Dear Sir :
We would like to take this opportunity to introduce our
company, Mar-King Construction Company Limited .
Although our company was recently incorporated, the
principals Of Mar-King
andRadsea ywherenfrome10 years t000verf
Sewers , water max
30 years .
To clarify, CraftXwood Construction has recently split
up. The principals of Mar-King are:
Mr. Frank DiPede, President
Mr . Domenic Baldesarra, Vice President
Mr. peter Bal,desarxa, Treasurer
Mx. Steve Polsi.nelli. , C. E.'>:. , Secretary
Frank Dipede was and still is the president Steve
was a ooe Peter tor was
with superintendent with
and Domenic wasoad,foremen.
was an estimator
with Con- Drain.
The equipment to used on
iz�anc hiso project is owned by
Mar-King construction with no
We are 'still with the
) 631e-5021 ,k
31e5021k manager , Mr_ G.C. Allen,
who can be reached
Because of , the recent incorporation of Mar--King, our
work experience is and r CRecans duct~iic includes countless
jobs similar to Beaver `
121
+73e5496 MAR-KING 054 P03 JUN 03 '91 12:37
some of the more recent jobs include:
1 . Reconstruction of ToWnline goad for
the Region of Durham
2 . Construction of sanitary & storm sewers,
watermains and reads for the
Town of Cobourg for which Totten Sims
Hubioki was the consultant
3. Construction of storm sewer, watermains
roads on Todd Read in Georgetown for the
Township of Halton Hills
while we were setting up Mar-King we completed a
sanitary sewer ,�� which Craftwood, for was the
stockyards Inc . he
consultant.
If you require any further information, please contaot
Steve Folsinelli @ (418 ) 738- 4182 .
'hank you,
yours truly
Mar-King Construction Company Limited
g. 1�olsineJli, C.E.T.
Sp/sp Estimator
,�22