REPORT
ENGINEERING SERVICES
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Report #: EGD-53-02
jF{)! Glf)-fffOA
File #: B.01.16.002 By-law #:
Date: DECEMBER 2, 2002
Subject:
ASPEN SPRINGS SUBDIVISION, PHASE 1, BOWMANVILLE,
PLAN 40M-1686, 'CERTIFICATE OF ACCEPTANCE', TRIBUTARY
STORMWATER MANAGEMENT WORKS AND WATER QUALITY WORKS
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report EGD-53-02 be received; and
2. THAT the Director of Engineering Services be authorized to issue a 'Certificate of
Acceptance' for the Tributary Stormwater Management Works and Water Quality Works
constructed within Plan 40M-1686.
Submitted by:
~ "~
( , /
tl?;Jli~/--
Anthony Cannella, C.E.T. Reviewed by:
Director of Engineering Services
O~.~{~
Franklin Wu,
Chief Administrative Officer
AHC*ASC*ce
November 25, 2002
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T905l623-3379 F 905-623-9282
719
'.
REPORT NO.: EGD-53-02
PAGE 2
1.0 BACKGROUND
1.1 The former Corporation of the Town of Newcastle, now the Corporation of the
Municipality of Clarington, entered into a Subdivision Agreement, registered October 10,
1991, with Martin Road Holdings Limited to develop lands by plan of subdivision, located
in Bowmanville, and described as Plan 40M-1686 (Attachment 1). The agreement
required the developer to construct all roadworks, including hot-mix paving, sidewalks,
curb and gutter, street trees, a storm drainage system and streetlights, hereinafter
referred to as the 'Works'.
1.2 The Subdivision Agreement provides for Phase 1 Works to be separated into five (5)
stages:
a) Storm Sewer System;
b) Roads and Above Ground Services;
c) Tributarv Stormwater Manaqement Works
d) Water Quality Works; and
e) CPR Underpass Work
1.3 This particular Agreement allows for the acceptance of the Stormwater Manaqement
Works and Water Quality Works, independent of the other Works, provided that the
maintenance provisions have been met.
1.4 The Tributary Stormwater Manaqement Works and Water Quality Works were issued a
'Certificate of Completion' dated July 31, 1998. This initiated a four (4) year
maintenance period, which expired on July 31,2002. The Works have been inspected
and have been found to be rectified to the satisfaction of the Director of Engineering
Services.
1.5 It is now appropriate to issue a 'Certificate of Acceptance' for the Tributary Stormwater
Manaqement Works and Water Quality Works. The Subdivision Agreement requires
720
,
REPORT NO.: EGD-53-02
PAGE 3
Council approval prior to the issuance of the 'Certificate of Acceptance' for the Tributary
Stormwater Manaqement Works and Water Quality Works.
Attachments:
Attachment 1 - Key Map
721
.
~. -\
~-
I
,I"\\
I I I
1\
, I.
"-,-
Water Quality
Works
'1/\
I \
I \
If 1\
II 'I
I I
I /
\",_/
-----------
Baseline Road
Q)
>
'C
o
.-Q)
""O-----:--T--
-wr( ,,', -,
-- W --"-~
Q) ,I ~/
_$
--..--
C 'tJ
~ I ~
IV
W~l!:
s
-LJ
Tributary Stormwater
Management Works
r-- - ,. ",
\~\\~
\/./.-........\ \, '
\
/T'
'\/
\
~
'1
(-" -
L-L____,
1-
----------j
ngmeermg ervlces
REPORT EGD-53-02
ATTACHMENT NO.1
Drawn By E. Lisinski
NOV. 2002