HomeMy WebLinkAboutPSD-142-03 .' . .. . . Cl!Jl-!lJglon REPORT PLANNING SERVICES Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE Date: Monday, December 8 , 2003 p--o g Res." Gf'f\-lf<l-S-03 Report #: PSD-142-03 . File#: PLN 18.1.7 By-law #: Subject: EA PROCESS, PREFERRED SOLUTION WATER SUPPLY PLANT CAPACITY WHITBY/OSHAWAlCOURTICE URBAN AREA RECOMMENDATIONS: It is respectfully recommended that the General Purpose and Administration Committee recommend to Council the following: 1. THAT Report PSD-142-03 be received; 2. THAT Council endorse the preferred solution, expansion of the Whitby Water Supply Plant as outlined in the Class Environmental Assessment Process. Submitted by: a id U. Crome, M.C.I.P., R.P.P. Director of Planning Services -". 0 r: C Reviewed by: J .~~---' ~~ Franklin Wu, Chief Administrative Officer FL *DJC*sh November 27, 2003 CORPORATION OF THE MUNICIPALITY OF CLARINGTON 40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1 C 3A6 T (905)623- 3379 F (905)623-0830 632 , , REPORT NO.: PSD-142-03 PAGE 2 1.0 BACKGROUND 1.1 In January 2003 the Region of Durham informed Clarington that they would be undertaking a Class Environmental Assessment for the provision of additional water supply capacity for the Whitby/OshawalCourtice urban areas. The study has proceeded with ongoing input and information being provided by the Region. The Region is now in the final steps of Phase 2 of the EA process where a preferred solution has been identified, they are seeking comments. 1.2 The existing water supply plant (WSP) capacity available for the Whitby/OshawalCourice urban areas is adequate to satisfy projected growth until 2011 only. After that time additional WSP capacity will be required if growth is to continue in accordance with the Regional and Local Official Plans. In addition, upgrading of the Whitby and Oshawa Water Supply Plants are required to satisfy the Safe Drinking Water Act Regulations which came into effect in 2002 and are to be implemented by 2005. 2.0 PREFERRED SOLUTION 2.1 The information package (attachment 1) from the Open House recently held for the EA process details the process, alternative solutions and evaluation that have taken place to date. From the evaluation the preliminary preferred solution is upgrading/expansion of the Whitby WSP with supplementary supply from the AjaX/Pickering water system. The preferred solution does not require any works within Clarington; however it does affect the timing and ability to continue urban growth in Courtice. This preferred solution would ensure adequate water supply and capacity to the Courtice Urban Area including any minor boundary adjustments that may result from the Durham Official Plan review. 3.0 CONCLUSION 3.1 Subject to the comments received as a result of the Open House and the advertised notice the Region intends to confirm a preferred solution and proceed with evaluation of alternative designs for the preferred solution in accordance with the Class EA. Since the preferred solution would ensure adequate water supply and capacity to the Courtice Urban Area staff are recommending that Council endorse the preferred solution. Attachments: Attachment 1 - Information Package, Public Information Centre 633 , WHITBY/OSHA W A/COURTICE URBAN AREAS CLASS ENVIRONMENTAL ASSESSMENT PUBLIC INFORMATION CENTRE NOVEMBER 12, 2003 INFORMATION PACKAGE , tJ ), VH WHITBY/OSHAWA/COURTICE URBAN AREAS CLASS ENVIRONMENTAL ASSESSMENT PUBLIC INFORMATION CENTRE: NOVEMBER 12,2003 INFORMATION PACKAGE INTRODUCTION The Regional Municipality of Durham is undertaking a Class Environmental Assessment (Class EA) to identify the preferred method of providing additional water supply plant capacity for the Whitby, Oshawa and Courtice Urban Areas, These areas are currently supplied with treated water from the Whitby and Oshawa Water Supply Plants. At the present rate of development, demands in these urban areas will exceed the total existing water supply plant capacity in approximately ten years. Additional water supply plant capacity will be required by that time. In addition to the need for additional capacity. the Whitby and Oshawa Water Supply Plants will require operational modifications in the near future to satisfy recently enacted provincial regulations. This Class EA is being undertaken at the present time to ensure that these operational modifications are compatible with any plans to provide additional water supply plant capacity in the future. The Regional Municipality of Durham has retained TSH Consulting Engineers to assist with the undertaking of this Class EA. THE PROBLEM The existing water supply plant capacity available for the Whitby/Oshawa/Courtice urban areas is adequate to satisfy projected growth until 2011 only. After that time additional WSP capacity will be required if growth is to continue in accordance with the Regional Official Plan. Additional treated water storage capacity will be required at the same time to serve the Zone I Water Pressure District Upgrading of the Whitby and Oshawa WSP's is required to satisfy the requirements of the Safe Drinking Water Act, which came into effect in 2002. These upgrading works are to be completed by 2005. New works constructed as part of the upgrading must be compatible with future development of the WSP sites. Planning to determine the optimum configuration of the future plants must be completed prior to design of the major upgrading works. Algae blooms in the sununer months have resulted in rapid filter clogging at the Whitby WSP, requiring increased frequency of backwashing. There is a limited volume of treated water storage available at the Whitby WSP. These factors have resulted in a reduction in the plant capacity during the peak consumption period. A separate Industrial Raw Water pumping system is installed in the former decommissioned plant at the Whitby WSP site. This system supplies raw (untreated) water for process use to three major nearby industries via dedicated pipelines. The existing Industrial Raw Water Supply facilities are in poor condition and lack automatic controls. adequate back-up facilities and standby power. Upgrading and expansion of these supply works is required to ensure a reliable supply to existing customers and to provide additional supply for other interested customers. , b)J 11M Regional Municipality of Durham Additional WSP Capacity for the Whitby/Oshawa/Courtice Urban Areas: Class EA Public Infonnation Centre No.1: Information Package 2 ENVIRONMENTAL ASSESSMENT PROCESS Planning for the project is proceeding in accordance with the Municipal Class Environmental Assessment (Class EA), dated June 2000. The project is designated as a Schedule "c" undertaking, under the Class EA. Schedule "c" projects are those with significant potential impacts which require a complete five phase planning and design process with public involvement, including preparation of an Environmental Study Report (ESR) that is filed for public review. The Class EA process provides for public and review agency input to allow all concerns to be identified and addressed when evaluating the alternative solutions. The purpose of this Public Information Centre is to provide information about the project and to receive public input so that any concerns can be addressed prior to selection of a preferred solution. A l4-day period is allowed following this Public Information Centre for receipt of public comment. ALTERNATIVE SOLUTIONS The alternative solutions available to address the problems are described below: Do Nothing For this alternative, the capacities of the existing Whitby and Oshawa water supply plants would be maintained at their currenr,.rates and no additional capacity would be provided. The maximum population that could be serviced by the existing plants is 300,000. This population is expected to be reached by 2011 and no further development would be possible after that time. The Regional Official Plan (ROP) provides for growth in the Whitby/Oshawa/Courrice urban areas to 378,000 by 2021. This alternative is not consistent with the objectives of the ROP and will not be considered further. Limit Growth The Regional Official Plan (ROP) provides for growth in the Whitby/Oshawa/Courtice urban areas to 378,000 by 2021. The Official Plan has been prepared in accordance with the Planning Act with public input throughout, taking into account the various planning factors, and has been adopted by Regional Council. This alternative is not consistent with the objectives of the ROP and will not be considered further. Demand Management Demand management may be used to achieve more efficient use of water in order to free up capacity to serve additional development. Demand management methods include water metering, user-pay water rate structures, reduction of system leakage, provision of water efficient fixtures, water use restrictions and public awareness programs. The Regional Municipality of Durham has had a comprehensive Water Conservation program in place since the mid 1990's that has led to more efficient water use throughout the Region. This program will continue. This alternative does not adequately address the long-term water demand issues as identified in the opportunity statement and will not be evaluated as a stand.alone solution. The continuance of the Region's Water Conservation program is part of good environmental stewardship and it is t~ '; ...lJ TIll Regional Municipality of Durham Additional WSP Capacity for the Whitby/Oshawa/Courtice Urban Areas: Class EA Public Information Centre NO.1: Information Package 3 recommended that it continue in the future as a component of the preferred alternative for providing additional water supply for the Whitby/Oshawa/Courtice Urban Areas. Upgrade/Expand Existing Water Snpply Plants The net maximum day water supply capacity of the Whitby and Oshawa WSP's during the peak period of smmner water use is 232 MUd (5I.lMIGD). This is adequate to meet projected demands in the Whitby/Oshawa/Courtice urban areas until 2011. Additional WSP capacity will be required by 2011 to satisfy increased demands after that date. The net capacity of the Whitby WSP in the summer is 109 MUd (24MIGD). The plant is supplied by a single 1372mm diameter intake that has an assumed maximum estimated capacity of 230 MUd (50.6MIGD). The Region intends to undertake flow tests in the near future to verify the intake capacity. The Whitby WSP currently has the capability to also supply approximately 9.5 MUd (2IMIGD) of untreated water to a separate raw water system that supplies local industries. The current maximum day demand of the raw water system is approximately 6,7 MUd (1.5MIGD). and recent studies indicate this demaud may ultimately increase to approximately 39.3 MUd (8,6MIGD). The net capacity of the Oshawa WSP in the summer is 123 MUd (27.lMIGD). The plant is supplied by two 750mm diameter and 900mm diameter intakes that have a combined maximum estimated capacity of 135 MUd (29.7MIGD). Expausion of tlle Whitby and Oshawa WSP's are feasible options. For the Whitby WSP, the eXisting site would be able to accommodate an expansion of the WSP to the ultimate required capacity of 327 MUd (72.0MIGD). Por the Oshawa WSP, the existing site provides limited opportunity for expansion, and off-site land acquisition would likely be required to accommodate expansion of the WSP to the ultimate required capacity of 327 MUd (72.0MIGD). The upgrading/expansion works to be provided initially should be designed, at a minimum, to meet the supply requirements for a IO-year design period. i.e, until 2021, assuming expansion in 2011. In accordance with sta!ldard design practice, provision should be made to accommodate future upgrading/expansion works to meet requirements for a 20-year design period, I.e. until 2031, assuming expansion in 2011. With regard to major plant sites, such as the sites of water supply plants, it is important to ensure that the property is large enough to accommodate undetermined future capacity requirements, I.e. beyond 2031. Section 5.3.17 of the Regional Official Plan (ROP) allows the Region to plan for land requirements for major water supply and sanitary sewerage infrastructure (e.g. water supply plants) to provide servicing capacity beyond tlle population targets and related employment targets indicated in tlle ROP Supplement Supply from Adjacent Water Supply System The Harwood Pumping Station provides a connection between the Whitby /Oshawa/Courtice distribution system and the Ajax/Pickering distribution system. Historically, the Harwood PS has been able to transfer a maximum flow of approximately 40 MUd (9 MIGD) westward from the Whitby/Oshawa/Courtice system to the Ajax/Pickering system. However, this was achieved prior to the commissioning of the Ajax WSP and also prior to improvements to the feederrnains on the Ajax/Pickering system, which are likely to impact the maximum flow that the Harwood PS can 65/ VH Regional Municipality of Durham Additional WSP Capacity for the Whitby/Oshawa/Courtice Urban Areas: Class EA Public Information Centre No.1: Information Package 4 transfer. This pumping station does not currently have the capability to transfer flows eastward from the Ajax/Pickering system to the Whitby/Oshawa/Courtice system. The pumping station was designed to allow for modifications to enable it to supply a capacity of approximately 55 ML/d (12 MIGD) either westward or eastward. This option is feasible as an interim measure to allow transfer of surplus water supply in either direction in order to defer a required water supply plant expansion, Develop New Water Supply Plant Since there are three existing sources of supply, with potential for expansion to meet the future requirements after 20 I I, construction of a new WSP is not considered to be a viable alternative at this time. EVALUATION OF FEASIBLE ALTERNATIVES The feasible alternatives selected for detailed evaluation are: Alternative 1: Upgrade/Expand Whitby WSP Alternative 2: Upgrade/Expand Oshawa WSP Altemative 3: Supplement Supply from Ajax/Pickering water system Alternative 1: Upgrade/Expand Whitby WSP For this option the Whitby WSP net capacity would be increased from 109ML/d (24.0MIGD) to 191ML/d (42.0MIGD); the Oshawa WSP capacity would be unchanged. Based upon projected demand growth, this expansion would be required in 20 II and would satisfy demands in the Whitby/Oshawa/Courtice urban areas until 2023. Additional water supply capacity would be required after that time. The works required at the Whitby WSP site to provide this additional capacity would include: . Provision of additionallow lift pumping capacity . Provision of settling tanks ahead of existing filters . Provision of additional flocculation tanks, settling tanks and filters . Addition of GAC to filters for taste and odour control . Provision of additional treated water storage . Provision of additional high lift pumping capacity . Provision of additional standby power facilities for the WSP . Provision of additional backwash treatment facilities Due to the poor condition of the existing Industrial Raw Water Supply system and the potential need to expand the system, this alternative would also include provision of new and expandable Industrial Raw Water pumping facilities, The existing Whitby WSP site area is adequate to accommodate the additional works required to provide a net capacity of 191ML/d (42.0MIGD) and potential future expansion to an ultimate target capacity of 327ML/d (72.0MIGD). Alternatively, the undeveloped lot on the north side of Water Street opposite the Whitby WSP, could be considered for future site expansion. This property is owned by the Town of Whitby. 6.5b TIll Regional Mnnicipality of Dnrham Additional WSP Capacity for the WhitbylOshawalCourtice Urban Areas: Class EA Public Information Centre No.1: Information Package 5 The assumed capacity of the existing intake is 230ML/d (50.6MIGD), subject to confirmation by flow testing to be undertaken by Regional staff For a net plant capacity of 191ML/d (42.0MIGD), the required intake capacity would be as follows: Net plant capacity Process Water Use Gross plant capacity Industrial Raw Water supply Industrial Raw Water supply Total required Intake capacity 191Ml/d 18ML/d 209ML/d 9.5ML/d (existing capacity) l1.5ML/d (future allocation) 230ML/d Additional intake capacity wonld be required after 2028 to accommodate any additional water supply plant capacity expansion. Trunk watermain (feedermain) improvements would be required to convey the additional flows to the Zone 1 Water Pressure District reservoirs. Alternative 2: Upgrade/Expand Oshawa WSP For this option the Oshawa WSP net capacity would be increased from 123MlId (27.1MIGD) to 205ML/d (45.1MIGD); the Whitby WSP capacity would be unchanged. Based upon projected demand growth, this expansion would be required in 2011 and would satisfy demands in the Whitby/Oshawa/Courtice urban areas until 2023. Additional WSP capacity would be required after that time. The works required at the Oshawa WSP site to provide this additional capacity would include: . Provision of additional intake capacity . Provision of additional low lift pumping capacity . Provision of additional flocculation tanks, settling tanks and filters . Addition of GAC to filters for taste and odour control . Provision of additional treated water storage . Provision of additional high lift pumping capacity . Provision of additional standby power facilities for the WSP . Provision of additional backwash treatment facilities Filter backwash water is currently discharged to Lake Ontario untreated. Backwash treatment facilities to remove particulate matter, are to be provided at the Oshawa WSP site as part of the upgrading works to be completed by 2005. A preliminary location for these works has been identified at the south side of the existing water supply plant, The existing Oshawa WSP site area is not adequate to accommodate the additional works required to provide a net capacity of 205M Lid (45.1MIGD) or potential future expansion to an ultimate capacity of 327ML/d (72.0MIGD). There are two potential expansion areas adjacent to the existing site; an undeveloped lot to the north, owned by the Region of Durham and a park on the east side of the existing site, owned by the City of Oshawa. 6)) VII Regional Municipality of Durham Additional WSP Capacity for the Whitby/Oshawa/Courtice Urban Areas: Class EA Public Information Centre No. I: Information Package 6 The existing intake capacity is adequate for a gross plant capacity of 135ML/d (29.7MIGD.For a net plant capacity of 205M Lid (45,IMIGD), the required intake capacity would be as follows: Net plant capacity Process Water Use Gross plant capacit'j Existing Intake Capacity Additional required Intake capacity 205Ml/d 18MLld 223MLld 135MLld 88MLld 111is would require a minimum pipe diameter of 900mm. Trunk watermain (feedermain) improvements would be required to convey the additional flows to the Zone I Water Pressure District reservoirs. Alternative 3: Supplement Supply from Ajax/Pickering Water System The Harwood Pumping Station can be used to transfer surplus flow westward from the Whitby/Oshawa/Courtice water system through a 750nun dia. transmission main to the Ajax/Pickering water system. The pumping station cannot currently transfer flow eastward; however, it was designed to allow for modifications to enable it to supply a capacity of approximately 55 MLld (12.0MIGD) either westward or eastward. Both the Ajax/Pickering and Whitby/Oshawa/Courtice water systems will require additional water supply plant capacity by 2012. Use of the Harwood Pumping Station to transfer water between the systems would allow for deferment of some future plant expansions by up to 8 years. Scenario I: Initial Supplementary Supply from Ajax/Pickering For this scenario the Ajax/Pickering WSP would be expanded by 2012 to a capacity of 327MLld (72.0MIGD). At the same time the Harwood Pumping Station would be modified to pump up to 50MLld (11.0MIGD) eastward from the Ajax/Pickering system to the Whitby/Oshawa/Courtice system. In 2019 the capacity of the Harwood Pumping Station would be reached and the Whitby or Oshawa WSP would be expanded to a minimum combined capacity of 314ML/d (69. I MIGD) , Transfer of water from the Ajax/Pickering system to the Whitby /Oshawa/Courtice system would resume in 2024 to satisfy the supply deficit in that system. By 2029 the Whitby/Oshawa/Courtice system would require additional water supply capacity. Scenario 2: Future Supplementary Supply from Aiax/Pickering For this scenario the Whitby or Oshawa WSP would be expanded by 2012 to a minimum combined capacity of 314MLld (69,IMIGD). Commencing in 2013 surplus capacity would be pumped via the Harwood Pumping Station to the Ajax/Pickering system to satisfy the supply deficit in that system. When the capacity of the existing pumping station is reached, sometime before 2020, the Ajax WSP would be expanded to a capacity of 327MLld (72.0MIGD). By 2024 the Whitby/Oshawa/Courtice system would require additional water supply. At that time the Harwood Pumping Station would be modified to pump up to 50MLld (11.0MIGD) eastward from the Ajax/Pickering system to the Whitby/Oshawa/Courtice system and surplus flow would be pumped to the Whitby/OshawalCourtice system to satisfy the supply deficit in that system. By 2029 the Whitby/Oshawa/Courtice system would require additional water supply capacity. b40 TIH Regional Municipality of Durham Additional WSP Capacity for the Whitby/OshawaJCourtice Urban Areas: Class EA Public Information Centre No,l: Information Package 7 PREFERRED ALTERNATIVE An Evaluation Sunnnary for the three alternatives is attached. The preliminary preferred solution is upgrading/expansion of the Whitby WSP with supplementary supply from the Ajax/Pickering water system. The preferred solution would require the following works: . Upgrading and expansion of the Whitby WSP . Replacement of the Industrial Raw Water Supply System . Upgrading of the Harwood Pumping Station . Provision of new feedermains FUNDING OF COSTS Capital costs for improvements that are required to correct existing deficiencies would be recovered from existing and future users via the user rates, Capital costs for improvements that are required to service future growth would be recovered from new users via development charges, assessed against the developers. FUTURE ACTIVITIES Following the Public Information Centre written comments are invited for incorporation into the planning and design of this project and will be received until November 26, 2003. Subject to comments received as a result oLthis notice the Regional Municipality of Durham intends to confirm a preferred solution and proceed with evaluation of alternative designs for the preferred solution in accordance with the Class EA. A second Public Information Centre will be arranged following evaluation of the alternative designs and prior to selection of a preferred design. SUBMISSION OF COMMENTS Comments should be submitted in writing before November 26, 2003. using the comment forms provided or a separate letter or e-mail message.ifpreferred.to: Mr. LD. Parr, P.Eng. Project Manager TSH Associates 300 Water Street Whitby, Ontario. UN 9J2 Mr. Rich Tindall Project Manager Regional Municipality of Durham Works Department 105 Consumers Drive, Box 623 Whitby, Ontario, UN 6A3 Fax: (905) 668-2051 E-mail: rich.tindall@re~ion.durham.on.ca Fax: (905) 668-0221 E-mail: lparr@tsh.ca E:\PROJECTS\Environmental\52-27403\PIC#1 \Information Package. doc blli 'UH TABLE 5.3 ALTERNATIVE SOLUTIONS EVALUATION SUMMARY AL TERNA nVE 1 AL TERNA TIVE 2 ALTERNATIVE 3: SUPPLEMENT SUPPLY AREA OF IMPACT EXPAND/uPGRADE WHITBY WSP EXPAND/UPGRADE OSHAWA WSP FROM AJAXlPICKERING SYSTEM Technical Environment Capacity Tolal WSP capacity in W/O/C system Total WSP capacity in w/o/e system Total WSP capacity in W/G/C system 314MUd adequate for future needs to 2028 314MUd adequate for future needs to 2028 232MUd adequate for interim period fa 2019 only. Expansion of Oshawa or Whitby plant required then. Natural Environment Water Quality Process wastewater would be discharged to Process wastewater would be discharged to Interim solution only. Minor iniiial impacts. Lake Ontario. Wastewater treatment would Lake Ontario. Wastewater treatment would Future impacts same as Alternatives 1 or 2 be provided to satisfy MOE .requirements for be provided to satisfy MOE requirements for surface water discharge. surface water discharge. Local water quality impacts in Lake Ontario during dredging for new intake. Terrestrial No terrestrial impacts for expansion on Potential expansion site at north is Interim solution only. Minor initial impacts. existing plant site. Some loss of trees if environmentally sensitive open space area. Future impacts same a3 Altematives 1 or 2 vacant site on north side of Water Street is used. Atmospheric Diesel generator exhaust emissions would Diesel generator exhaust emissions would Interim solution only. Minor initial impacts. increase. Exhaust stack to be provided to increase. Exhaust stack to be provided to Future impacts same as Alternatives 1 or 2 maintain air quality at property boundary maintain air quality at property boundary within acceptable limits established by MOE. within acceptable limits established by MOE. Groundwater Dewatering maybe required during Dewatering may be required during Interim solution only. Minor initial impacts. construction of tanks on site and trunk mains construction of tanks on site and trunk mains Future impacts same as Alternatives 1 or 2 off site. off site. Fisheries No in.wafer works required that 'NGuJj affect Construction of new intake would impact fish Interirn solution only. Minor initial impacts. fisheries. rabitat Timiog of CO"st,"ctiC" wou,d avoid Future impacts same as Alternatives 1 or 2 " spawninq period. Compensation in kind for loss of fish habitat would be provided per j DFO permit requirements. Social Environment Recreational Temporary access restrictions on Waterfront Relocation of Waterfront Trail required from Interim solutiGn only. Minor initial impacts. Trail on site during construction. potential plant expansion areas. Loss of Futul e impar:t:s sarna a3 Alternatives 1 or 2 parkland for plant expansion site at east side. Properly No land acquisition required for expansion at Potential expanSion site at north is owned by Interim solution only. Minor initial impacts. existing site. Altemativesite on north side of Region. Potential expansion site at east Future impacts same as Alternatives 1 or 2 Water Street Site owned by Town of Whitby. would have to be acquired from City of Surplus waterfront land on existing site Oshawa. Sites are currently zoned open could be exchanged with Town. SU!'TOunding space. Development may affect area is Industrial Zoning. neighbouring residential property values. Cultural Heritage Potential expansion site has moderate to Potential expansion sites have moderate to Interim solution only. Minor initial impacts. high potential for prehistoric archaeological high potential for historic and prehistOric Future impacts same as Alternatives 1 or 2 resources.. Stage 2 Archaeological archaeological resources Stage 2 Assessment would be required prior to Archaeological Assessment would be construction. required prior to construction. Economic Environment Initial Capital Cost Lowest initial capital cost. Higher initial capital cost due to requirements Initial capital cost for expansion of for additional trunk mains and new intake. AjaX/PIckering WSP similar to expansion of Whitby WSP. Additional capital cost for mocdification to Harwood Pumping Station Future Capital Costs Lower ultimate capital cost than expansion at Higher ultimate capital cost than expansion Future capital expenditure for expansion of Oshawa WSP. at Whitby WSP. Ajax WSP maybe deferred by uptd8 years if implemented in the future. IOptlmum for selected criterion Evaluation Summary.xls Planning Solution '.' !l.~ 1.) .,:L. 11/10/03 ~ j,.,i~._.1 ~ ADDITIONAL WATER SUPPLY CAPACITY FOR. THE WIllTBY /OSHA W A/COURTICE URBAN AREAS CLASS ENVIRONMENTAL ASSESSMENT PUBLIC INFORMATION CENTRE: NOVEMBER 12, 2003 COMMENT FORM I. Do you support the preliminary preferred solution selected (Upgrade/Expand Whitby WSP)? DYes o No 2. Please provide any comments regarding this project in the space below: (Continue overleaf if necessalY) Name: Address: Telephone #: E-mail: Return, by November 26, 2003, to: Mr. LD. Parr, P.Eng. Project Manager TSH Associates 300 Water Street Whitby. Ontario. UN 9J2 Mr. Rich Tindall, P.Eng Project Manager Regional Municipality of Durham Works Department 105 Consumers Drive, Box 623 Whitby, Ontario. UN 6A3 Fax: (905) 668-2051 E-mail: rich.tindall@region.durham.on.ca Fax: (905) 668-0221 E-mail: lparr@tsh.ca ... Ii "\ o .-t J . . (Comments continued from overleaf) bL++ 11M