HomeMy WebLinkAboutTR-57-97 THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
REPORT
i
Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE File # ` c�n' Q
Date: MONDAY, JUNE 16, 1997 Res. #
By-Law# —/
Report#: TR-5 7-9 7 File#:
Subject: TENDER CL97-7, RECONSTRUCTION OF BEAVER STREET NORTH, KING
STREET TO ANDREW STREET, ANDREW STREET AND GEORGE STREET FROM
BEAVER STREET TO 85M EASTERLY, NEWCASTLE
I
Recommendations:
It is respectfully recommended that the General Purpose and
Administration Committee recommend to Council the following:
1 . THAT Report TR-57-97 be received;
2 . THAT Bishop Construction, Stouffville, Ontario, with a total
bid in the amount of $490, 493 . 71, being the lowest responsible
bidder meeting all terms, conditions and specifications of
Tender CL97-7, be awarded the contract for the Reconstruction
of Beaver Street, as required by the .Department of Public
Works;
3 . THAT the total funds required in the amount of $406, 921 . 69
($490, 493 . 71 Contract, plus design, contract administration
and utilities, less Regional portion) , be drawn from Public
Works Account #7205-97003-0261;
4 . THAT the additional funds in the amount of $26, 921 . 69 be drawn
from the Public Works Lot Levy Reserve Fund, Account #1110-
00157-0000;
5 . THAT the attached By-law marked Schedule "A" authorizing the
Mayor and Clerk to execute the agreement be approved; and
6 . THAT the award be subject to the approval of the Region of
Durham.
BACKGROUND AND COMMENT:
Tender specifications were provided by Totten Sims Hubicki
Associates for the Reconstruction of Beaver Street, as required by
the Department of Public Works .
PAPEAD E A 826
THIS IS PiiI-D O 4 RECYCLED PAPER
REPORT NO. : TR-57-97 PAGE 2
TENDER CL97-7
Tenders were advertised in the local papers, as well as the Daily
Commercial News . Subsequently, tenders were received and tabulated
as per Schedule "B" attached.
The Municipality of Clarington' s portion of the total project cost,
including Project Administration, as detailed in the letter from
Totten Sims Hubicki Associates, marked Schedule "C" is estimated at
$406, 921 . 69 . Included in the total tendered price of $490, 493 . 71
is work to be performed on behalf of the Region, as identified in
Schedule "C" for which they will be invoiced as appropriate .
The budget estimate for this project did not include any works on
Andrew Street or George Street, which is why the Municipality of
Clarington chargeable costs exceeds the budget allocation of
$380 , 000 . 00 . The inclusion of works on George Street and Andrew
Street resulted from representations made by residents and a follow
up review by the Mayor and the Director of Public Works .
The required funds will be drawn from Public Works Account #7205-
97001-0261, as identified on Page 137 of the 1997 Draft Capital
Budget .
The additional funds required in the amount of $26, 921 . 69 are
recommended to be drawn from the Public Works Lot Levy Reserve
Fund, Account #1110-00157-0000 .
The subject firm has previously provided satisfactory service for
the Municipality of Clarington. In addition, they have
satisfactorily completed projects for the Town of Aurora, Town of
Markham and the Town of Whitchurch-Stouffville .
The Treasurer has reviewed the funding requirements and concurs
with the recommendation. Queries with respect to department needs,
specifications etc . , should be referred to the Director of Public
Works .
8 � I
REPORT NO. : TR-57-97 PAGE 2
TENDER CL97-7
After further review and analysis of the bids by Public Works,
Totten Sims Hubicki Associates and Purchasing, it was mutually
agreed that the low bidder, Bishop Construction, Stouffville,
Ontario, be recommended for the contract for the Reconstruction of
Scugog Street .
Respectfully submitted, Reviewed by,
Ma "ie Marano, H.BSc . ,AMCT. , W.H. Stockwell,
Treasurer Chief Administrative Officer
StepheA A. Vokes . P.Eng.
Director of Public Works
MM*LB*ld
828
i
Schedule "A"
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW NUMBER 97-
Being a By-law to authorize a contract between Bishop
Construction, Stouffville, Ontario for the Reconstruction of
Beaver Street North, King Street to Andrew Street from Beaver
Street to 85M Easterly, Newcastle,
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY
ENACTS AS FOLLOWS:
1. THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington, and seal with the Corporation Seal,
a Contract between Bishop Construction and said Corporation; and
2. THAT this agreement attached hereto as Schedule "A" form part of this By-law.
By-law read a first and second time this day of June, 1997.
By-law read a third time and finally passed this day of June, 1997.
I
Mayor
Clerk
B2 9
i
I
SCHEDULE 'B"
BID SUMMARY
CL97-7
BEAVER STREET NORTH RECONSTRUCTION
I1I»2 TUTA . B D AMQtJ
Bishop Construction $490,493.71 **
Concord, Ontario
616183 Ontario Inc. o/a Hollingworth Construction $493,5053.40
Gormley, Ontario
C.M. Dipede Group Limited $499,933.96
Concord, Ontario
Ron Robinson Limited $506,474.24
Oshawa, Ontario
LeBrun Northern Contracting Limited $516,717.55
Thunder Bay, Ontario
Miwel Construction Limited $519,000.00
Stouffville, Ontario
Behan Construction Limited $527,873.15
Cobourg, Ontario
B.N. Fenton Construction Limited $555,592.15
Courtice, Ontario
Hard-Co Construction Limited $572,728.20
Whitby, Ontario
Pachino Construction Co. $661,422.64
Stouffville, Ontario
* Error in extension
** Error in calculations
I
i
i
I
I
2 th
I± ANNiveRSARr SCHEDULE "C"
(L1962-1997
513 DIVISION STREET, P.O. BOX 910, COBOURG
a ONTARIO,CANADA K9A 4W4
totten sims hubicki associates (905)372-2121 FAX(905)372-3621
June 5, 1997
Mrs. Lou Ann Birkett
TT
Purchasing and Supply Agent
g !3
Corporation of the Municipality of Clarin ton `' q-T
40 Temperance Street JUN 0 6 1997
BOWMANVILLE, Ontario. L1C 3A6
OF`1 ARINGTON
Dear Mrs. Birkett:
Re: Beaver Street North Reconstruction, King Street to Andrew Street,
Andrew Street and George Street from Beaver Street to 85 m east of Beaver Street,
Newcastle, Municipality of Clarington Contract No. CL97-7
TSH Project No. 12 10589
Tenders for the above project were opened at the municipal offices on Friday, May 30, 1997. The bids
received, inclusive of GST, are summarized as follows:
Contractor Total Bid Atxiount
Bishop Construction $490,493.71 **
Hollingworth Construction $493,505.40
C.M. Dipede Group $499,933.96
Ron Robinson Limited $506,474.24
LeBrun Northern Contracting Ltd. $516,717.55
Miwel Construction Ltd. $519,000.00
Behan Construction Ltd. $527,873.15
B.N. Fenton Construction Ltd. $555,592.15
Hard-Co Construction Ltd. $572,728.20
Pachino Construction Co. $661,422.64
* Error in Extension
** Error in Calculation
Engineer's Estimate $528,500.00
The low bidder's submitted tender has been reviewed and is in order.
ENGINEERS ARCHITECTS AND PLANNERS
831
JUNE 3,1997
MUNICIPALITY OF CLARINGTON, CONTRACT No. CL 97-7
SUMMARY OF PROJECT COSTS ( BASED ON BISHOP'S TENDER UNIT PRICES)
BEAVER STREET NORTH RECONSTRUCTION,KING STREET TO ANDREW STREET
GEORGE STREET AND ANDREW STREET, BEAVER STREET TO 85 m EASTERLY
12-10589
DESCRIPTION OF ITEM ESTIMATED CHARGEABLE TO CHARGEABLE TO REMARKS
GROSS COST MUNICIPALITY OF REGION OF
CLARINGTON DURHAM
CONSTRUCTION
TOTAL SECTION 1-ROADWORKS $319,338.92 $315,652.92 $3,686.00 San.Lateral Costs Chargeable to Regan
TOTAL SECTION 3-WATERMAIN $109,839.70 $109,839.70
TOTAL SECTION 4-GENERAL ITEMS $9,226.72 $6,786.08 $2,440.64 Prorated on Construction Costs
TOTAL SECTION 5-CONTINGENCIES $20,000.00 $20,000.00
SUB-TOTAL CONSTRUCTION $458,405.34 $322,439.00 $135,966.34
DESIGN SERVICES(TO JUNE 6,1997) ; $37,000.00 $26,400.00 $10,600.00 Design Costs Billed Directly to Region of Durham
(INCLUDES PREP.OF TENDER DOCUMENTS)
I
CONSTRUCTION LAYOUT $5,000.00 $3,677.41 $1,322.59 Prorated on Construction Costs
CONTRACTADMINISTRATION I $35,000.00 $25,741.85 $9,258.15 Prorated on Construction Costs
MATERIAL TESTING $1,000.00 $735.48 $264.52 Prorated on Construction Costs
SUNDRIES
RELOCATION OF HYDRO PLANT(ESTIMATED) $1,500.00 $1,500.00
I
RELOCATION OF NATURAL GAS PLANT(ESTIMATED) $4,000.00 $4,000.00
GEOTECHNICAL INVESTIGATION $1,050.00 $1,050.00
AERIAL PHOTOGRAPHY $162.00 $162.00
03 LEGAL SURVEY $446.00 $446.00
L;-j DIGITAL IMAGE SCANNING $180.00 $180.00
SUB-TOTAL SUNDRIES $7,338.00 $7,338.00
CONTINGENCIES(excl.Water-) $9,000.00 $9,000.00
GST LESS REBATE(excl.contingencies) $16,312.30 $11,589.95 $4,722.35
i
TOTAL $569,055.64 $406,921.69 $162,133.95