HomeMy WebLinkAboutEGD-38-03
't;.-" -~
REPORT
ENGINEERING SERVICES
Date:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Ro+ ~4l'il'O~
October 6, 2003
Meeting:
Report #: EGD-38-03
File#:
By-law #:
Subject:
Bowmanville Community Park - Utility Relocation
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report EGD-38-03 be received;
2. THAT approval be granted in the amount of $46,200 plus GST for the Municipality of
Clarington's share of the cost for relocation of the overhead 44kv subtransmission line
between GreenRoad and Martin Road south of Baseline Road, and that the funds be
received from the Public Works Parks Capital Reserve Fund, account # 1110-00157-
0000
Submitted by:
~~f
Anthony Cannella, C.E.T.
Director of Engineering Services
u~s~~,
Nancy . Taylor , CA Reviewed by: Franklin Wu,
Director of FinancefTreasurer Chief Administrative Officer
ASC/PW/jw
September 30, 2003
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T 905-623-3379 F 905-623-9282
715
...... .
REPORT NO.: EGD.38-03
PAGE 2
1.0 BACKGROUND
1.1 As part of the works required for the development of the "Auto Mall" site, generally
bounded by Baseline Road to the north, Hwy. 401 to the south, Waverley Road (Reg.
Rd. 57) to the east and Martin Road to the west, Hydro One Networks Inc. is required to
relocate their existing overhead 44 kv subtransmission line which is located within the
development site. The subtransmission line is situated within an easement which runs
through the lands acquired by the Municipality for the future Bowmanville Community
Park.
During the early stages of the preliminary design phase for of the Bowmanville
Community Park the relocation of the existing hydro line was identified as a requirement
in the park development and was included as an item in the preliminary cost estimate for
the park. Hydro One was consulted during this preliminary design phase with regards to
the relocation of their plant and therefore was aware of the Municipality's future plans at
the park. As a result of their knowledge of the future relocation works within the park site
Hydro One approached Municipal staff to see if the relocation within the park could be
completed in conjunction with the relocation works at the "Auto Mall "site. Hydro One
provided an estimate of $46,200 plus GST to relocate the subtransmission line from the
park site to Baseline Road if done in conjunction with the work on the Auto mall site
(Attachment no. 1).
Staff informed Hydro One that the relocation would typically be completed during the
construction phase of the park, tentatively scheduled for 2004. Staff requested an
estimate of the additional costs that would be incurred if the Municipality deferred the
relocation work until 2004. Attachment no. 2 is a letter from Hydro One stating that there
would be an additional cost of approximately $13,000 (exclusive of GST) over and above
the estimated $46,200 plus GST.
Hydro One has scheduled the relocation of the line for October 15, 2003. Considering
the cost savings that will be realized if the relocation work proceeds in conjunction with
716
'-
REPORT NO.: EGD-38-03
PAGE 3
the "Auto Mall" site, it is staff's recommendation that approval be given for the relocation
work.
The Director of Finance has reviewed the funding requirements and concurs with the
recommendation.
Queries with respect to department needs, specifications, etc. should be directed to the
Director of Engineering.
Attachments:
Attachment 1 - Hydro One Letter Dated September 30, 2003
Attachment 2 - Hydro One Letter Dated September 24, 2003
Interested parties to be advised of Council's decision:
Hydro One Networks Inc.
483 Bay Street, 15th Floor
Toronto ON M5G 2P5
717
..
"5EP-30-2003 09: 56
HYDRO ONE BOWI'U'lNVILLE SC
905 623 0636
P.02/03
r~
hydro~
one
Hydro Oue Networks Iuo. - BowmanvUle Service Cenlrc
913 Crawford Drive, I'eterborongh, Ontario K9J 3Xl
Telephone (905) 623-1071 Fax (905) 623-0636
September30, 2003
The Corporation of the Municipality of Clarington
Attn: Mr, A. S. Cannella
40 Temperance Street
Bowmanville, On Lie 3A6
Dear: Mr, Cannella
Bowmanvllle Community Park. Overhead Hvdro One Line RelocatIon
As requested by Mr. P. Windolf of your office, we have completed a quick re-
estimate of this project based on the anticipated acceptance of your portion of
the cost.
The re-estimated cost to the Municipality of Clarington to relocate this line from
their property to the Baseline Road allowance is $46,200 plus GST. This is an
estimate only and our invoice will be based on the actual costs incurred. This
estimate is valid for 60 days. Please forward a Purchase Order or Letter of
Acceptance (our invoicing can be deferred until early 2004), in the amount of
$46;200,00 plus GST.
This estimate is also based on the relocation of the portion of our line on the
Bowmanville AutoMall property to the Baseline Road allowance. Should that
relocation not take place, our cost estimate to you will require adjusting.
. This cost estimate assumes a project approval as discussed, the successful
acquisition of one property easement from the Municipality, and a lead-time
of 60 days for ordering material, assigning resources, etc. Based on your
acceptance of this, and assuming normal crew complement and deployment,
we will endeavor to complete this project between 60 and 90 days after the
issuance of your Purchase Order, or letter of acceptance.
. If any of this is not acceptable to you, please discuss with us.
. It may be possible to meet an earlier completion date by using an alternate
complement and deployment of crews. Such an alternative plan will require
re-calculation of our cost estimate to include additional labour costs.
(10
ATTACHMENT NO.: 1
REPORT NO.: EGD-38-03
'.
SEP-30-2003 09:56
HYDRO ONE BOWMANUILLE SC
905 623 0636
P.03/03
hydroe1
one
Hydro One Networks Inc. - Bowmanvllle Service Centre
913 Crawford Drive. Peterborougb. Ontario K9J 3Xl
Telepbone (90S) 623-1071 Fax (90S) 623-0636
This information is provide to assist in project timeline definition and in the
interest of avoiding project completion date disputes.
We will not agree to proceed with work unless we arrive at agreeable completion
dates that are achievable and meet the requirements of both parties. Failure to
reach agreement on achievable dates will lead us to opt for the dispute
resolution processes available.
As the park property is developed, it could be serviced by the 44 kv line on
Baseline Road or Green Road, if you require a 1000 amp or greater service. It
could also be serviced from the 27.6 kv line on Baseline Road if your
requirements are less. Should you require a 27.6 kv service from Green Road,
the approximate cost to extend our line to your entrance is $8,000.00 .
Depending on the nature of your loading, Hydro One may provide a capital
contribution towards the construction of that line.
We trust that this information will be of assistance to you.
Yours truly,
~~~
J,M. (Jim) Hisson
Area Distribution Engineering Technician
JMH
! 1 9
TOTAL P.03
~P-25-03 THU 05:18 PM
oEP-25-2003 07:35
TSH COBOURG FAX NO,
HY~ ONE BOlM'INU1LLE SC
9"S 623 1:l636
p, 02
p, 02/02
hydr8~
ne
Hydro Oft. Networks Inc. - BOWIWIAVWC Service CeIllre
913 Crawford Drlv., Petorborou;h. Ontario K9J 3Xl
TO.lphau (905) 623-1071 Fa< (905) 623-OQ6
September 24, 2003
Totten Sims Hublckl Assodates
Attn: Mr, R, Albright
513 Division Street
Cobourg, On K9A SG6
Dear: Mr. Albright
lowmanville COmmunitY Park.. Overhead HYdro Ona Ling Rcdneatlon
Further to our conversation of September 23, 2003, I offer you the following
information.
Hydro One is now prepared to commence the relocetion of our overhead +lkv
subtransmission line between Martin Road and Waver1ey Road, known as the
Bowmll!lvllle AutoMall.
The portion of the overhead 44kv subtransmission line which crosses the Municipality of
Clartngton's property between Green Road and Martin Road would be best felocated In
conjunction with the previously stated relocation work, The completion of th_ two
projects simultaneously would result In cost savings to all parties concerned and afford
better utlllzation of resources. Should we complete your relocation work at a later date
there would be roughly a $13,000 increase over the cost quoted to you on August 20,
2003.
The relocation of our line from the Bowrnanvtlle AutoMal1 property has been hard
scheduled for October 15, 2003. If we do not recelve contlrmatlon from the Munldpallty
of Clarlngton accepting their portion of the cost to relocate the line which Is on their
property by October 15/ 2003 we will have no alternabVe but to complete that portion
separately in the future. The price quoted to you on August 20, 2003 would no longar
~ valid and a re-estimation of the cost would be necessary.
If you have any questions please contact me at your convenience.
Yours truly,
o/~d7~
J .M. (JIm) Hlsson
Area D1strlllUtlontEng1neering Technician
JMH:
ATTACHMENT NO.: 2
REPORT NO.: EGD-38-03
I r (
, i;J