REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date:
June 20, 2005
Report #:
COD-035-05
File#_
NJ/I-308'05
By-law#~/39
Subject:
CL2005-15 Sidewalk Construction, Various Locations
Recommendations:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report COD-035-05 be received;
2. THAT Trisan Construction, Schomberg, Ontario with a total revised bid in the amount of
$366,644.82 (Plus G.S.T.), being the lowest responsible bidder meeting all terms,
conditions, and specifications of Tender CL2005-15, be awarded the contract for the
Sidewalk Construction, Various Locations, as required by the Engineering Department;
3. THAT Part C - Enniskillen Sidewalks in the amount of $27.681.27 be removed from
Project #5800-8320-05102;
4. THAT Part F - south side of Highway 2 from Trulis Road to Courtice Road in the amount
of $98,384.97 be removed from Project #5800-8320-05101;
5. THAT the total funds required in the amount of $512,133.76 ($492,711.06 tender less
$27,681.27 for Enniskillen sidewalks, less $98,384.97 for south side of Highway 2 plus
contingencies, consulting and utilities) be drawn from Engineering 2005 Capital Projects
#5800-8320-05102 ($196,072.73) and #5800-8320-05101 ($308,615.03) and the Roads
Contribution Reserve Fund.
REPORT NO.: COO-03S-QS
PAGE 2
6. THAT the attached By-law marked Schedule "A" authorizing the Mayor and the Clerk to
execute the necessary agreement be approved.
Submitted by:
~p
. Marano, H.B.Sc., C.M.O.
Directo of Corporate Servic
Reviewedbd~~
Franklin Wu,
Chief Administrative Officer
A.S. Cannella, C.E.T.
Director of Engineering Services
MM/LAB/ld
REPORT NO.: COO-Q3S-QS
PAGE 3
BACKGROUND AND COMMENT
Tender specifications were provided by Totten Sims Hubicki Associates for the Sidewalk
Construction, Various Locations, as required by the Engineering Department.
Tenders were advertised in local papers, as well as electronically. Subsequently, tenders were
received and tabulated as per Schedule "B" attached.
Estimated project costs are as shown on the attached cost apportionment provided by Totten
Sims Hubicki marked Schedule "C". Based on the total project cost of $223,754.00 for the
sidewalk replacement work and the 2005 Capital Budget amount of $200,000.00 for Project
#5800-8320-05102, this portion of the contract is $23,754.00 over budget. In order to meet the
allocated budget for this work, it is recommended that Part C - Enniskillen Sidewalks, be
removed from the contract resulting in a $3,927.27 surplus for the replacement portion of the
contract.
The apportionment also shows the total project cost for Part F - Highway 2 Sidewalks, Courtice
is $407.000.00 is $97,000.00 over the 2005 Capital Budget amount of $310,000.00 allocated to
Project #5800-8320-05101. In order to meet the available budget it is recommended that the
portion of the works on the south side of Highway 2 from Trulls Road to Courtice Road be
removed from the contract which amounts to $98,384.97 resulting in a $1.384.97 surplus for the
portion of the sidewalk.
The three low bidders are in concurrence with this revision to the contract.
The total project cost, including Project Administration, and costing allocation is as detailed in
the cost apportionment from Totten Sims Hubicki Associates and will be provided from the 2005
Capital Project #5800-8320-05102 for Sidewalk Replacement, Various Locations ($196,072.73)
and from the Highway 2, Courtice Sidewalk Construction Project #5800-8320-05101
($308,615.03). For the sidewalk associated with development of Courtice Corners (south-east
corner of Highway 2 and Courtice Road), funds in the amount of $7,446.00 are recommended to
be financed from the Roads Contributions Reserve Fund. These funds have already been
received from the developer. For ease of processing this will be incorporated into Project #5800-
8320-05102.
REPORT NO.: COO-Q3S-QS
PAGE 4
The low bidder has previously performed satisfactory work for the Municipality of Clarington.
The Director of Finance has reviewed the funding requirements and concurs with the
recommendation. Queries with respect to department needs, specifications, etc., should be
referred to the Director of Engineering.
After further review and analysis of the bids by the Engineering Department, Totten Sims
Hubicki Associates and Purchasing, it was mutually agreed that the low bidder, Trisan
Construction, Schomberg, Ontario, be recommended for the contract for the Sidewalk
Construction, Various Locations.
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1 C 3A6 T(905)623-3379 F (905)623-4169
Schedule "An
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW 2005-
Being a By-law to authorize a contract between the
Corporation of the Municipality of Clarington and Trisan
Construction, Schomberg, Ontario, to enter into agreement for
the Sidewalk Construction, Various Locations.
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY ENACTS AS
FOLLOWS:
1. THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington and seal with the Corporation Seal, a
contract between, Trisan Construction. Schomberg, Ontario, and said
Corporation; and
2. THAT the contract attached hereto as Schedule "A" form part of this By-law.
By-law read a first and second time this day of
,2005.
By-law read a third time and finally passed this
day of
,2005.
John Mutton, Mayor
Patti L. Barrie, Municipal Clerk
Clw:..ilJglon
Municipality of Clarington
SCHEDULE "B"
BID SUMMARY
Tender CL2005-15,
Sidewalk Construction, Various Locations
Trisan Construction
Schomber ,ON
Brennan Paving
Markham, ON
Miwel Construction
Stouffville, ON
Aloia Bros. Concrete Contractors Limited
Toronto, ON
Ferma Road Construction
Mississau a. ON
Elirpa Construction
Pickerin ,ON
$492,711.06
$493,099.46
$537.703.16
$575,503.61
$616,679.70
$667,423.97
II
VII
Totten Sims Hubicki Associates
513 Division Street,
Cobourg, Ontario, Canada K9A 5GB
19051372-2121 Fax: (9051 372-3621
E-mail: cobourg@tsh.ca www.tsh.ca
engineers
architects
planners
June 10, 2005
SCHEDULE "C"
Ms. Lou Ann Birkett, CPP, AMCT
Purchasing Manager
Corporation of the Municipality ofClarington
40 Temperance Street
BOWMANVILLE, Ontario. LlC 3A6
Dear Ms. Birkett:
Re: Highway #2 Sidewalks, Centerfield Dr. to Trulls Rd. - N. Side, Trulls Rd. to Courtice Rd. -
S. Side, Courtice
2005 Sidewalk Rehabilitation - Various Locations
Contract CL2005-15, Municipality of CIa ring ton
Tenders for the above project were opened at the Municipal Offices on Thursday June 2, 2005 at 2:00
p.m. A list of the bids received is provided in the table below. All numbers are exclusive ofGST.
BIDDER
TOTAL BID AMOUNT
I
Trisan Construction, Schomberg, ON
Brennan Paving & Construction, Markham, ON
Miwel Construction Ltd., Stouffville, ON
$492,711.06*
$493,099.46*
$537,703.16*
$575,503.61*
$616,679.70
$667,423.97*
Aloia Bros. Concrete Contractors, Toronto, ON
Ferma Road Construction Ltd., Mississauga, ON
ELIRP A Construction, Pickering, ON
* Amended total ~ extension error.
The low bidder's tender has been checked and is in order. Trisan Construction has previously undertaken
projects for the Municipality of Clarington, most recently Contract CL2004-30 which was also sidewalk
construction at various locations. The work was performed to an acceptable standard although restoration
work was slow at times resulting in complaints from residents. This contract allows for 50% payment of
sidewalk upon placing, and the remainder upon completion of restoration works which should ensure a
timely restoration of disturbed areas. All restoration issues from CL2004-30 were eventually addressed to
our office's satisfaction.
Estimated project costs based on Trisan's low bid are as shown on the attached Cost Apportionment.
Based on the total project cost of$223,754.00 for the sidewalk replacement work and the 2005 Capital
Budget amount of $200,000 for Project lD 5800-8320-05102, this portion of the contract is $23,754.00
over budget. In order to meet the allocated budget for this work it is recommended that Part C -
Enniskillen Sidewalks be removed from the contract resulting in a $3,927.27 surplus for the replacement
portion of the contract.
Ms. Lou Ann Birkett
June 10. 2005
2
The apportionment also shows the total project cost for Part F - Hwy 2 Sidewalks, Courtice, is
$407,000.00 which is $97,000 over the 2005 Capital Budget amount of$31O,000 allocated to Project ID
5800-8320-05101. In order to meet the available budget it is recommended that the portion of the works
on the south side ofHwy. 2 from Trulls Road to Courtice Road be removed from the contract which
amounts to $98,384.97 resulting in a $1,384.97 surplus for this portion of the sidewalk.
The costs for the sidewalk required for the Courtice Comers development on the southeast comer of
Courtice Road and Highway 2 match the allocated funds ofS7,446 from Account # 514-X-X-X-6760.
Based on both of the above noted deletions from the replacement and new sidewalk portions of the
contract and the past performance of the contractor it is recommended that the tender in the amount of
$366,644.82 (exclusive ofG.S.T.) be awarded to Trisan Construction of Schomberg, Ontario
Please proceed with the award of this Contract which is scheduled for completion by Friday,
September 2, 2005.
Should you have any questions regarding this matter, please contact the undersigned.
::::;;/b!-
' r :~/ ~
Ron Albnght, P.Eng.
Project Engineer
RA/ym
P/29469/Cotresp,fJender Re~ull~.doc
pc: A.S. Cannella, Director of Engineering Services
Leslie Benson, Manager, Transportation and Design
Jennifer Welsh, Clerk II
Norm Clark, C.E.T., Manager of Construction
Fred Horvath, Director of Operations
Kaye Rand, Operations, Accounting Clerk II
IIH
Municipality of Clarington
SIDEWALK REHABILITATION AND NEW CONSTRUCTION
VARIOUS LOCATIONS
Cost Apportionment For Low Bid submitted by Trisan
Contract CL2005-15
June 10, 2005
T.S.H. Project: 12-29469 & 12-29447
Description Total Clarington - Engineering Services Comments
Sidewalk Associated
with Devleopment of Highway #2
Sidewalk Replacement Courtice Corners, Sidewalk Construction,
Various Locations (s.e. corner of Courtice
Hwy 2 and Courtice
R".1
Clarington Project ID/Account No. 5800-8320-05102 514-X-X-X-6760 5800-8320-05101
Part 'A' - BOWMANVILLE SIDEWALKS $ 67,179.76 $ 67,179.76
Part 'B' - COURTICE SIDEWALKS $ 29,504.31 $ 22,058.31 $ 7,446.00
Part 'C' - ENNIS KILLEN SIDEWALKS $ 27,681.27 $ 27,681.27
Part 'D' - KENDAL SIDEWALKS $ 37,690.70 $ 37,690.70
Part 'E' - BURKETON SIDEWALKS $ 19,702.77 $ 19,702.77
Part 'F' - HIGHWAY 2 SIDEWALK, COURTICE $ 310,952.25 $ 310,952.25
Sub-Total Construction $ 492,711.06 $ 174,312.81 $ 7,446.00 $ 310,952.25
TSH Project Number 12-29469 12-29447
Design and Tendering to May 28, 2005 $ 23,349.99 $ 6,302.87 $ 17,047.12 Estimated
Estimated Contract Administration
(TSH # 12-29469) from May 29, 2005 $ 48,500.00 $ 18,500.00 $ 30,000.00 Estimated
Prorated Based on Low Bid
Utility Relocations $ 24,000.00 $ 24,000.00
Contingencies $ 49,638.95 $ 24,638.32 $ 25,000.63 Estimated
Estimated T olal Project Costs $ 638,200.00 $ 223,754.00 $ 7,446.00 $ 407,000.00
Budget Amount $ 517,446.00 $ 200,000.00 $ 7,446.00 $ 310,000.00
Estimated Budget Surplus/Deficit -$120,754.00 -$23,754.00 -$97,000.00