REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE Fl 'is. Q-~
Date: September 8, 2003
Report #: COD-36-03
File#_
GPR - 35<+-03
By-law # ac03 - \3l:l, \~\
;-\~~
Subject:
TENDER AWARDS SUMMER COUNCIL BREAK.
Recommendations:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1, THAT Report COD-36-03 be received;
2. THAT the attached By-laws, marked Schedules "A", "B" and "C" authorizing
the Mayor and Clerk to enter into the necessary agreements be approved.
Submitted by,
arle Marano, H.B,Sc., C,M,O.
Directo of Corporate Services
Reviewed bY:O ~ ---3 ~
Franklin Wu,
Chief Administrative Officer
MM\NT\LAB\km
1212
G: \R E PORTS\2002RE\CO 0.3 G.03. TEN DE RA'N AR OS.COll N elL BRK .(Joc
REPORT NO.: COD-36-03
PAGE 2
BACKGROUND AND COMMENT
In accordance with Resolution #GPA-355-01, the Administrator and the Director of
Corporate Services and/or the Director of Finance awarded the following
Tenders/Contracts during the July/August Council Break:
A summary outlining the bids and awards is attached marked Schedule "0".
1. RFP2003-7, Supply & Installation of Playground Equipment
2. CL2003-15, South Courtice Soccer Field
3. CL2003-16, Sidewalk Construction Various Locations
4. CL2003-19, The Supply, Delivery & Installation of a Hoist
5. CL2003-20, The Supply & Delivery of (2) Two Handi Transit Vehicles
6, CL2003-23, Bowmanville Creek Valley Recreation Trail
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T(905)623-3379 F (905)623-4169
1213
Schedule "A"
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW 2003-
Being a By-law to authorize a contract between the
Corporation of the Municipality of Clarington and Dol Turf
Restoration, of Innisfil, Ontario, to enter into agreement for the
Soccer Field Construction at South Courtice Park,
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY ENACTS AS
FOLLOWS:
1. THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington and seal with the Corporation Seal, a
contract between, Dol Turf Restoration, of Innisfil, Ontario, and said Corporation;
and
2, THAT the contract attached hereto as Schedule "A" form part of this By-law.
By-law read a first and second time this day of
,2003.
By-law read a third time and finally passed this day of
,2003.
John Mutton, Mayor
Patti L. Barrie, Municipal Clerk
1214
Schedule "B"
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW 2003-
Being a By-law to authorize a contract between the
Corporation of the Municipality of Clarington and Trisan
Construction, of Schomberg, Ontario, to enter into agreement
for the Sidewalk Construction, Various Locations.
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY ENACTS AS
FOLLOWS:
1, THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington and seal with the Corporation Seal, a
contract between, Trisan Construction, of Schomberg, Ontario, and said
Corporation; and
2. THAT the contract attached hereto as Schedule "A" form part of this By-law.
By-law read a first and second time this day of
,2003.
By-law read a third time and finally passed this day of
,2003.
John Mutton, Mayor
Patti L, Barrie, Municipal Clerk
1215
Schedule "C"
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW 2003-
Being a By-law to authorize a contract between the
Corporation of the Municipality of Clarington and Elirpa
Construction and Materials Ltd, of Pickering, Ontario, to enter
into agreement for the Bowmanville Creek Valley Recreational
Trail.
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY ENACTS AS
FOLLOWS:
1. THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington and seal with the Corporation Seal, a
contract between, Elirpa Construction and Materials Ltd. , of Pickering, Ontario,
and said Corporation; and
2, THAT the contract attached hereto as Schedule "A" form part of this By-law.
By-law read a first and second time this day of
,2003.
By-law read a third time and finally passed this
day of
,2003.
John Mutton, Mayor
Patti L. Barrie, Municipal Clerk
1216
G:\REPOR TS\2002RE\COD-36-03- TENDERAW ARDS-COUNCILBRK.doc
1. RFP2003-7,
SUPPLY & INSTALLATION OF PLAYGROUND EQUIPMENT
A contract was awarded to Henderson Recreation Equipment Ltd., Simcoe, Ontario, for
the Supply and Installation of Playground Equipment.
Tenders were publicly advertised and issued with bids being submitted as per Schedule
"A" attached,
Funding is as identified on the attached Schedule "B" and includes both a 2000 to 2002
and 2003 Operations Capital Budget allocation.
The Request for Proposal specifications included evaluation criteria as follows:
. Durability
. Warranty
. Compliance with instructions
. Pricing
. References
. Creativity
. Number of users accommodated
. Deliveryllnstallation time frames
. Number of play events
. Appearance
. Quality
. Safety
Upon Review of the bids, it is staffs opinion that the creativity and conceptual plan, offered
by Henderson Recreation exceeds that which is offered by the other bidders, It is
therefore respectfully recommended that parts A, B, C, D and E be awarded to the subject
firm.
The Director of Finance has reviewed the funding requirements and concurs with the
recommendation. Queries with respect to department needs, specification, etc., should be
directed to the Director of Operations.
The low bidder has provided satisfactory service to the Municipality of Clarington in recent
years.
121 7
SCHEDULE A
BID SUMMARY
RFP2003-7, SUPPLY & INSTALLATION OF PLAYGROUND EQUIPMENT
TOTAL BID AMOUNT
PART C PART D
BIDDER
Belair Recreational Products Inc.
Paris, ON
Little Tykes
Paris, ON
Henderson Recreation Equipment Ltd.
Simcoe, ON
ABC Recreation Ltd,
Paris, ON
rv * Bid Amended - Addition Error
=
PART A
PART B
SUBTOTAL
Bid rejected - Incomplete, did not bid on all items.
$39,906,34 $29,763.02 $132,230,55 $24,640.06
10 -15 users 20 - 25 users 15 - 20 users
$39,103,04 $26,923,21 $151,058,03 $28,785,62
50 - 51 users 20 - 25 users 27 - 30 users
$32,089,16 $45,891.48 $171,573.30 $35,096,85
19 users 22 users 22 users
.,
SCHEDULE B
RFP 2003-7; SUPPLY & INSTALLATION OF PLAYGROUND EQUIPMENT
FUNDING:
CAPITAL BUDGET
YEAR AMOUNT
2003 $90,000
2002 - Page 423 $38,000
Park Furniture (7603-1-516)
2001 - Page 171 $14,000
Park Furniture (7603-100-516)
2000 - Page 214 $61,700
Park Furniture (7603-1-505)
ACCOUNT
8620-03100-1401
111 0-00157-0000
1110-00157-0000
2900-00001-0000
TOTAL
$203.700
1219
2. CL2003-15, SOUTH COURTICE SOCCER FIELD
A prequalification request and publicly advertised and issued with contractors being prequalified
as follows:
Dol Turf Restoration Ltd,
Innisfil, ON
Melfer Construction Inc,
Scarborough, ON
Mopal Construction Ltd,
Gormely, ON
Ron Robinson Ltd,
Bowmanville, ON
Rutherford Contracting Ltd.
Gormely, ON
Subsequently, a tender was issued with the prequalified bidders being invited to bid. Tenders
were received and tabulated as per Schedule "A" attached, The required funds, in the amount
of $312,081.71 ($288,081.71 + $24,000,00 consulting and contract administration), will be
provided from Capital Budget Account #8610-03101-1401 and are within the $350,000,00
allocation.
The Director of Finance has reviewed the funding requirements and concurs with the
recommendation. Queries with respect to department needs, specifications, etc., should be
directed to the Director of Engineering Services.
The low bidder has substantial similar experience and has provided satisfactory service to the
City of Vaughan and the City of Mississauga.
A recommendation from the project consultant is attached, marked Schedule "B".
1220
SCHEDULE "A"
BID SUMMARY
CL2003-15
SOUTH COURTICE PARK SOCCER FIELD CONSTRUCTION
I Bidder I Total Bid Amount (
Dol Turf Restoration Ltd. $288,081,72 **
Innisfil, ON
Mopal Construction Ltd, $382,939.00
Gormely, ON
Ron Robinson Ltd, $384,608,72 *
Bowmanville, ON
* Bid amount amended
** Bid amount amended, items 8.1 and 9.1 priced in sq. metres rather than linear meters,
1221
, "
, SCHEDULE "B"
Victor Ford and Associates Inc · Landscape Architects ·
525 Adelaide Street West, Suite 402. Toronto. Ontario M5V 1T6 Tel: (416) 703-0081 Fax: (416) 703-0083 e-mail: design@vfa.on.ca
,
June 16,2003
Our file: 0314
Lou Ann Birkett, C.P.P., A.M.C.T.
Purchasing Manager
The Municipality of Cia ring ton
40 Temperance Street
Bowmanville, Ontario
LlC 3A6
~IECCJE['VIE~
JUN 1 7 2003
Dear Ms. Birkett,
MUNICIPALITY OF CLARINGTON
PURCHASING DEPARTMENT
Reference: Tender CL2003-15, Letter of Recommendation
Soccer Field Construction
South Courtice Park
The Municipality of Clarington
We have reviewed the three tenders received for the above project. We have provided a spreadsheet
to compare the bids for each of the component items. The corrected totals for each bid including
GST are as follows:
Dol Turf Restoration Ltd.
Innisfil, Ontario
$288,081.71
Mopal Construction Ltd.
Gormely, Ontario
$382,739.00
Ron Robinson Ltd.
Bowmanville. Ontario
$436,527.78
The detailed breakdown spreadsheet for each tender is as follows:
1222
lof3
:-.1 SCHEDULE "B"
f'. .
~ ,. ~
.'
South Courtice Soccer Field Construction Tender Form Comparison
Dol Turf Mopal
Restoration Construction Ron
Item Description of Contract Items LId LId Robinson LId
Preparation
General Requirements, mobilization and
1,1 demobilization $4,500.00 $6,000.00 $7,735,00
Supply, install and remove construction fence around
1.2 work area $1,584.00 $5,940.00 $5,148,00
Sub-total $6,084.00 $11,940.00 $12,883.00
Topsoil/ Sand and Fine Grading
2.1 Supply and install topsoil/ sand mix $79,200,00 $99,000.00 $48,262,50
2,2 Provide fine grading of soccer field $3,300,00 $4,125.00 $24,667.50
Su b-total $82,500.00 $103,125.00 $72,930.00
Sub-Grade Drainage
Suppiy and install primary and secondary sub-grade
3.1 drainage systems $26,450 $34,600,00 $83,327.56
Sub-total $26,450.00 $34,600.00 $83,327.56
Irrigation
4.1 Supply and install irrigation system for the soccer field $15,634,00 $14,200,00 $36,750.00
Sub-total $15,634.00 $14,200.00 $36,750.00
Electrical/ Lighting
Supply and make complete electrical connection of 8
5.1 sports field light standards and luminaries $87,000,00 $136,400,00 $95,841.62
Sub-total $87,000.00 $136,400.00 $95,841.62
Miscellaneous Features
6.1 Supply and install one 5,tier aluminum bleacher $4,000,00 $5,200,00 $4,893,01
6.2 Supply and install two soccer goal posts with footings $4,500,00 $2,800.00 $3,583,74
6.3 Supply and install two player benches $1,500.00 $1,400,00 $1,304.89
6.4 Supply and install three garbage receptacies $2,290.00 $2,000.00 $2,362,31
6,5 Supply and install 'Permaline' permanent lines $6,320.00 $7,505.00 $7,050,75
Supply and install four corner flags and two middle
6,6 field flags $600,00 $517,00 $1,314,23
Sub-total $19,210.00 $19,422.00 $20,508.93
Fencing
7,1 Supply and install galvanized chain link fence 1.2m $5,917,00 $4,880.00 $4,978.82
7,2 Supply and install galvanized chain link fence 1,8m $6,527,95 $6,050.00 $5,730.56
7,3 Supply and install galvanized chain link fence 3,Om $1,774.80 $1,968,00 $1,694.40
Sub-total $14,219.75 $12,898.00 $12,403.78
1223
20f3
"
.111
tt'l ~
"i::;i~ SCHEDULE "B" J
i,..,f,):':,:", . _~________"'____
Seeding
8,1 Supply, plant, establish, maintain and reseed area
Sub-total
$3,712.50
$3,712.50
$4,125,00
$4,125.00
$5,610.00
$5,610.00
">,-
SOdding
Supply, plant, establish and maintain areas to be
9,1 sodded
Sub-total
$1,925.00
$1,925.00
$5,390.00
$5,390.00
$4,042.50
$4,042.50
Sports Turf Maintenance
Supply materials and perform on-going maintenance
10,1 operations
Sub-total
$11,000.00
$11,000.00
$14,100,00
$14,100.00
$13,650.00
$13,650.00
Allowances
11.1 Compaction and materials testing allowance
Sub-total
$1,500.00
$1,500.00
$1,500.00
$1,500.00
$1,500.00
$1,500.00
Total Items 1.0 through 11.0
Total $269,235.251" $357,700.00l $359,447.391
I
7% Federal Goods and Services
Total
$18,846.47 $25,039.00 $25,161.32
$288,081.721 $382,739.001 $384,608.711
ITOTAL CORRECTED BID PRICES
Dol Turf Restoration Ltd. has a good reputation for the construction of similar tournament soccer
fields across Ontario. We discussed their prices with Gord Dol of Dol Turf Restoration Ltd. after
copies of their bids were forwarded to us. They are comfortable with their prices as listed above.
We recommend that this tender be awarded to Dol Turf Restoration Ltd. in the amount of
$269,235.25 plus $18,846.47 GST for a Total of $288,081.71 including GST.
Please call me if you have any questions.
Thank you and best regards.
Yours truly,
VICTOR FORD AND ASSOCIATES INC
Victor S. Ford OALA, CSLA, ASLA
Principal
C: Mr. Peter Windolf
Manager of Park Development
Town of Clarington
1224
30f3
3. CL2003-16,
SIDEWALK CONSTRUCTION VARIOUS LOCATIONS
A contract was awarded to Trisan Construction, Schomberg, Ontario, for a total bid price of
$331,779.52.
Tenders were publicly advertised and issued with bids being submitted as per Schedule
"A" attached.
As the total costs associated with this contract exceed the budgets allocated to the respective
parts, the value of the contract had to be reduced. See details on Schedule "B".
Funding is included in the 2003 Engineering Capital Budget and as per the funding cost
apportionment provided by Totten Sims Hubicki in Schedule "B" attached, each of the three
projects is within the budget allocation,
The Director of Finance has reviewed the funding requirements and concurs with the
recommendation, Queries with respect to department needs, specifications, etc., should be
directed to the Director of Engineering Services,
The low bidder has provided satisfactory service to the Municipality of Clarington in recent
years,
1225
SCHEDULE "A"
BID SUMMARY
TENDER CL2003-16
SIDEWALK CONSTRUCTION, VARIOUS LOCATIONS
I Bidder I Total Bid Amount I
614128 Ontario Ltd. a/a Trisan Construction $437,294.02
Schomberq, ON
Brennan Paving & Construction Ltd. $560,825.18
Markham, ON
1226
.JUL-15-03 rUE 12:37 PM TSH COClOUI{G
l-AX NO,
p, U1
..
Tnt
Totten Sims Hubickl Associates
513 Division Street,
CoboLlrg, Onl.rio, C.nada K9A 5G6
(90S) 372.2121 Fax: 1905) 372-3621
E-mail: cobourg@tsh.ca www.rsh.ca
engineers
architects
planners
July 9, 2003 (revised July 15,2003)
SCHEDULE liB"
Ms. Lou Ann Birkett. CPP, AMCT
Purchasing Manager
Corporation of the MunicIpalIty of ClaTingtoll
40 Temperance Street
BOWMANVILLE, Ontario. LIC 3A6
Dear Ms. Birkett:
Re: Contract No. CL2003-16, Sidewalk Construction Varioa. Locations
Municiplllity of Clarington
Tenders for the above project were opened at the Municipal Offices on Friday June 27, 2003 at 2:00
P. M, The bids received, inclusive of GST, are summarized as follows:
BIDDER TOTAL BID AMOUNT
614128 Ontario Ltd. O/A 'frisan ConstrUc[ion Schomberg, Onlario $437,294.02
Brennan Pavine and Construction Ud., Markham, Ontario $560,825.18
During the preliminary review of Part" A" of this project, which was undertaken at the time of budget
preparation, it was estimated that the construction of a semI-urban cross-section with eurb and gutter
and a storm sewer system would be required to accommodate improvements to the sidewalks in the
area. For this reason for the works were identified as a storm sewer project. At the detailed design
stage for Part "A" it was determined that the improvements could be achieved without the need of a
complete storm sewer and the majority of the work was made up of sidewalk construetion and
replacement.
Tho low bidder's tender has been checked and is in order. As the total eosts assoeiated with this
eontract exceed the budgets allocated to the respective Part~, the value of the contract has had to be
reduced. A majority of this reduction was obrained by removing the north section of sidewalk in Part
" A" _ Ilnniskillen. between Werrydale Drive and Virtue Court on the west side of Old Scugog Road.
The potential for this removal, which amounts to a reduction of $71,607.48 (excl. G.S.T.) from Pari
"A", was known to the bidders durIng Tendering as it was noted in Clausa19 of the Instructions to
Tenderers. Additional modifications in the scope of the work for Parts "B" and "e", discussed with
the Low Bidder after tendering, resultoo in roouctions of $11,040.40 (excl. G.S,T.) and $15,963.80
(exc!. G. S. T .), respectively.
Revised quantities have been forwarded and reviewed by Trisan Construction and the amended tender
is acceprab Ie to the Contractor.
The tender, all associated costs and available budget amounts are summarized 011 the attached Cost
Apportionment, which also includes applicable Municipal account nwnbers.
1227
JUL-Ib-U3 rue. 1i::3tl I'M r~H I,;UliUUl'(!j
rRX NU,
r, U~
SCHEDULE "B"
Ms, Dirkett
July 9, 2003 (revised July 15,2003)
2
Based on the reduced quantities, the four paris of the contract are now casted as follows;
Total (Excluding GST)
GST (7% of Total)
TOT^L TENDER AMOUNT
$196,568.62
35,115.50
50,640.80
27,749.40
$310,074.32
21,705.20
$331,779.52
Total Part 'A' - Ennisklllen Sidewalks
Total Part 'B' - Newcastle Sidewalk
Total Part 'C' - Bowmanville Sidewalks
Total Part 'D' - Nash Road Sidewalk
Trisan Construction successfully completed Clarington's sidewalk contract in 2002 to an acceptable
level. This contract is similar in nature and we lhcrefore recommend acceptance of Trisan's bid for
this work as amended above.
Please proceed with the award of this contract as soon as possible as work requires completion prior to
September 1, 2003.
Should YOll have any questions regarding this matter, please contacr the undersigned.
Best regards,
Ron Albright, P.Eng.
Project Engineer
/~~
RA/sn
l'1292%/CClrrCllpIl9744.dcc
Encl.
pc:
A,S. Cannella, Director of EngineerIng and Services (+oocl.)
Leslie Denson, Manager, Transportation and Design (+enc\.)
Wendy Chandler, Engineering Services (+enc\.)
Kaye Rand, Operations (+encl.)
1228
TIM
."_."--r--n-... __ ___......,__n
SIDEWALK CONSTRUCTION AND REPLACEMENT
ENNISKILLEN AND VARIOUS LOCATIONS
:n
o
Cost Apportionment For LOW' Bid 5ubmitted By irisan Construction
Con~act C120ClJ.-16
SCHEDULE "B"
July 07. 2003
T.S.H. Project: 12-29296
:>...
~
L
n
""
o
OJ
Ll
OJ
Description Total Clarington - EnginBering ServicBs OPERATIONS' Comments
Part 'A' - Part'B' . Part.C.... Part '0' - NASH WORKS -
ENNISKlllEN NEWCASTLE BOWMANVll.LE ROAD SITES 22 (from
SIDEWAlK SIDEWAlKS SIDEWAlKS SIDEWAlK Part 'C') & 3D
[from Part 'B')
Account Number .B41Q..D31CH-1401 8320.o3201~ 14rl1 8:!ZG.o31D2.14G1 29oo.17.X
Construction Ccsts Contract C12003.16 Slla 22 Part C - $3.622.50
$310,074.32 $196,566.62 $31.493,00 $49,762AO $27.749.40 $4,SOO.90 Slla 30 Part B - 5876,40
Total Part B =$35.115.50
Total Part C = $5D 640.60
TSH Project Number 12-29207 12-29296 12-29296 12-10692 12-29296
Detailed Design... Approva[s and Tender Documents $34,064.87 $26.141,95 S2,334.66 $3.606.05 N;lsh Rood Delli!]n ar.d Tendering
(to June2B, 20(2) 5247.06 PI~lcuslycom~e1ed Ouring Road
Recanslructa. De$\;ln
Estimated COnstructlcn Admlnl.traUon (TSH tJ 12-29296) $33.400.00 $26.000,00 S2,900.00 54.500.00 5400.00 Proratelf Based on L.01.\' Bid
OtheT COsts
Bell Relocation 51,000,00 $1,000.00
Sub-Total Other Costs 51,000.00 $1,000.00 $0.00 $0.00 50,00 SO.OO
Sub-TDtal Estimated PTCJect Costs (exc.. contingencIes) $374,058.29 5251,710.57 536.727.88 557.670.45 $27.749,40 55,147.96
Net G.S,T. (3%) leke!. cDntingencles) 511.221.75 $7,551.32 $1.101.64 $1.736.11 5832,48 $154.44
Contingencies llncluding G.S.T.) $11.819.96 $7,938.11 $970.29 51.493.44 51,418.12 5197.56
Total EstImated Project Costs 5397.100.00 $267,200.00 . $36.800.00 561.100,00 $30,000.GO 55,500.00
Budget Amount 5405.000.00 $275,000.00 5100,000.00 $30,000,00 55,500.00
Eslimated Budget Surplus/Deficit $7.900.00 $7,800.00 $100.00 50,00 50.00
::5
z:
x:
0::
.L.
'"
'"
OJ
OJ
D
::>
:0>
I::
n.
Note: Col'\S1ruction Casts are based on amrrended Tender Quan1ities as rel;ulred to matGh alloca~ed Budg-ets.
The .secEal\ of (he proposed EnniskillEm sKlewalk ooihswest si~ {If Oid Scugog Road (rom tt-..e ~u.blic School oorther1y has been r.emoved from the ClJnlracL Fufure status for lhis secthA:' is undernwlew.
,.,
OJ
I
n
OJ
I
-1
OJ
.."
N
N
~
G:',ProjCC31-12-H}824\Spe;::i'.tow Bid O:rlL AllXIrtiarener.r Cl.2OO1-16.Ds
Prinh'don 7!&tOJ
tsh
4. CL2003-19,
THE SUPPLY, DELIVERY & INSTALLATION OF A HOIST
A contract was awarded to Toronto Garage Equipment Inc" Markham, Ontario,
The Municipality of Clarington advertised and issued a tender with bids being received and
tabulated as follows:
Bidder Total Bid Amount
Toronto Garage Equipment Inc. $69,996.22
Markham, ON
National Garage Equipment $80,029.76
Whitbv, ON
642056 Ontario Inc. $111,280.00
Cimech General Contractors
Weston, ON
The total bid price of $69,996.22 will be drawn from the 2003 Operations Capital Budget
Account #8345-03400-1401 and are within the total budget allocation of $90,000.00.
The subject firm have provided satisfactory service to the Toronto Transit Commission.
1230
5. CL2003-20,
THE SUPPLY & DELIVERY OF (2) TWO HANOI TRANSIT VEHICLES
The Municipality of Clarington issued a tender on behalf of the City of Oshawa and Clarington
for (2) Two Handi Transit Vehicles with bids being received and tabulated as per Schedule "A"
attached,
Of the total bid price of $144,824.00, the Municipality of Clarington portion is $72,412.00 plus
taxes.
The funds as approved in the 2003 Capital Budget, in the amount of $78,000,00 will be provided
from account # 7216-00002-0000. The additional funds will be drawn from the Clarington
Transit Reserve Fund,
The subject firm have provided satisfactory service to the Region of Peel.
1231
SCHEDULE "A"
BID SUMMARY
TENDER CL2003-20
TWO (2) HANDI TRANSIT VANS
Bidder Total Bid Amount (Before taxes)
CityView Bus and Truck Repair Sales $144,824.00
Etobicoke, ON
Corbeil Bus Sales Ltd. $145,600.00
lroauois, ON
Leeds Transit Sales Ltd. $148,384.00
Elain, ON
Pearson Bus Sales Ltd. $149,400,00
Brantford, ON
1232
6. TENDER CL2003-23
BOWMANVILLE CREEK VALLEY RECREATIONAL TRAIL
A contract was awarded to Elirpa Construction and Materials Ltd" Pickering, Ontario for a total bid
amount of $155,480.98 (including taxes).
Tenders were publicly advertised and issued with bids being submitted as per Schedule "A"
attached,
As the total costs associated with this contract exceed the budget allocation of $160,000,00, the
value of the contract had to be reduced. See details on Schedule "A".
Funding is included in the 2003 Engineering Capital Budget and will be provided from Capital
Account #8610-03201-1401,
The Director of Finance has reviewed the funding requirements and concurs with the
recommendation. Queries with respect to the department needs, specifications, etc" should be
directed to the Director of Engineering Services.
The low bidder has provided satisfactory service to the Municipality of Clarington in recent years.
1233
AUIj~LL-Uj ~I<l lU:4L f1111::i11 liUJ:jUUI<Ij
~f1)\ NU,
~, UI
..
. .
:I'
.
II
11M
SCHEDULE "A"
engineers
architects
planners
Totten Sims Hubickl ASGociatcs
513 Division Street,
Coboll'Oo Ontario, Canada K9A 5G6
(905) 372-2121 Fax: (9051372-3621
E-mail: cobourg@tsh.c. www.tsh.ca
August 22,2003
Ms. Lou Ann Birkett, CPP, AMCT
Purchasing Manager
Corporation of the Municipality of Clarington
40 Temperance Street
BOWMANVILLE, Ontario. LlC 3A6
Fax: 905-623-3330
Dear Ms. Birkett:
Rc: Contract No. CL2003-23, Bowmanville Creek Valley Recreational Trail, Bowmanville
Municipality of Clarlngton
Tel1ders for the above project were opened at the Municipal Offices on Friday August 8, 2003 at
2:00 P.M. The bids received, inclusive of GST, arc summarized as follows:
BIDDER TOTAL BID AMOUNT
Elirpa Construction & Materials Ltd. $190,663.38
Pickerinlt, Ontario
Jatec Ltd. $214,065.81
Courtice Ontario
Ron Robinson Ltd. $243,546.77
Bowmanvllle, Ontario
Harnden & King $279,963,32
Aiax, Ontario
*Error in Extension
The low bidder's tender has been checked and is In order. The contract was tendered in 2 parts, Part
'A' and Part 'R'. The award of Part 'B' was provisional on tlle availability of funding, As a result of
pricing r~ceived for Part 'A' It iR no longer feasible to complete Part 'B' works. In addition, after
discussions with the Manager of Parks Development, Peter Wlndolf, it was decided that tree planting
would be done by the TraH 2000 volunteer group. As such Items 14, ]5 and ]6 from Part 'A' will also
be deleted from the contract. This has been discussed with the low bidder EIirpa Construction &
Materials Ltd. and they have no objection to the deletion of these items. .
Estimated project costs based on the above noted adjustments to the low lender are now estimated as
follows:
1234
I1Uln~,:-Uj ~J(l jU:qj 11M j;jl1 liUI:lUUKli
FAX NO,
.. .'.-
.
..
Ms. Lou Ann Birkctt, CPP. AMCT
August 22. 2003
ConslIuction Costs (Part 'A'less Items 14, 15 -
and 16)
$145,309.33
Detailed Design & Tendering to June 28,
2003 TSH project # 12-29269
3,884.52
Contract Administration & Materials Testing
(Estimated)
1,500.00
Contingencies (includes G.S.T.)
4,785.43
4,520.82
Net G.S.T.. (excluding contingencies)
Total Project Costs
$160,000.00
p, 02
SCHEDULE "A"
Thc contract will be administered by Clarington Staff with materials testing by TSH and Golder
Associates.
2
Elirpa Construction & Materials Ltd. has successfully completed several projects for both Clarington
and the Region of Durham in the past, we thcrefore recommended the award of Contract C12003-23 to
E1irpa Construction of Pickering, Ontario for the revised Total Tender Amount, including G.S.T. of
$155,480.98.
Should you have any questions regarding this matter, please contact the undersigned,
You rs truly,
fiIL)1(~
William McCrae. P.Eng.
Senior Project Engineer
WMc/sn
P/2ryu9/Corr~/l9JI34.doo
pc: A.S. Cannella, Director Engineering Services
Peter Windolf, Manager of Parks Development
Wendy Chandler, Engineering Services