Report Subject: Bridge & Culvert Repairs
Recommendations:
1. That Report COD-006-15 be received;
2. That All Services Inc., Courtice, Ontario with a total bid amount of $301,932.10 (net H.S.T.
Rebate) being the lowest responsible bidder meeting all terms, conditions and
specifications of Tender CL2015-1 be awarded the contract for the Bridge and Culvert
Repairs as required by the Municipality of Clarington, Engineering Department;
3. That the total funds required in the amount of$332,500.00 (net HST Rebate) including
construction cost of $301,932.10 and $30,567.90 contingency be drawn from the following
accounts:
Structures Rehabilitation 110-32-330-83275-7401 (2014) $ 235,000.00
Roadside Protection Program 110-32-330-83338-7401 (2014) $ 88,000.00
Bridge Maintenance 100-36-380-10200-7112 (2014/15) $ 9,500.00
4. That all interested parties listed in Report COD-006-15 and any delegations be advised of
Council's decision.
Municipality of Clarington
Report COD-006-15 Page 2
Report Overview
To request authorization from Council to award the contract for the Bridge and Culvert Repairs
as required by the Municipality of Clarington's Engineering Department.
1 . Background
Tender specifications were provided by Engineering Department for the Bridge and
Culvert Repairs.
Tender#CL2015-1 was prepared and posted on the Municipality of Clarington's
website. Notification of the availability of the document was posted on the Ontario
Public Buyer's Association website and the Daily Commercial News. Twenty-seven
companies registered as downloading the document..
The Tender closed Friday, February 13, 2015.
2. Bridge and Culvert Repair
Three tenders were received in response to the tender call. Bids were reviewed and
tabulated (see Attachment 1). All submissions were deemed to be compliant.
After review and analysis of the bid the Engineering Department and Purchasing
Services it was mutually agreed that the low bidder, All Services Inc. be recommended
for the award of contract CL2015-1 for the Bridge & Culvert Repair work as required by
the Municipality.
All Services Inc. has completed several projects for the Municipality of Clarington in the
past.
3. Financial and Budget Considerations
The total project cost of$ 332,500.00 includes the construction costs of $301,932.10
(net H.S.T. Rebate), the total bid from All Services Inc., and project contingency of
$30,567.90 net H.S.T. Rebate).
Structures Rehabilitation $ 235,000.00
110-32-330-83275-7401 (2014)
Roadside Protection Program $ 88,000.00
110-32-330-83338-7401 (2014)
Bridge Maintenance $ 9,500.00
100-36-380-10200-7112 (2014/2015)
Municipality of Clarington
Report COD-006-15 Page 3
4. Concurrence
This report has been reviewed by Tony Canella, Director of Engineering Services, and
concurs with the recommendations.
5. Conclusion
It is respectfully recommended that All Services Inc. with the lowest compliant bid of
$301,932.10 (net H.S.T. rebate) be awarded the contract for the Bridge & Culvert
Repairs as per Tender CL2015-1.
6. Strategic Plan Application
The recommendations contained in this report conform to the Strategic Plan.
Submitted by.
by: Reviewed :
Marie Marano, H.B.Sc., C.M.O. Franklin Wu,
Director of Corporate Services Chief Administrative Officer
ancy a or B /CPA, CA.,
Director of Finance/Treasurer
Staff Contact: David Ferguson, Purchasing Manager, 905.623.3379 Ext 2209 or
dferguson@clarington.net
Attachments: Attachment 1 —Tabulation of Bid Summary
Attachment 2 — Memo from Engineering
List of interested parties to be notified of Council's decision is on file in the Corporate Services
Department.
MM/DF/sm
Municipality of Clarington Attachment 1 to
Report COD-006-15
Cla
Leading the Wiay
Municipality of Clarington
SUMMARY OF BID RESULTS
Tender CL2015-1
BRIDGE & CULVERT REPAIRS
Bidder Total Bid Total Bid
(net HST Rebate) with HST included
All Services Inc. $301,932.10 $335,282.30
Nick Carchidi Excavating Ltd. $317,453.92 $352,518.60
GMP Contracting Ltd. $506,388.08 $562,321.67
Attachment 2 to
Report COD-006-15
ciffifloon j
= M0
MEIVI
i
TO: David Ferguson, Purchasing Manager
FROM: Ron Albright, Manager, Infrastructure and Capital Works
DATE: March 2, 2015
RE: Bridge and Culvert Repairs
CL2015-1
The Engineering Services Department has reviewed the submissions for CL2015-1 and
offers the following comments.
The project includes the rehabilitation of various bridges and culverts throughout the
Municipality, as noted in the table below. The sites were selected based on the findings
of the annual bridge and culvert inspections. The repair work includes safety
improvements and repairs to extend the serviceable live of the structures.
Structure ID Road Location
9 8 003 Lolicessiurl V cd b ---- - U.20 k ri L of I eid I\d
98501 Lakeshore Rd 0.25 km E of Jaynes Rd
98534 Leskard Rd 0.02 km N of Concession Rd 7
-99054- -South Service Rd 1-.1 km W-of Waverly Rd
99512 Concession Rd 3 0.08 km W of Lambs Rd
94017 King St 1.2 km E of Liberty St
98043 Reid Rd 0.2 km N of Concession Rd 4
98523 Ochonski Rd 1.2 km N of Concession Rd 5
Based on past experience with this contractor, we recommend award of the contract to
All Services Inc. in the amount of $335,282.30, inclusive of HST, or $301,932.10 net of
HST'rebate.
A contingency amount of approximately 10% of construction costs is being carried.
Therefore, including contingencies and net HST costs, the Engineering Department
advises of the following project cost breakdown. Funding for the project will come from
i
i
Bridge and Culvert Repairs,
CL2015-1 2 March 2, 2015
the structures rehabilitation account, roadside* protection program account and the
Operations bridge maintenance account.
i
Construction Cost, Based on Low Bid (net of $ 301,932.10
HST)
Contingencies (net of HST) $ 30,567.90
Total Cost $ 332,500.00
Budget Amount
Structures Rehabilitation,
110-32-330-83275-7401 (2014) $ 235,000.00
Roadside Protection Program
110-32-330-83338-7401. (2014) $ 88,000.00
Bridge Maintenance,
100-36-380-10200-7112 (2014/2015) $ 9,500.00
Estimated Unexpended Budget $0.00
Additional Funding Required $0.00
* A more detailed breakdown to be provided to Finance to provide
necessary information for tracking of Tangible Capital Assets (TCA).
Considering all costs, the project is within budget and the Engineering Dept
recommends that the Purchasing Dept. move forward based on the above
apportionments. Should you have any further questions, please feel free to contact the
undersigned.
Regards,
Ron Albright, P. Eng.
Manager, Infrastructure and Capital Works
RA/sb/dv
I
Attachment
Pc: Nancy Taylor, Director of Finance
A.S. Cannella, Director of Engineering Services
Fred Horvath, Director of Operations
I
Bridge and Culvert Repairs,
i
CL2015-1 3 March 2, 2015
_ fiYO6trcra6wnniY� .: _
\ '• PrOtl13VYYAPI 'lH3Y ' mob{eJt�Onrpnl -`-
_�� �'I' MPY 3Y(laxnl 13V3 '
C �I"- i.. I 3uJiR•J _,3xP,YTP ��'b� � mJb'( s,a�n
' 'Z moa � � HOLt9 —'•� � —='�
1 4 p 1 aron J
�C.
.. , C�"'j"�'(t''- a Yoi'mo�v:.� °m-,•.:'r<c'�-s .cwu srvAMn1iv I1 1 mrox newly x
v
a:o�'
9- PAY avNnH ,i
rnnn a ' -,A3nY�bYP3P h /
pray uYOm-ism �3 P.ou tl �`\ Prop •\ f �
Pgtl PVrttMY r 1 ( \ r
y , � PYPn AtlaH PmY '•-� ����,•\ MPb '\ 6M-JL•Pnr' �.`.
.......�_
7—YYJ' ,, m ,. tlt. \„1 ?!�Y
� Ho,uon .'xosx3ura - Pwbrrsxu , (mpa � w - �icP �•
f_a.�i 1 ! m Mou
�PPI
mw MGYYP PAHA3,YlPP An31o1 `• -,, 1 1., '` q ( 1, 1
i 'PwY61mPN .. - 3i r�� ,mpu WsF9
'` MPtl3JF3bV.Y'i 2A tr`
�{fl AYAW9IH prey AP rvO � .,1 ,,-•PYPx1Y11gY) i ���It i/i JY \..i by
o, 1\ ,4 33n6Yruv�k- 5
1636 .,QYOY 163f
.Y.n _ -_[ ssr�FYA•Na l -__`t I_5
11��� ' O1 mivr,6, �.. •.. l , 3.vm � y° a
� � ���� - nHOO ...PYpnvmw �,mrtro iHnorwl mnures. m t 'O K �
0 � � I I�r mon omioa J U m
t
w.wl t nYwuY�uaYmrP ra j, � r .;+aoM .. „r
..,PYPH` LWO 4• ,,R MYnl3� ply ¢ �— _� fiYOa � PPYb9 Punom' ,
it
777,
r.,
PYM(. ' '-.YO63iLL3! \•1~ MoH LI �•prov � Pn p(/6®Yyl f
9x YS Utl3=.n�F Prasx9n3u •3�F3,YyTim}+ f - "� r
(J
LU
W Z
LL
,j Mouv3Ha6Y; PNaYY.bbY4n ° as ntlr"mmmo�63d 'I 7i-as 6YOU��P3e'—�E _ _o'i Q w m'
lo� MPnw`6PP. ._ 1 m O o
° YspvoiYixa'oiH ,o�� � � MoY �� _(rsYP U Q
]e _
/YJ§ 3- "� ra) �4 m awn
-� PYUY' LAN -QpV!'py'1.. OAY � 11oH � �01 rr
m Im
Municipality of Clarington
CL2015-1,Bridge and Culvert Repairs
Low Bid Cost Apportionment 2-Mar-2015
Contract CL2015-1
Engineering Operations Comments
Description Total Structures Roadside Bridge
Rehab Protection ' Maintenance
110-32-330- 110-32=330- 100-36-380-
Account Number/PO 83275-7401 83338-7401 10200-7112
Construction Costs Contract CL2015-1
PART'A': GENERAL ITEMS $ 46,000.00 $ 32,568.00 $ 12,144.00 $ 1,288.00 Pro-rated based on Parts B to N
PART'B': ROADWORKS CONCESSION ROAD 5 $ 71,025.00 $ 52,925.00 $ 18,100.00 $ -
PART'C': STRUCTURE 098083 CONCESSION ROAD 5 $ - 66,410.00 $ 53,740.00 $ 12,670.00 $ -
PART'D': STRUCTURE 098501 LAKESHORE ROAD CULVERT $ 10,900.00 $ 10,900.00 $ - .$ -
PART'E': ROADWORKS LESKARD ROAD). $ 29,575.00 $ 8,900.00 $ 20,675.00 $ -
PART'F': STRUCTURE 098534 LESKARD ROAD CULVERT $ 3,500.00 $ 3,500.00 $ - $ -
PART'G': STRUCTURE 099054 SOUTH SERVICE ROAD CULVERT $ 12,200.00 $ 12,200.00 $ - $ -
PART'H': ROADWORKS CONCESSION ROAD 3 $ 9,050.00 $ ' 9,050.00 $ - $ -
PART T: STRUCTURE 099512 CONCESSION ROAD 3 CULVERT $ 5,500.00 $ 5,500.00 $ - $
PART'S:ROADWORKS KING STREET $ 17,300.00 $ 2,500.00 $ 14,800.00 $ -
PART'K:STRUCTURE 094017 KING STREET BRIDGE $ 18,150.00 $ 18,150.00 $ - $ -
PART'L':ROADWORKS REID ROAD $ 1,500.00 $ - $ - $ 1,500.00
PART'M':STRUCTURE 098043 REID ROAD BRIDGE $ 2,000.00 $ - $ - $ 2,000.00
PART'N':ROADWORKS(OCHONSKI ROAD) $ 3,600.00 $ - $ - $ 3,600.00
Sub-Total Construction Costs $ 296,710.00 $ 209,933.00 $ 78,389.00 $ 8,388.00
Net HST @ 1.76%of Construction Costs $ 5,222.10 $ 3,694.82 $ 1,379.65 $ 147.63
Total Construction Costs $ 301,932.10 $ 213,627.82 $ 79,768.65 $ 8,535.63
Other Costs
10.0% Contingencies including net HST $ 30,567.90 $ 21,372.18 $ 8,231.35 $ 964.37 Adjusted for rounding
Total Other Costs $ 30,567.90 $ 21,372.18 $ 8,231.35 $ 964.37
Total Project Cost Incl.Net HST $ 332,500.00 $ 235,000.00 $ 88,000.00 $ 9,500.00
Budget $ 332,500.00 $ 235,000.00 $ 88,000.00 $ 9,500.00
(Over)/Under $ - $ - $ $ -