HomeMy WebLinkAboutPSD-076-05
Clw:mglOn
REPORT
PLANNING SERVICES
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date: Monday, June 6, 2005
Report #: PSD-076-05
File #: PLN 2.4.2.4
~ It (! p;t - ;;67-ct)
By-law #:
Subject:
MUNICIPALITY OF PORT HOPE OFFICIAL PLAN
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report PSD-076-05 be received;
2. THAT Report PSD-076-05 be submitted as the Municipality of Clarington's comments
on the Municipality of Port Hope Draft Official Plan dated April 12, 2005 and
3. THAT a copy of this report be forwarded to the Municipality of Port Hope.
Submitted by:
Reviewed by:
o~<6sk
Franklin Wu,
Chief Administrative Officer
a I . Crame, MCIP, R.P.P.
Director of Planning Services
HB/FLlDJC/df
30 May 2005
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-0830
REPORT NO.: PSD-076-05
PAGE 2
1.0 BACKGROUND
1,1 The Municipality of Port Hope was incorporated on January 1, 2001. It is the result of
the amalgamation of the former Town of Port Hope and the former Township of Hope.
1.2 Due to the amalgamation, the Municipality inherited two separate planning approaches.
In April 2003 the Municipality of Port Hope undertook an Official Plan Review, Update
and Consolidation by issuing a Policy Direction Report which Staff commented on,
1.3 The Planning Advisory Committee (PAC) of the Municipality of Port Hope issued a
working draft of the Official Plan which Clarington provided comments on in the form of
PSD-136-04 (Attachment 1). In addition to this report, Clarington staff held discussions
with the Director of Planning and the Chair of PAC elaborating upon Clarington's
comments; which seemed, at the time, to be well received.
1.4 The Planning Advisory Committee of the Municipality of Port Hope has now presented
the Draft Official Plan to Port Hope Council, the statutory public meeting in accordance
with the Planning Act will be held on June 23rd, 2005.
2.0 COMMENTS
2.1 Staff reviewed the working draft of the Municipality of Port Hope Official Plan and
provided comments which Council endorsed. As a result of those comments and our
discussion with the Director of Planning for Port Hope we had anticipated that the
comments would have been reflected in the final document. However, the
transportation impacts of the Wesleyville Employment Area and the concerns we have
with the Transportation Schedule showing a future collector road from Townline to
Wesleyville Road have not been addressed.
2.2 Likewise our comments regarding the necessity of showing the interconnections
between the Municipalities for trail systems, such as the Waterfront Regeneration Trail
and Oak Ridges Moraine Trail, even at a conceptual level have not been addressed,
The same is true for wildlife corridors through these natural systems.
2.3 Our suggestion that a policy be inserted in the General Provisions under Natural
Heritage regarding the need to undertake multi-stakeholder watershed planning studies
in order to protect the integrity of ecological and hydrological functions has also been
ignored; however, we can rely on the GRCA to inform us of such planning initiatives and
bringing the various stakeholders together.
2.4 Our greatest concern is with the Aggregate Reserve Area policies. Much of the
discussion we had with the Port Hope staff focused on the need to have aggregate
policies that were complimentary to Clarington's Official Plan policies. Policies that are
consistent or complimentary with bordering jurisdictions creates a seamless approach
when addressing resource management issues, ensuring the wise use of resources
within either jurisdiction. Our suggestions in this area have not been amalgamated into
the final draft.
REPORT NO.: PSD-076-05
PAGE 3
3.0 CONCLUSIONS
3.1 The final draft of the Municipality of Port Hope Official Plan does represent a significant
improvement over the existing Official Plans that the Municipality inherited for both
wards. It provides a comprehensive review and consistent approach for the entire
Municipality of Port Hope.
3.2 We are disappointed that the assistance that we provided to Port Hope has not been
incorporated into the final draft, resulting in a policy regime between the two
municipalities that will not be as seamless and consistent as could have been.
Attachments:
Attachment 1 - Copy of Report PSD-136-04
List of interested parties to be advised of Council's decision:
Mayor and Council
Municipality of Port Hope
ATTACHMENT 1
Report PSD-136-o4
Cl. a
L~~
REPORT
PLANNING SERVICES
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date:
Monday, November 1, 2004
Report #: PSD-136-04
File #: PLN 2.4.2.4
By-law #:
Subject:
MUNICIPALITY OF PORT HOPE OFFICIAL PLAN
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report PSD-136-04 be received;
2. THAT Report PSD-136-04 be adopted as the Municipality of Clarington's comments on
the Municipality of Port Hope Official Plan (working draft, dated September 14, 2004);
and
3. THAT a copy of this report be forwarded to the Municipality of Port Hope.
Submitted by:
David . Crome, MCIP, R.P.P.
Director of Planning Services
Reviewed by:
() ~~~
Franklin Wu,
Chief Administrative Officer
HB/FLlDJC/df
22 October 2004
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOW MANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-0830
636
REPORT NO.: PSD-136-04
PAGE 2
1.0 BACKGROUND
1.1 The Municipality of Port Hope was incorporated on January 1, 2001. It is the result of
the amalgamation of the former Town of Port Hope and the former Township of Hope.
1.2 Due to the amalgamation, the Municipality inherited two separate planning approaches.
In April 2003 the Municipality of Port Hope undertook an Official Plan Review, Update
and Consolidation by issuing a Policy Direction Report which Staff commented on.
1.3 The Planning Advisory Comrnittee of the Municipality of Port Hope has issued a working
draft of their Official Plan and requested comments prior to presentation of the
document to Port Hope Council scheduled for later this year.
2.0 COMMENTS
2.1 Staff have received and reviewed the working draft of the Municipality of Port Hope
Official Plan. The working draft is clear and comprehensive and addresses a number of
concerns that we had previously brought to the attention of the planning staff in Port
Hope. While we have some comments, specific to the inter-relationship of the two
municipalities, the Planning Advisory Committee is to be commended for the vision that
is set out in the document.
2.2 Wesleyville Employment Area is located in close proximity to the Municipality of
Clarington's eastern boundary. The eastem portion of Clarington is predominantly rural
in nature and it is anticipated to remain this way for some time. Development of the
employment area at Wesleyville, although planned for many years, will have an impact.
Careful consideration of the transportation impacts and induced pressure for other
forms of development will have to be carefully planned so as to preserve the rural
structure of that portion of Clarington.
2.3 The proposals for Tucker Creek have been deleted from this working draft of the Official
Plan. Clarington is very pleased to see that our comments regarding the impacts on
servicing, transportation and change to the predominantly rural and agricultural eastern
portion of Clarington have been taken into consideration in this most recent draft. The
precedent that the Tucker Creek proposal would have set for new uses and future
expansions, including the creation of a new settlement area supporting residential,
commercial, office and recreational uses was unacceptable to the Municipality of
Clarington as set out in our reports (PSD-063-03 and PSD-079-04).
2.4 We have concerns with Schedule D -Transportation as it does not show any future trail
connections, it would be reassuring to have indicated the Oak Ridges Moraine Trail and
Waterfront Trail at least conceptually to ensure that the future inter-connections
between the municipalities are there when the trails are being developed. Given the
removal of the Tucker Creek development and that Wesleyville will be serviced from the
401 and Wesleyville Road we see no need for the future collector shown from Townline
REPORT NO.: PSD-136-04
PAGE 3
to Wesleyville Road; futher we would have concerns that this future collector could
impact the transportation patterns in this portion of Clarington.
2.5 In Section C under the general principles outlined, it is troublesome that there is no
provision (even conceptually) for wildlife corridors. From the Second Marsh in Oshawa,
through Clarington and into the Municipality of Port Hope we have a rare opportunity of
being able to promote a near shore wildlife corridor that does not exist anywhere else
along Lake Ontario. Consideration should be given to adding an objective that
promotes wildlife corridors both along the lake and back up the valley systems to the
Ganaraska Forest and Oak Ridges Moraine.
2.6 In the General Provisions under the Natural Heritage Section we are suggesting that a
policy regarding the need to undertake multi-stakeholder watershed planning studies in
order to protect the integrity of ecological and hydrological functions be added. In this
regard, the inter-relationship between the headwaters of creeks and rivers that cross
from Port Hope into Clarington and vice versa will have reciprocal policies in the Official
Plans. In addition, this provides for the overall planning of how storm water
management will function when the drainage of an area will flow to the other
municipality. This will provide for consultation regarding contiguous natural features, as
well.
2.7. The draft Official Plan document permits alteration to the limits of the Aggregate
Reserve Area without the need for an amendment to the Official Plan. Identification of,
or deletion of, Aggregate Reserve Area requires studies to support the change and any
revision could have potential impacts on future land uses. As such, it is suggested that
changes to the limits of an Aggregate Reserve Area be undertaken by amendment.
2.8 It is suggested that upon closure of a licenced operation or a revoked licence that the
Municipality of Port Hope revisit the drafted Official Plan policies requiring that an
application be submitted to rezone the lands without the need for an Official Plan
Amendment. If the Municipality deletes the overlay designation without an amendment
to the Plan and then amend the Zoning By-law to delete aggregate extraction this would
remove the onus from the landowner to submit an amendment application.
2.9 Review of development applications and the supporting documentation to permit a new
or expanded Extraction Area can consume a lot of municipal resources. Also, there
may be technical studies submitted that either the Municipality or the Conservation
Authority do not have the technical expertise or resources to review. It is suggested
that the Municipality consider inclusion of policies that identify what studies would be
required to be submitted in support of an application to permit or expand an aggregate
extraction area and policies that would provide the Municipality with the opportunity to
peer review these studies at the expense of the proponent.
3.0 CONCLUSIONS
3.1 The Municipality of Port Hope is to be commended for the work completed to date. Vile
appreciate the opportunity to comment during the Official Plan review process.
. .
REPORT NO.: PSD-136-04
PAGE 4
List of interested parties to be advised of Council's decision:
Planning Advisory Committee
Municipality of Port Hope
56 Queen Street
P.O. Box 117
Port Hope, ON L 1A 3V9