HomeMy WebLinkAboutPSD-082-04
"
~
,
CJ~jgglon
REPORT
PLANNING SERVICES
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date:
Monday, June 21, 2004
Report #:
PSD-082-04
File #: PLN 23.5.14
/06p( ("f'::;'~3 /'oJrO'"
By-law #: .
Subject:
HIGHWAY 407 EAST COMPLETION -COMMENTS ON THE DRAFT TERMS
OF REFERENCE FOR THE ENVIRONMENTAL ASSESSMENT
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report PSD-082-04 be received;
2. THAT Staff Report PSD-082-04 be adopted as the Municipality of Clarington's
comments on the Draft Terms of Reference for the Highway 407 East Completion
Environmental Assessment;
3. THAT a copy of this Report and Council's resolution be forwarded to Totten Sims
Hubicki Associates, the Ontario Ministry of Transportation and the Region of
Durham.
Submitted by;
RevieWedbY;O~..:........ ~~
Franklin Wu
Chief Administrative Officer
vi . Crame, M.C.I.P.,R.P.P.
o~
Anthony S. Cannella, C.E.T.
Director of Engineering Services
JS/FLlDJC/df
11 June 2004
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-0830
699022
1
REPORT NO.: PSD-082-04
PAGE 2
1
1.0 BACKGROUND AND PURPOSE OF REPORT
1.1 In April 2003, the Ministry of Transportation (MTO) released draft Terms of
Reference (ToR) for the Highway 407 East Completion Environmental
Assessment. The ToR had been prepared under Section 6(2)(c) of the Ontario
Environmental Assessment Act (EAA) which allows a proponent to "set out in
detail the requirements for the preparation of the environmental assessment".
This section had been interpreted to allow the ToR for individual EAs to be
customized (or "scoped"); for example, the Highway 407 ToR reached a number
of conclusions about the need for Highway 407, route alignments and study
areas. The Municipality submitted its comments on the draft ToR in September
2003 through Staff Report PSD-099-03.
1.2 In June 2003, an Ontario Superior Court decision dealing with a ToR document
for a landfill proposal in Eastern Ontario created new case-law defining how
Section 6(2)(c) of the EAA should be interpreted. The court determined that the
wording and intent of the Act does not allow any scoping of work to be
completed within the ToR for an individual EA. The Ministry of Environment
subsequently indicated that it would no longer approve "scoped" ToR
documents. In response, MTO has prepared new draft ToR for the Highway
407 East Completion EA under Section 6(2)(a) of the EAA. This section
requires the ToR to address specific requirements as set out in the Act, such as
the rationale for the project and alternatives to the undertaking.
1.3 The new draft ToR are much more general than the previous version and set
out a process and a study framework for the preparation of the EA. The
deadline for the submission of comments on the revised draft ToR is July 2,
2004. MTO intends to submit the ToR to the Ministry of Environment in
September 2004 for approval. Following approval of the ToR, MTO will proceed
with the individual EA study for the Highway 407 East Completion.
1.4 The purpose of this report is to provide the Municipality's comments on the
revised draft EA Terms of Reference for the Highway 407 East Completion.
The Municipality's comments (indicated in bold italics) are, for the most part,
based on comments provided by the Municipality's peer review consultant, the
IBI Group (see Attachment 1), and the Clarington Highway 407 Community
Advisory Committee (see Attachment 2). As well, some comments provided in
Staff Report PSD-099-03 are relevant to the current draft ToR and have been
included. Cross-references to these docments are provided, where appropriate,
to identify the source of a comment provided in this report.
2.0 INTRODUCTION TO TERMS OF REFERENCE
2.1 Backqround
2.1.1 The ToR indicate that the need for additional east-west and north-south
transportation (not highway) capacity in Durham Region has been established
by the 2003 Durham Transportation Master Plan and the 1989 Highway 407
Overview Study. This need is referenced as the reason why MTO has
699023
,
REPORT NO.: PSD-082-04
PAGE 3
commenced the EA process to consider alternatives to address these
transportation deficiencies. The ToR will establish minimum requirements to be
followed during the preparation of the subsequent Individual EA.
2.1.2 Comments
a) The 1989 study is dated and does not take current travel patterns into
consideration. Additional studies should be undertaken to determine
the current need for additional transportation capacity in Durham
Region, and should also address transportation needs in
Kawartha/Halibuton and Northumberland County. (I B I, Section 1.1)
b) The ToR should address the policy context in which the EA is being
conducted and how it will be affected by other provincial initiatives,
such as the establishment of the Greater Toronto Transportation
Authority, the proposed GTA Greenbelt, GO Transit expansion, the
revised Provincial Policy Statement, and Smart Growth/Growth
Management. (CAC, Section 2.7)
2.2 Federal/Provincial EA Coordination
2.2.1 The project resulting from the EA will also be subject to the Canadian
Environmental Assessment Act (CEM). Federal authorities frequently wait
until a specific project has been defined to formally declare whether or not the
project will require an approval from thl;lt agency. However, it has been federal
practice for agencies to informally participate in the EA process prior to such a
determination being made.
2.2.2 Comments
a) Given that a specific project has not yet been defined, MTO should
formally re-invite all federal authorities to participate in the EA
process to ensure effective federal involvement throughout the EA
process. (CAC, Section 2.2).
3.0 PURPOSE OF THE UNDERTAKING
3.1 Overview and Outlook
3.1.1 This section summarizes the current and future factors that affect transportation
within and across Durham Region, as noted below:
· population and employment growth - between 2004 and 2031, the Region's
population is expected to grow from 550,000 to 1,055,00, while employment
is forecast to almost double from 170,000 to 311,000;
· trade - the manufacturing sector accounts for over 25% of the Region's
total gross domestic product, and commercial vehicle traffic in and through
Durham is anticipated to increase at an annual rate of approximately 3%;
699024
REPORT NO.: PSD-082-04
PAGE 4
,
. tourism and recreation - Durham Region, as the eastern gateway to the
GTA, will experience increased tourist travel, as will the
Kawartha/Haliburton areas to the north;
. transportation - traffic congestion occurs regularly on the roads in Durham
Region during morning and afternoon peak periods for commuter travel, as
well as during peak travel periods for tourist and recreational traffic.
The ToR establishes the area of consideration for the EA to be all of Durham
Region extending from the Oak Ridges Moraine to Highway 401, and from the
east Pickering area to Highway 35/115.
3.1.2 Comments
a) The draft ToR appear to rely on future population and employment
figures from the Durham Region's Official Plan Review. While the
figures for population can be considered forecasts, the numbers
used for employment are less reliable because they are based on a
full build out of employment lands at selected densities. Other
population and employment scenarios need to be considered. (CAC,
Section 2.3)
b) The EA must provide a comprehensive analysis of transportation
demand for existing and future conditions, including intermediate
planning horizons within the overall planning period. (CAC, Section
1.2 b)
c) The argument that improved transportation infrastructure is needed
to stimulate economic growth in Durham Region needs to be
supported by the appropriate studies. (Report PSD-099-03, Section
4.2.1 a)
d) In order to fully understand the discussion of the factors affecting
transportation in Durham Region, the relevant source studies must
be referenced. (181, Section 2.1).
e) The impact of rising gas prices and other operating expenses
associated with trucking needs to be considered on existing truck
traffic routes and potential truck traffic. Increased gas prices and
vehicle operating costs could also affect the volume of tourist and
cottager traffic through Durham Region. (CAC, Sections 2.4 and 2.5)
3.2 Transportation Problems
3.2.1 Previous studies are used as the source of information on existing and forecast
transportation problems in Durham Region. Major problems are listed, including
no freeway alternatives to Highway 401, limited ability to shift freight from road
to rail, and declining auto occupancy. The ToR commits to undertaking
additional analysis of transportation problems as part of the Individual EA.
699025
REPORT NO.: PSD-082-04
PAGE 5
3.2.2 Comments
a) Since the ToR does not describe the scope and type of analysis of
transportation problems that will be undertaken as part of the future
EA study, the resulting analysis could be very extensive or very brief.
The ToR should be modified to require the EA to undertake a
thorough analysis of transportation problems and use current
studies in the analysis. (IBI, Section 2.2)
b) The transportation problems as defined by the ToR should be
expanded to include related problems such as decreased air quality,
increased stress, and quality of life issues. (IBI, Section 2.2)
3.3 Transportation Opportunities
3.3.1 As required by the EA process, the ToR lists a number of opportunities
available in Durham Region that will be considered in the EA to address the
identified transportation problems. These opportunities involve:
· transportation - reduced congestion and associated impacts, improved user
safety, more transportation choices, reduced travel demand, improved
passenger rail service and optimized/expanded existing infrastructure;
· economy - improved efficiency/reduced costs for goods movement, improved
connections between economic centres, improved goods movement choices,
support for tourism and trade growth, etc.; and
· environment - develop transportation infrastructure that preserves natural
resources, and protects/enhances existing communities.
3.3.2 Comments
a) The analysis of transportation opportunities must include an analysis
of all current, promised and projected spending commitments
from/to various governments, including 10 Year and beyond capital
spending plans of Go Transit, Via Rail, CN and CP Rail, TTC,
local/regional transit systems, and improvements to provincial, local
and regional road infrastructure. (CAC, Section 2.6)
3.4 Summary
3.4.1 The ToR state the purpose of the undertaking is to address the identified problems
and opportunities by providing additional east-west and north-south transportation
capacity within the Region of Durham for a 3D-year planning horizon. The specific
need for any proposed undertaking(s) and a description of any proposed
undertaking(s) will be developed during the Individual EA through the preparation
of a Transportation Planning/Need Report.
699026
REPORT NO.: PSD-082-04
PAGE 6
3.4.2 Comments
a) The ToR describe the purpose of the undertaking, but do not
specifically define what the "undertaking" is. From a review of the
ToR, specifically Section 1.1, it would appear that the intended
undertaking is to be to provide additional east-west and north-south
transportation capacity within and through Durham Region over the
next 30 years.
However, it is not within MTO's mandate to provide a comprehensive
transportation plan for Durham Region that could involve
modifications to the regional and local road networks, local and GO
Transit, and rail freight on the CN and CP rail lines. As well, the title
of the ToR indicate that the EA will address the Highway 407 East
Completion.
Therefore, a definition of the undertaking should be included in the
ToR that accurately reflects what the EA will actually address. A
possible definition of an undertaking could be as follows:
· "To identify problems with east-west and north-south
transportation capacity in Durham Region over the next 30 years,
and to evaluate alternative solutions to the identified problems,
including the extension of Highway 407 East to Highway 35/115".
4.0 POTENTIAL ENVIRONMENTAL EFFECTS
4.1 Overview
4.1.1 The previous ToR included extensive information on natural and social
environment conditions associated with the proposed 407 East Completion study
area. This type of information is not included in the new ToR due to the recent
court ruling and, as a result, the new description of Potential Environmental
Effects is extremely brief. The ToR simply summarize how environmental
information is proposed to be used as part of the EA evaluation process.
4.1.2 Comment
a) Even though the ToR are not permitted to scope the EA study, the
ToR as currently proposed provide little guidance on how
environmental information will be collected and analyzed. It is
critical that the EA study process develop a thorough understanding
of environmental conditions in Durham Region. As such, the ToR
should provide greater direction on the collection of environmental
information to ensure that investigations and analysis occur at an
appropriate level of detail.
699027
REPORT NO.: PSD-082-04
PAGE 7
b) The ToR should specify that the definition of "environment" included
in the Ontario Environmental Assessment Act will be used in the EA.
This will help clarify for the reader that the term "environment"
includes not only the natural environment, but also the social,
economic and cultural conditions that influence the life of humans or
a community.
5.0 ALTERNATIVES TO THE UNDERTAKING
5.1 ldentifvinq and Assessinq Alternatives to the Undertakinq
5.1.1 "Alternatives to" an undertaking represent reasonable means of resolving the
stated transportation problems and opportunities, as well as meeting the purpose
of the undertaking. The alternatives to be examined include the "Do Nothing
Alternative" through to demand and system management alternatives, other mode
alternatives (air, rail, marine, transit) and roadways. Combinations are also
possible, and the ToR commit to considering additional alternative undertaking
that may be suggested by review agencies, stakeholders and the public.
5.1.2 The assessment of the alternatives to the undertaking will look at the fundamental
differences among the alternatives, but essentially says that the effectiveness of
each alternative to resolve the existing and expected transportation problems is of
prime importance. Therefore, even if an alternative performs well from an
economic or environmental perspective, if it does not resolve the transportation
problems it will likely not be considered further in the EA process.
5.1.3 Table 4.1 in the ToR lists the factors and criteria to be used in assessing the
alternatives to the undertaking. The factors listed are transportation, economy,
and environment. Criteria listed include for example under transportation, the
degree to which the proposed transportation system modifications resolve the
detailed problems. The general nature of the factors and criteria indicate that the
assessments will be done at a strategic level and are not intended to be project,
location or route specific at this stage.
5.1.4 Comments
a) The factors and criteria used to assess alternatives are critical to the
public having confidence that the alternatives will be assessed fairly
and comprehensively. The ToR do not define the extent of the
analysis that will be conducted on alternatives. Given that it is this
stage where alternatives are eliminated from further consideration,
the ToR should require a robust and more detailed evaluation than
what would appear to be currently required. (IBI, Section 4.1; CAC,
Section 2.9)
b) There is no reference in the ToR or the Supporting Documentation to
a process/methodology to identify, assess and evaluate Alternatives
To the Undertaking. (CAC. Section 2.9)
699028
REPORT NO.: PSD-082-04
PAGE 8
c) In order for the EA study process to be comprehensive and effective,
MTO should look at transportation problems and opportunities in a
holistic fashion and not just focus on highways. This will ensure that
other transportation providers, such as GO Transit, will contribute
the input necessary for alternative solutions to be considered. (CAC,
section 1.2 a)
d) For each factor, criteria should be added that addresses the degree
to which proposed transportation system modifications support
federal, provincial, regional and municipal policies that affect that
factor. (CAC, Section 2.9)
e) A full cost/benefit analysis should be provided of the Alternatives To
the Undertaking, for both the short and long-terms. Many costs and
benefits are long - term or cannot be easily quantified (eg. improved
or reduced air quality). (CAC, Section 2.9)
f) Given the length of time required to fully implement an alternative,
the specific analysis of any alternative must be conducted for the
short-term (5-10 Years), medium term (10-20 years), and long term
(up to 30 years). (CAC, Section 2.9)
g) The review of alternatives must include an analysis of the impacts
related to the possible termination of Highway 407 at the East
Durham Link (whether interim/temporary or permanent), and the need
for improvements to the Regional Road system to deal with the traffic
(eg. widening of Taunton Road). (CAC, Section 2.9)
h) The review of alternatives must include an examination of extending
full GO Rail services to Bowmanville. (Staff Report PSD-099-03,
Section 5.2.1 I )
i) In Table 4.1, the term "environment" must be used in its fullest sense
to include the natural, cultural, and socia-economic environments.
(CAC, Section 2.9)
5.2 Selectinq the Preferred "Alternative To" (Planninq Alternatives)
5.2.1 The assessment of all alternatives to the undertaking must conclude with a
recommended alternative(s) to carry forward into the second and more detailed
assessment process. The ToR states that if the Do Nothing alternative is
selected, the EA process is complete and over. If the preferred alternative is
outside of MTO's jurisdiction (eg, involving commuter rail or regional roads),
then the current EA process would stop and MTO would transfer responsibility
for the continuing process to the appropriate agency for further action. If the
preferred alternative falls under MTO jurisdiction, the EA process continues,
and if jurisdiction is shared (combined alternative), MTO will only continue with
the solutions under its responsibility.
699029
REPORT NO.: PSD-082-04
PAGE 9
5.2.2 Comments
a) Many of the alternatives, including the combined alternative, involve
improvements to infrastructure that are outside the jurisdiction of the
provincial government - ego improvements to local transit and the
regional road system. The analysis of the various alternatives must
address the ability of these alternatives to be implemented.
b) The process used to select a preferred alternative should include
descriptive tables or reports outlining the potential impacts of each
alternative on each feature, and potential mitigation and net impacts.
(Report PSD-099-03, Section 6.2.1 c)
6.0 ALTERNATIVE METHODS
6.1 Process for Generatinq a Studv Area
6.1.1 Once a preferred alternative to the undertaking has been identified, the EA
process will move into a more detailed assessment of that undertaking in terms
of its location, design, function and impacts. The first step is to define the study
area. Once defined, the study area boundaries can be refined or modified to
accommodate any reasonable alternative methods as the study progresses,
such as a change in an alignment.
6.2 Generatinq, Assessinq and Evaluatinq Alternative Methods
6.2.1 The ToR outlines a multi-step process for generating, assessing and evaluating
alternative methods. For example, if the undertaking is a highway, alternative
methods could include different alignments. Alternative methods will be
generated based on five general objectives - maximize use of existing
infrastructure, minimize impacts to existing land uses, minimize impacts to
significant natural features and functions, minimize impacts to urban/rural areas,
and resolve transportation problems. The reasons for including each alternative
method in the EA should respond to these objectives.
6.2.2 Table 5.1 of the ToR identifies twenty more detailed objectives for generating
the alternative methods - natural environment (11 objectives), socia-economic
environment (7 objectives), socia-cultural environment and economic
environment (1 objective each). Objectives identified here include "avoid
encroachment on Provincially Significant Wetlands and impairment of wetland
function", and "avoid, where possible, or minimize encroachment on prime
agricultural areas and agricultural infrastructure".
6.2.3 An assessment is subsequently undertaken of the net expected impacts of each
alternative method after standard mitigation measures are used (eg. noise
exposure after noise walls are installed). The advantages and disadvantages
of each alternative method are then compared by using two approaches. The
699030
REPORT NO.: PSD-082-04
PAGE 10
primary evaluation method will be the Reasoned Argument approach, which
discusses the main advantages, disadvantages and trade-offs for each
alternative method. A secondary method of evaluation will be the Arithmetic
Evaluation approach. which examines both the level of importance of each
environmental attribute (its weight) and the magnitude of the impact or benefit
associated with an alternative method (its score). The resulting weight-score
combination will be used to determine the best possible altemative method.
6.2.4 Table 5.2 of the ToR sets out the factors, criteria and indicators/effects that will
be used in the evaluation of the alternative means. The factors identified
include natural environment, social environment, economic environment,
cultural environment, and technical considerations. Each factor is divided into a
number of criteria, and indicators/effects are identified for each criteria.
6.2.5 Comments
General
a) The evaluation approach proposed appears to be suitable because it
allows for trade-offs and recognizes that it is unlikely that any
alternative method will be found to be "perfect" with maximum
advantages and no disadvantages. (IBI, Section 5.2)
b) The ToR should require that the EA include specific examples of
how alternative transportation solutions have been applied in similar
circumstances, and outline their effectiveness and environmental
impacts. The current 400 series highways could be used as
examples to demonstrate the impact and effectiveness of the 407
east extension. (CAC, Section 1.2 g, h)
c) The assessment of the 407 East extension should look at toll and
non-toll alternatives. (CAC, Section 1.2 i)
d) The various alternatives to the undertaking should be assessed at
various stages of implementation to tie in with the growth of
transportation demand. (CAC, Section 1.2 g. j)
e) The assessment of the various alternatives should include an
analysis of any required capital improvements by the local and
regional governments resulting from the construction of the
highway, and ways that the economic impact on the municipalities
could be mitigated.
f) The public should be involved in the development of the criteria for
the generation and evaluation of alternative methods. The
development of factors and criteria specific to each area municipality
should be considered to reflect local values. (CAC, Section 2.10)
699031
REPORT NO.: PSD-082-04
PAGE 11
Table 5.1 (Objectives for the Generation of Alternative Methods)
g) The ToR should address how a cut-off will be established to identify
when a candidate method does not satisfy a suitable number of the
20 recommended objectives in Table 5.1, and is therefore not
included as an alternative method for further assessment. (IBI,
Section 5.2)
h) Table 5.1 should specifically indicate that alternative methods that
encroach on the Oak Ridges Moraine will not be considered. (CAC,
Section 2.10)
i) Protection of urban separators should be added to Table 5.1 as an
objective. (Staff Report PSD-099-03)
Table 5.2 (Evaluation Factors, Criteria and Indicators)
j) The establishment of evaluation criteria and weights, as set out in
Table 5.2, is one of the key points in the EA process. It is therefore
important that the criteria and indicators identified in Table 5.2 be as
complete as possible so that no reasonable subject, issue or
question is missed when the alternative methods are being
evaluated. (IBI, Section 5.2)
k) The EA must address the quality of the features and indicators
identified in Table 5.2.
I) The following objectives should be given special consideration in the
evaluation of alternative methods:
· avoid critical ground water recharge areas, heritage homes, and
large contiguous blocks of prime agricultural land
. maximize distance from established hamlets
· avoid designated serviced industrial land. (CAC, Section 2.10)
m) Both the Black-Farewell Wetland Complex and the Maple Grove
Wetland Complex have been identified as Provincially Significant.
The protection of both of these wetlands, as well as the protection of
the Bowmanville-Courtice urban separator, will need to be
considered when determining an appropriate alignment for Highway
407 and/or the East Durham Link.
n) The ToR should require that that the human health risks be
addressed in the assessment of alternative methods.
0) Cumulative effects thresholds should be examined, especially from a
natural environment perspective - for example, for area sensitive
breeding birds. (Staff Report PSD-099-03; Section 7.2.1 e)
699032
REPORT NO.: PSD-082-04
PAGE 12
p) The impact of terminating the Highway 407 extension at the East
Durham Link on traffic and the operation of the local and Regional
Road network must be examined, even if the termination is an interim
step. In particular, the potential impact on the operational
characteristics of area roads and the financial burden on municipal
taxpayers to pay for road improvements must be considered (Staff
Report PSD-099-03, Section 5.2.1 f; 6.2.1 m)
q) Under the Social Environment Factor, the indicators for property
impacts should be expanded to include proximity impacts on nearby
land uses that may be only partially displaced by a particular
alternative method.
r) The extension of Highway 407 will provide a greater benefit to areas
to the west; the potential negative economic effects of the highway
on Clarington should be addressed. (Staff Report PSD-099-03; Section
6.2.1 m)
s) The maintenance of easy and efficient access between farm
properties is essential to the viability of farm operations and should
be specifically addressed in the EA. (Staff Report PSD-099-03; Section
6.2.1 p)
t) The potential impact on crop production if stream flows and
groundwater used for irrigation are reduced must be addressed.
(Staff Report PSD-099-03; Section 6.2.1 q)
u) The EA should address the effect of the fragmentation of farm
parcels, agricultural clusters of farms, and farm-related businesses
on the viability of farming. (Staff Report PSD-099-03; Section 6.2.1 r)
v) Increased traffic on roads leading to a new highway will jeopardize
the efficient and safe movement of farm machinery. (Staff Report PSD-
099-03; Section 6.2.1 s)
w) Impacts on agricultural operations related to the operation of a
highway, such as salt spray, should be addressed. (Staff Report PSD-
099-03; Section 6.2.1 t)
x) The cumulative effect of a major transportation project on Clarington's
agricultural community should be addressed.
6.3 Concept Desiqn
6.3.1 Once the preferred alternative method is selected, a concept design will be
prepared based on design standards to be established for the project. The
concept design usually shows the plan (horizontal alignment) and profile
(vertical alignment) of the preferred method, assuming it involves infrastructure
699033
REPORT NO.: PSD-082-04
PAGE 13
such as a roadway extension, transitway or commuter rail line. The process for
preparing the concept design is not outlined in the ToR, as it will be developed
during the EA in association with interested stakeholders.
6.4 Monitorinq Strateqy and Schedule
6.4.1 The ToR indicates that, during the Individual EA, MTO will develop a strategy
and schedule to monitor the construction and operation of the recommended
alternatives to ensure that all requirements of the EA are met. Monitoring and
follow-up programs may also continue beyond the end of the implementation
phase.
a) A statement should be added to the ToR to indicate that the EA
process and the specific conditions of the EA will be adhered to
should the project proponent change - ego transferred to another
agency or sold to the private sector. (Report PSD-099-03, Section
3.2.1 a)
b) Monitoring and follow-up programs must continue beyond the end of
the implementation phase to allow unintended impacts and
mitigation failures to be properly identified and addressed.
Restoration and compensation must be a key component of such a
strategy. Effective monitoring is dependent on the collection of
appropriate environmental baseline information. (CAC, Section 2.11)
6.5 Consultation
6.5.1 The ToR propose a program for consulting with the public, stakeholders and
agencies during the EA study. A variety of consultation techniques will be used,
including Public Information Centres, and the establishment of a Community
Advisory Committee and a Municipal Technical Advisory Group. Additional
forms of consultation will be considered as the project progresses. The
consultation strategy appears to be similar to that proposed in the 2003 ToR.
6.5.2 MTO has committed to make their draft EA Report available for municipal,
regulatory agency, public and First Nations review prior to formally submitting
the final EA to the Minister of the Environment for review and approval.
Changes may be made to the draft Report based on the results of this pre-
submission review.
6.5.3 Comments
a) Effective consultation is dependent upon MTO providing sufficient
information about the project to agencies and public in a timely
manner. (CAC, Section 2.12)
699034
REPORT NO.: PSD-082-04
PAGE 14
b) The general nature of the ToR will require public consultation
throughout the EA process to ensure that alternatives are not
dismissed too easily. (CAC, Section 2.12)
c) MTO has not made sufficient effort to explain major changes to the
ToR and the EA process arising out of the recent court decision.
PICs should include a presentation component, along with Q & A
session, to permit the public to better understand the project and
process, to hear answers right there and then to ask questions. This
still permits those preferring to ask questions one on one the
opportunity to do so. (CAC, Section 2.12)
d) The results of specific environment studies and the overall on-going
study should be presented to the CAC in a timely and complete
manner to allow feedback and input to the study. MTO should make
a specific commitment to meet with the Clarington Highway 407 CAC
on a regular basis during the EA process (eg. once per quarter).
(CAC, Section 1.2 f)
6.6 Flexibility
6.6.1 The EA ToR must be submitted to and approved by the Minister of the
Environment before the EA process can begin. It will then be used to guide
how the EA will be prepared. Based on the new rules for ToR preparation, the
407 East Completion ToR represent the minimum requirements to be followed,
and certain modifications may become appropriate as the project progresses.
The ToR lists the types of additional work that may be contemplated in the
project, including but not limited to: consideration of additional problems and
opportunities, additional objectives to be used in evaluating alternative
undertakings, additional criteria to be used in evaluating alternative methods,
additional evaluation methodologies, additional technical studies and
enhancements to the consultation programs.
6.6.2 Comment
a) The flexibility built into the EA by the ToR may involve additional
work to enhance the EA process, but it could also mean reducing the
scope of work in any particular area. Significant changes to the EA
process should not proceed without consultation with the public and
other stakeholders.
7.0 CONCLUSION
The Draft Terms of Reference for the Highway 407 East Completion EA are
very general in keeping with the objective of not "scoping" the project. As a
result, the EA study will need to be well managed and coordinated to meet the
objectives, requirements and expectations of the various stakeholders in this
process. The implementation of various transportation solutions in Durham
699035
REPORT NO.: PSD-082-04
PAGE 15
Region, including the extension of Highway 407, has the potential to
significantly affect the quality of life in Clarington.
Attachments:
Attachment 1 - Memo from Don Drackley, IBI Group
Attachment 2 - Memo from the Clarington Highway 407 Community Advisory
Committee
Interested parties to be advised of Council and Committee's decision:
Mr. Doug Allingham, P. Eng.
Consultant and Project Manager
Totten Sims Hubicki Associates
300 Water Street
Whitby, ON L 1 N 9J2
Mr. John Slobodzian
Provincial and Environmental Planning Office
Ontario Ministry of Transportation
301 St. Paul Street
St. Catherines, ON L2R 7R4
699036
~
MEMO
From:
Community Advisory Committee
Municipality of Clarington
Don Drackley, IBI Group
Janice Szwarz, Municipality
Faye Langmaid, Municipality
Date:
May31,2004
dd
To:
Steno:
cc:
File No:
TO-0696
Subject: REVIEW OF 2004 TERMS OF REFERENCE - 407 EAST COMPLETION
COMPARISON WITH 2003 TERMS OF REFERENCE
MAJOR ELEMENTS 2003 VERSION 2004 VERSION
OF THE TOR
The Terms of Reference was This time the TOR has been written
COMPLIANCE WITH prepared in accordance with in accordance with Section 6(2)(a)
THE ACT Section 6(2)(c), which requires owing to the Richmond Landfill
the proponent to "set out in detail" court decision MaE cannot "scope"
the requirements for how the EA or "focus" work in an Individual EA
TOR will be prepared. (can not "custom-make" the EA
process)
The result was that the 2003 TOR Section 6(2){a) requires only that
RESULTING TOR was extremely detailed in it's the proponent indicate that the EA
COPE AND LEVEL reassessment of Transportation will be prepared in accordance with
OF DETAIL Need and collection of the requirements of section 6.1 (2).
Environmental Condition data The result is a more narrowed
scope of work to address only the
requirements of 6.1 (2). The TOR is
a much simpler document since it
only has to address the
requirements of 6.1 (2).
The 2003 TOR was very specific There is no study area included in
STUDY AREA about the location and rationale this TOR, as the entire Region of
for 3 types of study area Durham is considered the area of
segments, with Segment 1 and 2 investigation for this EA. This
being very detailed in their means that hypothetically, works
alignment, and with Segment 3 associated with a Highway 407
(Clarington) being left open to East Completion could be located
routing alternatives anywhere, although assessments
of conditions, opportunities and
constraints would be expected to
"reasonable" alignments.
699037
IBI Group
CANADIAN
ENVIRONMENTAL
ASSESSMENT ACT
NEED &
JUSTIFICATION
ALTERNATIVES TO
THE UNDERTAKING
FACTORSICRITERIA
ALTERNATIVES TO
UNDERTAKING
ALTERNATIVE
METHODS
The previous TOR would have
been subject to any conditions of
the Individual EA that would
"trigger" federal CEAA
involvement.
The 2003 TOR went into great
lengths at reporting on previous
studies and current analyses that
confirmed the need for the East
Completion at least east to the
East Durham Link. The data
sources and methodology used in
this research was one are of
criticism in the Peer Review of the
TOR conducted by ISI Group in
June, 2003.
Following on the requirements of
Section 6(2){c ), this TOR focused
down the alternatives to the
undertaking to be highway
solutions, and specifically the 407
East Compietion. The option of
not extending the highway was
not an option. Some alternatives
to this undertaking included
widening Highway 401, improving
the Regional road system and
increase passenger and freight
transportation by rail. However,
the scope of the TOR was able to
eliminate all of these alternatives
from further consideration as not
be reasonable.
This is one area that generated
much debate as there is no clear
requirement in the Act as to what
evaluation factors and criteria are
used, as long the Natural, Social,
Culturai and Economic
Environments are represented.
In the 2003 TOR, the Alternative
Methods focused on alternative
routes for the three Highway 407
east Completion segments.
June 9, 2004
This is also the case in 2004 as
documented in Section 1.2 of the
TOR and Supporting Document A.
The TOR say very little about
project need (see page 8, 9), as
this is not specifically listed as a
necessary topic of inclusion under
Section 6.1 (2) does not specifically
include the question of "need".
However, clause (2){b){i) does
require "a description of and a
statement of the rationale for - the
undertaking" (in this case the 407
East Completion. The Act gives no
indication of the scope of work
required to make this description
and statement. They could be very
complex and detailed, or very brief
and general.
The 2004 TOR proposes
examination of a wider number of
alternative undertaking, many of
which are not highway-based,
ranging from Transportation
System Management and improved
transit service, through to improved
rail, marine and air service. Once
again, there is no indication in
either the TOR or the Act of the
scope of these evaluations, as they
couid be extensive or brief.
Same situation in this version and
the Committee should be assured
that Table 4.1 represents all of
these concerns for the proposed
"undertaking", but do not confuse
this with factors and criteria to iater
evaluate alternative methods which
is an entirely different subject.
In the 2004 version, the TOR do
not present the alternative
methods, but rather introduce the
process and Objectives of
699038
IBI Group
June 9, 2004
establishing alternative methods
(i.e. routes), a standard evaluation
methodology well-used in EAs and
the detailed evaluation factors,
criteria and indicators. In is here
that the Committee should once
again confirm their comfort with the
scope of issues to be evaluated.
The 2004 TOR called for a Although the Act is not specific on
CONSULTATION relatively in-depth consultation the type of consultation to provide
process using a variety of formats in an Individual EA, the new TOR
and measures. appears to propose a similar
program as proposed last year.
DESCRIPTION OF CONTENTS - 2004 TERMS OF REFERENCE
1.0 INTRODUCTION
1.1 Background - The need for additional east-west and north-south transportation (not
"highway") capacity determined in the Durham Transportation Master Plan (2003) and
Highway 407 Overview Study (1989) is referenced as the reason why MTO plans on
conducting an Individual Environmental Assessment (EA) of possible transportation
solutions in the Region. In our previous Peer Review of the 2003 Terms of Reference
(TOR), we noted concern about using the 1989 study as it is dated and does not take into
consideration current travel patterns. Conversely, it can likely be argued that traffic
conditions have only worsened since 1989, so any conclusion made in that study about
transportation need would be expected to remain valid today, and supported by traffic
analysis and forecasting conducted as part of the recent Durham Transportation Master
Plan.
The Background commits MTO to "consider" every phase of the EA process; Establish
Need, Evaluate Alternatives to the Undertaking (the Undertaking is the provision of
added transportation capacity), Evaluate Alternative Methods (these will likely involve
alternative routes and operations) and Recommend Specific Infrastructure.
1.2 Federal/Provincial EA Coordination - We agree with the TOR that the project will
trigger the need to address the Canadian Environmental Assessment Act (CEAA), and so
MTO wants to proactively coordinate this project to address both the federal and
provincial EA requirements. The federal requirements will be established by the
"Responsible Authority" (RA) pursuant to Section 5(1) of CEAA, but until we know what
will trigger the federal EA, we do not know what federal authority (department) will be the
Responsible Authority. For example, it could be Transport Canada if railways will be
crossed, or the Department of Fisheries and Oceans if fish habitat is impacted. MTO has
extensive experience in coordinating the federal and provinciai EA processes.
1.3 Submission Statement - This confirms MTO is the project proponent having charge,
management and control of the proposed undertaking. However, the TCR states later on
that if the preferred undertaking that results from the project falls under the responsibility
of another jurisdiction, for example Durham Region if the undertaking involves regional
6990:19
IBI Group
June 9, 2004
road widenings or Go Transit if it involves expanded commuter rail service, then MTO
would transfer the project all or in part to that jurisdiction.
2.0 PURPOSE OF THE UNDERTAKING
2.1 Overview and Outlook - This section summarizes why MTO is planning the
"undertaking", which is defined as providinq additional east-west and north-south
transportation capacity within the Reqion of Durham, by referring to previous
transportation need studies. Note that the TOR does not focus the undertaking down to
be the 407 East Completion, but rather leaves all options open. Section 2.4 states that
the need for and description of any proposed undertaking(s) will be developed in the EA
through preparation of a Transportation Planning/Need Report. The scope and content
of that report are not described, so it could be the previous Transportation Planning/Need
Report prepared last year and reviewed by IBI Group.
Not fully describing the transportation need in the TOR is an extremely different approach
than used in the 2003 TOR where extensive traffic analysis and forecasting was included
in the Transportation Planning/Need Report to justify the 407 East Completion. However,
the subsequent Ontario Superior Court decision preventing the scoping of IndiVidual EA
TOR also means that the need for and type of undertaking must be determined as part of
the EA process, and not as part of the TOR. The TOR also establishes the area of
consideration for the EA to be the entire Durham Region extending from the Oak Ridges
Moraine to Highway 401, and from the east Pickering area to Highway 35/115.
The remainder of this section briefly summarizes the findings of various growth-related
studies that support the position that the undertaking is required on the basis of
population and employment growth, trade, tourism and recreation (i.e. Kawarthacottage
country traffic), economics and business. It also briefiy summarizes the current state of
the raii, highway, regional road and transit corridor systems within the area of
consideration. In order to fully understand and analyse this information, reference must
be made to the source studies.
2.2 Transportation Problems - Once again, previous studies are used as the source of
information on existing and forecast transportation problems in Durham Region. Major
problems are listed and the TOR commits to additional analysis of transportation
problems as part of the EA, but does not describe the scope and type of this analysis. In
other words, the analysis could be very extensive or very brief since the TOR provides no
guidance for this work. Also, note that the stated problerns are limited only to
transportation, and do not inciude any related probiems associated for example with air
quality, other environmental impacts, affordability or quality of life issues.
2.3 Transportation Opportunities -As required by the EA process, the TOR lists a number
of opportunities available in Durham Region that will be "considered" in the EA to address
the previous stated transportation problems. These opportunities involve:
· Transportation - reduced congestion and associated impacts, improved user safety,
more transportation choices, reduced travel demand, improved passenger rail service
and optimized/expanded existing infrastructure;
699040
IBI Group June 9, 2004
. Economy - improved efficiency/reduced costs for goods movement, improved
connections between economic centres, improved goods movement choices, support
for tourism and trade growth, etc.; and
· Environment - develop transportation infrastructure that preserves natural
resources, and protects/enhances existing communities.
3.0 POTENTIAL ENVIRONMENTAL EFFECTS
The previous 2003 TOR included extensive information on natural and social
environment conditions associated with the proposed 407 East Completion study area.
Since the subsequent court ruling does not permit this type of inforrnation to be included
as part of a TOR, the new description of Potential Environmental Effects is extremely
brief. It is assumed that the previous environmental research and data will be recycled
into the new EA process. Section 3.0 of the TOR simply summarizes how environmental
information is proposed to be used as part of the EA evaluation process.
4.0 ALTERNATIVES TO THE UNDERTAKING
4.1 Identifying and Assessing Alternatives to the Undertaking . Once again, the
"undertaking" involves a project or projects that will be selected through the EA process
to provide additional east-west and north-south transportation capacity within the Region
of Durham. Various alternative types of projects are listed that will be examined and
assessed in the EA, ranging from the Do Nothing Alternative that is required in any EA,
through to demand and system management alternatives, other mode alternatives (air,
rail, marine, transit) and roadways. Combinations are also possible, and the TOR
commits to considering additional alternative undertaking that may be suggested by
review agencies, stakeholders and the public. However, the TOR does not described the
scope and extend of assessment to be conducted on the alternatives, so the work could
be very extensive or very brief.
This section of the TOR also correctly states that the assessment of alternatives to the
undertaking will look at the fundamentai differences among the alternatives, but
essentially says that the effectiveness of each alternative to resolve the existing and
expected transportation problems is of prime importance. We take this to mean that even
if an alternative performs well from an economic or environmental perspective, if it does
not resolve the transportation problems it will likely not be considered further in the EA
process.
This TOR section also lists the "minimum considerations" or criteria on Table 4.1 to be
used in assessing the alternatives to the undertaking. Since these alternatives involve
strategic ievel comparisons, such as the performance of improved/new roads compared
to say improved air transport service, the assessment criteria involve strategic subjects
such as ability to reduce peak hour travel demand, support trade and impact
environmentai areas. The criteria are not intended to be project, location or route specific
as these more detailed types of assessment come later in Section 5.0. Also, the TOR
clearly states that the criteria for assessing alternatives to the undertaking are the
minimum to be used, and the list will be augmented and refined based on agency,
stakeholder and public input, and on the progress of the actual assessment process.
6991Hl
IBI Group
June 9, 2004
4.2 Selecting the Preferred "Alternative To" (Planning Alternative)- The assessment of
all alternatives to the undertaking must conclude with a recommended alternative(s) to
carry forward into the second and more detailed assessment process. The TOR states
that if the No Nothing alternative is selected, the EA process is complete and over. If the
preferred alternative is outside of MTO's jurisdiction involving commuter rail or regional
roads for example, then the current EA process would stop and MTO would transfer
responsibility for the continuing process to the appropriate agency for further action. If
the preferred aiternative falls under MTO jurisdiction, the EA process continues, and if
jurisdiction is shared, MTO wili only continue with the solutions under its responsibility.
5.0 ALTERNATIVE METHODS
5.1 Process for Generating a Study Area - Once the more strategic undertaking has been
selected, the EA process moves into a more detailed assessment of that undertaking in
terms of its location, design, function and impacts. The first step is to define the study
area where these aspects of the preferred undertaking will be considered. The previous
2003 TOR included a relatively detailed description of the study area divided into three
sub-areas, but the new TOR does not include any study area. This is consistent with
MTO's own EA process, called the Class EA For Provincial Transportation Facilities,
where the study area is determined based on the preferred undertaking. It is also
important to note that even once the study area is defined, its boundaries can be refined
or modified to accommodate any reasonable alternative methods as the study
progresses, such as a change in an alignment.
5.2 Generating, Assessing and Evaluating Alternative Methods - This section of the
TOR is the most detailed, describing the process to be used in generating, assessing and
evaluating alternative methods. This is usually an iterative process that involves 5 main
steps:
STEP 1: Set the basic or strategic objectives for the alternative methods as listed on
page 17 of the TOR, such as maximize use of existing infrastructure (i.e. roads, rail,
transit, etc.). The reasons for including each alternative method in the EA should
respond to these objectives.
STEP 2: Set the more detailed Environmental and Technical objectives for the alternative
methods as listed in Table 5.1 of the TOR, remembering that Environment includes the
Natural Environment, Socio/Cultural Environment and Economic Environment. It is
important to note that Table 5.1 includes Objectives for alternative method generation, not
evaluation criteria (see Table 5.2). Also, the TOR does not explain what happens if a
candidate method does not satisfy one or more of the objectives on Table 5.1, but it must
be expected that some cut-off will be established to identify when a candidate method
does not satisfy a suitable number of the 20 recommended objectives, and is therefore
not included as an alternative method for further assessment. It is also interesting to note
that 11 objectives (1 through 11) involve the Natural Environment, 7 the Socio-Economic
Environment (12 through 18) one the Socio-Cuitural Environment (19) and one the
Economic Environment (20). This means that natural and social environment conditions
will be very influential in generating alternative methods.
STEP 3: Assess the net expected impacts of each alternative method expected to remain
after standard mitigation measures are used (i.e. noise exposure after noise walls are
installed).
699042
181 Group
June 9, 2004
STEP 4: Expand the assessment into a comparative evaluation of the advantages and
disadvantages of each alternative method by first using a Reasoned Argument rnethod to
describe in words these pros and cons based on know legislation, policies, conditions,
issues and professional expertise. The resulting descriptions are then assigned a level of
importance called a WEIGHT, and a SCORE that numerically measures the extent of
advantages or disadvantages. This process is called an Arithmetic Evaluation method,
and both methods are used extensively in the EA process.
STEP 5: The descriptive and numeric results of Step 4 wiil be used to compare each
alternative method against the others and determine which method offers the best
weight-score combination, usually interpreted as representing the best possible method.
This process also allows for trade-offs to be made where it may be possible to accept a
certain type of impact or impacts of the best performing method because it still offers
many other advantages. In fact the entire process to select the preferred method
invoives trade-offs since it is seldom that one particular method is "perfect" with rnaximum
advantages and no disadvantages.
This is where the setting of evaiuation criteria and weights is so important in the EA
process. The criteria in Table 5.2 should be heavily scrutinized so that no reasonable
subject, issue or question is missed when the alternative methods are being evaluated.
This reviewer finds Table 5.2 to generally be complete, except under Social Environment
where property impacts could be expanded to include proximity impacts on nearby land
uses that are not entirely displaced by a method, but may still be affected by partial
displacement.
5.3 Concept Design - Once the preferred alternative method is selected, a concept design
will be prepared based on design standards to be established for the project. The
concept design usually shows the "plan and profile" of the preferred method, assuming it
involves infrastructure such as a roadway extension, transitway or commuter rail line.
The "plan" shows the horizontal alignment of the facility, and the "profile" shows the
vertical alignment based on the existing and engineered profile of the land it traverses.
The process for preparing the concept design is not reported in the TOR, as it will be
developed during the EA in association with interested stakeholders.
6.0 MONITORING STRATEGY AND SCHEDULE
This is a very brief commitment that MTO will develop a strategy and schedule to monitor
the construction and operation of the recommended alternative(s) to ensure all
requirements of the EA are met. This could involve, for example, the treatment of
watercourse crossings, stormwater management and noise attenuation.
7.0 CONSULTATION
All consultation held during the EA will conform to provincial and federal environmental
assessment requirements. MTO proposes to use a variety of techniques to consult with
the public, stakeholders and agencies. A Community Advisory Committee will be
established, and additional forms of consultation will be considered as the project
progresses.
6990lj3
IBI Group
June 9, 2004
7.1 Public Consultation - Section 7.1 of the TOR briefly describes what are standard
consultation techniques used in EAs, with four rounds of Public Information Centres (one
during each of the four EA stages), required notifications, project web site, toll-free phone
number, letters, faxes, the Community Advisory Committee and individual meetings and
presentations to stakeholder groups. Except for the mandatory public meetings, the
other consultation techniques are not specifically required by the EA process or Ontario
EA Act. The consultation process appears to be similar to that proposed in the 2003
TOR.
7.2 Municipal Consultation - The use of a Municipal Technical Advisory Group (MTAG)
and Council presentations appear similar to those proposed in the 2003 TOR, and are
also not mandatory consultation requirements.
7.3 Methods of Consultation for External Agencies- MTO proposes to involve regulatory
groups in the EA through a Reguiatory Advisory Group, which is often used in larger,
complex EAs.
7.4 First Nations - A specific First Nations consultation plan wili be developed and followed
during the EA based on First Nations interests in the project and study area.
7.5 Pre-Submission Review of the Draft EA Report- MTO commits to make their draft EA
Report available for municipal, regulatory agency, public and First Nations review prior to
formally submitting the final EA to the Minister of the Environment for review and
approval. Changes may be made to the draft Report based on the results of this pre-
submission review.
8.0 FLEXIBILITY
The EA TOR must be submitted to and approved by the Minister of the Environment
before the EA process can begin. It will then be used to guide how the EA is prepared. It
is important to note that based on the new rules for TOR preparation, the 407 East
Completion TOR presents the "minimum requirements to be followed'; and it states that
certain modifications may become appropriate as the project progresses. This may
involve additional work to enhance the EA process, but it could also mean reducing the
scope of work in any particular area, although reducing scope is difficult to do when an
EA in under careful and continuous public scrutiny. The TOR lists the types of additional
work that may be contemplated in the project, including but not limited to consideration of
additional problems and opportunities, additional objectives to be used in evaluating
alternative undertakings, additional criteria to be used in evaluating alternative methods,
additional evaluation methodologies, additional technical studies and enhancements to
the consultation program.
699044
Q~-!lJglon
TO:
Mayor and Members of Council
FROM:
Clarington Highway 407 Community Advisory Committee
DATE:
04 June 2004
RE:
Comments on Draft Terms of Reference - 407 East Completion
Environmental Assessment
The Clarington Highway 407 Cornmunity Advisory Committee has reviewed the revised
Draft Terms of Reference for the Highway 407 East Completion EnYironmental
Assessment, and has prepared the following comments for Council's consideration.
Janice Szwarz, Senior Planner
Staff Liaison to the Highway 407 CAC
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T(905)623-3379 F (905)623-0830
699045
Clarington Highway 407 Community Advisory Committee
Recommendations to Clarington Council on the
Draft EA Terms of Reference for the Highway 407 East Completion
1. General Comments
1.1 The Draft Terms of Reference (ToR) are very general in keeping with the
objective of not "scoping" the project. As a result, the project will need to be well
managed and coordinated to rneet the objectives, requirements and expectations
of the stakeholders in this process. A very specific ToR with clearly outlined
tasks and completion targets can give very clear definition of study expectations
in terms of the level of effort to be directed to the various components of the
study. It is not possible with this type of ToR to determine how much effort will
be given to the various aspects of the work program.
Because the ToR are so general, the CAC has developed some expectations of
the Environmental Assessment study process. These expectations, as outlined
below, would be benchmarks that the CAC could use as a guide in our dialogue
with the Study Team.
1.2 Expectations
a) That the study will provide a definitive recommended Transportation Plan
for the eastern GT A and from our particular point of view, the Municipality
of Clarington.
b) That transportation demand for existing and future conditions, including
intermediate planning horizons within the overall planning period, will be
dealt with in a very thorough manner.
c) That the Transportation Departments of the Region of Durham and the
Municipality of Clarington will work in conjunction with the Study Team to
provide a comprehensive overall plan that will deal with local and regional
transportation issues that arise from proposed solutions.
d) That the Region of Durham Official Plan will be completed in a timely
rnanner to provide a basis for the transportation planning.
e) That the Ministry of Transportation will assume a transportation mode of
thinking beyond that of a Department of Highways frame of mind and, as
necessary, ensure that other transportation providers, such as GO
Transit, will contribute the necessary input for alternative components of
the study.
f) That results of specific enYironment studies and the overall on-going
study will be presented to the CAC in a timely and complete manner to
allow feedback and input to the study. It is suggested that the Study
Team meet with the CAC once a quarter.
g) That the Study Tearn will present specific examples where alternative
transportation solutions have been applied in similar circumstances and
699046
will outline their effectiveness in the context of the Municipality of
Clarington and also the environmental impacts associated with a specific
proposal.
h) That the current 400 series highways will be used as examples to assess
the impact and effectiveness of the 407 east extension.
i) That the assessment of the 407 east extension will look at the toll and
non-toll alternatives.
j) That the recommended alternatives for the transportation plan will be
assessed at various stages of implementation to tie in with the growth of
transportation dernand as outlined in Point b) above.
2. Specific Comments on Draft Terms of Reference
2.1 Introduction (p. 1)
The ToR state that the document will establish minimum requirements to be
followed during the preparation of the subsequent Individual EA, and will allow
flexibility to consider enhancements to the process.
CAC Comments
The inclusion or consideration of any enhancements would be at the
discretion of the proponent. It is therefore extremely important that as
many issues as possible be commented on now.
2.2 Federal/Provincial Environmental Assessment Coordination (p. 1)
The project resulting from this EA will also be subject to the Canadian
Environmental Assessment Act (CEAA). Federal authorities frequently wait until
a specific project has been defined to formally declare whether or not the project
will require an approval frorn that agency. However, It has been federal practice
for agencies to informally participate in the EA process prior to such a
determination being made.
CAC Comments
To date, some federal agencies have not participated in Regulatory
Advisory Group meetings. MTO should formally re-invite all potential
participants in Regulatory Advisory Groups to ensure active consultation
with all appropriate federal agencies throughout the EA.
2.3 Population and Employment Growth (p. 3)
The ToR state that, between 2004 and 2031, Durham Region's population is
expected to grow from 550,000 to 1,055,000, while employment is forecast to
almost double from 170,000 to 311,000.
CAC Comments
The draft ToR appear to rely on future population and employment figures
from the Durham Region's Official Plan Review. While the figures for
699047
population can be considered forecasts, the numbers used for employment
are less reliable because they are based on a full build out of employment
lands at selected densities. Other population and employment scenarios
need to be considered.
2.4 Trade (p. 3)
The ToR note that the manufacturing sector accounts for over 25% ($2.3 billion)
of the Region's total gross dornestic product, and that comrnercial vehicle travel
in and through Durham is anticipated to increase at a rate of approximately 3%
per annum.
CAC Comments
The impact of rising gas prices and other operating expenses associated
with trucking needs to be considered on existing truck traffic routes and
potential truck traffic on a future Highway 407 with and without tolls.
2.5 Tourism and Recreation (p. 5)
The ToR note the importance of tourism and recreation to Ontario's economy
and that Durham Region, as the eastern gateway to the GTA, will experience
increased tourist travel. Tourism is also important to the Kawartha/Haliburton
areas to the north.
CAC Comments
Increased gas prices and vehicle operating costs could also affect the
volume of tourist and cottager traffic through Durham Region.
2.6 Transportation (p. 5)
Traffic congestion occurs regularly on Durham Region's road network during
morning and afternoon peak periods for commuter travel, as well as during peak
travel periods for tourist and recreational traffic. Planned growth in the Region
will require improvements to the regional and provincial road systems, local
transit systems, and rail for both passengers and freight.
CAC Comment
Analysis of transportation alternatives must include an analysis of all
current, promised and projected spending commitments from/to various
governments, including 10 Year and beyond capital spending plans of Go
Transit, Via Rail, CN and CP rail, York Region Transit, TTC, locallregional
transit systems etc. This must include a full discussion of possible
improvements to existing provincial, local and regional road infrastructure.
2.7 Summary (p. 11)
The ToR states that the purpose of the undertaking is to address the identified
problems and opportunities by providing additional east-west and north-south
transportation capacity within the Region of Durham for a 30 year planning
horizon. The specific need for any proposed undertaking(s) and a description of
699018
any proposed undertaking(s) will be developed during the Individual EA through
the preparation of a Transportation Planning/Need Report.
CAC Comments
The draft ToR do not meet the requirements of the OEAA [Sec. 6.1(2)(2)( b)]
which requires both a description of the undertaking and a rationale for the
undertaking. There is a discussion of need, which is not the same as a
rationale. The ToR need to be amended to include both a description and a
rationale for the undertaking.
The ToR should also address the policy context in which the EA is being
conducted and how it will be affected by other provincial initiatives, such
as the establishment of the Greater Toronto Transportation Authority, the
proposed GTA Greenbelt, GO Transit expansion, the revised Provincial
Policy Statement, and Smart Growth/Growth Management.
2.8 Potential Environmental Effects (p. 12)
The ToR indicate that research already undertaken has led to a basic
understanding of the existing environment and major environmental features in
Durham Region. Further environmental investigations will occur during the
Individual EA.
CAC Comment
A description of the environment to be affected, and the data that would be
used to describe it, should be included in the draft ToR. This would
address such matters as data collection and comprehensiveness and the
level of additional field investigations required. A very good
understanding of the environment is required before a proper examination
of potential environmental effects can occur.
2.9 Alternatives to the Undertaking (p. 13)
The ToR defines alternatives to a proposed undertaking as being "functionally
different ways of approaching and dealing with a specified problem or
opportunity." A process for identifying and assessing the alternatives to the
undertaking is described. Table 4.1 sets out three factors (transportation,
economy, environment) and criteria for each factor to be used in the assessment
of the alternatives.
CAC Comments
The factors and criteria used to assess alternatives are critical to the public
having confidence that the alternatives will be assessed fairly and
comprehensively.
For each factor, a criteria should be added that addresses the degree to
which proposed transportation system modifications support federal,
provincial, regional and municipal policies that affect that factor.
699049
A full cost/benefit analysis must be provided of the alternatives to - both
short and long-term. Many costs and benefits are long -term or cannot be
easily quantified (eg. improved or reduced air quality).
Given the length of time required to fully implement an alternative, the
specific analysis of any alternative must be conducted for the short-term
(5-10 Years), medium term (10-20 years), and long term (up to 30 years).
The review of alternatives must include an analysis of the impacts related
to the possible termination of Highway 407 at the East Durham Link
(whether interim/temporary or permanent), and the need for improvements
to the Regional Road system to deal with the traffic (eg. widening of
Taunton Road). The Province should also commit to provide funding to
assist the Region and the local municipalities with any required capital
improvements resulting from the construction of the highway.
The term "environment" must be used in its fullest sense to include the
natural, cultural, and socio-economic environments.
There is no reference in the ToR or the Supporting Documentation to a
process/methodology to identify, assess and evaluate Alternatives To.
The ToR do not define the extent of the analysis that will be conducted on
alternatives. Given that it is this stage where alternatives are eliminated
from further consideration, the ToR should require a robust and more
detailed evaluation than what would appear to be currently required.
2.10 Alternative Methods (p. 16)
The ToR indicate that, once a preferred alternative to the undertaking has been
identified, a study area will be defined and the process commended to generate,
assess, evaluate and select the preferred alternative method(s) to resolve the
defined transportation problem. For example, for a highway, alternative methods
could include different alignments. The ToR outline a number of environmental
and technical objectives to be used to generate alternative methods, such as
"minimize impacts to water bodies" and "avoid encroachment on Provincially
Significant Wetlands and impairment of wetland function."
CAC Comments
. The CAC believes that the Oak Ridges Moraine and the Black-Farewell
Wetland should be identified in the ToR as exclusionary objectives.
The CAC also believes that the following should be given special
consideration in the evaluation of alternative methods:
· avoid critical ground water recharge areas, heritage homes, and large
contiguous blocks of prime agricultural land
· maximize distance from established hamlets
· avoid designated serviced industrial land.
699050
.
The public should be involved in the development of the criteria for the
generation and evaluation of alternative methods. The development of
criteria specific to each area municipality should be considered to reflect
local values.
The ToR should also require seasonal transportation alternatives to be
considered.
2.11 Monitoring Strategy and Schedule (p. 27)
The ToR indicates that, during the Individual EA. MTO will commit to developing
a strategy and schedule for monitoring the implernentation of any recommended
alternative(s). Monitoring and follow-up prograrns may also continue beyond the
end of the implementation phase.
CAC Comments
Monitoring and follow-up programs must continue beyond the end of the
implementation phase to aI/ow unintended impacts and mitigation failures
to be properly identified and addressed. Restoration and compensation
must be a key component of such a strategy. Effective monitoring is
dependent on the collection of appropriate environmental baseline
information.
2.12 Consultation (p. 28)
The ToR outlines a process for consulting with the public, municipalities,
regulatory agencies and First Nations throughout the EA process.
CAC Comments
Effective consultation is dependent upon MTO providing sufficient
information about the project to agencies and public in a timely manner.
The general nature of the ToR will require public consultation throughout
the EA process to ensure that alternatives are not dismissed too easily.
MTO has not made sufficient effort to explain major changes to the ToR
and the EA process arising out of the recent court decision. PICs should
include a presentation component, along with Q & A session, to permit the
public to better understand the project and process, to hear answers right
there and then to ask questions. This still permits those preferring to ask
questions one on one the opportunity to do so.
MTO should make a specific commitment to meet with the Clarington
Highway 407 CAe on a regular basis during the EA process (eg. once per
quarter).
699051