HomeMy WebLinkAboutPSD-034-04
.
Cl!Jlmgron
REPORT
PLANNING SERVICES
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date:
Monday, March 8, 2004
1'.)1'.1-
~GPA-lI~-O~
Report #: PSD-034-04
File #: PLN 8.6.5
By-law #:
Subject:
OMB DECISION ON APPEALS BY THE TDL GROUP LTD.
258 King Street East, Bowmanville
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report PSD-034-04 be received for information.
Submitted by:
o . Crame, MCIP, R.P.P.
Director of Planning Services
Reviewed by:
f
~
"O";OWu.
Chief Administrative Officer
CP/DJC/df
3 March 2004
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623- 3379 F (905)623-0830
I ,-- '.
00)
REPORT NO.: PSD-034-04
PAGE 2
1.0 BACKGROUND
1.1 The TDL Group applied for site plan approval in April 2002 and removal of holding
application in September 2002, for the property located on the north west corner of Kin~
Street East and Galbraith Court in Bowmanville. They proposed to construct a 130 m
restaurant with a drive-through facility on the property. Appeals were filed to the OMB
for failure by the Municipality to make a decision on these applications within 90 days.
On January 6, 2003, Council adopted an Interim Control By-law for the lands known as
the King Street East Corridor, which included the subject lands. The TDL group, Janet
and John Rice, George Tzalis, the Bowmanville Mall and the Jean Coutu Groupe filed
appeals to the Interim Control By-law. Janet and John Rice had also appealed an
application for site plan approval for 209 and 215 King Street East, the Kentucky Fried
Chicken and Pizza Hut property. Staff was able to negotiate a withdrawal of the appeals
by the Bowmanville Mall and the Jean Coutu Groupe.
1.2 The Municipality's solicitor and the Director of Planning and Engineering have briefed
Council on the OMB's decision. The purpose of this report is to summarize the decision
for the public.
2.0 OMB HEARING AND DECISION
2.1 The procedural order for the hearing divided the hearing into two phases: Phase 1
dealing with the Interim Control By-law and Phase 2 dealing with the site plan and
zoning appeals by the TDL Group. The OMB scheduled five days at the end of June to
hear the appeal to Interim Control By-law, as well as the two appeals by the TDL Group
Ltd. At the end of the five days of hearing all the evidence related to the Interim Control
By-law appeal had not been heard. As a result the Board member determined an
additional 10 days was needed to hear the remainder of the evidence and argument on
the appeal to the Interim Control By-law and the two appeals by the TDL Group Ltd.
The hearing was adjoumed until December 2, 2003, the first available date
accommodating the schedules of the board member and the solicitors for the TDL and
the Municipality.
2.2 While the Board hearing was adjourned the Municipality completed the King Street East
Corridor Study. A report with the study findings was prepared for Council's
consideration in September. In October, Council adopted an Official Plan Amendment
and zoning by-law amendment, implementing the study recommendations related to
land use and repealed the Interim Control By-law. Both amendments were appealed to
the OMB by three different parties, including the TDL Group Ltd.
2.3 When the hearing resumed in December, George Tzalis withdrew his appeal as the
Interim Control By-law had been repealed. The lawyer for the Municipality brought
forward a motion requesting that the Phase 1 portion of the hearing be terminated. He
argued that there was no point in continuing with the hearing on the appropriateness of
the Interim Control By-law. The Municipality had completed the study intended during
the Interim Control By-law, adopted Official Plan Amendment and Zoning By-law
Amendment implementing the study recommendations related to land use and repealed
the Interim Control By-law. Therefore, there was no longer a by-law in place for the
OMB to amend, repeal or confirm. He further argued that the TDL applications should
UC;-T
REPORT NO.: PSD-034-04
PAGE 3
be reviewed in the context of the planning policies that the Municipality had adopted
through Official Plan Amendment #36 and a related Zoning By-law Amendment.
Therefore, the appeals by TDL on the site plan and removal of holding applications
should be dismissed or consolidated with the appeal of Official Plan Amendment and
the related zoning by-law amendment for the King Street East Corridor.
2.4 The Board after receiving both verbal and written argument provided a ruling on the
motion. The Board member ruled that the appeal to the Interim Control By-law was
"moot" and the Phase 1 portion of the hearing should not continue. However, the Board
member determined that because the Official Plan Amendment and zoning by-law
amendment have been appealed, and the Interim Control By-law was repealed, the
planning regulations in place prior to January 6, 2003 are applicable for the review of
the TDL applications. As a result the appeal by TDL on the site plan and removal of
holding applications would proceed. The balance of the two weeks, as well as two
additional days, were dedicated to planning, transportation and urban design evidence
and legal argument with respect to why the application and removal of holding
application should, or should not be approved.
2.5 In February the Board released its decision (Attachment 1). In summary the Board
allowed the appeal on the site plan application, preferring the evidence of TDL on most,
but not all, issues. However, on the removal of holding, the Board determined that there
is need to have intersection improvements completed at Galbraith and King St. E. prior
to allowing the development to proceed. Therefore the removal of Holding is premature.
"However, due to the promising manner that intersection improvements were addressed
by the Municipal Engineer, his engineering consultants. . . the Board will withhold its
Order dismissing the Appeal for six months to allow, in the public interest, for the
intersection improvements to be advanced in the good faith expressed to date."
3.0 FOLLOW-UP ON THE DECISION
3.1 Further to the Solicitor's report to Council on the decision, and Council's authorization,
an application seeking leave to appeal certain aspects of the Board's decision has been
filed with the Divisional Court on the grounds that the Ontario Municipal Board erred in
law. The Municipality's Solicitor will continue to keep Council informed of ongoing
matters related to the Board's decision.
3.2 Engineering Services is continuing to review opportunities for improvements to traffic
safety, operations and capacity for the King Street East Corridor.
3.3 A pre-hearing conference on the appeals of Official Plan Amendment #36 and the
related Zoning By-law to implement the King Street East Corridor is being scheduled for
April.
Attachments:
Attachment 1 - O.M.B. Decision
\) C) j
ATTACHMENT 1
ISSUE DATE:
February 4, 2004
DECISION/ORDER NO:
!Ii
PL021 066
PL020908
PL030235
0214 Ontario
Ontario Municipal Board
Commission des affaires municipales de l'Ontario
Janet Rice and John Rice have referred to the Ontario Municipal Board under subsection 41 (12)
of the Planning Act, R.S.O. 1990, c. P.13, as amended, determination and settlement of details
of a site plan for lands composed of 209 and 215 King Street East, in the Municipality of
Clarington
OMB File No. M020115 (PL021 066)
TDL Group Ltd. has referred to the Ontario Municipal Board under subsection 41 (12) of the
Planning Act, R.S.O. 1990, c. P.13, as amended, determination and settlement of details of a
site plan for lands identified as 258 King Street East, in the Municipality of Clarington
O.M.B. File No. M020094 (PL020908)
TDL Group Ltd. has appealed to the Ontario Municipal Board under subsections 36(3) of the
Planning Act, R.S.O. 1990, c. P.13, as amended, from Council's refusal or neglect to enact a
proposed amendment to Zoning By-law 84-63 of the Municipality of Ciarington to remove the
Holding (H) symbol from lands municipally known as 258 King Street East, in the Municipality of
Clarington
OMB File No. Z020171 (PL020908)
Janet Rice and John Rice, TDL Group Ltd., 591617 Ontario Limited, Le Groupe Jean Coutu
(PJC) Inc., and Bowmanville Mall have appealed to the Ontario Municipal Board under
subsection 38(4) of the Planning Act, R.S.O. 1990, c. P.13, as amended, against Interim Control
Zoning By-law 2003-01, in the Municipality of Clarington
OMB File No. R030046 (PL030235)
APPEARANCES:
Parties
Counsel*/Aaent
TDL Group Ltd.
S. Makuch'
S. B. Leisk'
Municipality of Clarington
D. Hefferon'
591617 Ontario Limited
George T. Zalis
DECISION OF THE BOARD DELIVERED BY N.C. JACKSON
U :JJ
- 2 -
PL021066
PL020908
PL030235
Before the Board in this Hearing are a number of Appeals to Clarington Interim
Control By-law 2003-01 passed January 6, 2003 to be in effect for the period of one
year. There have been a number of settlements with Appellants and other Appellants
have chosen not to be present. Only TDL Group Ltd. (hereinafter referred to as TDL)
is now present as an Appellant to the Interim Control By-law. Also part of this hearing
and set for hearing by this panel following the Interim Control By-law first phase hearing
is a hearing on TDL Appeals to determine a site plan and to amend Zoning By-law 84-
63 to remove the H Symbol for property at 258 King Street, in the Municipality of
Clarington. The removal of the H is related. Both of these TDL Appeals on site Plan
determination and the removal of the H were set for Hearing by this Board but were
adjourned at the request of Clarington to be heard with the Interim Control By-law.
That decision was contested by TDL, however at this point in time the site plan and
related H-zoning removal are within a Procedural Order of this Board providing for
hearing by this panel. A site plan control Appeal by Janet and John Rice for their
property at 215 and 209 King Street was also consolidated with the Interim Control By-
law Appeals. That appeal, at the request of counsel for the Appellants Rice, was set for
a later date before this panel and then not proceeded with. The Rice site plan control
Appeal has not been abandoned. The Appellants Rice and their counsel, are not
present in this Interim Control By-law first phase hearing although they did appeal the
Interim Control By-law.
This Panel commenced hearing evidence during the week of June 23, 2003 on
the TDL Appeal to Interim Control By-law. Evidence was not completed in that week
and the Hearing was adjourned to December 2, 2003. That delay was in part due to
commitments by Counsel for TDL. Counsel for Clarington sought a one-day
adjournment to December 3, 2003 that was granted on Consent.
On the resumption of this Hearing on December 3, 2003, counsel for Clarington
informed the Board that Clarington Council had enacted new zoning, an Official Plan
Amendment and repealed the Interim Control By-law 2003-01. The Repealing By-law
2003-173 was given three readings and passed on October 20,2003. The new zoning,
By-law 2003-153 and Official Plan Amendment 36 were passed the same date, October
c) U (
- 3-
PL021 066
PL020908
PL030235
20,2003. To date, there have been four Appeals to the new Zoning and Official Plan
Amendment. Three of the Appellants were not Appellants to the Interim Control By-law
and not Parties in the present Hearing. Accordingly, following the discussion with
counsel present, this Panel of the Board determined that the Appeals to the new Official
Plan Amendment and Zoning would be heard by new panel of the Board following the
Municipality applying to the Board for a Hearing date. The presently constituted panel
then would not hear evidence on those new instruments. It was noted by counsel for
the Municipality that included in the new instruments were changes in zoning and the
Official Plan from commercial to residential for the TDL property at 258 King Street.
On December 3 2003, The Municipality moved for the striking of issues 1 to 3
inclusive from the Issues List in the Procedural Order, dealing with TDL's appeal to the
Interim Control By-law. The effect of that Motion is to terminate this Phase 1 Hearing.
Mr. Hefferon for the Municipality asserts that the three issues associated with the
repealed Interim Control By-law are now moot. He relies upon that doctrine as set out
in Borowskiv. Canada, [1989] 1 S.C.R. 342. In that case, Mr. Justice Sopinka explains
the mootness doctrine as follows:
The doctrine of mootness is an aspect of a general policy or practice that a
Court may decline to decide a case which raises a hypothetical or abstract
question. The general principle applies when the decision of the court will not
have the effect of resolving some controversy which affects or may affect the
rights of the Parties. If the decision of the court will have no practical effect on
such rights, the court will decline to decide the case. The essential ingredient
must be present not only when the action or proceeding is commenced but at
the time when the court is called upon to reach a decision. Accordingly, if
subsequent to the initiation of the action or proceeding, events occur which
affect the relationship of the Parties so that no present live controversy exists
which affects the rights of the Parties, the case is said to be moot. The
general policy or practice is enforced in moot cases unless the court exercises
its discretion to depart from its policy or practice.
The Court then outlined the following three considerations:
1. The competence of the court is rooted in the adversary system. Are
lj :,.) 0
- 4-
PL021 066
PL020908
PL030235
there collateral consequences of the outcome that will provide the
necessary adversarial context?
2. Judicial economy.
3. The need of the court to demonstrate an awareness of its proper law
making function. Pronouncing in the absence of a dispute may be
viewed as encroaching on the legislative branch.
Moreover, Mr. Hefferon asserts that a repealing By-law does not require approval
and is not before this Board. Re: Cadillac Development Corp. Ltd. et al and City of
Toronto (1974) 1 OR (2d) 1 and Re: City of Hamilton Official Plan Amendment 12 and
By-laws 84-64 and 88-86(1990) O.M.B.R.476.
Mr. Hefferon then requests that the TDL Group Ltd. Site Plan and related H
removal not be heard by this panel, but be heard by the new panel of the Board after
the hearing of the new Official Plan and Zoning Amendment 2003-153.
Mr. Makuch for TDL Group in his primary argument, does not dispute mootness
but asks that the Board find the repeal date not be on October 20, 2003 but effective
back to the day of passing - January 6, 2003. In the alternative, Mr. Makuch asks that
this hearing continue based upon the collateral consequence that he has applied for a
building permit which may be litigated. In that litigation the three issues sought to be
struck, could, he asserts, if a finding is made in his favour, be relevant as to the timing
of the permit application and its determination. The three issues relate to an attack on
the Interim Control By-law respecting bad faith, lack of planning purpose and failure to
exempt the TDL property from the By-law.
Mr. Makuch requests the second phase hearing on his site plan appeal and
removal of the H be heard by this panel based upon the doctrine of adjudication upon
the planning instruments in effect at the time of the Application. Clergy Properties Ltd. v.
City of Mississauga 34 O.M.B.R. 277 as confirmed in Greater Toronto Airports Authority
v. Clergy Properties Ltd. (Div.Ct.) File No. 3/97.
. ~,;"
- 5-
PL021066
PL020908
PL030235
The Board has carefully considered the oral and written legal argument. Both
Parties agree the Board has jurisdiction to rule on this issue of mootness as inherent to
the Board's jurisdiction to decide questions of planning and law under section 37 of the
Ontario Municipal Board Act. Toronto (City) v. Goldlist Properties Inc.,[2003] O.J. No.
3931. The Board finds issues 1, 2, and 3 as related to the Interim Control By-law to be
moot as a result of the repeal of that By-law. The Board is aware that there may be a
dispute in respect of a building permit application made by TDL in 2002. The
jurisdiction over any other possible dispute rests with the courts under the Building
Code Act. The Board has listened carefully to arguments imputing bad faith as a result
of the repeal. Those arguments, following the repeal, are for the Courts to determine.
Although the Board was interested in the effect of the repeal, particularly under the
enabling legislation in section 38, subsections 6 and 6.1 of the Planning Act, the Board
cannot implement, following a legislative repeal, in the normal manner of a Board
ordered repeal or amendment to the By-law, if it found in favour of TDL on those three
issues. The request of TDL to order a repeal effective the date of enactment appears
retroactive and more in the nature of a Declaration that is best left to the courts,
following the repeal. The Repealing By-law is not before the Board nor does it require
approval. It may be judicially interpreted.
The Board understands that in repealing the Interim Control By-law on October
20, 2003, the Municipality can no longer claim the benefit of the deeming in section
38(6.1) as they couid have, if its Interim Control By-law had expired before the new
zoning comes into effect. An Interim Control By-law comes into effect on the day it is
passed whereas normal Zoning under section 34 of the Planning Act, if appealed,
(inchoate), does not come into effect until the disposition of the Appeals by the Ontario
Municipal Board. The deeming of section 38(6.1) of the Planning Act expanded the
normal breathing space intended by the Legislature from the term of the Interim Control
By-law to the time of disposition by the Board of the new section 34 Zoning By-law.
\.... j ,-,'
- 6-
PL021 066
PL020908
PL030235
If the Municipality is successful in the new Appeal of the section 34 Zoning By-
law, that By-law could date back in effectiveness to the date of its passage on October
20, 2003. If the Municipality is not successful, in all respects, the new section 34 By-
law, depending on disposition, may not date back. Those considerations and
inferences as to the intent in giving up the deemed extension to an interim control under
section 38(6.1) at a point, after the Appellants case is in on the Interim Control By-law,
and the Municipality has only commenced its case, are best left to the Courts. At this
point in time, collateral consequences are indefinite and not of sufficient clarity to deter
from the general principle of mootness. The Board finds for the Municipality on the first
part of its Motion and orders issues 1, 2, 3, on the Issues List of the Procedural Order,
struck.
With regard to the second part of the motion, to adjourn the second phase (site
plan control and deleting the H from the Zoning), of this Hearing to the new hearing on
By-law 2003-153 and Official Plan Amendment 36 (not yet fixed as to time), the Board
finds against the Municipality for the following reasons. Based upon the Clergy principle
affirmed in the Courts aforementioned, the Appellant has the right to have the site plan
control appeal and the second Appeal related to the lifting of the H in the Zoning heard
under planning instruments in effect at the time of the Application. The Interim Control
By-law is repealed. The new Zoning By-law 2003-153 is not in effect as it is under
Appeal. If By-law 2003-53 withstands the appeals and comes into effect, its effective
date would be the date of its passing. That is yet to be determined. The adjournment of
the site plan and H-Zoning appeals to this time and to this panel was made in
conjunction with the Interim Control By-law at the request of the Municipality. This panel
is seized, and in accordance with the Procedural Order, those Appeals ought to be
heard. This Hearing will continue to hear the TDL Appeals respecting site plan
approval and the lifting of the H-Zoning under the Zoning and Official Plan in effect at
the time of the Applications and now in effect following repeal of the Interim Control By-
law.
\~~.i I
-7 -
PL021 066
PL020908
PL030235
The Motion of Clarington is accordingly granted in part to strike issues 1 to 3
inclusive from the Issues List of the Procedural Order. The Motion is not granted in
respect of the adjournment of the second phase of this Hearing to the new hearing for
Official Plan Amendment 36 and Zoning By-law Amendment 2003-153.
Second Phase of the Hearing-Site Plan Control Appeal and Appeal from the
failure of Clarington to lift the H Holding Symbol from By-law 84-63 by Zoning
Amendment.
258 King Street east is a vacant property in the King Street East Corridor of the
Bomanville urban area, Municipality of Clarington. The property is 36.58 meters in
width, 49 meters in depth, with a size of 1796 square meters. The site is leased and is
under option by TDL. The location is at the northwest corner of King Street East and
Galbraith Court, a residential cul-de-sac, serving approximately 92 homes. Across King
Street, south of the subject property is the Bowmanville Mall with an exit -entrance from
King Street East. To the east across Galbraith is the Strathaven Nursing Home with
some 329 beds. To the west, on King Street East is the Henry Apartment Building with
some 52 units. King Street East abutting the subject property is a five-lane arterial
which changes in number of lanes west of Frank Street. King Street is recognized
under the Clarington Official Plan as the primary commercial street of Bowmanville.
258 King Street East is designated in the Official Plan as Strip Commercial. The Plan
requires the Main Central Area (the subject property is part of the Main Central Area of
the Bowmanville Urban Area) to be developed in accordance with urban design
objectives and to be a place of high quality urban environment for pedestrians.
Proposed is one-storey restaurant of 130.9 square meters. Twenty- six seats are
planned inside with a take-out stacking line with capacity for 15 cars. Parking spaces
are provided for nine cars, none of which are located within the front yard facing King
Street East. The front yard setback is 11 metres from the property line to building face.
There is an additional seven-metre strip to the sidewalk reserved through an earlier
vi :.-
- 8 -
PL021066
PL020908
PL030235
street widening. Vehicular access is planned to Galbraith Court with no vehicular
access to King Street East. A loading area is planned to the rear-north area of the site.
Pedestrian access is planned from King Street East. Current zoning in effect is
Neighbourhood Commercial permitting an eating establishment - a take out. The
primary use must be consumption of food off the premises. The Holding Symbol has
the effect of restricting this and other uses while the Holding Symbol remains in effect.
Following the filing of Applications for site plan Approval and Zoning Amendment
to remove the H Symbol, the Municipality failed to approve of the site plan following
discussions and circulation. The Application to remove the H was not circulated or
processed and was not approved. Both Appeals, as noted above were consolidated
and are heard together. The Board undertook a site visit with counsel for the Parties so
as to best appreciate evidence brought forward in the Hearing. The Board hearing was
hotly contested with each side calling expert planning witnesses, traffic design and
engineering and urban design evidence, followed by informed, cogent, legal argument.
Site Plan Control Reference to the Ontario Municipal Board
Very early in this site plan control process, in writing, the Director of Engineering
of the Municipality, with support from his consulting engineers on retainer, expressed to
the TDL that TDL ought to look for another site and that he could assist. The reasons
given amounted to concerns with the capacity of King Street East, the accident rate at
the intersection of King Street East and Galbraith Court and that the site at 258 King
Street East was too small. It should be noted that TDL had recently tried to locate at
219 King Street East. TDL had, following discussions with the Municipality, particularly
over access, abandoned the application. In viva voce evidence by the Director of
Engineering it was apparent to the Board that his concerns were heartfelt arising for the
safety of users of municipal roads under his mandate. In his evidence he referred to
other Tim Horton outlets in another municipality, where he lives that at peak times may
backup, in the stacking lane, and onto the street access. There are admissions in the
~.....; ; -J
-9-
PL021 066
PL020908
PL030235
written materials filed that led planning and engineering staff of the Municipality to
consider that they could not achieve their goals through the site plan control process
and accordingly Clarington proceeded with the Interim Control By-law as noted above.
Through a lengthy site plan control process for 258 King Street East, evidenced by
correspondence filed with the Board, there is an effort by both sides to arrive at a
mutually acceptable site plan. The use was recognized by the Municipality and
constructive suggestions were advanced by the planner of the municipality. Those
suggestions were mainly accepted by TDL:
The Proposed building was downsized from 230 square meters to
130 square meters;
Access originally proposed to King and Galbraith was restricted to
Galbraith; .
The location of the building was reconfigured, landscaping, design
features and fencing were addressed;
The motor vehicle stacking lane was increased to 15 spaces with
capacity for over-storage of three more spaces on site,
Nine on-site parking spaces were provided in accordance with the
Zoning By-law,
The number of eat in chairs was reduced to 24, pedestrian access
was provided from King Street East.
Technical agencies and the Region on circulation raised no objection. From this
process and the viva voce planning evidence at the hearing, the Board concludes the
planning process was proceeding to the determination of a site plan, if off-site traffic
engineering for the intersection could be resolved.
1 i ( -T
U.
- 10-
PL021066
PL020908
PL030235
Traffic
There was however a concern with intersection traffic that was first expressed by
the Director of Engineering. That resulted in TDL being requested to file an Engineering
Report on the accident history at King Street East IGalbraith intersection. That was filed
and the consultant concluded that from the accident history, the problem movement was
a northbound left hand movement at the Bowmanville Mall access. That movement, the
engineering consultant concluded was not relevant to the proposed development. TDL
was then requested by the Engineering consultant for the Municipality, to undertake a
trip generation and trip distribution analysis. That second report was prepared by
Engineers for TDL and filed with the Municipality. That report based its findings on ITE
Trip Generation Manual and trip generations of Tim Horton estabiishments in the
Greater Toronto Area. It notes from Traffic engineering literature based upon surveys
that 70% of traffic generated by fast food facilities is impulse traffic. Morning peak, in
and out volume was estimated at 85 trips per hour. Consulting engineers for the
Municipality could, after deliberations with engineers for TDL, not accept trip generation
figures proposed. Following disagreement on traffic engineering trip generation and
then concern respecting level of service operating levels at the intersection of King
Street East and Galbraith Court, the proposed site plan was not approved, a reference
was made to this Board to determine the site plan and Interim Control was passed by
the Municipality.
The Municipality sought through the Board process, disclosure of data of similar
sized Tim Horton establishments (Model 1400). Restaurants at 3316 Lake Shore
Boulevard West, Toronto, 426 Kipling Avenue, Toronto, 380 Weston Road, Toronto
were surveyed as were larger restaurants at Highway 2 and Centrefield Drive and
Highway 2 and Townline Road, the latter two in Clarington. The municipal consulting
engineers carried out fieid research at the above five locations regarding parking and
traffic characteristics. Conclusions reached include:
1. A higher trip generation up to 350 per peak hour with resultant high
turning movement volumes on the public road system. Trip Generation
rates vary with floor area and the volume of passing traffic. At the two
\..) j ..;
- 11 -
PL021066
PL020908
PL030235
Clarington sites, trip generation has exceeded earlier estimates.
2. Parking and stacking numbers varied by site but 15 spaces for stacking
"may be sufficient," although the conclusion emphasizes the difficulty in
being definitive.
3. Parking at the three 1,400 restaurants was found to be inadequate and
on the subject site the nine proposed parking spots were found to be
insufficient, such that there could be adverse impacts on the residential
neighbourhood.
4. The conclusion reached regarding the proposed use is that with higher
turning movement vehicular traffic, the existing safety issue in the
intersection would be exacerbated.
5. Improvements recommended include restricting the Bowmanville Mall
Access opposite Galbraith Court to right turns only and establishing a
new signalized access for the Bowmanville Mall to the east of Galbraith
Court and opposite the Strathaven Lifecare Centre.
The Director of Engineering clarified that meetings had been held with the Mall
and Strathaven representatives with some agreement. Public information meetings
were scheduled for early January 2004, to further the intersection change process. This
appears to the Board to be a proactive process for which the Municipality ought to be
acknowledged. The importance of the intersection change is clear from the evidence of
the municipal consulting engineer that this existing intersection must remain
unsignalized although meeting traffic warrants, due to the close proximity of an existing
signalized intersection to the west. The possibility of confusing the motorist is called
"conspicuity".
The municipal consulting engineer's evidence addressed how the intersection
was now operating and how it could operate with projected traffic for TDL proposal. The
conclusions reached were that southbound left turn would be at level of service F during
mid-afternoon Saturday, peaktime for both TDL operation and for the road (the evidence
of TDL is that the peaks do not occur at the same time on Saturday). The same Level
;' !
\..)' \.-J
- 12 -
PL021066
PL020908
PL030235
of Service F is evident in the municipal consulting engineering evidence for existing
northbound left hand turns from the Bowmanville Mall at peaks.
The consulting engineer retained by TDL for this hearing, did not present the
same type of trip generation actual data nor a formal traffic impact assessment for the
proposed TDL restaurant. Rather he undertook a gap study and then mixed that data
with market and other data from other TDL restaurants. His estimated trip generation
was at peak 200 in and outs. Although the evidence of the consulting traffic engineer for
the Municipality was more direct and "by the book" - the Highway Capacity Manual, the
Board found the evidence of the TDL consulting engineer helpful as well. The timing of
gaps is referenced in the Traffic Manual for unsignalized intersections - the American
Highway Capacity Manual 2000. This Manual provides under Performance Measures
that the computer model is based upon a critical gap size. The Manual references the
assistance of field data and the importance of not focusing on a single measure of
effectiveness for the worst movement only. The TDL traffic consultant showed a high
degree of familiarity with other TDL operations, setting the context of other requirements
and site plans. For instance, the goal of serving a customer every 25 seconds in the
context of efficiency, staffing and location was helpful. The TDL consulting traffic
witness presented a video taken on the second Saturday before Christmas, one of the
busiest days of the year for the Bowmanville Mall. The timing as with other similar
evidence was disputed as to road peak and TDL peak. The Board was satisfied the
video made, Exhibit 30, was proper reply evidence depicting significant gaps across the
King Street East - Galbraith Court intersection. The TDL witness suggested other traffic
considerations such as two lanes south on Galbraith on existing pavement, adjusting
the stop line and concurring in improvements to the Mall entrance. He suggested this
access to the Bowmanville Mall backed. up due to a poorly designed site plan for exiting.
The Municipal consulting engineer also queried site circulation based upon his
surveys. In his conclusion, after reviewing an additional TDL store in Cobourg near the
401 with signage on the Highway, he stated, "If you build it, they will come". This
u f I
- 13 -
PL021066
PL020908
PL030235
statement the Board disregards as an admission of the difficulty of arriving at any
meaningful standard.
Two residents residing on Galbraith Court testified of their concerns with safety
arising from accident reports.
The Board in weighing the traffic evidence finds that from the cogency of the
Municipal Traffic evidence, when combined with the history of 27 accidents in the King
Street East - Galbraith Court intersection in the last five years, that there is a need to
address intersection improvements prior to this project proceeding. The accidents and
evidence adopted by the Board relates primarily to turns in and out of the Bowmanville
Mall. The approval of a site plan is however not the proper tool to address off-site
improvements. Site plan approval under section 41 of the Planning Act is site oriented.
First City Shopping Centre Group v. Gloucester, [1990] O.M.B.D. No. 2035 at 7 and
Polla v. Toronto (City) Chief Building Official, [2000] O.J. No. 4399. Counsel for
Clarington, concedes this point, but argues the state of the intersection is relevant to the
other Appeal respecting the lifting of the H Symbol. The Board, in the site plan Appeal
must find that off-site intersection considerations are beyond its jurisdiction to consider
under section 41 of the Planning Act. The consideration of same in the other Appeal
will follow.
Parking on site can be a site plan control consideration if not legislated in the
Zoning By-law. In this case nine on site parking spaces are provided on site. In
February of 2000 a Joint Municipal Study of Fast Food Restaurant, Drive-Thru and
Parking was completed. Clarington participated in the study. Although the study was
not formally adopted, evidence in this Hearing indicates it has been applied. Although
that study would require 19 parking spots on this site, the Study states, "the results of
the survey of parking utilization suggest that a reduced parking ratio for fast food drive-
thru restaurants is justified in comparison to standards for convenience restaurants
without drive-thru lanes". This principle is not disputed by the traffic engineers testifying
I~.' i U
- 14 -
PL021 066
PL020908
PL030235
in this hearing. That study could require 12 spaces in the drive-thru. A 15-space drive-
thru with capacity for three more spaces on site is provided. The Board finds from the
planning and traffic evidence of TDL that the combination of nine parking and 15 spots
in the drive thru are reasonable. Since nine spaces are in the Zoning By-law of
Clarington for on site parking, the Board is, in any event, not in a position to impose
more. Martins v. Ottawa (City), [1996] O.M.B.D. No. 320 and Kally's Restaurant Inc. v.
Scarborough (City), [1991] O.M.B.D. NO.1248, reversed on other grounds, 12 O.R. (3d)
3129 (Div. Ct.).
The drive-thru itself provides 15 spaces, with capacity for 18. The drive-thru was
crucial to the first expression of concern in the site plan process. This stacking lane is
not regulated under the current zoning By-law and is subject to regulation under site
plan control. The evidence of TDL that the drive-thru capacity is generous, relative to
other sites with problems, is truly a distinguishing factor. This conclusion is admitted by
the Municipal traffic consultant after an in-depth survey and study of other comparable
sized operations.
On site circulation was questioned. The evidence asserted by the TDL witnesses
is that pedestrian access crossing the stacking lane is safer than through a parking lot.
The loading space, also regulated by the Zoning By-law, provides for forward entry and
backup into the 15th space at the end of stacking line. Although the size of the delivery
truck was questioned, it was reasonably answered that different sized trucks are used
relative to the size of space on the different sites. On-site circulation is found to be
reasonably provided for on the site plan.
Urban Design
The Official Plan of the Municipality requires the consideration of urban design
principles including:
1. Street front oriented;
\..) /
- 15-
PL021 066
PL020908
PL030235
2. Ease of access and safety;
3. Parking to be to the side and rear;
4. Land use compatibility through appropriate siting;
5. Design and landscaping;
6. Existing trees are to be preserved where possible;
7. Pedestrian areas;
8. Building siting to provide a continuous edge to the street, and
9. Consistency of setback with the established building line of
abutting properties.
Municipal evidence was entered through a staff planner and a consulting urban
designer. They asked the Board to consider the maintenance of a number of mature
trees at the northwest corner of the site. The building they suggested should be
enlarged and reoriented, so that the larger side view would face King Street. They
requested that the pitched roof on the King Street face functionally extend around the
building to integrate with residential uses on Galbraith Court. With respect to buffering,
it was requested the Board consider a nine metre setback to the south of the property to
be sensitive to the proximity of the stacking lane, with impact of noise, light and
emissions on the residential home to the south. They suggested a 1.8 metre buffer to
the west to buffer the five-storey apartment building.
Planning evidence and urban design evidence from TDL suggested that in the
site plan process the building had, in redesign, become street oriented. It had been
moved but now was setback in accordance with the Strathhaven setback and minimum
front yard zoning setback. That front zoning setback would have to be amended if the
building was to be brought to street edge. Parking is situate to the rear and west side
of the proposed building and no parking is provided either in the front yard abutting King
Street or the yard abutting Galbraith Court. The evidence of TDL through its urban
U 'J 0
- 16 -
PL021 066
PL020908
PL030235
designer, an architect previously employed administering site plan approval for the City
of Toronto, is that this proposal will enhance the street pedestrian realm with the
building being brought closer to the street yet conforming with other policies respecting
setback of other buildings. The evidence of the TDL witnesses confirmed compliance
with the Municipality's landscape Design Guidelines whereas the municipal consulting
urban designer was not familiar with those Municipal Guidelines set out in Exhibit 19.
The same municipal witness was not familiar with the detail of Ministry of the
Environment Guidelines on Noise to substantiate his concerns raised on noise.
The Board will not impose greater setback and buffering than is contained in the
Municipalities Zoning and Landscape Guidelines. The three metre setback to the north
together with an existing fence were recognized by the municipal planner in the earlier
detailed site plan control process as was the fence proposed in accordance with the
Zoning on the westerly lot line. Significant landscaping on the separate landscaping
plan, a part of the site plan package, was reviewed earlier with the Municipality and
seemed acceptable at that time. Credibility is diminished when there is not consistency
with the earlier municipally administered site plan process. The voice speaker box has
been located toward King Street where the proposed building will act as a buffer for the
residence to the north and west. The Board finds general conformity of the proposed
site plan with the Official Plan and in particular, with the urban design policies set out
therein and in the Secondary Plan.
The Board will however require that the roofing design, as depicted facing King
Street, be consistent on all sides. In addition, the height of the fence to the west is to be
reduced to .75 meters for a distance of three metres as specified in section 3.1 (I)(V) of
the Zoning By-law. Thirdly, TDL is required to submit a lighting plan showing the
manner in which light will be deflected away from the residential neighbours. Fourthly,
the pylon sign will be relocated and vegetation removed from the southwest corner in
accordance with section 3.21 of the Zoning By-law.
I~,J .J I
- 17 -
PL021066
PL020908
PL030235
The Board was urged by the Municipal counsel to not approve of the site plan.
Counsel argued that the deletion of the word "settle" in section 41 ,subsection12.1 of the
Planning Act, as it now reads through an amendment in 2002 strengthened the Board's
position to not approve of the site plan. The Board, on consideration, believes the
continuation of the word "determine" with the word "referral" in section 41 leaves the
Board with a similar jurisdiction as before the amendment. That amendment was made
in an omnibus bill for efficiency dealing with repetition in the legislation. The Board does
agree with Municipal Counsel that even in the absence of direct language in section 41
of the Planning Act to allow or dismiss the Appeal, the Board could, where evidence
warranted, refuse to approve of the Site Plan. In this case, the evidence does not so
warrant and the Board chooses to determine the site plan as set out above. The Board
requires the Plan be changed to reflect the above and will remain seized for
implementation in the form of amended plans and an agreement in the form of Exhibit
17.
Appeal to remove the H Holding Symbol
This appeal was not processed by the Municipality pending the resolution of the
site plan. There was limited evidence and argument on this Appeal in this Hearing.
There is no argument as to invalidity of the use of the Holding mechanism under the
enabling authority section 36 of the Planning Act. Section 36(2) of the Planning Act
requires that the Official Plan contain provisions relating to the use of the holding
symbol. The main section 36(1) stipulates that the Council may specify the use to which
the lands may be put in the future when the Holding Symbol is removed by amendment
to the By-law. Section 36(4) provides for an Appeal to the Board if Council refuses or
neglects to make a decision on an application to amend the By-law. The Board's
authority is to hear the Appeal and dismiss or amend the By-law to remove the holding
symbol.
I..> ..-.J ;_
- 18 -
PL021066
PL020908
PL030235
The Board is urged by the Municipality to dismiss the Appeal since it is argued
the amending By-law is not in accordance with the Official Plan and would then
transgress section 24 of the Planning Act. The Official Plan provides inter alia, in
section 23.4.3, Holding provisions may be used to ensure, that prior to development the
following matters have been addressed and approved to the satisfaction of the
Municipality:
A) services and municipal works;
G) any other requirements as may be deemed necessary by Council
including the implementation of the policies of this Plan.
The Board finds conformity with G.
The Zoning By-law provides that with the H, the use of lands shall be limited to
residential uses, conservation, forestry and farm uses exclusive of livestock operation.
The Zoning By-law states the Holding Symbol may be removed upon Council being
satisfied that the uses to be permitted will be adequately serviced; the lands to be used
have adequate access.
The Municipality argues that "services and municipal works" could include the
intersection transportation services. TDL relies upon evidence that the H was passed in
conjunction with the subdivision creating the lot and other residential lots on Galbraith
Court in 1990. A sentence in the Planning Report referenced the lifting of the H when
the Subdivision Agreement was registered.
The Board finds, as set out in the Site Plan Appeal, that there is a need to
address intersection improvements prior to this project proceeding. Those
improvements can be interpreted as municipal works or services and are related directly
to the usability of the subject property. Intersection improvements planned by the
Municipality in moving the mall entranceway and restricting the current Mall access, if
implemented, will satisfy this Official Plan requirement. The Board has carefully
~ . oJ _,
,
- 19 -
PL021066
PL020908
PL030235
weighed all Planning and Engineering evidence. The Board notes that the Official Plan
restricts access to King Street and intends the use of locai streets such as Galbraith
Court where possible. The Official Plan also prohibits drive-thrus in another down town
designation, the Street Related Commercial Area. The designation of Strip Commercial
on the subject property does not prohibit drive-thrus. The Official Plan encourages the
improvement of traffic operations on King Street. Since the intersection improvement
has not been effected and will involve the final approval of third parties, the Board
concludes that, at this moment the H-zoning Appeal must be dismissed as premature.
However, due to the promising manner that intersection improvements were addressed
by the Municipal Engineer, his engineering consultants and the past and present
consulting engineers for TDL, the Board will withhoid its Order dismissing the Appeal for
six months to allow, in the public interest, for the intersection improvements to be
advanced in the good faith expressed to date. The Board may be spoken to by both
legal counsel. If the intersection improvements planned for, proceed, the Board will
hear evidence in a continuation. In the event that the improvements do not proceed, the
Board's Order will issue dismissing the H Symbol zoning amendment. Despite the
Board having found favour with the site plan subject to certain amendments because
the site plan requires that the H be lifted, the Board will dismiss the site plan appeal if
the intersection improvements do not proceed.
TDL has raised the issue of costs. If costs are pursued, Clarington will be served
in accordance with the Boards Rules.
"N.C. Jackson"
N.C. JACKSON
MEMBER
i~! ',j -T