Loading...
HomeMy WebLinkAboutEGD-05-05 Cl~i!Jglon REPORT ENGINEERING SERVICES DEPARTMENT Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE Monday, February 21, 2005 Resolution #: (}.,{J!i - / OJ/O~ Date: Report #: EGD-05-05 File#: By-law #: Subject: PRE-BUDGET APPROVAL OF CAPITAL WORKS PROJECTS FOR THE RECONSTRUCTION OF: SCUGOG STREET - MIDDLE ROAD TO FUTURE BONS AVENUE, BOWMANVILLE HUNT STREET - BASELINE ROAD TO ALBERT STREET, BOWMANVILLE STATION STREET - MAIN STREET (REGIONAL ROAD 17) TO COBBLEDICK STREET, ORONO Recommendations: It is respectfully recommended that the General Purpose and Administration Committee recommend to Council the following: 1. THAT Report EGD-05-05 be received; 2. THAT pre-budget approval in the amount of $1,750,000 be granted for the reconstruction of Scugog Street - Middle Road to Future Bons Avenue; 3. THAT pre-budget approval in the amount of $1,070,000 be granted for the reconstruction of Hunt Street - Baseline Road to Albert Street; 4. THAT pre-budget approval in the amount of $520,000 be granted for the reconstruction of Station Street - Main Street (Reg. Rd. 17) to Cobbledick Street; and 5. THAT staff proceed with the coordination and authorization of necessary utility relocation, with land acquisition negotiations with the affected parties adjacent to the subject projects, and with the preparation of all necessary tender documentation and detailed design for all three of these projects and call for tenders as early as possible. CORPORATION OF THE MUNICIPALITY OF CLARINGTON 40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L lC 3A6 T 905-623-3379 F 905-623-9282 706 Report #EGD-05-05 Page 2 Respectfully by, ../) ~ ,/ VU-Aut..-::-- Submitted by: A.S. Cannella Director of Engineering Services O~~~ Reviewed by: Franklin Wu Chief Administrative Officer ASC/jo February 15, 2005 707 Report #EGD-05-05 Page 3 1.0 BACKGROUND 1.1 The Engineering Services Department's Road Program has planned for the reconstruction of the following streets in 2005 and as such has included them in this year's Capital budget: · Scugog Street from Middle Road to future Bons Avenue, Bowmanville · Hunt Street from Baseline Road to Albert Street, Bowmanville · Station Street from Main Street (Regional Road 17) to Cobbledick Street, Orono All of these projects are time sensitive in that they are large projects that require either land acquisition to accommodate the future reconstructed road, utility relocation due to conflicts with the proposed design, or both prior to commencing with construction. Based on the times historically taken to complete both land purchase negotiations and utility relocation it would severely reduce the time available for construction if these items were not initiated prior to early April when it is anticipated the budget approval process will be completed. If these items were left until the budget is approved, completion of these works may not be done until late Mayor early June cutting nearly 2 months from the time available for the actual reconstruction works. Based on the proposed design for the reconstruction of the subject roads it is estimated that each project will require the following time to complete: . Scugog Street, Bowmanville - 4 months . Hunt Street, Bowmanville - 6 months . Station Street, Orono - 3 months 708 Report #EGD-05-05 Page 4 Should tendering of the projects not be allowed to commence until the budget is approved, award of the contract would not be made until mid to late May, 2005, which would lead to completion dates well into late November for the Scugog Street and Hunt Street projects. If any bad weather is experienced during the time of construction the completion date could be pushed into December risking the chance of having less than favourable conditions to complete construction. The reason that the Station Street project is included in the request for pre- budget approval is in order to ensure that all works are completed and established prior to the start of the Durham Central Fair which is scheduled from September 18 - 11 this year. If not tendered before the anticipated budget approval date, there is the risk that the works on Station Street and adjoining side streets will not be completed before September. In addition to the reasons noted above there are also a couple of other factors that should be considered when evaluating the merits of providing pre-budget approval for these projects. Historically projects tendered earlier in the year have come in with 5% - 15% lower pricing than those tendered just two months later in the year as most contractors have already secured sufficient work for the summer and price the later tendered jobs accordingly. Another factor that will influence the price of construction this year is the additional work generated by the 2005 Canada Ontario Municipal Rural Infrastructure Funding program which saw applications submitted by most of Ontario's municipalities on January 10, 2005 and it is anticipated that approval of some of these projects will begin in April 2005 and therefore will be competing with the Clarington's subject projects most likely resulting in inflated pricing due to the increase in available work. In consideration of these factors it is requested that the Council provide pre- budget approval for all three projects. 709