Report To: General Government Committee
Date of Meeting: May 6, 2024 Report Number: FSD-022-24
Authored by: David Ferguson
Submitted By: Trevor Pinn, Deputy CAO/Treasurer, Finance and Technology
Reviewed By: Mary-Anne Dempster, CAO
By-law Number:
Resolution Number: GG-075-24File Number: RFP2024-2
Report Subject: Engineering Services for Multiple Bridge and Culvert Replacements
Recommendations:
1.That Report FSD-022-24, and any related delegations or communication items, be
received;
2.That the proposal received from Cima Canada Inc. being the most responsive bidder
meeting all terms, conditions and specifications of RFP2024-2 be awarded the
contract for the provision of Engineering Services for Multiple Bridge and Culvert
Replacements for the specific locations highlighted in Section 1.3 of the report;
3.That the funds required for this project in the amount of $412,152.42 (Net HST
Rebate) be funded from the approved budget;
4.That subject to municipal resources at the time of construction, budget approval and
construction contract award, CIMA Canada Inc. be authorized to provide the
required Inspection and Contract Administration at a maximum cost of $218,580.48
(net HST Rebate); and
5.That all interested parties listed in Report FSD-022-24, and any delegations be
advised of Council’s decision.
Municipality of Clarington Page 2
Report FSD-022-24
Report Overview
To request approval to award RFP2024-2 to the most responsive proponent to provide
Engineering Services for Multiple Bridge and Culvert Replacements.
1. Background
1.1 The Municipality of Clarington (Municipality) requires the assistance of a qualified firm to
provide Engineering Services for Multiple Bridge and Culvert Replacements.
1.2 A Request for Proposal (RFP) was drafted to allow the Municipality to select a qualified
Engineering Services Consultant with the skills, resources, and experience necessary to
provide a cost-effective design, tender preparation, construction inspection, and
contract administration services for the replacement of one (1) bridge and five (5)
culverts within the Municipality of Clarington.
1.3 The various locations of bridges and culverts being replaced are as follows:
Culvert 98513 – East Townline Road between Regional Hwy. 2 and Hwy. 401
Culvert 98535 – Best Road between Concession Road 8 and Hwy. 407
Culvert 98533 – Concession Road 7 between Best Road and Hwy. 35/115
Structure 99077 – Hancock Road between Nash Road and Regional Hwy. 2
Culvert 99125 – West Townline Road between Concession Road 9 and Regional
Road 9
Culvert 99525 – Concession Road 6 between Acres Road and Darlington-Clarke
Townline Road
1.4 East Townline Road and West Townline Road are boundary roads with the adjacent
Municipality of Port Hope and City of Oshawa, respectively. Therefore, Culverts 98513
and 99125 will be eligible for partial cost recovery through the Municipality’s Boundary
Road Agreements. As outlined in these agreements, infrastructure replacement costs of
this nature shall be split in equal parts between each Municipality that share the subject
boundary road.
1.5 The RFP was split into two Parts. Part 1 included the detailed design and tendering for
the bridges and culverts and Part 2 included provisional inspection and contract
administration services during construction. Part 2 of this contract is subject to Council
budget and contract approval for the construction of this project.
Municipality of Clarington Page 3
Report FSD-022-24
1.6 RFP2024-2 was issued by the Purchasing Services Division and advertised
electronically on the Municipality’s website. The RFP was structured on a two-envelope
system with price being an evaluated factor.
2. Analysis
2.1 The RFP closed on February 23, 2024.
2.2 The RFP stipulated, among other things, that the proponents were to provide a
description of the Firm/Consulting team, key qualifications, firm profile, highlights of past
service and experience of team members with projects of similar size, nature and
complexity, and demonstrate an understanding of the Municipality’s requirements.
2.3 Twenty-two companies downloaded the document, and eight proposals were received
(refer to Attachment 1) by the stipulated closing date and time. Submissions were
reviewed to ensure that they met the Phase 1 - Mandatory Requirements. Two
submissions received did not meet the mandatory requirements and were deemed non -
complaint. Six proposals met the mandatory requirements and were deemed compliant.
The six compliant proposals were distributed to the evaluation committee for review,
evaluation, and scoring.
2.4 The technical proposals were evaluated and scored independently by the members of
the evaluation committee in accordance with the established criteria as outlined in the
RFP. The evaluation committee was comprised of staff from the Planning and
Infrastructure Services Department.
2.5 The evaluation committee met to review and agree upon the overall scores for each
proposal. Some of the areas on which the submissions were evaluated were as follows:
The Proponent’s understanding of the Municipality’s requirements;
Highlights of services provided performing similar work on projects of comparable
nature, size, and scope in a municipality of similar population size;
Proposed team’s experience with projects similar in size and nature;
A methodology describing the Proponent’s project management approach, work
plan, goals, objectives, and methods of communication to be utilized to meet the
requested deadlines; and
A proposed solution including a detailed work plan indicating the project method,
schedule, Gantt chart, tasks and deliverables showing an estimated overall
timeline of the project.
2.6 Upon completion of the evaluation, four submissions met the established passing
threshold of 80 percent for Phase 2—Technical Submission and moved to Phase 3—
Pricing. The evaluation committee determined that a presentation from the short-listed
proponents would not be required.
Municipality of Clarington Page 4
Report FSD-022-24
2.7 The pricing envelopes were opened, reviewed and scored as stipulated in the RFP
document.
2.8 The RFP was structured to award the detailed design and tendering for the bridges and
culverts with the option to include inspection and contract administration services during
construction.
2.9 The inspection and contract administration was bid as a provisional item dependent on
the construction budget and contract being approved by Council. The amendment to
include Part 2 Inspection and Contract Administration will be subject to budget
availability, Council approval of the construction contract and Municipal resources at the
time of award.
2.10 Upon completion of the evaluation scoring, the recommendation is to award the contract
for this work to the highest-ranked proponent, Cima Canada Inc.
2.11 Cima Canada Inc. has provided Engineering Services to the Municipality in the past,
and as such, a reference check was not required.
3. Financial Considerations
3.1 The Proponents provided provisional pricing for the inclusion of Inspection and Contract
Administration. The fees are allocated between the two items is as follows:
Part 1 – Lump Sum for Detailed Design and
Tendering
$412,152 Total net HST rebate
Part 2 – Provisional Item: Lump Sum for
Inspection and Contract Administration
$218,580 Total net HST rebate
3.2 The funding required for Part 1 of this contract award is up to $412,152.42 (Net HST
Rebate) and will be funded from the following account:
Description Account Number Amount
Structures Rehabilitation 110‐50‐330‐83275‐7401 $252,152
Oshawa Cost Recovery (99125) 110‐50‐330‐83275‐7402 50,000
Port Hope Cost Recovery (98513) 110‐50‐330‐83275‐7402 20,000
Hancock Rd. Box Culvert (99077) 110-32-330-83365-7401 90,000
Municipality of Clarington Page 5
Report FSD-022-24
3.3 Part 2- Inspection and contract administration for the project was included in the issued
RFP as a provisional item in addition to the pricing requested to complete the design
and tendering work. There are cost and quality efficiencies when the contract
administration and inspection are performed by the same consultant as the design of
the capital work. Contract administration and inspection costs will be included in the
2025-2027 multi-year capital budget. Approval of the award of the contract for this work
is subject to the project receiving budgetary approval in a subsequent year.
3.4 The funding required for Part 2 of this contract in the amount of $218,580 (net HST
rebate) will be required to complete inspection and contract administration for the
project and will be identified in a future budget submission.
4. Strategic Plan
4.1 Not Applicable
5. Concurrence
This report has been reviewed by the Deputy CAO, Planning and Infrastructure
Services who concurs with the recommendations.
6. Conclusion
It is respectfully recommended that Cima Canada Inc. be awarded the contract for the
provision of Engineering Services for Multiple Bridge and Culvert Replacements.
Staff Contact: David Ferguson, Purchasing Manager, 905-623-3379 Ext. 2209 or
dferguson@clarington.net.
Attachments:
Attachment 1 – Summary of Proposals Received
Interested Parties:
List of Interested Parties available from Department.
Municipality of Clarington Page 6
Report FSD-022-24
Attachment 1 - Summary of Proposals Received
Municipality of Clarington
RFP2024-2– Engineering Services
Multiple Bridge and Culvert Replacements
Proposals Received
Bidder
CIMA Canada Inc.
D.M. Willis
GHD Ltd.
The Greer Galloway Group Inc.
Jewell Engineering Inc.
Q&E Engineering Inc. *
REMISZ Consulting *
TSI Inc.
Note: Companies with * were deemed non-compliant.