HomeMy WebLinkAboutPDS-056-23Clarftwn
Staff Report
If this information is required in an alternate accessible format, please contact the Accessibility
Coordinator at 905-623-3379 ext. 2131.
Report To: Special Planning and Development Committee
Date of Meeting: October 23, 2023 Report Number: PDS-056-23
Submitted By: Carlos Salazar, Director of Planning and Infrastructure Services Mary -
Reviewed By:
File Number:
Anne Dempster, CAO
Resolution#: PD-070-23
By-law Number:
Report Subject: CL 2022-22 Various Court Replacements Budget Reallocations
Recommendations:
1. That Report PDS-056-23, and any related delegations or communication items, be
received;
2. That the Deputy CAO/Treasurer is authorized to reallocate up to $60,000.00 from
the "Municipal Capital Works Reserve Fund" to the "CL2022-22 Various Court
Replacements Project" capital account to complete the necessary work.
Municipality of Clarington
Report PDS-056-23
Report Overview
Page 2
CL 2022-22 Various Courts Replacements Tender is now complete, however additional
funding was required due to unforeseen poor soil conditions. The additional funding was
approved as an emergency under the Purchasing By-law by Financial Services and the CAO
Office to avoid additional costs being charged by the contractor for stand-by time and
remobilizing.
1. Background
History of the CL2022-22 Various Court Replacements Project Award
1.1 CL2022-22 Various Court Replacements Tender was awarded to Royalcrest Paving and
Contracting Ltd. in August 2022 through the Council Recess Procedure. Award of this
Contract was reported to Council through Staff Report FSD-035-22.
1.2 The Various Court Replacement was intended to replace the deteriorating playing
surface of the tennis courts at Guildwood Park in Bowmanville as well as to rehabilitate
the deteriorating basketball court and convert the deteriorating tennis courts playing
surface to four new pickleball courts at Stuart Park in Courtice.
Figure 1- Ribbon Cutting at Stuart Park
Municipality of Clarington
Report PDS-056-23
Project Overage
Page 3
1.3 When removing the existing asphalt playing surface at the Stuart Park basketball court,
the Contractor encountered poor existing soil conditions. Upon having the soil reviewed
by our Geotechnical Consultant it was determined that the existing soil under the
basketball court was unsuitable to support an asphalt playing surface and would need to
be removed and replaced with suitable material.
1.4 A change order was issued to the Contractor to remove and replace the unsuitable
material as recommended by the Geotechnical Consultant.
1.5 This change order required an additional $60,000.00 of funds to be approved to
complete the project. This additional funding was approved on an emergency basis and
to avoid additional charges due to Contractor standby time. The capital over-
expenditure requires Council approval if the additional funds exceeded 5% of the
Contract value as required under the Municipality's Capital Over -Expenditure Policy.
Figure 2: Basketball court at Stuart Park
Municipality of Clarington
Report PDS-056-23
2. Financial Considerations
Page 4
2.1 The funds that are being reallocated to the CL2022-22 Various Court Replacements
project were initially approved by the Deputy CAO / Treasurer and the CAO under the
emergency clause of the Purchasing By-law. This was to keep the project moving
forward and prevent any standby costs from being incurred during summer recess. Staff
are now reporting the overage as required under the Municipality's Capital Over -
Expenditure Policy to ensure transparency on the use of capital funds.
3. Concurrence
3.1 This report has been reviewed by the Deputy CAO/Treasurer, who concurs with the
recommendation.
4. Conclusion
4.1 It is respectfully recommended that Council approve the reallocation of funds from the
"Municipal Capital Works Reserve Fund" to the "CL2022-22 Various Court
Replacements" project to ensure that the investment made to date can be completed.
Staff Contact: Tony Ricciardi, Manager of Infrastructure, tricciardi a().clarington.net .