REPORT TO THE GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
MEETING OF SEPTEMBER 6, 1983.
REPORT NO.: WD -75 -83
SUBJECT: DRAINAGE OUTLET FROM DARLINGTON INDUSTRIAL
SUBDIVISION THROUGH F. HOWARD SMITH PROPERTY
LOT 28, BROKEN FRONT CONCESSION, FORMER
TOWNSHIP OF DARLINGTON.
RECOMMENDATION:
It is respectfully recommended:
1. That this report be received for information; and,
2. That a copy of this report be forwarded to Mr. F.
Howard Smith, R.R. # 1, Oshawa, Ontario, L1H 7K4.
BACKGROUND AND REPORT:
As members of Council may recall, late in 1982, the matter
of completion of the works in Darlington Industrial
Subdivision was considered, and the Works Department was
directed to arrange for the completion of the servicing
works, since the developer was not attending to them. As a
result, Town forces performed ditching, including an outfall
which leads to the boundary with Mr. Smith's property, in
accordance with the approved drainage plan for the
subdivision.
...2
vii
Page 2
REPORT WD-75-83
IV l(�l
The exceptionally wet spring caused considerable runoff from
the subdivision which was directed through this ditch with
the result that Mr. Smith's property was in a wetter than
usual state.
Mr. Smith contacted the Public Works Department complaining
of the added runoff to his property and the following
information was provided to him:
"In response to your recent enquiry, we have reviewed
the drainage situation noted above. Our investigation
reveals that the drainage ditch was originally
constructed, and more recently deepened, in accordance
with the approved drainage plan for the Darlington
Industrial Subdivision. This plan was approved by the
Town some five to seven years ago and, therefore, the
drainage pattern cannot be changed without some
direction from Council.
In your letter you mention that you are now being
forced to accept drainage from lands outside the
natural drainage area. We have investigated this and
found that, in fact, the drainage from the lands in the
Darlington Industrial Subdivision has always found its
way to your property. The elevation of the land at the
east end is higher than that at the boundary with your
lands. What has occurred, however, is an increase in
the amount of runoff which gets to your lands.
The result of paved areas and buildings has reduced the
amount of water which seeps into the ground. Also,
rather than the drainage following the contours of low
lying areas, it has been directed in a ditch to the
point where it formerly entered your lands.
...3
Page 3
REPORT WD -75 -83
I realize that this does not assist you in resolving
your problems, however, it does point out the position
the Town must take in this matter. As the drainage
plan was approved as part of a plan of subdivision,
public funds cannot be spent to alter it without
Council approval."
The information which has been provided to Mr. Smith is, in
fact, the case. Firstly, the drainage works, including the
outlet are in accordance with the drainage plan approved for
the subdivision. Secondly, without further negotiations
with the developer, and subsequently an amending agreement,
the Town is not at liberty to seek an alternate drainage
outlet or become involved in construction of same.
Mr. Smith should have these facts reaffirmed by copy of this
report.
J)
' �� R'GD: j c o
V August 22, 1983.
Respectfully submitted,
ZX 14 I
R.G. Dupuis, P. Eng.,
Director of Public Works.