HomeMy WebLinkAboutCS-23-85CORPORATION OF THE TOWN OF NEWCASTLE 16
40 TEMPERANCE STREET
BOWMANVILLE, ONTARIO
LIC3A6 TELEPHONE 623 -3379
REPORT TO THE GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
MEETING HELD OCTOBER 7 1985
REPORT: CS -23 -85
SUBJECT: ENERGY AUDITOR'S PROGRAM SCHEDULE (TENTATIVE)
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration
Committee recommend to Council the following:
1. That report CS -23 -85 be received for information.
BACKGROUND AND COMMENT:
As Committee members are aware, Mr. Kevin Greene was contracted by the
municipality to perform the Energy Auditor's duties on municipal buildings
for a period of one year commencing September 9 1985.
A program schedule (attached) has been developed outlining a number of
phases that will take place in performing the audit. I would point out
to Committee members that this schedule is merely a working guide and
as a result must be flexible to allow changes if the need arises.
It is our intention to conduct the audit on all municipal buildings at
the same time, in an effort to allow the various Hall Boards the
opportunity to benefit from the program.
Mr. Greene has been provided with office space at the Newcastle Fitness
Centre and may be reached there or through the Community Services
Department during office hours.
Hopefully this guideline will be of benefit to Committee members in
following the progress of the program.
Respectfully submitted,
/— 6:�)�
Jan Devantier, R.D.M.R.
Director of Community Services
ui- 5(d)
CORPORATION OF THE TOWN OF NEWCASTLE
DEPARTMENT OF COMMUNITY SERVICES
ENERGY AUDITOR'S PROGRAM SCHEDULE (TENTATIVE
1985
September 9 - October 9 HISTORICAL ANALYSIS
Purpose: 1) To gather past and present energy consumption costs.
2) To determine energy consumption patterns through
graphical representation.
3) To provide an opportunity to compare the efficiency
of facilities of similar use.
October 10 - November 15 WALK THROUGH AUDIT
Purpose: 1) To yield a list of minor energy sensitive items which
can be attended to without capital investment.
2) To identify other items requiring further study
and /or major capital investment.
November QUARTERLY REPORT
November 18 - April 30 1986 DIAGNOSTIC AUDIT
Purpose: 1) To technically analyse individual equipment and processes.
(Identifying each piece of equipment and how much
energy it should be consuming based on its size).
2) To examine operating and maintenance procedures.
3) To simulate an energy balance which traces the flow
and transformation of energy.
4) The Diagnostic Audit should answer the question
"Why does this building consume as much energy as it does ?"
1986
February QUARTERLY REPORT
March 9 SEMI ANNUAL REPORT - MINISTRY OF
MUNICIPAL AFFAIRS
U1 - 5(d)
May 1 - June 18 PRIORITY LISTING /GRANT INVESTIGATION
Purpose: 1) To reduce payback on capital investment projects and
categorize them as to implementation feasibility.
2) To investigate the possibility of obtaining grants
to perform necessary work.
May QUARTERLY REPORT
June 19 - August 1 ESTABLISH MONITORING AND MAINTENANCE PROGRAM
Purpose: 1) To reduce wear on machinery and cost of repair by establishing
preventative maintenance scheduling.
August 4 - September 12 FINAL REPORTS
Purpose: 1) To summarize energy conservation activities and results
undertaken throughout the year.