HomeMy WebLinkAboutCS-54-86. . , yY �MI4 u,, �,.
TOWN OF NEWCASTLE
SING: COUNCIL FLEETING
DATE: SEPTEMBER 8, 1986
REPORT #: CS -54 -86 FILE #:
SUBJECT: ORONO TOWN HALL ROOFING
REPORT
RECOMMENDATIONS:
It is respectfully recommended that Council approve the following:
1. That CS -54 -86 be received and
■
File # Z,
Res. #
By -Law #
2. That staff be authorized to engage Warnock Horsey Professional Services
Ltd. to set up the tender specs for the Orono Town Hall for:
a) the removal and replacement of the roof shingles
estimate $21,000
b) the installation of insulation and vapour barrier
estimate $ 6,000
c) the installation of exhaust fans and related vents
estimate $ 4,000
d) setting up tender documents and specifications and site
inspection estimate $ 1,500
e) contingencies 15% estimate $ 4,650
TOTAL $37,150
Council Meeting
Report CS -54 -86
page 2
3. That funding of the project come from the Building and Energy
Conservation Account 2900- X -20 -5 and the General Capital Reserve
Account 2900- X -17 -0 and
4. That staff seek any funding available from the Ministry of Energy
to off set the cost of the project.
BACKGROUND AND RECOMMENDATIONS
Council authorized staff to proceed to obtain a professional appraisal of the status
of the Orono Town Hall roof including possible energy saving options.
Attached please find the report from Warnock Horsey as received September 2,1986.
Staff would recommend that option #1 as recommended by the consultant be approved and
that staff be authorized to tender the project as outlined. It is also recommended
that Warnock Horsey set up the specifications and do a final inspection of the
project.
Some funding from the Ministry of Energy may be available and will be investigated
immediately.
Respectfully Submitted,
Jan Devantier, R.D.M.R.
Director of Community Services
JD:wf
Warnock Hersey Professional Services Ltd.
® 3210 American Drive, Mississauga, Ontario L4V 1 B3 (416) 678.7820 Telex 06.968801
August 29, 1986
The Corporation Of The Town Of Newcastle
Department Of Community Services
40 Temperance St.
Bowmanville, Ontario
L1C 3A6
Attention: Mr. Joseph Caruana
Dear Si r:
RE: Roof Replacement
Orono Town Hall
Orono, Ontario
Please find enclosed our preliminary report No. 1 dated Aug. 29, 1986
with reference to the above project. We sincerely regret it's late
submission which was delayed by the further submission of estimated prices
from various contractors.
We will be pleased to meet with you at your earliest convenience to
discuss further the preparation of specifications. and tender documents.
Yours very truly,
F
WARNOCK HERSEY ROFES ZONAL SERVICES LTD.
Wayne Goe rfen
Roofing Co
WG:Ip
VANCOUVER REGINA WINNIPEG THUNDERBAY SAULT STE. MARIE SUDBURY HAMILTON TORONTO MONTREAL DARTMOUTH
ANTinru me AAIRFI Fc KAMnI FTnN CC\/CO. OAOY IAITCOIJAT MMA1 ACCII IAT —A1C
FORM 135 -50 -E
_ Warnock H onal ices ltd.
® 3210 American Drive, Mississauga, Onrario L4V 1133 Telex 06- 968801
Attention: Mr. Joseph
The Corporation Of The
CLIENT Department Of Community
40 Temperance St.
ADDRESSBowmanviIle, Ontario
P. Caruana
Town Of Newcastle
Services
TORONTO
CLIENT'S INSPECTION ORDER NO.
CLIENT'S MATERIAL ORDER NO.
SUPPLIER SUPPLIER'SJOB ORDER NO,
ADDRESS SUPPLIER'S MATERIAL ORDER NO.
SUBCONTRACTOR SUB- CONTRACTOR'S JOB ORDER NO.
ADDRESS
REPORT NO. ON OUR MAIN ORDER NO. REPORT NO. I ON OUR SUB -ORDER NO. INSPECTOR
THIS REPORT REFERS TO THE
PROJECT:
Roofing & Sheetmetal
Orono Town Hall
Orono, Ontario
DATES OF INSPECTION: Aug. 13, 22, 1986.
Introduction
OF THE FOLLOWING:
At the request of Mr. Joseph Caruana of the Corporation of The Town of Newcastle, Warnock
Hersey Professional Services Ltd. conducted a visual examination of the roofing &
sheetmetal on the above project. The purpose of the investigation was to determine and
report upon the existing condition of the roof system and recommend various methods of
replacement incorporating a minimum of insulation with an R -30 Yalue.
Results of the visual examination: (First Option)
The existing shingled roof system and ceiling cavity below were visually examined in
order to confirm their method of construction and present conditions. The framing
details were closely inspected to determine the feasibility of installing blown
insulation and a vapour barrier within the ceiling cavity. It was confirmed that
due to the structural members, various cross bracings and limited space that the vapour
barrier could not be properly installed on top of the ceiling deck below the considered
blown insulation without having numerous gaps permitting air infiltration,,it was
therefore considered to create a flat substrate for the vapour barrier by installing
an initial layer of 6 inches of fiberglas fill to the top of the existing roof joists,
and then apply the vapour barrier on top of the insulation and mechanical fasten and
caulk the vapour barrier to the top of the ceiling joists.
Cont'd.......
T1415 CERTIFICATE, OR REPORT, 15 VALID ONLY FOR THAT WORK WHICH WAS SPECIFICALLY REQUESTED, THE COMPANY IS NOT RESPONSIBLE FOR ANY
VIEWS OR OPINIONS EXPRESSED BY EMPLOYEES PERFORMING THIS WORK WHICH FALL OUTSIDE THE EXACT TERMS OF REFERENCE, ALL CERTIFICATES
AND /OR REPORTS ARE THE RESULT OF WORK PERFORMED IN CONFORMANCE WITH APPLICABLE SPECIFICATIONS AND STANDARDS TO THE BEST OF OUR
ABILITY AND INTENT. HOWEVER, THE COMPANY WILL NOT BE RESPONSIBLE FOR DEVIATIONS WITHIN THE NORMAL LIMITS OF ACCURACY IN ACCORDANCE
0
WITH STANDARD PRACTICES.
Warnock Hersey Professional Services Ltd.
Page 2.
Although this design is not a recommended practice within the insulation industry
it is acceptable, if twice the amount of insulation is applied over the vapour
barrier. This would give the system a total R -value of 52. Since the existing
shingles are totally deteriorated they will require immediate replacement prior to
the insulating of the ceiling. Should this methodology not be excepted it would
cost in excess of $55,000 to reshingle and insulate the roof from the roof deck.
Conclusions (Second Option)
In order to insulate the ceiling from the roof deck, the existing shingles would
have to be removed and additional wood blocking be installed on the wood roof deck.
New ridge insulation would be mechanically fastened to the roof deck, over which
new 2 inch plywood would be i- nstalled. Upon the completion of the above work, a
new shingle roof could be applied. All cable ends would also have to be insulated
and any openings within the ceiling cavity closed. Prior to the start of the above
repair option a complete structural analysis would have to be completed to comfirm if
the new loads introduced could be carried by the existing structure.
Since the first option of remedial repairs will only introduce 12lbs /per square foot
of additional loads to the existing structure we strongly recommend that the Town
of Orono proceed with this option.
Recommendations
We presently recommend that the existing shingle roof be removed and replaced
prior to the installation of the fiberglas blowing wool, vapour barrier and
exhaust fans. The cost of the above would be as follows:
Option No. 1
Item (1) The removal and replacement of'the shingles. Price
$21,000 Dollars.
i
Item (2) The installation of blown fiberglas insulation and the vapour barrier
Approx. Price $6000.00 Dollars.
Item (3) The Installation of exhaust Fans and related vents.
Approx. Price $4000.00 Dollars.
Total estimated costs $31,000.00 (A 15% contingency should also be considered for
wood deck replacement)
Res ectfully Submitted,
WARNOCK HERS Y PROF SSIONAL SERVICES LTD.
Wayne Goe tzen
Arch. Tec
Roof Consultant
WG:Ip
Warnock Hersey Professional Services Ltd.
PHOTOGRAPHS
The wood cathedral Ceiling.
#1
#Z
Warnock Hersey Professional Services Ltd.
PHOTOGRAPHS
The ceiling cavity above the wood cathedral ceiling.
#3
#4
Warnock Hersey Professional Services Ltd.
PHOTOGRAPHS
The existing deteriorated shingled roof system.
Photo #5
Photo #6
Warnock Hersey Professional Services Ltd.
Remedial repairs to the existing shingled roof system.
Lower Canopy shingle roof system.
Photo #7
Photo #8