Report To: Joint Committees
Date of Meeting: February 27, 2023 Report Number: LGS-010-23
Submitted By: Rob Maciver, Deputy CAO/Solicitor
Reviewed By: Mary-Anne Dempster, CAO
File Number: L4000-10-64
Resolution#: JC-025-23
By-law Number:
Report Subject: Durham-Hospice Clarington
Recommendations:
1.That Report LGS-010-23 and any related delegations or communication items, be
received;
2.That the Deputy CAO/Solicitor be authorized to execute an amendment to the
agreement dated April 23, 2021, between Durham Hospice-Clarington and the
Municipality to extend the Construction Commencement Date to December 31,
2023.
3.That all interested parties listed in Report LGS-010-23 and any delegations be
advised of Council’s decision.
Municipality of Clarington Page 2
Report LGS-010-23
Report Overview
That the agreement dated April 21, 2021, between Durham Hospice-Clarington and The
Corporation of the Municipality of Clarington be amended to extend the Construction
Commencement Date from December 31, 2022 to December 31, 2023.
1. Background
1.1 On January 19, 2018, Council approved Report CAO-022-18 entitled, “Potential
Locations for Durham Hospice-Clarington”, which was passed by resolution C-109-18
and which stated Council’s intention to donate land to Durham Hospice-Clarington at
1785 Cobbledick Road, Newcastle (the “Property”) for the purpose of constructing a
hospice facility.
1.2 On April 21, 2021, the Municipality entered into an agreement with Durham Hospice -
Clarington to transfer the Property to Durham Hospice-Clarington (the “Agreement”).
1.3 Pursuant to the Agreement, Durham Hospice-Clarington was required to commence
construction of the building by December 31, 2022, failing which the Municipality could
exercise the right to have the Property reconveyed .
1.4 In the intervening time period, various economic factors have prevented Durham
Hospice-Clarington from commencing construction, and the date has now lapsed.
1.5 Durham Hospice-Clarington has requested that the date be extended by one year to
December 31, 2023. There has been progress in the last several months with
fundraising and the site plan application for the hospice, and it is anticipated that
construction can begin before the end of 2023.
2. Financial Considerations
Not Applicable
3. Concurrence
This report has been reviewed by the Director of Planning and Infrastructure Services
who concurs with the recommendations.
Municipality of Clarington Page 3
Report LGS-010-23
4. Conclusion
It is respectfully recommended that the Deputy CAO/Solicitor be authorized to execute
an amendment to the Agreement dated April 23, 2021, to extend the Construction
Commencement Date to December 31, 2023.
Staff Contact: Robert Maciver, Deputy CAO/Solicitor, 905-623-3379 ext 2013.
rmaciver@clarington.net.
Attachments:
Attachment 1 – Agreement of Purchase and Sale – Paragraph 11.01
Interested Parties:
The following interested parties will be notified of Council's decision:
Durham Hospice-Clarington
Attachment 1 to Report LGS-010-23
Agreement of Purchase and Sale – Clarington and Durham Hospice-Clarington,
April 23, 2021
SECTION 11
RIGHTS OF
RECONVEYANCE
11.01 The Purchaser covenants and agrees that it shall have commenced the
construction of the Purchaser’s intended building on the Property on or before
December 31, 2022 (the “Construction Commencement Date”). For clarity,
commencing the construction of the Purchaser’s intended building on the
Property means the commencement of physical works on the Property directly
related to the construction of the building.
In the event that the Purchaser has not commenced the construction of the
Purchaser’s intended building on the Property by the Construction
Commencement Date (or such other date as the parties may have mutually
agreed to in writing to extend the Construction Commencement Date), then
the Vendor shall have the option, to be exercised by the Vendor within one
hundred and twenty (120) days after the Construction Commencement Date
by delivery of written notice to the Purchaser (the “Construction
Commencement Reconveyance Notice”), to have the Property reconveyed
from the Purchaser at no cost (the “Construction Commencement
Reconveyance Transaction”).