HomeMy WebLinkAboutCOD-017-12 SERVICES Clarington REPORT
CORPORATE
Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date: June 25, 2012 Resolution#: By-law#:
Report#: COD-017-12 File#:
Subject: TENDER CL2012-04, DUKE STREET RECONSTRUCTION
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report COD-017-12 be received;
2. THAT Behan Construction Ltd., Cobourg, Ontario, with a total bid in the amount
of$1,197,895.33 (net of H.S.T. Rebate), being the lowest responsible bidder
meeting all terms, conditions and specifications of Tender CL2012-04 be
awarded the contract for Duke Street Reconstruction, as required by the
Municipality of Clarington, Engineering Department;
3. THAT the funds required in the amount of $784,700.00 (which includes,
$1,197,895.33 for tendering, design, contract administration, material testing,
contingencies and net HST less Region of Durham costs) be drawn from the
following Engineering Department Capital Accounts:
Accounts:
110-32-330-83359-7401 (2011) ............................................................$75,000.00
110-32-330-83359-7401 (2012) ..........................................................$709,700.00
Total funds required ............................................................................$784,700.00
4. That the tender award be subject to the approval of the Regional Municipality of
Durham; and
5. THAT the May r and Clerk be authorized to execute the necessa .agreement.
Submitted by: f 2r Reviewed by:
CM-arie Marano, H.B.Sc., Franklin Wu,
Director of Corporate ervices Chief Administrative Officer
Nancy Taylor, B.B.A., C.A.,
Director of Finance/Treasurer
MM\JDB\km
REPORT NO.: COD-017-12 PAGE 2
1. BACKGROUND
1.1 Tender specifications were provided by AECOM Canada Ltd. for the Duke Street
Reconstruction.
1.2 Tender CL2012-04, Duke Street Reconstruction was advertised in the Daily
Commercial News as well as electronically on the Municipality's website and the
Ontario Public Buyer's Association website. Subsequently, tenders were
received and tabulated as per "Attachment 1".
2. ANALYSIS
2.1 A total of five (5) submissions were received in response to the tender call. All
submissions were deemed compliant.
2.2 After further review and analysis of the compliant bids by AECOM, the
Engineering Department and Purchasing, it was mutually agreed that the low
bidder, Behan Construction Ltd., Cobourg, Ontario be recommended for the
contract for the Duke Street Reconstruction. A copy of the recommendation
memo from the Department of Engineering and AECOM is appended as
"Attachment 1".
2.3 Behan Construction has not provided similar services to the Municipality of
Clarington in the past. However, a review of the references provided with the
submission indicates that Behan Construction has completed similar work in to
specifications and to their satisfaction.
2.4 Queries with respect to the department needs, specifications, etc. should be
referred to the Director of Engineering.
3. FINANCIAL
3.1 The total project cost of$1,804.000:00 represents the Region of Durham's
portion with Clarington's portion amounting to $784,700.00 (net of H.S.T.
Rebate). The total project cost includes $1,197,895.33 for tendering, design,
contract administration and contingencies. The funding and costs for this
project are outlined in the memo from Engineering Services ("Attachment 1
3.2 Funding for this project will be drawn from the following Engineering 2011 and
2012 Capital account:
Roads and Structures Account:
Accounts:
110-32-330-83359-7401 (2011) ............................................................$75,000.00
110-32-330-83359-7401 (2012) ..........................................................$709,700.00
Total funds required ............................................................................$784,700.00
REPORT NO.: COD-017-12 PAGE 3
4. CONCURRENCE
4.1 This report has been reviewed by Tony Cannella, Director of Engineering
Services who concurs with the recommendations.
5. CONCLUSION
5.1 To award the contract to Behan Construction Ltd., Cobourg, Ontario for the Duke
Street Reconstruction.
CONFORMITY WITH STRATEGIC PLAN —
The recommendations contained in this report conform to the general intent of the
following priorities of the Strategic Plan:
Promoting economic development
Maintaining financial stability
Connecting Clarington
Promoting green initiatives
x Investing in infrastructure
Showcasing our community
Not in conformity with Strategic Plan
Staff Contact: Marie Marano, Director of Corporate Services
Attachments:
Attachment 1 — Recommendation Memo from Engineering Services
and letter from AECOM Canada Ltd.
List of interested parties to be advised of Council's decision:
NONE
Attachment 1
MEM U
Leadizzg the Way
TO: Jerry Barber, Purchasing Manager
FROM: Ron Albright, Manager, Infrastructure and Capital Works
DATE: June 19, 2012
RE: Duke Street Reconstruction, Bowmanville
C.L2012-04
The Engineering Services Department has reviewed the recommendation provided by AECOM
Canada Ltd. ("AECOM") and offers the following comments.
Prior to completing the design and tendering work for Duke Street, a Public Information Centre
was held on December 14, 2011 to review the project with the public and to get their input
regarding the proposed works. For more detailed information on the PIC, please refer to Report
EGD-006-12.
Duke Street is currently constructed to an urban cross section between Baseline Road and Park
Drive. The scope of work for this section is rehabilitation and replacement of some of the
existing storm sewer. New storm sewer will be constructed on Ann Street between Duke Street
and Hunt Street. The section of Duke Street between Park Drive and Nelson Street is currently
constructed to a rural . cross section. Upon completion of the works, the street will be
reconstructed to an urban standard with concrete curb and gutter, new storm sewers and new
road structure. The surface asphalt will be placed in 2015 under a separate contract. The
Municipality of Clarington is working in cooperation with the Region of Durham on this project
and they will be replacing their watermain and sanitary servicing on_Duke Street.
We concur with AECOM's recommendation to award the contract to Behan Construction Ltd. in
the amount of $1,330,210.02, inclusive of HST, or $1.,197,895.33 net HST, for the
reconstruction of Duke Street.
A detailed breakdown of the Clarington's and the Region of Durham's funding is provided on the
Cost Apportionment provided with AECOM's tender review letter. The design costs reflect
design for the reconstruction of the entire length of Duke Street from .Baseline Road to.Argyle
Street, as well as Nelson Street between Hunt Street and Ontario Street. The reconstruction of
Duke Street from Nelson Street to Argyle Street and Nelson Street is tentatively,scheduled for
2013, pending Council approval. The design costs also reflect a considerable amount of effort
coordinating utility relocations and. dealing with MTO for the work at the intersection of Duke
Street and Baseline Road, due to the close proximity to the Highway 401 westbound ramps.
Oukc� `street i-�econ truction.
CL20-12-04 2 June 19, 012
Due to past experiences on similar projects, and the preliminary nature of the utility relocation
estimates, a contingency amount of approximately 12% is carried forward. Therefore, including
design and tender fees, contract administration fees, and other project costs such as the
Municipality's share of utility relocation costs, the Engineering Department advises the following
breakdown for the above referenced project:
Total Project Value $784,700.00
Budget Amount
110-32-330-83359-7401 (2011) $75,000.00
110-32-330-83359-7401 (2012) $750,000.00
Estimated Unexpended Budget $40,300.00
Additional Funding Required $0
We recommend the report to Council move forward based on the above apportionments.
Attached for your files is the recommendation provided by AECOM which includes a more
detailed breakdown of estimated project costs. Should you have any further questions, please
feel free to contact the undersigned.
Regards,
f
Ron Albright, P. Eng.
Manager, Infrastructure and Capital Works
RA/sb/dv
Attachment
Pc: Will McCrae, P. Eng., Manager, Cobourg Office, AECOM
Nancy Taylor, Director of Finance
A.S. Cannella, Director of Engineering Services
At t6awc"h t1
QO
M Qn ^'t
arirraAtrTTOSdwjS c°
U ..a
p.r�na�rTOg 11*11 {a O a �, pa 111
.� C*O,
al �' o
a hd ME
pz)14 Spa T-,j D
�• �
o��eet J� to A W
D2
A
-aa,-PSTH w
a
B
ui -
Sea a
anua S.rclS— `
Attachment 9
AECOM 905 372 2121 tet
AXOM
513 Division Street 905 372 3621 fax
COBOURG,Ontario K9A 6G6
w�vvr.agcom.caia
June 14, 2012
Mr.A. S. Cannella, C.E.T,
Director, Engineering Services
The Municipality of Clarington
40 Temperance Street
BOWMANVILLE, Ontario L1C 3A6
Dear Sir:
Project No: 60215500
Regarding: Duke Street Reconstruction, Bowmanville
Contract No. CL2012-04(the "Contract")
Municipality of Clarington
Tenders for the above project were opened at the Municipal Offices on Thursday, June 7,2012 at
2;15p.m. A list of the bids received is provided in the table below,
BIDDER TOTAL BID TOTAL BID TOTAL BID
(Excl. HST) (Incl. 13% HST) (Intl. Net HST Rebate)
Behan Construction Ltd.
Cobourg, ON $1,177,177.01. $1,330,210,02 $1,197,895.33
Hard Co Construction Ltd.
Whitby, ON $1,187,789.00 $1,342,201.57 $1,208,694.09
Coco Paving Inc. $1,240,166.40 $1,401,388.03 $1,261,993.33
Bowmanville, ON_-_._:—.
Eagleson Construction
Millbrook, ON $1,271,003.37 $1,436,233.81 $1,293,373.03
Macklin Bros. Construction $1,294,895.37* $1,463,231.77* $1,317,685.53'`
Grafton, ON
*Calculation Error
The Municipality of Clarington's Purchasing Department(the"Purchasing Department") reviewed all
bids to confirm compliance with the Clarington Purchasing By-Law. All bids were deemed compliant
by the Purchasing Department. AECOM Canada Ltd. ("AECOM") has reviewed the two lowest bids
and confirmed the bid values noted above, A calculation error was noted on Macklin Bros,
Construction's bid. This error in no way affects the bid order. Behan Construction Ltd, is the lowest
bidder. Its submitted tender has been reviewed and is found to be arithmetically correct.
Attachment 1
Page 2
June 14,2012
As requested by the Purchasing Department, references were checked only for the lowest bidder.
Behan Construction Ltd. has completed projects of similar scope and value. References stated that
Behan Construction Ltd, has completed work to specification and to their satisfaction.
With the low bid from Behan Construction Ltd., and other associated project costs noted on the
attached cost apportionment, the project is within budget. Should funding be available and based on
the input provided by the references contacted regarding performance on previous projects, we are
not aware of any reason why the Municipality would not be entitled, in its sole discretion, to award the
Contract to Behan Construction Ltd, in the amount of$1,177,177.01 (exclusive of HST)subject to all
provisions of the Clarington Purchasing Bylaw being met.
Bid Cheques or Bid Bonds shall be retained for Behan Construction Ltd. and Hard-Co Construction
Ltd., the second low bidder, until the Contract has been executed.
Should you have any questions regarding this matter, please contact the undersigned.
Sincerely,
AECOM Canada Ltd.
Will McCrae, P.Eng.
Associate Vice-President, East District, Water
will.mccrae@aecom.com
WM:cs
encl.
cc: Mr.Ron Albright,P.Eng., Manager of Infrastructure and Capital Works,Municipality of Clarington
Mr.Sean Bagshaw,P.Eng.,Capital Works Engineer,Municipality of Clarington
Mr.Paul Storms,C.E.T., Environmental Services—Design Division,Regional Municipality of Durham
Municipality of Clarington/Region of Durham
2012 Duke Street Reconstruction
Cost Apportionment Based on Low Bid June 15,2012
Contract CL2012-04 AECOM Project#60215500/60117330
Description
Total
Municipality of Clarington
Region of Durham
Comments
Roadworks and Storm
Sewer
Sanitary Sewer&
Appurtenances
Watermain&
Appurtenances
Project ID/Account Number
110-32-330-83359-7401
)000000000=
)0000OV-100=
Construction Costs Contract CL2012-04
Total Part'A'-Roadworks and Storrs Sewers
$ 593,546.56
$ 396,481.86
$ 131,376.47
$ 65,68823
Items Apportioned at Varying Percentaaes per Item,
Earth Ex,Curb Removal,S/W Removal,Subdrain,Granular,'B'and'A',Extra
Depth Gmnular'B',Calcium,Water,Geogdd,Geotextle,Curb,S/W,Relay Brick
Pavers,Sawcutting,HL8,HL3 in Driveways,AC Adjust,Topsoil,Sod
Total Part'B'-Sanitary Sewer and Appurtenances
$ 256,626.82
$ -
$ 256,626.82
$ -
Total Part'C'-Waternain and Appurtenances
$ 278,746.44
$ -
$ -
$ 278,746.44
Sub Total Construction
$1,128,919.82
$ 396,481.86
$ 388,003.29
$ 344,434.67
Total Part'D'-General Items
$ 48257.19
$ 8,977.78
$ 23.915.38
S 15.364.03
prorated
Total Construction
$1,177,177.01
$ 405,459.64
$ _ 411,918.67
$ 359,798.71
AECOM Design Project Number
60215500
60117330
60117330
'
Detail Design,Tendering and Approvals
Claringlon-Commencementto Tender -
$ 101,476.09
-
$ 101,476.09
$ -
$ -
Including:
Duke Street-Baseline Road to Argyle Street Chet.side-streets)
Nelson Street-Hunt Street to Ontario Street
Region of Durham-Commencement to Tender
$ 57.432.76
$
$ 27.63327
$ 29,799.49
Including,
Duke Street-Baseline Road to Argyle Street Qncl.side-streets)
Nelson Street-Hunt Street to Ontario Street(W(M Only)($6,900.00 Pending)
Total Detail Design,Tendering and Approvals
$ 158,908.85
$ 101,476.09
$ 27,633.27
$ 29,799.49
Construction Administration and Materials Testing
Construction Admin.and Materials Testing
$ 117,717.70
$ 40,545.96
$ 41.191.87
$ 35,979.87
Including,
Duke Street-Baseline Road to Nelson Street(ind.side=slreeW
Total Tendering,Construction Admin.and Materials Testing
$ 117,717.70
$ 40,545.96
$ 41,191.87
$ 35,979.87
Other Costs
Storm Sewer Investigations
$ 2,965.00
$ 2,965.00
$ -
$ -
Sewer Tech Invoice
Gas Main Exposures
$ 6,500.00
$ 6,500.00
$ -
$ -
Springrove Invoice
Bell Relocations at Park Drive
$ 10,784.51
$ 10,784.51
$ -
$ -
Estimate provided by Bell "
Enbridge Relocations(Nelson to N.of Albert)
$ 38,674.00
$ 38,674.00
$ -
$ -
Enbridge PO Value
Legal
$ 3,650.00
$ 1,825.00
$ 1,216.67
$ 606.33
Ivan B.Wallace Invoice
Geotechnical Investigations
$ 3,950.00
$ 1,975.00
$ 1,316.67
$ 658.33
DSA Invoice
MTO Encroachment Permit
$ 450.00
$ -
$ 300.00
$ 150.00
Utility Relocations(Estimated)
Bell at Nelson Street
$ 11,000.00
$ 11,000.00
$ -
$ -
Lump Sum Estimate(Unknown Scope)
Bell at Victoria Street
$ 5,000.00
$ 5,000.00
$ -
$ -
Lump Sum Estimate(Unknown Scope)
Bell at Albert Street
$ 11,000.00
$ 11,000.00
$ -
$ -
Lump Sum Estimate(Unknown Scope)
Bell at Bell at Durham Street
$ 11,000.00
$ 11,000.00
$ -
$ -
Lump Sum Estimate(Unknown Scope)
Veridian
$ 75.000.00
$ 75,000.00
$ -
$ -
Lump Sum Estimate(Unknown Scope)
Total Other Costs
$ 179,973.51
$ 175,723.51
$ 2,833.33
$ 1,416.67
Additional Project Costs
1.76%Unrecoverable HST
$ 28,754.48
$ 12,728.41
$ 8,510.96
$ 7,515.11
12%Contingencies(inclusive of Net HST)
$ 141,46B.45
$ 48,766.40
$ 49,511.90
$ 43,190.15
Total Estimated Project Costs
$1,804,000.00
$ 784,700.00
$ 541,600.00
$ 477,700.00
BudgetAmount
$ 825,000.00
$ -
$ -
REQUIRE R.O_D 2012 BUDGET VALUES(incl.2011 fordesign)
Under/(Over)Budget Amount
$ 40,300.00
$ (541,600.00)
$ (477,700x0)
AECOM