HomeMy WebLinkAboutCOD-012-12 Clarbgton REPORT
CORPORATE SERVICES DEPARTMENT
Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date: May 28, 2012 Resolution#: By-law#:
Report#: COD-012-12 File#:
Subject: TENDER CL2012-12, PAVEMENT REHABILITATION, VARIOUS LOCATIONS
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report COD-012-12 be received;
2. THAT Coco Paving Inc., Oshawa, Ontario, with a total bid in the amount of
$2,018,867.52 (net of H.S.T. Rebate), being the lowest responsible bidder
meeting all terms, conditions and specifications of Tender CL2012-12 be
awarded the contract for Pavement Rehabilitation, Various Locations, as required
by the Municipality of Clarington, Engineering Department; and
3. THAT the funds required in the amount of$2,360,000.00 (which includes
$2,018,867.52 for tendering, design, contract administration and contingencies)
be drawn from the following Engineering Department Capital Accounts:
Pavement Rehabilitation Accounts:
110-32-330-83212-7401 (2012) .......................................................$1,483,866.00
110-32-330-83 12-7401 (2011) .......................................................$ 421,134.00
110-32-330-"12-7401 (2010) .................................................... $ 455,000.00
Submitted by: Reviewed by:
arie Marano, H.B.Sc., ranklin Wu,
C.M.O., Chief Administrative Officer
Direfdtor of Corporate Services
Nancy tayfork(B.B. ., C.A.,
Director of Finance/Treasurer
MM\JDB\km
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, SOWMANVILLE, ONTARIO L1C 3A6 T 905-623-3379
REPORT NO.: COD-012-12 PAGE 2
1. BACKGROUND
1.1 Tender specifications were provided by AECOM Canada Ltd. for the Pavement
Rehabilitation, Various Locations.
1.2 Tender CL2012-12 Pavement Rehabilitation, Various Locations was advertised
in the Daily Commercial News as well as electronically on the Municipality's
website and the Ontario Public Buyer's Association website. Subsequently,
tenders were received and tabulated as per "Attachment 1".
2. ANALYSIS
2.1 A total of two (2) submissions were received in response to the tender call. Both
submissions were deemed compliant.
2.2 After further review and analysis of the compliant bids by AECOM, the
Engineering Department and Purchasing, it was mutually agreed that the low
bidder, Coco Paving Inc., Oshawa, Ontario be recommended for the contract for
the Pavement Rehabilitation, Various Locations. A copy of the recommendation
memo from the Department of Engineering and AECOM is appended as
"Attachment 1".
2.3 The low bidder has provided similar services to the Municipality of Clarington in
the past and the level of service has been satisfactory.
2.4 The references were contacted by AECOM and were found to be acceptable.
2.5 Queries with respect to the department needs, specifications, etc. should be
referred to the Director of Engineering.
REPORT NO.: COD-012-12 PAGE 3
FINANCIAL
3.1 The total project cost is $2,360,000.00 (net of H.S.T. Rebate). The funding
required for the project is outlined in the memo from Engineering Services
("Attachment 1").
3.2 Funding for this project will be drawn from the following Engineering 2011
Capital accounts:
Pavement Rehabilitation Accounts:
110-32-330-83212-7401 (2012) .......................................................$1,483,866.00
110-32-330-83212-7401 (2011) .......................................................$ 421,134.00
110-32-330-83212-7401 (2010) .......................................................$ 455,000.00
Total Available Funds ......................................................................$2,360,000.00
4. CONCURRENCE:
This report has been reviewed by Tony Cannella, Director of Engineering Services
who concurs with the recommendations.
5. CONCLUSION
5.1 To award the contract to Coco Paving Inc., Oshawa, Ontario for the Pavement
Rehabilitation, Various Locations.
CONFORMITY WITH STRATEGIC PLAN —
The recommendations contained in this report conform to the general intent of the
following priorities of the Strategic Plan:
Promoting economic development
Maintaining financial stability
Connecting Clarington
Promoting green initiatives
X Investing in infrastructure
Showcasing our community
Not in conformity with Strategic Plan
Staff Contact: Marie Marano, Director of Corporate Services
Attachments:
Attachment 1 — Recommendation Memo from Engineering Services
and letter from AECOM Canada Ltd.
Attachment 1
MEMOLeading the Way
TO: Jerry Barber, Purchasing Manager
FROM: Ron Albright, Manager, Infrastructure and Capital Works
DATE: May 22, 2012
RE: 2012 Pavement Rehabilitation, Various Streets
CL2012-12
The Engineering Services Department has reviewed the recommendation provided by AECOM
Canada Ltd. ("AECOM") and offers the following comments.
We concur with AECOM's recommendation to award the contract to Coco Paving Inc. in the
amount of $2,241,863.50, inclusive of HST, or $2,018,867.52 net HST, for the rehabilitation of
various streets throughout the Municipality.
A detailed breakdown of the project cost is provided on the Cost Apportionment provided with
AECOM's tender review letter. Due to past experiences on similar projects, a contingency
amount of approximately 5% is carried forward.
Funding for the project will come from the Pavement Rehabilitation account including the current
funding year and unexpended funds from previous years, as shown in the table below.
Total Project Value $2,360,000.00
Budget Amount
Pavement Rehabilitation,
110-32-330-83212-7401 (2012) $1,483,866.00
110-32-330-83212-7401 (2011) $421,134.00
110-32-330-83212-7401 (2010) $455,000.00
Estimated Unexpended Budget $0.00
Additional Funding Required $0.00
Attachment 1
2012 Pavement Rehabilitation
Reconstruction, CL2012-12 2 IMay 22, 2012
We recommend the report to Council move forward based on the above apportionments.
Attached for your files is the recommendation provided by AECOM which includes a more
detailed breakdown of estimated project costs. Should you have any further questions, please
feel free to contact the undersigned.
Regards,
Ron Albright, P. Eng.
Manager, Infrastructure and Capital Works
RA/sb
Attachment
Cc: Will McCrae, P. Eng., Manager, Cobourg Office, AECOM
Nancy Taylor, Director of Finance
A.S. Cannella, Director of Engineering Services
Attachment 1
A. AECOM 905 372 2121 tat
513 Division Street 905 372 3621 fax
COBOURG,Ontario K9A 5G6
www.aecom.com
May 18 2012
Mr. A. S. Cannella, C.E.T.
Director, Engineering Services
The Municipality of Clarington
40 Temperance Street
BOWMANVILLE, Ontario L1C 3A6
Dear Sir:
Project No: 60263511
Regarding: 2012 Pavement Rehabilitation,Various Streets
Cgntract No. CL2012-12(the"Contract")
Municipality of Clarington
Tenders for the above project were opened at the Municipal Offices on Friday, May 11, 2012 at
2:15p.m. A list of the bids received is provided in the table below.
BIDpR T1�TAL SID TOTAL BID; TC7TAL 131D
( xcl kiST} (Intl 13 % HST) (Incl Net HST Rebate)
Coco Paving Inc., $1,983,950.00 $2,241,863.50 $2,018,867.52
Bowmanville
Miller Paving Limited, $2,238,911.09* $2,529,969.53* $2,278,315:93*
Whitby
*Calculation Error
The Municipality of Clarington's Purchasing Department(the"Purchasing Department") reviewed all
bids to confirm compliance with the Clarington Purchasing By-Law. All bids were deemed compliant
by the Purchasing Department. AECOM Canada Ltd. ("AECOM") has reviewed the two lowest bids
and confirmed the bid values noted above. A calculation error was noted on Miller Paving Limited's
bid. This error in the amount of$30.00 (excl. HST) in no way affects the bid order. Coco Paving Inc.
is the lowest bidder. Its submitted tender has been reviewed and is found to be arithmetically correct.
As requested by the Purchasing Department, references were checked only for the lowest bidder.
Coco Paving Inc. has completed projects of similar scope and value. References stated that Coco
Paving Inc. has completed work to specification and to their satisfaction,
With the low bid from Coco Paving Inc., and other associated project costs noted on the attached cost
apportionment, the project is within budget. Should funding be available and based on the input
CL2012.12 Tender Award Letter.Dac
Attachment 1
JUCOM Page 2
May 18,2012
provided by the references contacted regarding performance on previous projects, we are not aware
of any reason why the Municipality would not be entitled, in its sole discretion, to award the Contract
to Coco Paving Inc. in the amount of$1,983,950.00 (exclusive of HST) subject to all provisions of the
Clarington Purchasing Bylaw being met.
Bid Cheques or Bid Bonds shall be retained for Coco Paving Inc, and Miller Paving Limited, the
second low bidder, until the Contract has been executed.
Should you have any questions regarding this matter, please contact the undersigned.
Sincerely,
AECOM Canada td.
Will McCrae, P.Eng.
Associate Vice-President, East District, Water
will.mccrae@aecom.com
WM:cs
encl.
cc: Mr.Ron Albright,P.Eng.,Manager of Infrastructure and Capital Works,Municipality of Clarington
Mr.Sean Bagshaw,P.Eng.,Capital Works Engineer,Municipality of Clarington
CL2012-12 Tender Award Letlec0oe
Attachment 1
Municipality of Clarington
2012 Pavement Rehabilitation,Various Streets
Cost Apportionment based on Low Bid May 18,2012
Contract CL2012-12 AECOM Project#60263511
Clarington
Description Total 2012 Pavement Comments
Rehabilitation
ProjectiD/Account Number 110.32.330.83212.7401
Construction Costs Contract CL2012-12
-- -- _
PART A':Nash Road from Rundle Road to Hells Road(Pulverize)
(PROVISIONAL) $ 7.33,245.07 $ 233,245.07
PART'B':Baseline Road from Trulis Road to Prestonvale Road(Pulverize) $ 409,476.10 $ 409,476.10
PART'C:Munday Court from Stevens Road to North End Cul-de-Sac(Full
Depth Asphalt Removal)(PROVISIONAL) $ 93,937.49 $ 93,937.49
PART'D:Lorraine Court from Liberty Street to West End(Partial Depth Asphalt $ 00,117.16 $ 90,117.16
Removal)
PART'S':Galbraith Court from King Street E to North End Cul-de-Sac(Micro $ 06,594.04 $ 86,594.04
Surfacing)(PROVISIONAL)
PART T':Concession St E From Lambs Road to Providence(Micro Surfacing) $ 126,957.24 $ 126,957.24
PART'G:Concession Street E from Providence to Bragg Road(Micro Surfacing) $ 103,892.93 $ 103,892.93
PART'H':Concession Street E from Bragg Road to Towniine,(Micro Surfacing) $ 69,584.52 $ 69,584.52
----- ------- - --- -- - - -- - -— - --
- ----------- --------
PART T:Concession 6 from Hwy 35 to Old Kirby Road(Partial Depth $ 187,499.39 $ 187,499.39
and Pulverize)
PART'J:Millson Hill Drive from Main Street to Orono Mill Street(Full Depth $ 188,275.07 $ 1$8,275.07
Asphalt Removal)
PART W:Concession 7 Leskard Road to 320m West of Leskard Road(Pulverize $ 134,924,96 $ 134,924.96
PART'L':King Street and Scugog Street Intersection(Partial Depth Asphalt Rem $ 115,645.40 $ 115,645.40
PART'M:Concession Street Intersection Repairs $ 35,437.86 $ 35,437.86
PART'N.Climie Court from Galbraith Court to East End Cul-de-Sac(Micro $ 22,216,31 $ 22,216.31
Surfacing)(PROVISIONAL)
PART'O':Salina Road from Hillside Drive to 200 m North of Odium Street $ 12,834.00 $ 12,834.00
(Crack Repair)(PROVISIONAL)
PART'P':Provisional Items
$ 57,644.72 $ 57,644.72
Sub-Total Construction(Excl.General Items) $ 1,968,282,26 $ 1,968,282.26
PART'Q':General Items $ 15,667.74 $ 15,667.74
Total Construction $ 1,983,950.00 $ 1,983,950.00
Tendering,Contract Admin.,and Materials Testing AECOM Project No 60263611
Tender Preparation and Approvals $ 26,426.82 $ 26,426.82
---------- - --°----- ._ - ----- --- --- ------------ ------- ---------
Construction Admin,and Materials Testing $ 198,395.00 $ 198,395.00 Estimate
--------------- ------------- ----------------- ----- _- -..__--------- --------------------
Total Construction Administration $ 224,821.82 $ 224,821.82
Other Costs
Traffic Loops @ King/Scugog $ 8,326.31 $ 8,326.31 Region of Durham Quote
Permits and Approvals $ 2,000.00 $ 2,000.00 PTTW(Milson Hill,Baseline Rd.),CLOCA(Baseline Rd.)
Total Other Costs $ 10,326.31 $ ----10,326.31 ---`------ - -- ------
Additional Project Costs
5%Contingencies(Intl.1.76° unrecoverable HST) $ 101,845.74 $ 101,845.74
-— -----._...-----------
----- ----- ---- --- — --
1.76%Unrecoverable HST(excl.contingencies) $ 39,056.13 $ 39,056.13
Total Estimated Project Cost $ 2,360,000.00 $ 2,360,00D.00
BudgetAmount $ 2,360,000.00 $ 2,360,000.00
(Over)IUnder Budget Amount
-�--------- --- -- - ------- ----------------
All costs exclude H.S.T.