HomeMy WebLinkAboutCS-25-87TOWN OF NEWCASTLE
r REPORT
MEETING: General Purpose and Administration Committee
DATE: JULY 6, 1987
REPORT #: CS -25 -87
FILE #:
SU&ECT: COMMUNITY SERVICES DEPARTMENT STATUS AND UPDATE
File # . >J
Res.
By -Law #
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following: -
1. That Report CS -25 -87 be received for information.
BACKGROUND AND COMMENTS:
The year to date has been a very active one for the Community Services Department as
previewed in our 1987 Capital and Operating budgets. Generally speaking divisional
budget actuals are on target, as related to the department's operational budgets.
With respect to our Capital Equipment purchases and our Capital Projects, preliminary
figures indicates that we are well within the budget allotment for 1987.
Currently, the department has provided for and filled 39 summer positions. These
students are employed predominantly in the Parks and Cemetery Maintenance Division,
and our Aquatic Program Division.
For the most part, the weather has been most obliging this past spring, which made the
transfer from fall & Winter to our Spring and Summer operation a relatively smooth
one. As a result, our ongoing maintenance work is on schedule.
../2
General Purpose and Administration Committee
REPORT NO. #CS -25 -87
Page 2.
Outdoor pools in Newcastle Village and Orono have been approved by the Public Health
Officials, and the doors opened to the Public on June 28th, for our summer season.
The enclosed attachments are provided to members of Council as a status report on the
various divisions within the Community Services Department and are as follows:
- Parks Development and Upgrading - Attachment #1
- Program Division - Attachment #2
- Park Facilities / Scheduling - Attachment #3
- Building Maintenance - Attachment #4
Respectfully submitted,
-9'VA't-a��
Jo h P. Caruana
Acting Director of Community Services
JPC:sa
Attachments
Recommended for presentation
to the Committee
C
Lawrence otseff
Chief A ni trative Officer
ATTACHMENT #1
PARKS DEVELOPMENT AND UPGRADING
PROJECT DETAIL BUDGET
Enniskillen Park Land Acquisition $ 40,000.00
Site Preperation $ 15,000.00
Seeding $ 2,500.00
Staff has received a Draft Plan of Subdivision which is being proposed for this
area. We are in the process of negotiation for appropriate properties as
parkland dedication which would compliment our original intent of expanding
existing facilities with the Enniskillen Public School. If this can
appropriately be accomplished, funds budgeted for land acquisition may not be
required.
':# »I
Maple Grove East
(upgrading)
DETAIL
Install New Backstop
BUDGET
$ 1,700.00
This project is complete and facilities at Maple Grove East are being utilized by
the public.
PROJECT
Courtice West Park
DETAIL
Seeding & Fertilizer
BUDGET
$ 2,500.00
Through negotiations with staff, the developer has agreed to fertilize, seed and
in some areas, sod this park.
As of mid June, this park has been graded to specifications and is now being
prepared for seed and sod. Equipment for this park will be requested through the
1988 capital budget for installation next year. It is our intent to bring this
park on stream and available for public use next summer. However, implementation
will be conditional, depending on.the condition of the new grass.
...2
-2-
PROJECT DETAIL BUDGET
Cherry Blossom Parkette Landscaping $ 1,600.00
Seed & Fertlizer $ 1,000.00
Creative Playground $ 12,500.00
Walkway $ 9,600.00
Grading and Seeding of this park, is now complete. Landscaping and the
installation of the walkway system and playground equipment will be completed
this fall. The park will be available for public use this winter and will be
fully operational in the spring of 1988.
PROJECT DETAIL BUDGET
Gatehouse Parkette Seeding & Fertilizer $ 1,000.00
(Courtice) Landscaping $ 1,600.00
In previous discussion with the developer, intentions were to prepare this park
for seeding and landscaping this fall. At present, our timing is still
consistent with the developer, and we are expecting to develope the park as
scheduled. Funding for park equipment will be requested in our 1988 capital
budget for installation in the spring /summer of next year.
PROJECT
DETAIL
BUDGET
Courtice North Diamond Base Line Fencing $ 1,400.00
This project is complete, and the facility is fully operational.
PROJECT DETAIL BUDGET
Memorial Park (Bow.) Tile Drainage $ 4,000.00
This project has been re- scheduled to the fall of this year.
PROJECT
DETAIL
BUDGET
le! tai
Soper Creek (Erosion Gabions
Control) Rip Rapping $ 20,000.00
Limestone
Engineering Fees
Certified Engineer Drawings of this project are required by C.L.O.C.A. because of
its magnitude. Purchasing is in the process of engaging a suitable firm to
prepare the necessary engineering work required.
...3
PROJECT
_3_
DETAIL
BUDGET
Baseline Park Grading $ 15,000.00
Seeding & Fertilizer $ 2,500.00
Playground Equipment $ 12,250.00
Staff has been working with C.L.O.C.A. on this project, as the property is
located in flood plain. Detailed mapping is now being prepared for submission to
C.L.O.C.A. Once approved, this job will be contracted for immediate
implementation. Funding will be required for the installation of a baseball
backstop through our 1988 capital budget.
PROJECT DETAIL
Lord Elgin Park Tennis Nets
This project is complete and fully operational.
PROJECT
Orono Park
DETAIL
Fencing Repairs
Foot Bridge
Barbecues
BUDGET
$ 600.00
BUDGET
$ 1,800.00
$ 4,500.00
$ 450.00
Fencing Repairs have been completed and the Tennis Courts are now fully
operational. The new foot bridge and barbecues have been received and are now
installed.
PROJECT DETAIL BUDGET
Peters Pike Parkette Playground Equipment $ 6,250.00
(Orono) Landscaping $ 1,000.00
Park Benches 400.00
Picnic Tables 450.00
As requested during budget deliberations, staff has contacted area residents and
received positive reaction to the proposed playground development. Equipment is
now ordered and will be installed late summer.
U/
PROJECT DETAIL BUDGET
Newcastle Tennis Courts Fencing Repairs $ 1,100.00
Nets $ 900.00
This project has been completed and the facility is fully operational.
PROJECT DETAIL BUDGET
Newtonville Park Land Acquisition $ 40,000.00
Site Preparation $ 15,000.00
Seeding and Fertilizer $ 2,500.00
Staff has been communicating with representatives of the owner of the property in
question. A preliminary Draft Plan of Subdivision for this area has been
discussed and as in the Enniskillen Project. We are optimistic that we will
obtain required parkland, through Parkland Dedication. Negotiations are still in
the initial stages.
PROJECT DETAIL BUDGET
Foster Creek Park Seeding & Fertilizer $ 2,000.00
Unfortunately, this piece of property is not conducive to development of an
active play area as previously anticipated. As a result, staff has required
additional parkland through a related development to the west of this property,
therefore, we will be developing a larger site which will accommodate both soccer
and baseball. The existing park will be developed as a passive areas.
PROJECT
DETAIL
BUDGET
Memorial Park (Newcastle) Fencing $ 1,800.00
Playground Equipment $ 3,000.00
Park Benches $ 800.00
The fencing contract has been completed at this park. Park benches are on order
and will be installed when delivered. Staff is working together with the
Separate School Board and members of the Parent /Teacher Association, to develop a
substantial playground for this area. Staff have been negotiating with the
developer of the adjacent property and are optimistic that an arrangement can be
made with respect to securing property as parkland dedication which would permit
joint development of a play area. Equipment will be purchased, and stored for
installation in 1988.
...5
U V - <)
-5-
PROJECT DETAIL BUDGET
Mearns Ave. East Soccer Goal Posts $ 1,400.00
Equipment for this soccer pitch has been ordered, and will be installed for
public use in 1988.
PROJECT DETAIL BUDGET
Burketon Community Park Site Preparation $ 16,200.00
Seeding $ 21500.00
Staff is currently communicating with the Burketon Park Board, with respect to
preparation of specifications for the excavation work required. We are
anticipating a contract to be awarded this fall.
ATTACHMENT #2
PROGRAM DIVISION
Aquatics
At present, programs at the Fitness Centre have been running to capacity. The
following is a breakdown of registrations for the past Winter, Spring and current
Summer swimming sessions.
TOTAL
WINTER REGISTRATIONS
Youth
399
Adults
106
Privates
16
Semi - Private
56
Totals 577
TOTAL
SPRING REGISTRATIONS
Youth
Adults
Privates
Semi- Private
Totals
573
117
37
152
TOTAL
SUMMER REGISTRATIONS
N.F.C. 311
N.L.P. 35
Orono 59
Totals 405
The aquatic staff is currently examining our potential for expanding into the
following program areas.
1) Snorkeling
2) Rescue Patrol (for schools)
3) Expanding pre - school program
4) Programs for Special Needs (Handicapped)
5) Policy for Red Cross Standards for Town of Newcastle
6) Expanding Special Events - (Hallowe'en & Christmas)
-2-
SPECIAL EVENTS
March Break Bonanza
The Community Services Department offered its fourth Annual March Break Bonanza
from March 16 -20 this past Winter. Activities are coordinated with the Library
and Visual Arts Centre in order to avoid duplication while at the same time offer
a variety of recreational and leisure opportunities for the youth of our
communities.
The weeks activities were geared for children six to twelve yeas of age and
included: swimming, bowling, gym -bics, movies, Easter egg painting, print making,
a magic show, a puppet show, a theatre show and field trips to the Bowmanville
Museum, Ganaraska Forest Centre, and the Darlington Generating Station. All
activities took place within our municipal boundaries to make children and
parents aware of the recreational opportunities available to them right on their
doorsteps. Total number of participants for these activities was 1,285, and
Included children from throughout our municipality.
Sneaker Dav and Participaction Challenqe
Staff from all departments competed in the "Sneaker Day Contest" and everyone
seemed to have a lot of fun with it. This event was a promotional tool used to
kick off "Participaction Week ".
Once again, residents of the Town of Newcastle won the "Participaction Challenge"
for the Durham Region and even better, we improved our participation over last
year with 16,251 people or 48.5% of our population taking part as compared to
9,510 people or 29% in 1986. The national average was 41.28 %.
Other interesting statistics are noted as follows:
1) Newcastle was 21st of 59 communities with populations over 25,000; and
2) Newcastle was 33rd of 68 communities who participated in Ontario; and
3) Newcastle was 122nd of 257 communities who participated across Canada.
ATTACHMENT #3
PARK FACILITIES /SCHEDULING
Once again, the demand for use of our play fields was extremely high this year
and for the most part, staff has been able to accommodate all teams requiring
baseball diamonds and soccer pitches throughout the municipality.
We have a total of 156 baseball teams within the Town of Newcastle, of these 87
are adults and 69 are youth teams. Each of the teams are being accommodated on a
total of 32 diamonds. For the most part, our diamonds are used to capacity on
weekdays with weekend use being reserved for practices and various Tournaments.
We also have a total of 58 soccer teams within Town Boundaries of these 9 are
adults and 49 are youth teams. At present these teams are using a total of 23
soccer pitches located throughout the municipality.
i
The following is a breakdown of these totals:
WARD #1
Courtice -Zion
Hampton
Burketon
Tyrone
Solina
Enniskillen
Hydro
TOTALS
ARD #2
Bowmanville
WARD #3
Newcastle
Brownsdale
Newtonville
Orono
Kendal
TOTALS
OVERALL TOTALS
ADULT
MINOR
TOTAL #
TOTAL # 0
ADULT
MINOR
TOTAL #
TOTAL #
BASEBALL
BASEBALL
OF TEAMS
BALL FIELDS
SOCCER
SOCCEF
OF TEAMS
PITCHES
1
9
10
5
2
1
3
3
4
4
8
3
1
5
6
2
1
0
1
1
3
3
6
3
1
5
6
3
2
4
6
1
1
3
4
1
3
-
3
1
-
-
-
-
6
-
6
0
-
-
-
-
20
20
40
14
5
14
19
9
53
35
87
8
3
25
28
7
4
-
2
1
6
1
3
1
-
6
6
2
'
8
-
10
-
18
1
3
-
1
-
4
-
5
1
4
2
1
3
2
14
14
28
10
1
10
11
7
87 69 156 32 9 49 58 23
PROJECT
Newcastle Fitness Centre
BUILDING MAINTENANCE
DETAIL
Roof Repair
Fibre- glass(Filtration
Tank)
Deck Flange Anchors
ATTACHMENT #4
BUDGET
$ 10,000.00
$ 6,000.00
$ 2,500.00
Purchasing is in the process of receiving tenders for the roof repair work. We
anticipate that this job will be completed in August /September of this year. The
main filtration tank at the Fitness Centre has been lined with fibre -glass and is
again fully functional. The Deck Flange Anchors will be installed during this
fall.
PROJECT DETAIL BUDGET
Darlington Sports Centre Paint Exterior $ 14,000.00
Replace Down Pipes $ 1,000.00
Heat Recovery System $ 13,000.00
Replace Overhead Doors $ 2,500.00
The painting contract has been awarded. We are expecting the work to commence
any day and will be completed this month. The Down Pipes will be installed after
completion of painting contract. Purchasing is now accepted quotes on the Heat
Recovery System. We expect the contract to be awarded in July or August for
installation prior to the start up of the ice making plant this fall. The
contract for installation of new overhead door has been awarded. We are
expecting installation to be completed in early July.
PROJECT DETAIL BUDGET
Orono Armories Soffits, Facia & Eaves $ 1,800.00
Specifications are being prepared to have this contract awarded this summer.
U1.
5C
PROJECT DETAIL BUDGET
Bowmanville Library Window Replacement $ 1,000.00
This job was completed this past spring.
PROJECT DETAIL BUDGET
Clarke Library Replace Eaves & Facia $ 1,800.00
Repair Main Root $ 1,500.00
Replace Flat Roof $ 1,200.00
Replace Furnace $ 4,000.00
The contract for the eaves, facia, roof repairs and replacement has been awarded.
The contractor is on site and is working on these jobs. The furnace contract has
been awarded and we are expecting installation in late July or August.