HomeMy WebLinkAboutCS-36-87TOWN OF NEWCASTLE
REPORT File #,' =0
Res. #
By -Law #
MEETING: GENERAL PURPOSE & ADMINISTRATION COMMITTEE
DATE: November 16, 1987
REPORT #:CS -36 -87 FILE #:
SMECT:
COMMUNITY SERVICES PROGRAM DIVISION UPDATE
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose &
Administration Committee recommend to Council the following: -
1. That report no. CS -36 -87 be received for information.
BACKGROUND & COMMENTS:
The Program Division of the Community Services Department has been very
active in Promotion, Community Development, and Program Administration
during this past Summer and early Fall. Highlights of various activities
of this division are noted in the various subsections as follows:
OUTDOOR POOLS
The two outdoor pools (Orono Park and Newcastle Lions) had an excellent
year involving both structured and unstructured programs. Good weather
conditions and front line staff have contributed to meet and in some
cases exceed both revenue and participant projections (see Schedule I and
II for detailed breakdown). Newcastle Lions Pool offered swimming
lessons in August for the first time in the past three years due to
requests for specific staff and demand for program at that pool. This in
turn, helped to exceed departmental program revenue projections.
../2
( / (A
GENERAL PURPOSE & ADMINISTRATION COMMITTEE
REPORT NO. CS -36 -87 PAGE 2.
NEWCASTLE FITNESS CENTRE
The Newcastle Fitness Centre is also having a successful year to date in
terms of participant numbers and revenues in program. Youth programs
continue to operate at capacity and currently additional program times
are being considered. Semi - private and private lessons also continue to
be popular despite substantial fee increases introduced September 1st.
Adult programs are the only classes which have not been filled every
session although even this trend seems to be changing this Fall.
Other revenue accounts at the Fitness Centre are in line with projection
figures at this time (see Schedule II) however, due to reduced daytime
programming because of staff shortages this may affect swimming
admissions and membership revenues.
AQUATIC STAFF
Availability of qualified staff to meet an increasing demand for pleasure
swimming and lessons became a problem this Fall when a large number of
staff left for college or university. There were also two daytime staff
that left for full time positions with the School Board which taxed an
already existing staff shortage. The high school staff shortage will be
somewhat alleviated by December when potential candidates will complete
some of the necessary leadership courses we are presently offering.
A daytime crash course has also been offered in conjunction with a
babysitting service operated by the YWCA, to encourage adults available
during the day to go through the leadership courses required. There are
presently ten candidates taking this course and it is anticipated some of
these individuals will be successful and able to work daytime hours by
January of 1988. Based on these numbers we anticipate operating our
regular daytime swims and School Board programs at that time.
../3
GENERAL PURPOSE & ADMINISTRATION COMMITTEE PAGE 3.
REPORT NO. CS -36 -87
The Aquatic Manager recently attended the A.A.P.P. (Association of Aquatic
Personnel in Ontario) Conference where the province-wide problem
ASSOC'
conducted shortage of aquatic staffing was discussed.
in This Ontario (see Schedule III)
conducted a study of aquatic profe ssionals n have also
to provide a document to deal with thissinu�ecruitingestaff. This
developed a VHS tape for Managers to us e
staffing issue will also be discussed at the upcoming term solutionseto this
After this review,
staff will be considering long
problem as well as items which may be considered for the 1988 budget.
SPECIAL EVENTS resently completed
The March Break Program and Participaction were successfully
working with the
and reported on earlier this year. Staff are p
special program of events to
Celebration 188 Committee in developing a
occur on December 21st, 1987 when the Olympic Torch arrives in
Bowmanville.
PROMOTION
The Fall and Winter Community Activity Guide went out information epackage
mid - August. As our community continues to grow this
a cating to the public what
of
is
plays an even more important role in communi
y
available to them. Local "welcome wagons "tuhasthis
also been approached by
e to newcomers. Department
their package Our this Guide accessible to
local real estate agencies to consider making
their prospective customers.
The Department has also been working
on a marketing
strategy to promote
not only facilities and programs but also to give staff and the
some
Department a higher profile in the Community.
consideration in the capital budget for this type of promotion.
../4
GENERAL pURPOSE& ADMINISTRATION COMMITTE
PAGE 4.
REPORT NO. CS 3 6
COMMUNITY GROUPS or not at all during the Summer,
Although most groups meet infrequently
communicated with a number of groups this Fall he NCSAB onlow: as noted
staff have co set up in cooperation with t
1) A fundraising workshop
October 7th. Approximately 60 organizations took advantage of
this training opportunity.
staff met with Courtice park and the Oshawa Cente�lt council
2) St in September Neighborhood Association (O.C.C.N.A•)
the status of Courtice Park and their "integration" ietW e st ff
based programs. Courtice Park Board is to communicate
transition.
1 when they are ready to proceed with this gradual
and Hall
3) staff met with the Hampton Recreation
including the
Board in October to discuss a number of issues
future of the Hampton Hall. ring for the
4) various grant enquiries and brochure submissieen handled by staff.
& Summer Community Activity Guide have also
STAFF DEVELOPMENT AND 'TRAINING o ort-
Adman
istration staff have been involved in a numbere f training
asnoted below:
unities this year to remain updated on current issu
(ORS) Conference
- Ontario Recreation Society ( Computers 1) Feb — r --uarY attended sessions on: Comp
program Director (Coordinator) e Risk Managem
in Recreation, Management ent
in a Context of Chang
Design.
& Legal Liability, playground artment & NCSAB)
Grants workshop (sponsored by Dep
2) May - attended to
Acting Director & Program Director (Coordinator) MCC and New Horizons.
review present grants available for M ,
../5
GENERAL PURPOSE & ADMINISTRATION COMMITTEE PAGE 5.
REPORT NO. CS -36 -87
3) June - Aquatic Staff Pre - Summer Training first aid and CPR.
Aquatic staff updated qualifications including Department & NCSAB)
October Fundraising Workshop (sponsored by
�) -- Director (Coordinator) attended.
Acting Director and program
Oct- obey - p,APO Conference
5) eting, Creative
Aquatic Manager attended sessions on: Budg promotional Tools
Resource Development (professional begging)►
and Risk Management.
- Risk Management Seminar
6) October Director (Coordinator)
parks & Cemetery
Manager and program
attended one day seminar on risk management.
November - Advanced Instructor Clinic
7) required to train RLSSC
Aquatic Manager attended session as req
Swimming Instructor.
g) Nov_ e_ mbar - SDMRO Conference sessions on:
program Director (Coordinator) will Leadership,
1 Attitudes & work
Humor in the workplace, ce Affecti eness Training.
Habits of Youth, Sery
Recommended for presentation
Respectfully submitted, to the Committee
ECG' Rotseff
wrence
Caruana, Acting Director Chief Ad i istrative Officer
Josep Services
Depment of Community
JC:sa
SCHEDULE I
AQUATIC PROGRAMS
REGISTRATION NUMBERS
Winter (NFC)
Youth
399
Adults
106
Privates
16
Semi - Private
56
TOTAL 577
Spring (NFC)
Youth
573
Adults
117
Privates
37
Semi - Private
152
TOTAL 879
Summer (July & August)
NFC 610
Newcastle Lions Pool 64
Orono Park Pool 66
TOTAL 740
Fall (NFC)
Youth 647
Adult 127
Privates 21
Semi- Privates 96
TOTAL 891
Winter (NFC) 1988
Youth 46
Adult 107
Privates not set
Semi- Private not set
TOTAL 153
OF
.�
SCHEDULE II
-PROGRAM REVENUES
AS AT NOVEMBER 1, 1987
ACTUAL BUDGET
Newcastle Lions Pool
1,598.50 1,000
Swim Lesson Program 4,0 3,000
Admissions & Memberships
5,602.50 4,000
Orono Park Pool
1,670 2,000
Swim Lesson Program 4,519 4,300
Admissions & Memberships
6,189 6,300
Newcastle Fitness Centre
75,823.30
78,000
youth Lesson Program
11,132.75
15,000
Adult Lesson Program
114.98
200
Department Issue
19,409.48
27,000
Memberships
29,319.00
37,000
Swimming Admissions
10,368.50
14,000
Squash Admissions
349.26
600
Miscellaneous
10,838.00
111000
Rentals
157,355.27
182,800
Special Programs
1,602.50
1,500
March Break
SCHEDULE III
0. SIP)
i • ► nlli lummIll
Association of Aquatic Pefsonnel of Ontafio
Q_
SCHEDULE III
* * * MESSAGE. FROM TILE EXECUTIVE
Dear AAPo member:
This year, my role as AAPO Vice President involved the task of completing a full -time
salary survey. After listening to comments and concerns of delegates at our 1986 Fall
Conference, we decided to include a needs assessment to determine how well AAPO was serving
to renew etheir membergships, picture of our
conduct deficiencies, and why
included some fail
members as
to
well as current members.
The size of this task grew larger and more complex, so the AAPO executive decided to
of Lakehead University, act as Research
contract the service of Rick Rollins, PhD.,
Director to supervise the project. The AAPO executive worked closely wit h Rick throughout
t
the study, helping to develop the questionnaire, as well as reviewing a draft of the final and
especially Overall, the
3i executive
rate to they mailasurveysby our members. Thankhyoutvery� much
espe Y
for your participation.
I would like to briefly mention a few highlights of the study. First, the report
indicates that the Association is meeting the needs of its members. Second, the report
indicates that we should investigate how the Association can assist its members in their
professional development, especially with regard to career planning and dealing with
supervisory staff. Third, the Association needs to focu s some hourshworked c raise
by aquatics
profile of aquatics in the municipal setting. Finally, large proportion of our members
personnel (including volunteer work) is extremely high.
are not satisfied with their compensation.
In summary, this research project . has mmediately clear
following direction
1987t Fall Conference,
in its tasks for the upcoming y
information from the detailed final report will be used in the objective planning session
for the next year, discussed in Aqualine, reflected in workshops and conference sessions,
and directly addressed by the executive. In the years to come, this survey will likely be
repeated to provide guidance for future AAPO executives.
fi d
The end result of this process will be a more effective Association, a more satis e
membership, and an increase in membership.
Thank you again for your participation.
I- • - = a —1
Sincerely yours,
ROY WARREN
Vice President, AAPO
WHY DID WE DO THIS STUDY?
The purpose of this study was to survey aquatics professionals in Ontario in order to
fulfill the following objectives:
1. To measure the factors affecting job satisfaction. To what extent are aquatics
professionals in Ontario satisfied with their work; and, more specifically, what
aspects of their work do they find particularly satisfying or unsatisfying?
theirseffortsntof improve cthe working environments of aquaticstprofessionals. in
2. To measure opinions on how AAPO can best serve the aquatics field in Ontario
(i.e. a needs assessment).
3. To describe a profile of aquatics professionals in Ontario. This includes a ile
descrition of allowsp members tosp compare stheir working g� situations f and salary. This
with others throughout the
province.
SCHEDULE III
Page 2
HOW DID WE DO THIS STUDY?
The scope of this project was determined by the AAPO executive, particularly in
deciding the types of issues to be addressed and the groups of people who would be included
in the survey population.
Questionnaire items were developed by reviewing the literature on job satisfaction,
and through personal interviews with a small sample of AAPO members and the AAPO executive.
The questionnaire was further refined with reviews by the AAPO executive, and by another
small sample of AAPO members. Although the length of the questionnaire was considerable,
the issues were of such importance that no attempt was made to shorten the questionnaire.
To collect this information, a questionnaire was developed and sent in
the mail to 151 current AAPO members, and to 142 recent AAPO members.
After two additional reminder mailings to non — respondents, a total of
83% of the questionnaires were returned from current members and 50%
from recent members.
In this report, we have described highlights of the response we
received from AAPO members. A more detailed report including the
responses of previous AAPO members, can be obtained by contacting Roy
Warren.
RESULTS: JOB SATISFACTION
AAPO members reported high levels of satisfaction with their job, with only a few
people (8 %) expressing negative overall feelings about their job. However, a number of
concerns were expressed, as follows:
TABLE 1: CONCERNS WITH THE JOB
1. Amount of feedback received from supervisors.
2. Hours of work, particularly shift work.
3. Salaries, particularly when compared to education, training and experience.
4. Opportunities for promotion.
5. Extent of involvement in budget planning and implementation.
6. Size of aquatics budgets.
7. Clients (public) may not be learning enough, or appreciating the program
schedule.
8. Extent to which the facility is marketed.
9. Working relationships with competitive organizations (such as the Water Polo
Association, and the Canadian Amateur Diving Association) are weaker than with
non — competitive aquatics organizations.
AAPO members seemed to be particularly concerned with hours of work, and their
salaries. Table 2 explores the relationship between work satisfaction and lieu time
received. This table indicates that people who are satisfied with the amount of lieu time
they receive tend to be satisfied with hours worked per week and the amount of overtime
work they do. Clearly, lieu time partially compensates for the number of hours worked per
week.
TABLE 2: COMPARISON OF "SATISFACTION WITH LIEU
TIME RECEIVED" WITH OTHER FACTORS
Item Compared With "Satisfaction Nature of Relationship
With Lieu Time Received" (Yes /No)
Satisfaction With Hours Worked Per Week
Yes
Satisfaction With Amount of Overtime Work Yes
No response from 5 people.
TABLE 3:
COMPARISON OF SALARIES WITH BUDGETS
Under $20,000-
MARY RECEIVED 45,000 -
$25,000- $30,000- $35,000- $40,000- $
45 000 $50 000 $50
Over
000
BUDGET 20
000 $25 000
30 000 35 000 $40 000
Under -
25 L4
2 0 1
12 6
0
$20,000
0
0
$20,000 -
5 5
5 2 1 0
$40,000
0
0
$40,000 -
L 3
1 3 2 p
$60,000
0
0
$60,000 -
2 0
L 1 4 1
$80,000
i
0
$80,000 -
1 0
p 1 0 2
$100,000
0
L
$100 +000-
0 3
L 3 0 0
$200,000
p
0
$200,000-
2 0
0 0
1 1
$400,000
O
1 0
p i L 0 0
Over
$400,000
No response from 9 people.
COMPARISON OF SALARIES WITH SIZE OF .COMMUNITY
TABLE 4;
SALARY RECEIVED
Under $20,000- $25,000- $30'x- $35'x- $45'000 $50 000
Over
$50,000
SIZE OF
CommITY
$20,000 25 000
$30,000 35 000 $40, 000
7 4
2 4 0 0 0
2
Under
10,000
1
0
10,000 -
17 10
0
4 2 0
50,000
0
0
50,000 -
6 5
4 2 2 0
100,000
0
0
100,000-
2 3
4 5 4 p
200,000
0
0
200,000-
1 2
1 0 1 1
300,000
1
0
300,000-
3 5
5 2 2 1
500,000
0
0
��.
4 1
2 3 0 l
Over
400,000
No response from 5 people.
SCHEDULE III
RESULTS: JOB SATISFACTION (Continued) Page 4
TABLE 5: COMPARISON OF SALARIES WITH NUMBER OF FACILITIES SUPERVISED
SALARY RECEIVED
NOHBER OF Under $20,000— $25,000— $30,000— $35,000— $40,000— $45,000 — Over
FACILITIES $20,000 $25,000 $30,000 $35,000 $40,000 $45,000 $50,000 $50,000
0 4 1 2 0 1 0 1 0
1 31 22 17 8 1 2 0 1
2 1 0 3 7 4 0 0 0
3 2 1 0 0 2 0 0 0
4 0 0 0 2 2 0 0 0
5 12 0 0 0 0 1 1 0
8 1 1 0 1 0 0 0 0
o response trom
TABLE 6: COMPARISON OF SALARIES WITH NUMBER OF PEOPLE SUPERVISED
SALARY RECEIVED
PEOPLE Under $20,000— $25,000— $30,000— $35,000 - $40,000— $45,000 — Over
SUPERVISED $20,000 $25,000 $30,000 $35,000 $40,000 $45,000 $50,000 $50,000
0 -5 22 9 5 7 1 0 1 0
6— 10 8 7 6 3 0 0 0 0
11 — 15 1 4 7 4 3 2 0 0
16 -20 1 3 1 1 0 0 0 0
21 — 30 1 0 1 3 4 0 0 0
31 — 40 0 0 0 1 0 0 0 0
41 -50 0 0 0 3 0 1 1 0
Over 50 6 2 1 2 2
0 0 4
Table 7 compares the relationship between "satisfaction with salary received" and a
number of other factors. This table indicates that salary satisfaction is not influenced
by the amount of income received or the amount of training people possess. Rather, salary
satisfaction is influenced by the other factors shown on the table, namely: satisfaction
with hours worked per week, satisfaction with amount of overtime worked, number of
responsibilities held, and sum of benefits received.
TABLE 7: SATISFACTION WITH SALARY COMPARED WITH OTHER FACTORS
Item Compared With Nature of Relationship
Salary Satisfaction (Yes /No)
Satisfaction With Hours Worked Per Week Yes
Satisfaction With Amount of Overtime Work Yes
Income Received No
Sum of Responsibilities Yes
Sum of Benefits Received Yes
Amount of Training No
SCHEDULE III
Page 5
Table 8 compares education with income peoople receive, and with job satisfaction.
Although people holding a degree appear to have higher income, this difference is not large
enough to be significantly different.
TABLE 8: COMPARISON OF EDUCATION WITH INCOME AND JOB SATISFACTION
Average Average
Education Income Satisfaction
No University Degree $ 22,689.00 4.67
University Degree 28,404.93 4.93
1. Average income not significantly different.
2. Average job satisfaction (or a scale of 1 -7) not significantly different.
RESULTS: NEEDS ASSESSMENT
The overall assessment of the work of AAPO, by AAPO members was very positive (5.5 on
a satisfaction scale ranging from 1 to 7). The current direction and activities of AAPO
received a strong endorsement, with just two exceptions. First, AAPO members indicated a
clear preference for a broad selection of topics at the Annual Conference, rather than an
intensive institute. Second, not much attention was attached to the suggestion of
providing workshops in effective writing techniques. The items that received the highest
ratings in the needs assessment portion of the questionnaire are listed in rank order in
Table 9.
TABLE 9: ITEMS RATED HIGHEST IN THE NEEDS ASSESSMENT
1. Discussion of trends, methods and techniques in aquatics and recreation.
2. To have a provincial organization that contributes to the development of aquatics
in Ontario.
3. To sustain an atmosphere that encourages positive change in aquatics and
recreation.
4. To effect positive change in health regulations.
5. To raise the public profile of aquatics issues.
6. To address the issues of staff shortages.
7. To raise the perception (i.e. importance) of aquatics in municipal government.
RESULTS: PROFILE OF AAPO MEMBERS
Tables 10 through 14 highlight characteristics of the working
environment of AAPO members. With regard to hours worked
(Table 10), it should be recalled that AAPO members indicated
w elsewhere their concern for the number of hours worked. With
regard to benefits received (Table 11), it should be recalled
that a relationship exists between the number of benefits
received and salary satisfaction, salary received and size of
community. Likewise, with regard to responsibilities (Table
12), a relationship exists between the number of
responsibilities and salary satisfaction, salary received,
and size of community.
TABLE 10: PROFILE OF HOURS WORKED
1.
Average hours
worked per week
= 39.9 hours
2.
Average hours
of nonpaid extra work per week
= 9.3 hours
3.
Average hours
of volunteer work per week
= 5.6 hours
4.
Proportion who
worked shift work this year
= 50.0%
5.
Proportion who
worked split shift this year
= 53.2%
6.
Proportion who
had a lieu time alternative
= 80.2%
7.
Proportion who
were limited to a maximum lieu time
= 34.1%
8.
Proportion who
could receive cash for overtime
= 24.6 %.
SCHEDULE III _
Page 6
TABLE 11: PROFILE OF BENEFITS RECEIVED
1. OHIP: 83.37
2. Extended Health Care: 78.2%
3. Dental Plan: 83.1%
4. Eye Glasses: 62.1%
5. Life Insurance: 84.77
6. Canada Pension Plan: 84.7% RRSP: 47.6%
7. Contributions by Employee
8. Uniforms: 29.8%
9. Parking: 54.8%
10. Credit Union: 28.2%
11. Canada Savings Bonds: 55.6%
12. Personal Facility Membership: 43.5%
13. Family Facility Memberships: 16.1%
14. Mileage or Other Reimbursement When Using our Car at Work: 81.5%
15. Time Off to Attend Workshops, Conferences,_ etc.: 94.4%
16. Subsidies to Cover the Cost for Attending Workshops, Conferences, etc.: 79.0%
17. Time Off in Lieu of Subsidies to Cover the Cost of Attending Workshops,
Conferences, etc.: 26.6%
nding Workshops, Conferences, etc: 90.3 %.
18. Regular Salary While Atte
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
TABLE 12: PROFILE OF RESPONSIBILITIES
TABLE 13: PROFILE OF SUPERVISORY RESPONSIBILITIES
1. Average Number of Full -Time People Supervised = 6.2
2. Average Number of Part -Time People Supervised = 13.0
3. Average Number of Full-Time/Part-Time People Supervised = 10.1
4. Average Budget Size = $125,754.00
5. Average Number of Facilities Supervised = 1.8
Page 7
RESULTS: SERVICES PREFERRED BY AAPO MEMBERS
73.7% of AAPO members rosin ted hof
With regard to the annual AAPO
conference, eprefer to maintain the present
planned to attend, and 72.1% said they
October. , rociobe loos] • .1
1�
yMt Sri 'ie. LL'I�1.Mt it z�l�tis seir l
4 15
e �o .ro� xol. '.exe vl o;.�x �o.saie�o evo
xx�xex'xs x0'xe xOx xn01x''. xe 70 t e,.o xOx xx xe nx0'x'xs xe,pxe
xe xolsos x vnev xe xvbo! xo w��
ted they intend to renew their membership.
92.9% indicated With regard to AAPO membership, Y
the no longer retained their AAPO
Former AAPO members indicated the following reasons why
membership:
1. No longer in aquatics.
2. Money not available.
3. Time not available.
4. Disappointed with AAPO.
Preferences for AAPO services are summarized in Table 17.
TABLE 17: PREFERENCES FOR AAPO SERVICES
1. Annual Conference: 77.8%
2. "Aqualine" Newsletter: 81.0%
3. Representation With Parks and Recreation Federation of Ontario: 56.3%
4. "Issues Update ": 73'O Surveys: 64.3%
5. Publication of Salary Y
6. Regional Workshops: 65.1%
7. Publication of Technical Article in Aquatics and Recreation: 63.5
8. Access to "Federation Job Mart 63.5%
SCHEDULE 1I1
Page 8 °
The Association of Aquatic Personnel of Ontario would
i
like to gratefully acknowledge the Ministry of Tourism
and Recreation, and the contributions of the Wintario
Development Program, for their support of this project.