HomeMy WebLinkAboutPSD-097-11 Clarftwn REPORT
PLANNING SERVICES DEPARTMENT
Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date: December 12, 2011 Resolution #:6PA-4,96 1) By-law #:
Report#: PSD-097-11 File #: PLN 33.4
Subject: APPLICATION FOR EXPROPRIATION OF LANDS NECESSARY FOR
THE RECONSTRUCTION OF A PORTION OF ELLIOTT ROAD
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Council authorize an application to be made to the Council of the
Corporation of the Municipality of Clarington, as the approving authority under
subsection 4(1) of the Expropriations Act, for approval of the expropriation of the
following interests in land that are required to facilitate necessary upgrades to
Elliott Road:
(a) a temporary easement or right in the nature of a temporary easement
expiring on December 31, 2014 in, under, over, along and upon the land
shown as Parts 1 and 2 on Attachment 1 to Report PSD-097-11 for the
purpose of entering upon and occupying the land with all necessary
machinery, equipment and material required for, or in connection with, the
reconstruction of Elliott Road and for the purpose of installing temporary silt
fencing and permanent fencing;
(b) a permanent easement or rights in the nature of a permanent easement in,
under, over, along and upon the land shown as Part 3 on Attachment 1 to
Report PSD-097-11 for the purpose of entering upon and occupying the
land with all necessary machinery, equipment and material required for, or
in connection with, the construction, maintenance, alteration, inspection,
repair and operation of stream crossings and erosion protection works;
(c) a permanent easement or right in the nature of a permanent easement in,
under, over, along and upon the land shown as Part 4 on Attachment 1 to
Report PSD-097-11 for the purpose of entering upon and occupying the
land with all necessary machinery, equipment and material required for, or
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L1 C 3A6 T (905)623-3379 F (905)623-0830
REPORT PSD-097-11 PAGE 2
in connection with, the construction, maintenance, alteration, inspection and
repair of a stream crossing; and
2. THAT the Municipal Clerk be authorized to serve and publish a Notice of
Application for Approval to Expropriate Land as required by the Expropriations
Act;
3. THAT the Municipal Clerk be authorized to forward to the Chief Inquiry Officer
any requests for a hearing of necessity that are received;
4. THAT staff be directed to represent the Municipality at any hearing of necessity;
5. THAT Council, as the approving authority under the Expropriations Act, approve
the expropriation of the interests in land described in Recommendation 1
provided there is no hearing of necessity, and
6. THAT, if approval to expropriate is given, the Municipal Clerk and Mayor be
authorized to take such steps as are necessary to vest in the Municipality the
interests in land described in Recommendation 1 and obtain possession.
Submitted by: Reviewed by:
Da J.. Crome, MCIP, RPP Franklin Wu
Director, Planning Services Chief Administrative Officer
JAS/FL/df/av/ah
6 December 2011
REPORT NO.: PSD-097-11 PAGE 3
1. BACKGROUND
1.1 During the Environmental Assessment (EA) process for the Port Granby Project, a
number of alternative routes were evaluated to determine the primary haul route for
trucks carrying construction materials and equipment to the Project sites. This will be
the route along which virtually all of the material and equipment required for the Port
Granby Project, including the construction of the new long term waste management
facility, the water treatment plant, and the Lakeshore Road underpass, will be
transported.
1.2 The primary haul route selected through the EA consists of Newtonville Road from
Highway 401 to Concession Road 1, Concession Road 1 to Elliott Road, and Elliott
Road to the entrance of the new long-term waste management facility south of the CN
rail corridor (see Attachment 2). A key reason for the selection of this route was that it
minimized the number of residences that would be affected by Project-related traffic, in
particular the small community of Port Granby. Council concurred with the selection of
the primary haul route in June 2006 with its endorsement of the Preferred Option for the
Port Granby Project, and again in October 2009 when it concurred with the findings of
the Screening Report for the Project.
1.3 On November 30, 2011, the Canadian Nuclear Safety Commission approved the
issuance of a Waste Nuclear Substance Licence to Atomic Energy of Canada Limited to
permit the Port Granby Project to proceed.
1.4 The Port Hope Area Initiative Management Office (PHAI MO) will be upgrading all of the
roads along the primary haul route in order to make them suitable to accommodate the
truck traffic for the Project. Elliott Road is currently a seasonally maintained road in
very poor condition. As such, the section between Concession Road 1 and the
entrance to the new waste management site will require complete reconstruction.
1.5 The upgrades to Elliott Road will require limited access and encroachment onto the
lands immediately east of the road allowance. The required encroachments, as
described below, are shown in more detail in Attachment 1:
• a 10 metre wide temporary working easement along the east side of Elliott Road
between Concession Road 1 and the CN rail corridor (approximately 1,000 m) to
permit the manoeuvring of road construction equipment, and to permit temporary
silt fencing to protect certain watercourses (Part 1 on Attachment 1); and
• a 20 m wide temporary working easement along the east side of Elliott Road
between the CN and CP Rail corridors (approximately 140 m) to permit the
manoeuvring of road construction equipment and to permit temporary silt fencing
to protect certain watercourses (Part 2 on Attachment 1); and
• a 2.5 metre permanent easement along the east side of Elliott Road between
Concession Road 1 and the CP Rail corridor (approximately 1,000 m) to permit the
construction and maintenance of stream crossings, roadside ditch work and/or the
REPORT PSD-097-11 PAGE 4
placement of fill (Part 3 on Attachment 1); and
s a 10.5 metre wide by 138 metres long permanent encroachment onto the land
between the CN and CP rail corridors to permit the construction and maintenance
of a stream crossing upgrade and a 2:1 slope on the east side of the approach to
the level crossing at the CN tracks (Part 4 on Attachment 1).
1.6 Full legal descriptions will be substituted for Recommendation 1 and Attachment 1 as
soon as reference plans have been completed.
2. DISCUSSION
2.1 The schedule for the Port Granby Project requires Elliott Road and the other roads on
the primary haul route to be completed in 2012 in order for the construction of the other
elements of the Project to begin. Work on Elliott Road cannot start until the half-load
restriction for 2012 is lifted, which generally occurs in mid-to-late April. Construction is
expected to continue until November.
2.2 In order to ensure the Project is not delayed, it is necessary to initiate the expropriation
process.
2.3 If expropriation proceedings are initiated, they can be abandoned should the parties
reach a negotiated settlement or if other options are developed that can eliminate the
need for an expropriation.
3. EXPROPRIATION PROCESS
3.1 Municipal expropriation of land generally proceeds as follows:
• Municipal Council provides authority to expropriate the land.
• The Municipality serves a Notice of Application for Approval to Expropriate on the
landowner and publicizes that Notice in a local newspaper.
• The landowner has 30 days to request a hearing of necessity. If a hearing is
requested, the Municipality notifies the Chief Inquiry Officer who arranges a hearing
to determine whether the "taking of the lands ... is fair, sound and reasonably
necessary in the achievement of the objectives of the expropriating authority". At the
conclusion of the hearing, the Chief Inquiry Officer submits a report to Council.
• Council, after considering the report, approves (with or without modifications) or
does not approve the expropriation with written reasons and arranges for service of
its decision on all parties within 90 days.
• Where Council approves the expropriation, the Municipality must register the
expropriation plan and Council's certificate on title to the lands within three months.
REPORT PSD-097-11 PAGE 5
• The Municipality services the Notice of Expropriation on the landowner within 30
days of registration of the expropriation plan.
• The landowner then has 30 days to elect the date on which the compensation
should be assessed (being one of the following - the date notice of hearing was
served, the date of registration, or the date of service of Notice of Expropriation).
• The Municipality serves a compensation offer along with its appraisal report (the
"Section 25 offer") on the landowner within 90 days of registration and before taking
possession of the lands;
• The Municipality serves the Notice of Possession on the landowner a minimum of
three months prior to taking possession.
• If compensation is not agreed, compensation can be determined by:
(a) Board of Negotiation; and/or
(b) Ontario Municipal Board arbitration (which usually involves a procedural order
outlining requirements for discoveries, motions, exchange of documents,
witness statements and experts reports and full hearing).
4. CONCURRENCE
4.1 This Report has been reviewed by the Municipal Solicitor who concurs with the
recommendations.
5. CONCLUSION
5.1 Staff are recommending that Council authorize the initiation of expropriation
proceedings to acquire the necessary interests in the lands to permit the reconstruction
of Elliott Road. This action is necessary in order to ensure that the construction of the
Port Granby Project can proceed as scheduled, and is consistent with the 2001 Legal
Agreement which commits Canada and the Municipality to cooperate and take
appropriate action necessary to expedite the completion of the Project.
CONFORMITY WITH STRATEGIC PLAN
The recommendations contained in this report conform to the general intent of the following
priorities of the Strategic Plan:
Promoting economic development
Maintaining financial stability
Connecting Clarington
Promoting green initiatives
X Investing in infrastructure
Showcasing our community
Not in conformity with Strategic Plan
Staff Contact: Janice Szwarz
REPORT PSD-097-11 PAGE 6
Attachments:
Attachment 1: Lands Affected By Expropriation
Attachment 2: Map Showing Primary Haul Route
Interested parties to be advised of Council's decision:
Garfield Payne
Christine Fahey
Attachment 1
To Report PSD-097-11
Concession Rd 1
I
I PART 1
10m Temporary Easement
I
1
I
PART 3
I 2.5m Permanent Easement
I
I PART 2
20m Temporary Easement
I
1
I PART 4
I 10.5m Permanent Easement
1
I
CP
a
O
0
w I
I
I
CN
N
ELLIOTT ROAD EASEMENTS
ceAatng nee wAy Port Granby Project
Attachment 2
To Report PSD-097-11
./
7::�
ns
J ue
n '
'
RaA Hig ay 401 Highway 401
fW
QL it
2LL"-,
Lake Ontario
ClabgWa PRIMARY HAUL ROUTE
Leading the Way Port Granby Project