HomeMy WebLinkAboutWD-32-85 (a)
[File No � .2-101 vaP.,aP as„. wa
CORPORATION F THE TOWN OF NEWCASTLE
PUBLIC WORKS DEPARTMENT R. DUPUIS, P. ENG., DIRECTOR
HAMPTON,ONTARIO TEL.(416)263-2231
LOB 1JO 987.5039
REPORT TO THE GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
MEETING OF MAY 21 , 1985.
REPORT NO. : WD-32-85
SUBJECT: INVOICES RELATING TO THE RECONSTRUCTION
PROJECT FOR THE KING STREET CONNECTING
LINK IN NEWCASTLE VILLAGE.
RECOMMENDATION:
It is respectfully recommended:
1. That this report be received; and,
2. That an invoice to the Newcastle B.I .A. in the amount
of $2,010.43, be forgiven and charged to Account No.
1170-X-1-9, General Accounts Receivable - allowance
for bad debts.
3. That an invoice to the Newcastle Hydro Electric
Commission in the amount of $2,151.70 be forgiven and
charged to Account No. 1170-X-1-9, General Accounts
Receivable - allowance for bad debts.
4. That both of these groups be so advised.
. . . .2
n
UT - 6060
Page 2
REPORT NO. WD-32-85
REPORT:
Reconstruction of the Newcastle Village Connecting Link was ,
for the most part, completed in 1983 with most of the
invoices relating to the project being processed during that
year. However, there were some charges carried over into
the early part of 1984 and further, due to an M.T.C. audit
of both engineering and payment quantities, final payment
was delayed until almost the end of 1984. This has resulted
in a couple of problems.
Firstly, when final payments were processed, the contractor
indicated that he had entitlement to interest on the funds
which had been held back from him for an excessive period of
time. Such interest charges amount to some $400.00 and
there is presently discussion with M.T.C. and their auditors
over who should pay same. It is our position that the delay
was caused by M.T.C. audit.
With respect to the Newcastle B.I .A. , the charges relate to
matters other than the delay in final billing. On the
spring road tour, details were discussed. As pointed out at
that time, the original tenders for the Connecting Link
project included an item for supply and installation of
decorative lights at the expense of the B.I .A. However, the
bid prices for such lights exceeded funds available to the
B.I.A. and the item was deleted from the contract. The
street lights were then tendered for separately and were
secured at a lower price which could be afforded by the
B.I.A. Unfortunately, the tendered price did not include
installation, but the contractor did perform this work.
However, this was work over and above that in the accepted
project tender and was billed as an extra.
. . . .2
ul
Ca)
Page 3
REPORT NO. WD-32-85
In the final payment documents this oversight was discovered
and an invoice was forwarded to the B.I .A. That group did
not expect such charges and does not have funds available to
pay the installation costs of about $2,000.00. As the
street lights are not subsidizable by M.T.C. charges cannot
be placed with them and it is recommended that they be
forgiven per this report' s recommendation.
Finally, the Newcastle Hydro Electric Commission did
participate in the project for relocation and upgrading of
the main street light system and paid for fifty percent
(50%) of the relocation and one hundred percent (100%) of
the upgrading costs through its budget. All invoices to
that body were processed and paid through the regular
payment certificates, however, again, the pro-rating of the
final holdback placed the Newcastle Hydro Electric
Commission in the position of receiving a late invoice for a
nominal amount. The Commission does not have funds budgeted
for this cost and since the delay was outside their control ,
i .e. , the amount of time required by M.T.C. audit, the
charges should be covered in the manner recommended in this
report.
In a project with the magnitude and cost of the Newcastle
Village Connecting Link it is inevitable that certain
oversights and delays will occur, especially when final
approval is by an outside agency like M.T.C.
. . . .4
Page 4
REPORT NO. WD-32-85
It is, therefore, proposed that the payments be handled as
recommended, as the easiest method of dealing with them.
These adjustments will finalize the bills relating to the
Connecting Link project.
Respectfully submitted,
R.G. Dupuis, P. Eng. ,
Director of Public Works.
RGD:jco
May 13, 1985.