HomeMy WebLinkAboutWD-40-87 TOWN OF NEWCASTLE
J
i REPORT Fi le
Res S.
By-Law #
MEETING: THE GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
DATE: June 1 , 1987
REPORT #: WD-40-87 FILE #:
SLBJECT: VARCOE ROAD CONSTRUCTION
RECOMMENDATIONS:
It is respectfully recommended:
i
1. That Report WD-40-87 be received; and,
2. That the urbanization of the west side of Varcoe Road be completed in
conjunction with the Town ' s 1987 Nash Road reconstruction project.
3. That the cost of the urbanization be funded from Public Works Lot
Levies.
. . .2
3 Qb)
Page 2
Report No. WD-40-87
REPORT:
As part of the Schleiss and Holland development, Varcoe Road north of Nash
has been reconstructed complete with storm sewers and with curb and gutter,
sidewalk and streetlighting on -the east side of the road all at the expense
of the developer.
To complete the urbanization of the west side of Varcoe Road, curb and
gutter and boulevard restoration is required. The estimated cost of the
works required is $70,000.00.
The option is to restore the boulevard and leave the west side of Varcoe
Road with a rural cross section similiar to the situation that used to be on
Martin Road north of Baseline Road and on West Townline Road north of Bloor
Street.
It is hereby recommended that the urbanization of the west side of Varcoe
Road be completed in conjunction with the Town' s 1987 Nash Road
reconstruction project (ie:Nash Road east of Varcoe Road to the Sid Warden
Public School ) which is scheduled to take place in July 1987, and that lot
levies be used to cover the cost of said works.
Respectfully submitted, Recommended for presentation
to the Committee,
Gordon J. Ough, P. Eng. , Lawrence . Kotseff,
Director of Public Works Chief Administrative Officer.
GJO:lly
THE CORPORATION OF THE TOWN OF NEWCASTLE Lit
REQUEST FOR CAPITAL PROJECT APPROVAL
PROJECT DESCRIPTION AND LOCATION
Urbanization of the west side of Varcoe Road, north of Nash Road,
Public. Work-, duly 6, 1987 August 14, 1987
ORIGINATING DEPARTMENT ESTIMATED STARTING DATE ESTIMATED COMPLETION DATE
DEPARTMENT HEAD REPORT
See WD-40-87
APPROVED BUDGET ESIMATE $ _ PRESENT ESTIMATE $ 70.000,0 _
DEPARTMENT APPROVAL
May 22, 1987
,--,"Signafure Date
TREASURER'S REPORT
I hereby certify that the financing source proposed in Report WD40-87 is valid
and that funds will be made available from the Public Works Lot Levy Reserve
Fund subject to Council's approval of this project. Balance in the Public Works
Lot Levy Reserve Account at May 27, 1987 is $663,357. The 1987 budget has
allocated approximately $90,000 to approved capital projects.
! ),y) ' E May 27, 1987
Treasurer's Approval Date