HomeMy WebLinkAboutEngineering Memo 79-76MEMORANDUM #79
TO: Bruce Tink, Chairman of the Public Works Committee
FROM: John Ferguson, C.E.T., Engineering Department
TOPIC: Subdivisions - Time Limits
DATE: October 28, 1976
The Town of Bowmanville entered into many subdivision
agreements between the Town and the developers in 1972
and 1973. Under the terms of all of the agreements, a
time limit was stipulated for work to be completed.
In many of these agreements, the work has been completed
and the subdivisions have fulfilled the terms of their
own contracts.
In other agreements, these terms have not been complied
with, and under the terms of the subdivision agreement,
this constitutes a breach of contract. There are many
reasons why the work has not been completed but all of
the developers have full intentions of completing the
required work.
Therefore, I would recommend that extensions be given
to several of the agreements as detailed on the
attached chart. The subdivisions which require
extensions to the time limit are as follows:
Lamers Bros., 696 18 months
Waverley Gardens, Phase II, 702 18 months
Bowmanville Heights, Phase II, 705 36 months
Bowmanville Heights, Phase I11, 707 36 months
Cean Investments, 708 36 months