HomeMy WebLinkAboutADMIN 38-83 (2) (not a duplicate)CORPORATION OF THE TOWN OF NEWCASTLE
OFFICE OF THE TOWN CLERK
40 TEMPERANCE STREET TELEPHONE 623-3379
BOWMANVILLE, ONTARIO
Ll C 3A6
REPORT TO THE COUNCIL MEETING OF JUNE 13, 1983.
ADMIN- 38-83
SUBJECT: HAMPTON WASHROOM TENDER
RECOMMENDATIONS:
1. That this report be received; and
2. That Council award Tender T83-9, Washroom Renovations,
Hampton Hall, to Gerr Construction Ltd., in the amount of
$59,315.00, being the lowest responsible bid; and
3. That the total estimated project cost of $73,315.00 be
financed from the 1983 budget in the amount of $30,000.00;
from the Parkland Reserve Account in the amount of
$18,050, and from the Administrative Improvement Reserve
Account in the amount of $25,265.00; and
4. That the Town proceed to submit an application for
Capital Grants for the Hampton Hall Project.
BACKGROUND AND COMMENT:
As members of Council will recall, Report Admin 31-83 Re: Washrooms Hampton
Hall (Tender) was considered at the Council Meeting of May 24, 1983, and the
recommendations not approved. Report Admin 31-83 was referred to a Special
Meeting of Council on May 30, 1983 for reconsideration, but the motion to
reconsider was not approved.
At the General Purpose and Administration Committee Meeting of June 6th,
1983, the matter of the Hampton Hall Washroom Tender was referred to the
C.A.O. and Councillors Taylor and Cowman, for a further report to Council.
Continued ..... /2
Admin 38-83 - 2 - June 13, 1983
During the discussions on Report Admin 31-83, questions were raised by members
of Council as to the eligibility of the "Hampton Project" for Wintario and
Community Centres Grants. Members of Council will recall that the Ministry of
Tourism and Recreation has not announced criteria for gramtsin 1983-84, and
that the Town has requested that both the Hampton and Haydon projects be
rendered eligible for grants when the new criteria are announced e.i.; that
they not be dismissed as ineligible if actually started before applications
under the 1983-84 criteria are announced.
Mayor Rickard and Mr. Cureatz have been in contact with the Minister of
Tourism and Recreation. The C.A.O. has discussed this matter with Councillors
Taylor and Cowman and has been in contact with the Minister's office. It is
understood that a letter from the Minister in reply to the correspondence from
the Town will be forthcoming to the effect that:
1. The Minister will exercise his Ministerial discretion and accept an
application from the Town at this time for Capital Grants i.e. if we
proceed with the project at this time, it will not make our application
ineligible for Provincial Funding;
2. On the submission of the application to our Field Office Representative
(B. Neilsen) the project will be reviewed as to whether it is a
"Maintenance", a "Capital" project i.e.; a portion of the total project
may be rated ineligible under the new criteria as it is a maintenance
requirement rather than a new capital project.
Tender T83-9 must be awarded by June 17, 1983 (30 day price guarantee expiry
date). It would be appropriate therefore, to award the Tender at the June
13, 1983 Council Meeting, if at all.
Council may wish to consider the following points in their deliberations:
1. The low bid on Tender T83-9, at $59,315.00, provides for the construction
of new washrooms (Part A - $36,650), installation of a new septic tank
and tile bed (Part B - $15,000), and upgrading of electrical work
(Part C - $4,665), and an.overall contingency of $3,000.
Estimated engineering and other costs are $14,000, bringing the total project
cost to $73,315 (See attached breakdown of works).
Continued ..... /3
Admin 38-83
- 3 - June 13, 1983
2. From the above, Parts B and C ($19,665) and a proportionate share of the
other costs ($5,600), total ($25,265), are necessary in order to continue
safe use of the Hampton Offices. These funds, originally, should be
withdrawn from the Administrative Improvements Reserve Account, designed
to provide funds for "Capital" and "Other" improvements to the administration.
3. From the above, Part A ($36,650) and a proportionate share of the other
costs ($11,400), (total $48,050), are required to undertake the washroom
expansion alone. However, Part A requires that Part B (the septic tank) be
also undertaken. Part A, originally, should be financed from the $30,000
in the 1983 budget and from the Parkland REserve Fund providing for Capital
Improvements to Parks and Community Recreational Projects.
4. If the electrical works is not undertaken, then not only will a potentially
unsafe condition persist, but the possibility of the expansion of computer
facilities in the Planning and Public Works Departments will be lost.
Respectfully submitted,
D. ?Smith, M.C.I.P.,
Chief Administrative Officer.
DNS/ms
Attachment.
June 10, 1983.
HAMPTON,HALL WASHROOMS
1. Tender Cost: $ 59,315.00
(Includes Contingency of $3,000)
2. Engineering: Other 14,000.00
Costs (Estimated)
3. Total Estimated Cost $ 73,315.00
4. Part A Washrooms $ 36,650.00
Engineering 9,400.00
Contingency 2,000.00
$ 48,050.00
5. Parts B & C Septic Tank $ 19,665.00
Tile Bed and
Electrical
Engineering 4,600.00
Contingency 1,000.00
$ 25,265.00
($15,000 Septic,
$4,665 Electrical)