HomeMy WebLinkAboutPD-26-93 T COOF~AT'I®hJ O 1"Fi °fON O~ C`Tt~
DN: 18T82037.GPA
t~eetfng: General Purpose and Administration Committee ~ffe<..1~1~ .~`v 0•~c~~ ~7
Date: F{2s. ~,- p A ° ~'at-9~
Monday, February 1, 1993
fay-Late
F~epert #:.~H-2~0 33 rife -~E~T 02-93-7
Subject: SUBDIVISION AGREEMENT NEWCASTLE MEADOWS PHASE II
REFUND REQUEST AND TERMINATION OF SUBDIVISION AGREEMENT
PART OF LOT 11, CONC. 2, FORMER TOWN OF BOWMANVILLE,
TOWN OF NEWCASTLE
o
~teCOC31t71~tlf{~C1:
It is respectfully recommended that the General Purpose and
Administration Committee recommend to Council the following:
1. THAT Report PD-26-93 be received;
2. THAT the request submitted by Mr. David Fine on behalf of Newcastle
Meadows Inc. for the termination of the Subdivision Agreement
between Newcastle Meadows Inc. and the Town of Newcastle,
registered on title November 22, 1991, Instrument Number LT 572714
and for refund of all monies paid pursuant to said Agreement be
denied; and
3. THAT Mr. David Fine, on behalf of Newcastle Meadows Inc. be advised
of Council's decision.
1. BACKGROUND
1.1 Council at their December 14, 1992 meeting endorsed the following
resolution:
"That the delegation of Mr. David Fine, Newcastle Meadows
Inc., be acknowledged and referred to the Chief Administrative
Officer for review and preparation of a report to be submitted
to the General Purpose and Administration Committee."
1.2 In addition to Mr. Fine's presentation to Council, staff received
on December 24, 1992, correspondence providing further
clarification as to the extent of Newcastle Meadows Inc.'s request
of Council. Mr. Fine indicated that not only would Newcastle
~Iaad-eats I::e. recpeetf~;?' j=r-e~*~ ~ re-fund-cf ;tom ;.,;+-;a, ,~+- i
payment but also a refund of the contributions made for "external
~R ~ ~ ~ AE~Y~~E ~ 6
nits is viaiureo ~.,.ecvcieu i•nee~
REPORT NO.: PD-26-93 PAGE 2
works" attributable to this development (Mann Street Storm Sewer
Works) and lastly the termination of the Subdivision Agreement.
The refund sought is reflected below:
Schedule 'D' - 25% of levies $36,431.50
(1st instalment)
External Costs 13,581.87
Mann Street Storm Sewers
TOTAL $50,012.87
1.3 Mr. Fine indicated that inasmuch as the mortgagee was proceeding by
Power of Sale, they were unable to perform their obligations and
therefore requested the refund and termination of the Agreement.
Staff were not advised as to the events which precluded Newcastle
Meadows from .fulfilling their obligations under the terms of the
Subdivision Agreement and proceeding with the second phase of
development.
2. STAFF COMMENTS
2.1 Committee may recall, through the lot development charge exercise,
because of the provisions of the Development Charges Act, the
termination/expiry date of the Town's previous lot levy by-law was
November 23, 1991. Subsequently, on March 23, 1992, Council passed
the Town's Development Charges By-law, By-law 92-105.
2.2 Prior to the expiry date of November 23, 1991, the Town executed
twelve (12) Subdivision Agreements which resulted to date in the
registration of fifteen (15) M-Plans. Staff would note that the
additional three (3) registrations reflected "second phases of
development" as contemplated within the context of each respective
Agreement.
2.3 The following chart illustrates the Subdivision Agreements
completed prior to November 23, 1991 and their current status. The
use of the term "status" implies that the development has proceeded
through the construction stage and issuance of building permits.
- X67
REPORT NO.: PD-26-93 PAGE 3,
Number Plan Number Status
I1. Penwest - Phase 1 40M-1669 Yes
I2. Macourtice - Phase 1 40M-1675 Yes
(3. Ashdale 40M-1676 Yes
4. Veltri & Sons - 40M-1680 Yes
Liberty/Concession
5. Delbert #1 40M-1684 Yes
6. Delbert #2 40M-1685 Yes
7. West Bowmanville - Phase 1 40M-1686 Yes
8. Liza Development 40M-1688 Yes
9. Eiram Development - Phase 1 10M-840 Yes
10. Eiram Development - Phase II 40M-1670 Yes
11. Veltri & Sons - River Valley 40M-1691 No Construction
Phase II No Permits
12. Macourtice - Phase II 40M-1693 Yes
13. Penwest - Phase II 40M-1709 Yes
14. Newcastle Meadows Plan Not No Construction
Registered No Permits
15. Veltri & Sons - High Street Plan Not No Construction
Registered No Permits
Staff would note that only three (3) Plans of Subdivision have not
proceeded past the Agreement stage.
2.4 Within each of the twelve (12) Subdivision Agreements, the timing
for the payment of Lot Development Charges was consistent. with the
then Town practices. For example, a one hundred (100) lot Plan of
Subdivision would have the following lot levy payment schedule:
i) 25% of total upon execution of the
levies due Subdivision Agreement
ii) 25% of total prior to the issuance of the
levies due (1st) first building permit
_ ~J~~~
REPORT NO.: PD-26-93 PAGE 4
iii) 25% of total prior to the issuance of the
levies due fifty-first (51st) building
permit or the first (1st)
anniversary date of the
issuance of the first (1st)
building permit
iv) 25% of total prior to the issuance of the
levies due seventy-fifth (75th) building
permit or the second (2nd)
anniversary date of the
issuance of the first (1st)
building permit.
2.5 The Subdivision Agreements as earlier referenced, were all executed
prior to the passage of the new Development Charges By-law.
Inherent to each, the first levy payments were made at the time of
execution of the Subdivision Agreement. It was through the
execution of the Agreements that the developer was afforded the
opportunity to proceed with their individual projects. This in
turn would have permitted the issuance of building permits based on
the levy rates contained within the Subdivision Agreement. This
principle was prefaced with the understanding that any building
permits not issued prior to the passage of the new Development
Charge By-law would be subject to the new Development Charge rate.
2.6 Due consideration of the existing Lot Levy Reserve Funds on hand
and projected to the end of 1991, formed an integral part of the
Development Charge calculation exercise. These funds were
envisioned within the Development Charge Policy Report to be
applied to capital works as identified through the 1992 and future
capital budgets. The funds were anticipated to help capital works
to proceed, as approved by Council, during the transitionary phase
and until sufficient funds were collected under the new Development
Charges Act to allow capital works to be undertaken. In other
words, the lot levies collected have been earmarked for capital
works. Any refund would require complete recalculation of the
rurrPnt development rr.arae quantum and could potentially cause the
development charge to be adjusted upward. Therefore, It is staff's
- ~ ;
REPORT NO.: PD-26-93 PAGE 5
opinion the refunding of any lot levy monies received pursuant to
the provisions of a Subdivision Agreement would be inappropriate in
consideration of the Development Charges Policy Report.
2.7 With respect to Newcastle Meadows requests for the refunding of
monies attributable to their portion of the "Mann Street Storm
Sewer Oversizing Works", staff can not support same in light of the
provisions contained within the 1989 Schickedanz Bros. Ltd.
Subdivision Agreement, dealing with lands located to the south-
east. Within the Schickedanz Bros. Agreement, Schedule "P" states
that the Town has agreed to make every effort to collect from the
benefitting property owners the amount specified in the "Cost
Sharing Report for the Stormwater Management Works for the West
Branch of the Soper Creek". In effect, this amount was collected
on behalf of Schickedanz Bros. upon the execution of the Newcastle
Meadows Subdivision Agreement. The applicant has not provided the
Town with the authorization of Schickedanz Bros. to repay the
amount to Newcastle Meadows.
2.8 In discussing-the possibilities of termination of the Subdivision
Agreement with the Works Department, staff were advised that in
light of the "Works" described within the Agreement, termination
would place the eventual development of the lands in jeopardy of
being premature. The timing of the execution of this Agreement,
similar to the other (11) eleven noted in paragraph 2.2, was
critical in terms of the elements contained within Schedules "J"
and "G" - Works to be completed. This Agreement recognized that
the Owner was responsible for the construction, to municipal
standards, of the "major collector road" within the limits of the
draft plan. Under the parameters of the Development Charges Act
and Town Development Charges Policy Report, if an agreement were
executed today, the cost of constructing the "major collector road"
within the development would have to be cost-shared with the
Municipality. It is staff's opinion that it would not be prudent
LO exeCULe any LULUre ~uiJC11V1S1Oi1 t~c~r"eetll~I1L utlLil 5u~:11 LluiC LiiaL
the Towns share of the cost for the oversizing of the "major
collector road" is of a benefit to the Town.
~-
- -, r
REPORT NO.: PD-26-93 PAGE 6
3. RECOMMENDATIONS
3.1 In light of the above comments, staff can not support either the
refunding of any monies nor the termination of the Subdivision
Agreement.
Respectfully submitted,. Recommended for presentation
to the Committee,
J,//
`~~-fi"~~
Franklin Wu, M.C.I.P. Lawrence E. Ko s ff
Director of Planning Chief Adminis five
and Development Officer
Walter A. Evans, P.Eng.
"'Director of Public Works
LT*FW*ld
*Attach
Interested parties to be notified of Council and Committee's decision:
David Fine
Newcastle Meadows Inc.
4300 5teeles Ave. W.
Unit 17
WOODBRIDGE, Ontario
L4L 4C2
71