Report To: Joint Committees
Date of Meeting: April 6, 2020 Report Number: COD-005-20
Submitted By: Marie Marano, Director of Corporate Services Andrew C. Allison,
Reviewed By: CAO Resolution#: JC-023-20, C-164-20
File Number: CL2020-3 By-law Number:
Report Subject: North Scugog Court Reconstruction
Recommendations:
1. That Report COD-005-20 be received;
2. That Nick Carchidi Excavating Ltd. with a total bid amount of $886,718.48 (Net HST
Rebate) being the lowest compliant bidder meeting all terms, conditions and
specifications of tender CL2020-3 be awarded the contract for the North Scugog
Court Reconstruction as required by the Engineering Services Department;
3. That the total funds required for this project in the amount of $1,023,300.00 (Net
HST Rebate), which includes the construction cost of $886,718.49 (Net HST
Rebate) and other costs including design, material testing, utility daylighting,
inspection, contract administration, permit fees and contingencies in the amount of
$136,581.51 (Net HST Rebate) is in the approved budget allocation as provided and
will be funded from the following accounts;
Description
Account Number
Amount
North Scugog Court Reconstruction -
Dan Sheehan Lane to Concession Rd 3
110-32-330-83358-7401
679,500.
(Prior years and 2020)
North Scugog Court Reconstruction -
Dan Sheehan Lane to Concession Rd 3
110-32-330-83358-7402
343,800
Region of Durham Recovery
4. That the contract award be subject to the Region of Durham receiving approval for
the funding required to complete their portion of work for this project; and
Municipality of Clarington Page 2
Report COD-005-20
5. That all interested parties listed in Report COD-005-20 and any delegations be
advised of Council's decision.
Municipality of Clarington
Report COD-005-20
Report Overview
Attachment 1
Page 3
To request authorization from Council to award the contract for the work as required for the
reconstruction of North Scugog Court. The reconstruction of the road includes but is not
limited to work to sanitary sewer, watermain, storm sewer installation, road urbanization,
sidewalk installation and drainage improvements.
1. Background
1.1 Tender specifications for the reconstruction of North Scugog Court including work to
sanitary sewer, watermain, storm sewer installation, road urbanization, sidewalk
installation, drainage improvements, etc. were prepared by the Engineering Services
Department and provided to the Purchasing Services Division.
1.2 Tender CL2020-3 was prepared and issued by the Purchasing Services Division and
advertised electronically on the Municipality's website. Notification of the availability of
the document was also posted on the Ontario Public Buyers Association's website.
Twenty-three Companies downloaded the tender document.
1.3 The Tender closed February 19, 2020.
2. Analysis
2.1 Eight bids were received in response to the tender call.
2.2 Of the companies who downloaded the tender documents but chose not to submit
pricing:
• Two companies downloaded as potential subcontractors for the project;
• Two companies were unable to meet our schedule due to their current workload;
• One company decided that they were not able to quote competitively after
reviewing the specifications;
• One company downloaded out of interest due to the area in which the work was
occurring; and
• Nine companies did not respond to our request for information.
2.3 The bids were reviewed and tabulated by the Purchasing Services Division (see
Attachment 1). All eight submissions were deemed compliant.
2.4 The results were forwarded to the Engineering Services Department for their review and
consideration.
Municipality of Clarington
Report COD-005-20
Page 4
2.5 After review and analysis of the submissions by the Engineering Services Department
and the Purchasing Services Division, it was mutually agreed that the low bidder, Nick
Carchidi Excavating Ltd.be recommended for the award of tender CL2020-3 (see
Attachment 2).
2.6 Nick Carchidi Excavating Ltd. has successfully completed work for the Municipality in
the past.
3. Financial
3.1 The total funds required for this project in the amount of $1,023,300.00 (Net HST
Rebate), which includes the construction cost of $886,718.49 (Net HST Rebate) and
other costs including design, material testing, utility daylighting, inspection and contract
administration, permit fees and contingencies in the amount of $136,581.51 (Net HST
Rebate) is in the approved budget allocation as provided and will be funded from the
following accounts;
Description
Account Number
Amount
North Scugog Court Reconstruction -
Dan Sheehan Lane to Concession Rd 3
110-32-330-83358-7401
$679,500
(prior years and 2020)
North Scugog Court Reconstruction -
Dan Sheehan Lane to Concession Rd 3
110-32-330-83358-7402
343,800
Region of Durham Recovery
3.2 The award is subject to the Region of Durham receiving approval for the higher than the
anticipated costs for their portion of the contract which consists of the sanitary sewer
main line extension and associated servicing of the new watermain services as well as
25% of the road reconstruction items. The Region of Durham will be proceeding to
Regional Council with a report for the reallocation of funding to fund their portion of this
project. Therefore, award of this project will be dependent on the Region of Durham
obtaining approval to reallocate funds to proceed.
3.3 The Municipality's portion of the work is within both the construction estimate and the
funding which the Municipality has dedicated to this project.
4. Concurrence
This report has been reviewed by the Director of Engineering Services who concurs
with the recommendations, and the Director of Finance has signed off approval to the
financial components of this report.
Municipality of Clarington Page 5
Report COD-005-20
5. Conclusion
It is respectfully recommended that Nick Carchidi Excavating Ltd. being the lowest
compliant bid be awarded the contract for the North Scugog Court Reconstruction in
accordance with all the terms, conditions specifications, drawings and addenda of
tender CL2020-3.
Staff Contact: David Ferguson, Purchasing Manager, 905-623-3379 Ext 2209 or
dferguson@clarington.net.
Attachments:
Attachment 1 — Bid Summary
Attachment 2 — Recommendation Memo from Engineering
Interested Parties:
List of Interested Parties available from Department.
Municipality of Clarington Attachment 1
Report COD-005-20 Page 6
Municipality of Clarington
CL2020-3
North Scugog Court Reconstruction
Bid Summary
BIDDER
Total Bid
(including HST)
TOTAL BID
(Net HST Rebate)
Nick Carchidi Excavating Ltd.
$984,661.85
$886,718.48
Coco Paving Inc.
$1,020,396.55
$918,898.70
Hard -Co Construction Ltd.
$1,064,087.67
$958,243.90
Primrose Contracting Ontario Inc.
$1,158,443.68
$1,043,214.42
Ratcliff Excavating & Grading Inc.
$1,204,492.25"
$1,084,682.58
Dufferin Construction Company
$1,281,177.05
$1,153,739.62
Blackstone Paving & Construction Ltd. *
$1,445,448.09*
$1,301,670.77
GFL Green For Life Environmental *
$1,626,443.92
$1,464,663.12
Note: * Denotes an addition error within the submission.
Orin
CIMMgtoll Attachment #2 - COD-005-20
Memo
If this information is required in an alternate format, please contact the Accessibility
Co-ordinator at 905-623-3379 ext. 2131
To: David Ferguson, Purchasing Manager
From: Robert Brezina, Capital Works Engineer
Date: March 5, 2020
Subject: CL2020-3 — North Scugog Ct. Reconstruction
File: CRC.NorthScugogCt
The Engineering Services Department has reviewed the submissions for CL2020-3 and
offers the following comments.
Road
Limits
Description
North Scugog Ct.
From Dan Sheehan Lane to North
Reconstruction of the road
Terminus (south of Concession
inclusive of sanitary sewer,
Road 3)
watermain, and storm sewer
installation, road urbanization,
sidewalk installation, drainage
improvements, etc.
The low bidder on this contract was Nick Carchidi Excavating Ltd. Based on past
experience with this contractor, we recommend award of the contract to Nick Carchidi
Excavating Ltd. in the amount of $984,661.85 inclusive of HST, or $886,718.48, net of
HST rebate.
A total contingency amount of approximately 12.0% of construction costs is required for
this project, based on past experience. The tender includes provisional items that equal
approximately 8.8% of the construction cost, so 3.2% of construction costs have been
carried to bring the contingency to the required 12.0%. Therefore, including other costs
such as design, material testing, utility daylighting, inspection and contract
administration, permit fees, contingencies, and net HST costs, the Engineering
Department advises of the following funding:
Page 11
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1 C 3A6 1 905-623-3379
File No.: CRC.NorthScuaoaCt
Construction (net of HST) (Based on Low Bid)
$886,718.49
Other costs (net of HST)
$136,581.51
Total Project Value
$1,023,300.00
Budget Amount:
• North Scugog Crt. Reconstruction (Dan Sheehan Ln to
$679,500.00
Conc Rd 3)
110-32-330-83358-7401
• North Scugog Crt. Reconstruction (Dan Sheehan Ln to
$343,800.00
Conc Rd 3)
Region of Durham Recovery*
110-32-330-83358-7402
Total
$1,023,300.00
*Note that the Region of Durham Recovery costs are higher than the anticipated costs
that the Region of Durham had budgeted for. As such, the Region of Durham will be
required to proceed to Regional Council with a report for the reallocation of funding to
fund their share of this project. Therefore, this project cannot be formally approved and
awarded until such a time that Regional Council has approved a reallocation of funding
to contribute the recovery portion of this project.
Based on the 2011, 2016, 2019, and 2020 Budget allocations for this project as well as
for continuity, cost efficiencies, and maintaining project schedule, D.G. Biddle will
complete the inspection and contract administration. This is important to have the
design consultant available during construction to address any changes that may be
required and to provide stamped as -constructed drawings at the completion of the
project.
Considering all project costs, there is sufficient funding available and the Engineering
Department recommends that the Purchasing Department move forward with award of
the contract based on the above apportionments and once Regional approval for
reallocation of funding has been received.. Should you have any further questions,
please feel free to contact the undersigned.
Page 12
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1C 3A6 1 905-623-3379
File No.: CRC.NorthScugogCt
Regards,
Robert Brezina
Capital Works Engineer
O
Pc: Trevor Finn, Director of Finance
Marie Marano, Director of Corporate Services
R. Albright, Acting Director - Engineering Services
Page 13
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1 C 3A6 1 905-623-3379
File No.: CRC.NorthScuaoaCt
""""""■ � """""""■ I11111i111i1 11111 11111 �
Illlllllll�
' Illlllll' 11111 Illlllllll-�
' ,���� __�_ .11111MZIM
G� �� Illlllll v �Illllllllll llll� .1111111 • ��. �� ��
•, ��� —MINION 11111 HIM= lllllllll� Illllllllllllllllllllllllll� �11111111�11111111 11111\
��� — �' -- Illlllllllllll. Il�������llllllllllllll ���1111111111 111111
®�� �� =� ��11 �� 11111111�II1 1111111 11111111111111 • pf�llllllllllllllll �
'��_ ���/\rr/�/� � Illllq�yll� Illl�l�� I�Il�lll�llllllll=11111111111111111111111
•/� �Ill►r►/. r�rrr�� IIIIII III +_ -- ___ =_ __ __ �
1��IIIIIIIlu11� �i� 11���►1\\ \p\\�\\ ���M�i1111A1III111111111NA11 �'
' 1111111 �\\�������,,,,, �� �{i11111AIIIIIIIIIINIIIII
KEY MAP
N.T.S.
Page 14
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1 C 3A6 1 905-623-3379