HomeMy WebLinkAboutEGD-001-11~I~~~ton REPORT
a r
ENGINEERING SERVICES DEPARTMENT
Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date: Monday January 10, 2011 Resolution #: 6' /~irf-QU4-ll
Report #: EGD-001-11 File #: CRC.ConcRd6.1 By-law #:
Subject: INFRASTRUCTURE STIMULUS FUND, ISF 2036
CONCESSION ROAD 6 REHABILITATION
Recommendations:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report EGD-001-11 be received;
2. THAT the Municipality is committed to the completion of the Concession Road 6
Rehabilitation as funded by Building Canada Fund, Infrastructure Stimulus Fund;
3. THAT the Municipality will continue to contribute the municipal share for all
eligible costs for this project incurred after March 31, 2011;
4. THAT the Municipality will be solely responsible for any costs incurred for this
project after October 31, 2011; and
5. THAT the Mayor and Clerk be authorized, upon approval of the extension
request, to execute the amended contribution agreement.
Respectfully by,
Submitted by:
A.S. Cannella, C.E.T.
Director of Engineering Services
Reviewed by: U ~~`^"~'~~" " ~' "~--
Franklin Wu
Chief Administrative Officer
ASC/RA/jo
January 4, 2010
REPORT NO.: EGD-001-11
1.0 BACKGROUND
PAGE 2
1.1 On October 22, 2009 the Municipality of Clarington entered into the Infrastructure
Stimulus Fund Contribution Agreement with Ministry of Energy and Infrastructure
and the Minister of Agriculture, Food and Rural Affairs for the rehabilitation of
Concession Road 6 from Old Scugog Road easterly which was to be completed by
March 31, 2011. The approved project budget was $2,480,001 with the costs to be
split evenly between the governments of Clarington, Ontario and Canada.
2.0 PROGRAM EXTENSION
2.1 In December 2010, the federal government announced an extension of various
economic stimulus programs under the Economic Action Plan, including the BCF-
ISF program. The program was to be extended to October 31, 2011.
2.2 On December 21, 2010 the Canada Ontario Infrastructure Secretariat issued a
letter outlining the details of the BCF-ISF Program extension (Attachment 1). This
correspondence outlined the details for applying for an extension. The
requirements include a council resolution confirming the Municipality is committed
to complete the project; will. continue to provide the Municipal share of all eligible
project costs incurred after March 31, 2011 and will be solely responsible for all
costs incurred afte7 October 31, 2011. The deadline date for the extension
application is January 17, 2011.
2.3 The majority of the work related to the rehabilitation of Concession Road 6 was
completed in 2010 but during construction there were issues related to the
rehabilitation and the extension of structures crossing existing watercourses that
arose which required in-water works. As these issues arose after the September
15, 2010 dead line for such works to be undertaken as mandated by the
Department of Fisheries and Oceans the work could not be completed and was
deferred until the regulated time of July 1 and September 15, 2011.
REPORT NO.: EGD-001-11
PAGE 3
2.4 The design of the rehabilitation and extension are underway and will be completed
shortly and submitted to the local Conservation Authority for approval with
anticipated in-water works scheduled to start July 2, 2011 with an estimated
completion of August 31, 2011. All works related to this project are estimated to be
completed by September 30, 2011:
2.5 Due to weather conditions the permanent line painting for the project was not
completed and will be completed in the spring of 2011 at such time that the
conditions permit.
3.0 COMMENTS
3.1 The Municipality of Clarington is committed to completing this project and
appreciates the governments of Canada and Ontario extending the completion
deadline to October 31, 2011, allowing the Municipality to be able to take
advantage of the remaining committed funding for this project to complete the
outstanding works.
3.2 Staff are preparing the project extension application and will, be submitting it prior to
the January 17, 2011, deadline. We will indicate in the application that the required
resolution will be forwarded following the January 17, 2011 council meeting.
Attachments:
Attachment 1 -Canada Ontario Infrastructure Secretariat letter (December 21, 2010)
ATTACHMENT N0.:1
REPORT NO.: EGD-007.11
..:
Cartade Ontario Infrastructure Secretariat Emell: bcf ccQontario.ca
1 Stone Road West, 4NW Telephone: 1 866 306-7827
Guelph ON N1G4Y2 Facsimile: 519826-4336
Frank Wu
Municipality of Clarington
CAO
40 Temperance Street
Bowmanville, ON, L1 C 3A6
December 21, 2010
Dear Frank Wu:
Ontario
1, chemin Stone Ouesl, 4N: O. Courrlel: bd.cc@ontario.ca
Guelph ON Nt G 4Y2 TBIBphone: 1 866 306-7827
TBIBcopieur. 519 826-4336
r~~
DEC 2 Z 2010
MUNICIPAE.ITY OF CLARINGTON
ADMINISTRATOR'S OFFICE
Over the past two years, the governments of Canada and Ontario have worked with you to
implement a range of economic stimulus programs. These programs have helped to boost our
economy and create jobs, while also investing in the critical infrastructure that our communities
need.
The purpose of this letter is to advise you that Canada and Ontario have agreed to extend the
deadline for the completion of stimulus projects funded under the Infrastructure Stimulus Fund
from March 31, 2011 to October 31, 2011,
In order to receive an extension, it is mandatory that you submit a written request for an
extension by January 17, 2011.
The extension recognizes the benefits of allowing for the completion of projects that are
underway but which, for various reasons, are at risk of not being completed by March 31, 2011.
At the same time, we expect that the vast majority of stimulus projects wilt still be completed by
the original March 31, 2011 deadline.
There are important conditions governing the extension for the completion of infrastructure
projects funded under the iSF. In order to be eligible for an extension, your approved project
must have started before March 31, 2011. Starting a project is defined as having incurred
eligible costs for the project.
The federal government requires that for projects receiving an extension, a claim for all costs
incurred up to March 31, 2011 must be submitted to the federal government by April 30, 2011.
All final claims for all projects being extended under the program, covering eligible costs
incurred up to October 31, 2011, must be submitted to the Province no later than January 31,
2012. In addition, we wilt be requesting a bi-monthly update on the progress of those projects
being extended.
The federal government has mandated that specific documentation be submitted for all projects
seeking an extension. In order to receive an extension, you must submit in writing:
• A list of all of the projects that require an extension, including the relevant funding
program, the project title, and the project identification number;
• A revised financial forecast for the project with estimated costs to be incurred up to
March 31, 2011;
• A forecast of project expenses and federal and provincial funding required from
April 1 to October 31, 2011;
• A detailed construction schedule for the completion of the project, signed by an
engineer or architect; and
• A council resolution committing to finish the project and accepting responsibility for
any costs incurred beyond the October 31, 2011 date. Aboard resolution is required
for not-for- profit organizations.
These documents are required for each individual project for which you are requesting an
extension. Templates for your list of projects requiring an extension, a draft council resolution
and a solemn declaration concerning the construction schedule have been developed to assist
you in meeting these requirements. Templates have been sent by email with the electronic
version of this letter and will be available on the web site: www.ontario.ca/in#rastructure
The deadline for you to submit your extension request is Monday, January 17, 2011. If you
need additional time to submit your construction schedule or resolution, please clearly state this
in the extension request that you submit on January 17~'.
The extension request must be submitted by email to bcf.ccclaimsCa.ontario.ca or by fax to 519-
826-4336. Please also copy your provincial program analyst on your extension request.
If you do not apply for an extension, or if you do not submit the required documentation,
you will not receive an extension and the original March 31, 2011 deadline will continue
to apply to your projects}.
The extension being granted now is an exceptional, one-time measure, and further extensions
will not be considered. Any costs incurred after October 31, 2011 will not be reimbursed by
Canada or Ontario.
If you choose to submit a request for an extension, provincial staff will follow up with you to
confirm that all of the required documentation has been submitted, and will advise you if an
extension has been granted. In the event that you receive an extension, provincial staff will also
work with you to amend your existing contribution agreement. All contribution agreements must
be amended by all parties no later than February 28, 2011.
Thank you for your continued cooperation in the implementation of our infrastructure stimulus
programs. If you have any questions about the deadline extension, please contact your
program analyst.
Sincerely,
Federal Co-Chair
Provincial Co-Chair
~~
Sonja Adcock
Director, Ontario Infrastructure Canada
Ontario Directorate -Program Operations
Branch
Martin Bohl
Director
Rural Community Development Branch
Economic Development Division
Ministry of Agriculture, Food and Rural
Affairs