HomeMy WebLinkAboutEGD-021-10Clarington
Leading tfie Way
E
Meeting: GENERAL PURPOSE AND AD
Date: Monday July 5, 2010
Report #: EGD-021-10 File #:
Subject: KENDAL DRAINAGE REVIEW
Unfinished Business
REPORT
NGINEERING SERVICES DEPARTMENT
MINISTRATION COMMITTEE
GPA--Si//- is
Resolution #: ~'-3a8-/0
C'-3s -/o
By-law #:
Recommendations:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
THAT Report EGD-021-10 be received;
2. THAT Engineering Services recommend the implementation of the preferred
Option #3 contained in report EGD-021-10, Construction of a ditch on the south
side of Regional Road 9, directing flow easterly to the watercourse immediately
east of Regional Road 18;
3. THAT Engineering Services complete the detailed design for Option #3 and
conduct a Public Information Centre for this project and obtain input from area
residents and stakeholders;
4. THAT construction of the recommended option be completed in 2010
construction season;
THAT funding for the works be reallocated from the Bowmanville Creek Erosion
Protection budget item, account no. 110-32-340-83234-7401; and
6. THAT remaining funds from the Bowmanville Creek Erosion Protection account
be carried over to the 2011 Budget and additional funding to complete the work
be considered as part of the 2011 Budget.
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L1C 3A6 T 905-623-3379 F 905-623-9282
REPORT NO.: EGD-021-10
PAGE 2
Respectfully by,
i~~.--
SL fitted by: A.S. Cannella
Director of Engineering Services
F.~ J~~ ~
Reviewed by: Franklin Wu
Chief Administrative Officer
ASC/bb/jb/dv
June 28, 2010
REPORT NO.: EGD-021-10
1.0 BACKGROUND
PAGE 3
1.1 The Hamlet of Kendal is home to approximately 65 residential properties ranging
from 0.1 to 1.0 hectares in size, a local public school, recreational facilities, and a
general store. stormwater management is currently provided by a system of
swales, open ditches and culverts that draw overland flow east to Regional Road
18 and south to outlet at the Smiths Creek tributary of the Ganaraska River. Due
to a relatively flat topography, recurrent flooding has occurred at various locations
within the hamlet during spring run-off and high-intensity rainfall events.
1.2 In 1990, TSH (currently AECOM) was directed by the Municipality to develop a
proposal to improve drainage within the hamlet. A plan was prepared to construct
a comprehensive storm sewer system in three phases at a cost of $1.0 million
(1990 dollars); however, further work was deferred due to financial constraints
and the need to pursue projects with higher priority.
1.3 In 1994, the unresolved drainage issues were brought to the attention of Council
by local residents and TSH was advised to revisit the original project design and
investigate the feasibility of discharging all or part of Kendal's storm drainage to
the north-south drainage course which is located on the west side of Regional
Road 18. A preliminary survey was conducted on Regional Road 18 and
concerns were raised that the depth of ditching required to support proper
drainage of the hamlet would be cost prohibitive.
1.4 To further investigate the feasibility of both the original three-phased stormwater
drainage plan and the Regional Road 18 stormwater drainage concept, the
Report on Soil Conditions for Hamlet of Kendal Storm Sewer & Road
Reconstruction (June 6, 1994) was commissioned and prepared by Site
Investigation Services Limited. Report findings concluded that a high
groundwater table would render proposed design alternatives cost prohibitive and
cited concerns over the probable disturbance of the groundwater table and the
potential adverse effects on domestic wells that would result from installation of
REPORT NO.: EGD-021-10
PAGE 4
the storm sewers. At this time, a petition signed by 38 residents in opposition of
the proposed sewer construction was also received by Municipal staff and a
mutually agreeable decision was made between residents and the Municipality
not to proceed with construction of a storm sewer system.
1.5 At the November 9, 2009 Council meeting the Engineering Services department
was requested to research drainage issues along Regional Road 9 from Kendal
Church Street to Regional Road 18 as they relate to the overall drainage of
Kendal. Due to both current and historical concerns, the Municipality requested
AECOM to renew efforts and find an amenable solution that would address the
hamlet of Kendal's most pressing drainage needs.
1.6 In the spring of 2010, complaints were received by the Municipality from the
owner of 43 Kendal Church Street regarding poor drainage from the property
through the informal swale system that exists on the block bounded by Kendal
Church Street, Monck Street, and Regional Roads 9 & 18 (see Attachment 1-
Existing Conditions drawing). As part of their ongoing work associated with the
preparation of their report AECOM investigated these complaints and
photographed the situation to document the concerns.
1.7 Subsequent study of the project's pre-history and current conditions revealed
three alternative solutions:
1. Do nothing
2. Comprehensive Shallow-Pipe/Ditching System
3. Ditching Improvements
Ditching Improvements was evaluated as the preferred solution due to previous
concerns regarding high groundwater table conditions and the hamlet's flat
topography which would render a Comprehensive Shallow-Pipe/Ditching System
largely unfeasible.
REPORT NO.: EGD-021-10
PAGE 5
1.8 Four ditching options were then developed under the preferred solution, based
on mitigation of drainage concerns, impact on the environment, impact on
property owners and financial cost. These four options are graphically
represented in Attachments 2 through 5 as follows:
• Option 1: Formalize Existing Back Yard Swale-Preliminary estimated cost:
$180,000
o Advantages
-follows existing drainage patterns
o Disadvantages
- reliance on individual property owners to keep swale maintained and
unaltered
- uncertainty of subsurface existing conditions and environmental
impacts (i.e. septic beds)
- perceived or actual damage to private septic systems caused by
swale construction
- legal easements should be procured to ensure future access
-does not address road runoff from Regional Road 9
• Option 2: Improve Ditch: Kendal Church Street and Monck Street-
Preliminary estimated cost: $150,000
o Advantages
-within existing Right of Way
o Disadvantages
- Right of Way is narrow thus requiring the shallow sewers
-sewer slopes would be less than desired but are constrained due to
existing condition of inlet and outlet
- does not address road runoff from Regional Road 9
• Option 3: Construct New Ditch: Regional Road 9 (South Side) directing flow
easterly-Preliminary estimated cost: $110,000
o Advantages
REPORT NO.: EGD-021-10
PAGE 6
-within existing Right of Way
-directs flow from Kendal Church Street culvert away from rear yard
drainage swale
- captures road runoff and directs it away from private property
-provides potential well draining outlet for sump pumps
o Disadvantages
- impact to existing entrances off of Regional Road 9
-minor grading required on private property to provide flatter ditch side
slopes to allow for easier maintenance
- relocation of utilities required
• Option 4: Improve Ditch: Regional Road 9 (North Side) flows easterly -
Preliminary estimated cost: $90,000
o Advantages
- within existing Right of Way
-directs flow from Kendal Church Street culvert away from rear yard
drainage swale
- minimal impact to existing residents
o Disadvantages
-does not capture road runoff and direct it away from private property
-does not provide potential outlet for sump pumps
- relocation of utilities required
1.9 Study findings were subsequently documented in the Kendal Stormwater
Drainage Review (AECOM, June 2010) with a recommendation to proceed
forward under Options 3 which is briefly evaluated below:
• Option 3 proposes new ditch construction on the south side of Regional Road
9 with a significant improvement of overall drainage for adjacent properties
while having a marginally higher cost due to affected private drive entrances
and utility relocation cost.
• In addition to conveying flows from the cross culvert just south of Regional
REPORT NO.: EGD-021-10 PAGE 7
Road 9 on Kendal Church Street it also captures road run off and directs
flows away from the properties towards an outlet to the east.
• This option also provides property owners with an alternative location for
discharging their sump pumps where the flows will be directed away from
their property.
2.0 PROPOSED APPROACH
2.1 Further effort is required to proceed to construction and provide timely relief for
residents who have been struggling with this long-standing issue. Public
consultation will offer a step forward by providing interested residents with an
opportunity to understand the complexities involved, review the preferred option
as noted and provide, their input. To this end, detailed design of the preferred
option should proceed for presentation at a Public Information Centre. (PIC) with
construction following shortly thereafter taking into consideration the input of the
residents and stakeholders.
3.0 FUNDING
3.1 Opportunity exists to move forward in the current budget year through
reallocation of funding for the Bowmanville Creek Erosion Protection works.
Estimates for the Bowmanville Creek project were initially made on the basis of a
conceptual design and, upon the completion of detailed design, were found to be
significantly higher than the budgeted amount of $200,000. As such, Engineering
Services was planning to defer works for the project to the 2011 budget year,
provided that additional funding could be committed during 2011 budget
deliberations, and has reviewed financing possibilities for the Kendal drainage
works by utilizing the Bowmanville erosion protection funding from account
number 110-32-340-83234-7401.
3.2 The Municipality could also benefit from delay of the Bowmanville Creek Erosion
Protection project due to the recently passed Development Charge By-law
REPORT NO.: EGD-021-10
PAGE 8
update and staff will review potential to fund a portion of the work with
Development Charge reserves as the work has a growth related component to it.
4.0 RECOMMENDATIONS
4.1 Given the above, Engineering Services concurs that Bowmanville Creek funding
should be utilized for the Kendal drainage works and that additional funding
should be sought for the Bowmanville erosion protection project as part of the
2011 budget. It is further recommended that:
1. Detailed design of Option 3 as described above and defined in the Kenda!
Stormwater Drainage Review proceed to completion;
2. A Public Information. Centre be conducted for Kendal residents and
stakeholders to review the preferred option; and
3. Construction of the preferred option be tendered and constructed in the 2010
construction season.
Attachments:
Attachment 1 -Existing Conditions
Attachment 2 -Design Option 1
Attachment 3 -Design Option 2
Attachment 4 -Design Option 3
Attachment 5 -Design Option 4
~
i~ l~i#e~ C a w W i yy.. s M
" ~ V ~ ~ ,
~ a ~ eg~,
:
o g: ~ i~qt
~
~e ~sfl
~~
~ Nz
a x ~
.
X ~ i 'ss=~
y a f~ 4 < ~~394 ~
;;e;i ii
tee ~~ ~
a
~ a
Us ~ o
~ x _
££ w
7 s
~ ~
3 'j s
33
~a
i ~ ~ ~~ ~
~ ~~
snob NosawaNl ^ ~ / ~
\ ~",
~. ~ I ~~
, ~_
~ ~ ~ ra
~~, ~ ~ ~_
~94UZJN 1YN01'J3b~10K0b13Tb{NUliA3N
w 'J
, _ ~~q ~ ~~U'f e
e m~
4 \\
~w
~~u _041 ~ '~~
,~ 1
<~ ' -~
a~ eo _ ( _ 1
1 \)
~~' ~ a~8 ~~ o.. ~/ ~W ~ w.„.,m .~ ~ ... 133b18 A3MJ10 ..p( ~` I
~. \ ~
i 21 ~ ~ , W IW
m
Iii ~o J 1':q bw y
~ a 6
b Y
l ~1~ A - ~f , z Y~ ( -
~m I
a #f
a ~ ~J ~
i r
a~
w ~~ ee o ~\~,,~~
p ~ • ~ ~~
w ~
p w ,
~~ I I l ~° ~~~ s~ I w r ~ j
e
~ ~ ~~ ~ ~ `~a ( o
a
~~ '~O ~; 133b18 aN3N ~ /
\ / NJL'ONJ 1b '~ ~
x
~~i~i
~w ~,,. I ~'~i r`
iF
_~.- ~' _
~ ~ ~,s ~ ~ r ~ ~--
~~ ~~ ~ ~~ ~~ ~~ ~ ~ ~~i~
~.
-~ 9noaauNm l ~ ~ ~~~ ~ ~~~~ ~ I ~~lf ~~ ~ ~ ,
ff''ll I I A~1 ~ "a ~I~ ~V ~ ~~~ 1~/ ~ ~~. ~ ~ ~
Attachment 1
~§ A ~ rw n e ~
9 ?[:~~~
~' ae~ WaBaaE ~' t- a $w M
$ 8 3 ~tF j~R~7 ~s~ ~ w ` ~ ~ E
* ggOpg~F [,a~. A zo a R
~~~ w ~~ 5C9€ f€dp 6~ - S~d gg wY € ® (~
~_.. Sel.€! 3 U 1 g - '~ '~
-atloa Noeawowa- ~ ~ + \~
i 6~~ `
i g1TVpa6l'VNOI'J3lInpMOaR3l+l1/~NO~I'NS3N
~ ___ ~,..I, _
~ r
~ r ~7i o~' ~~~~ } t
i
am O
' ids =c\
io
e i
111ff/// ,~ n„
i --a
oa
,~
r -
,~
~ _~
=w o= ' _
,~ ~_ ._ -
~I i ~ p~ ; A. ~ ( ~ _ 133b13 A3bOlp~ n
a~
~ z ~ r i
O ,
~. /~
s t ~~~~
Y ~ .,1 ~ f
°sF r
i ._. ~:@ _XS °133tl13AON ~~ r, _
i
w :G ('
i ;~3 ~ 9E ~~ /
Y'~ " ~
:~ 9G ~ Sn YV i,~ ~
' ~
~ w ._: f
rc +G "
g-w ~,
~ l ~ ~ .~ , ,_._ H
~~
u
j
1~ o r~~
. ~ a` '-•, 133b13 H~bpH N
OltlpN3 ~~
~~~~\~-j"spy )
„t -
~ ~ ~
r
{ a " ~ i \r\
`v. ~
N (,,. ~~ \ .,~,t~
E Jf
`// i ~-
~~
\ \~
:1
ptlpa3LHM ~~ ~~
i
~, ~~'
Attachment
o k ~ ~ _ a ~p~~~ ttfi E~~ pV ~~~ 3 0~ 4Wu` s ~iEe R
g ~''~ a c y o g g$~~ t{2131 ~ a°=` • a <~ oiQ~ K ~§ o f
~, %
C~I ~ ~
.anoa NOSawoNl
-t j---~ ~ f ~~
1 - ~ i
,. ~~
~$
~~
- -
~ I~tloa6l3NOT03$)IOYOai3"IlIAN6EN3
._._ _ _. .f..~,._ _. ~._. _.
w
r
w
1 on
_ -
~ ~= I a~
° ' P
&~ ~ E „1~
1 ~ ~~
~~ ~ _
~a P
o ~ ,
~ '¢m y o -.. W~
' 1~ 4 F ~~ a ~~1 ~ W
a
~ ep8 ~ r'# ~ ,1 1 ''133b1SA n
',J r 3HOIO v ~
G2 ~n
_ \
I 4~ 2w ~ ~ w ~ __
Soy ) ~~" ,~,~ ~1 ~~ J
w
i _.. p& y p ~ ~ ~.
~ ~~~*J f)
' 3 w
i
o ~ n 133a1S AON /~'
!~ _ ; 11 w 1
x
1 .'
` 1
~~~ 1 or •u
r I wz ~ 'AC I E~ \~ w
V w g.
z n e """ T'w----- """'nww _
w
~ ~ ~~ f~ ~
~ s
V i'. ~' ~ 3 ~ ~..
®, ~ x.-_.iYq ~ ~~ ,;off f
133b1S N.~LLI1H0 ~
~. zi ~~YON3N ~~ '~
n
z y ~
M ~ ~ ~ g;
x Li_
u
z I ~i:
i• _..
.~
'-~
Attachment 3
_ ~ _ N p
e y I '
~~ 1
roa 31~HM
I
~~
~,
5
'1
°~~
ryyt
SFa I,'.f
: ~
~
2 K
r3
a
w -
g
'a ~
ya:
~
~ ~
qq; ~
i ~ 4~ ~x
sEa
3 LL k ~
~~
ae 3sFGi
s ~/
BS ., rcrc i~
-' e
~
~asH
~~~~ t
i[~. el'
y1J ltd
t[ /
~
V/ g~g _
~ ~ gig
~ 34°
~ 5` Oo
° 2
Q - F~~
00.
£ s
~ i @z
$
Y ~ s
S
€~v ~Ii~E~ ~ ~a W 0 ~ -
a
~~~~g .sE: ~ _ e ~ ~ ' j ~
:c °
Ev ~~ 4
r ~
2e O
W= ~Og ~ ~ ~ i..
J u ( s
N V 4 i~ nu
ON e O ~
5 ~
CU ~
] //
~i
9~S ~ os
n I u `~~
~~ ~ p
co `
i
4
~ i~g 8° i _ 11 ~ ~ W
c : I ~ 133a15A3MJ10~
n ~ M1\
WOn.. 8~~ ~ ...V y JG ~~I ;a
1 1 S
po ~& ?w '
z
` ,``~\^
`r\\ _.. 3~& > .. _. ~~133}j15 AOM l- 14 V
~ ~ ~ `~
Saes r A"' Jr/" r „'"
/ o^
~ € ~ =n
\ z ~ 3G
1 L
i w ~ W ~ N
F I f
a0 ~ O ~t
0
> ~~ ~~ ~fi~~ ~ ~~~
~~
J w ~~ 133b~ n
'ten ~O~T/UN3M
~~ ~ _~~l'l'~l~
\ o' uC~
~ iw f
N a i
w fl ~ .~
a
~ ~ _ ~ :~ ,
~ _~ ~
~ 1 r\~ r
,---~
~ J ~~1~ \~. fir=
Attachment 4
__ ~~ 3.t~i~ ~. ; w3 ~ `s N
o N ~ ~ ~ax a{' sA rcw oe. ' a
o p ~ U ae_ 3 O _
~ p 8 "L3 dPtt~ '- ~ ~ v~iQ d ~ p~ i
8 5 n ` F €~r'fr ~g~a' ~ rah w a~ ~i. 7 £
~ I~ g~~B in r € Y~
I I ~ i
i
I °~
o
o "_:
dos c ,
°~~ S€
i
a ~ ~ ,~ ..
yy s ~ ' ~
f e ~. }
w z w i,°,~ , E~
a ~ o 0 40 ~ _ ;4
2 N 3 r ~ a ~ ,.ar. '
WW vm .. 1 W
N XO~ E~& ~ ~ ~ II 1 F:
' Q OX'.' ~_~.. __ _.. W ~n
~E ~p /+ ~C' ~~ ~ G
x ~
~~~ 8ag / £ i N' iG
$w
~l ~ i ly/
~ ~ V n i
F
m t O.
a~
~ s ~
{yl
2 ~ ~ x~.u.
~~~ F ( 8w 6~ ~ ~,
C w ° :w
I ~ ~ ~ ~ ~~ y
w w
1 i a
f ~ ~
p~ ~ V U w
¢ I• ~ ._.~ 133N18H ZfOH9 rypM3N.,.. ~~ ~
w o ~~
> Ia= I
~ o0
N u ~~I ' F
w
x y `w
I au y ~ Y w
nN L~~ ~~ ~ ~~~
~ w
r
z ~ "
F~
~ I ~ ~~ '~~/ ,di
~ .$ ~ __ ,,
~ i
AttacM1ment 5