Loading...
HomeMy WebLinkAboutWD-19-96} THE CORPORATION OF TH16 MDNICIPALITY OF REPORT Meeting: GENERAL PURPO~E AND ADMINISTRATION COMMITTEE File # ~n ,C Date: MAY 6, 1996 Res.#~~9'~-.~01'~~. ', BY-Law # Report #: ~~~~ File #: ', D~^ .'~~ ,~.4 Subject: APPROVAL OF E7~PSNDITURES ON CHDRCH STREET, BOWMANVILLS CONTRACT CL94+13 Recommendations: It is respectfully recommended that the General Purpose .and Administration Comuhittee recommend to Council the following: 1. . THAT Report WIb-19-96 be received; 2. THAT Council a¢:prove funding in the amount of $105.,638.20 from .the Public Woks Lot Levy Reserve Fund to provide for the balance of the additional expenditures incurred in completing Church Street lInfrastructure Project, Contract CL94-13. REPORT 1.0 ATTACHMENTS ~! No. l: Sumglary of 1995 Public Works Projects with partial or full financing from the Public Works Lot Levy Res~rve.Fund 2.0 BACKGROUND 2.1 Accelerated Schedule As outlined in'Report No. WD-17-94, the "normal" procedure for the completio#: of the Church Street project could not be followed as ajresult of the guidelines for funding under the Canada-Ontarip Infrastructure Works Program. Due to the accelerated process, many issues that would normally have been resolved prior to the commencement of construction were not i R13PORT NO.: WD-1996 PAG13 2 resolved, res lting in additional works being added to the contract durix~g the actual progress of the project. i 2.2 Public Input Although the Church Street project was to be completed within a compressed schedule, every effort was made to incorporate all facets of the "normal" process into the shortened time- frame. This. included input, through Public Information Centres and individual consultation, from residents and other parties affected by the proposed works. The residents and businesses on Church Street and adjacent streets were very concerned about the reconstruction and had significant input in the final design. As a result of the public concern, the project was redesigned several times to incorporate these issues, resulting in time delays and increased consulting fees. 2.3 Unresolved Isst:es As a result of the accelerated schedule, some design issues were unresolved prior to the tendering of Contract C194-13. These issues are briefly described as follows: • Reduction. of the steep grade, to ensure public safety, at the parking area in front of Lisa Villa, No. 133 Church Street, Bowmanville. The delay in final design was due to ongoing negotiations with the property owner, Mr. Mario Veltri. • Utility companies (gas and hydro) were unable to complete relocation work in advance of construction due to the redesigns. and a shortened schedule. The utility companies, were required to work during winter months to complete their relocation work prior to the general 1~flZ REPORT NO.: WD-19-96 PAGE 3 contractor, Hard-Co Construction Ltd., recommencing. operations in the Spring of 1995. This resulted in the Municipality paying premium labour and equipment rates. • Specifics of the renovations to the Old Firehall were not finalized prior to tendering the Municipal contract; therefore;, costs associated with works to be done at the Firehall under the Church Street contract could not be incorporated into the initial contract bid price (i.e. electrical servicing, water/sanitary servicing requirements and treatment of the ramp connecting the building at the basement level). • Construction of the retaining wall and steps at the east limit of the Municipal parking lot fronting the west side of Division Street (south of Church Street) resulting from public input after tendering the contract. The retaining wall, for the most part, was outside the original limits of the contract but was constructed in conjunction with Contract CL94-13, as it was the most cost effective time to do so considering the other retaining wall work being carried out as part of the contract.. The construction of the wall improved public safety at this location by eliminating the steep ramp from the Municipal parking lot level to the Division Street sidewalk level. • Subsequent to the award of the tender, the local residents requested that concrete brick pavers be used for the boulevard treatment on the north side of Church Street (east of Division Street) as an alternative to the sod which was specified in the contract. The precedent for this was set with the completion of the Liberty 1003 REPORT NO.: WD- PAGE 4 Street si~ewalk contract which also used concrete brick pavers fopr boulevard treatment. Due to time constraints, the design details for the above noted works were not available prior to tendering and it was not considered acceptable to include a large lump sum contingency in the contract to address the inevitable additional unresolved work. 2.4 Costs of the Unresolved Issues The final "as constructed" costs for this project were reviewed and the cost of the unresolved issues, as explained in section 2.3 of this report, are valued at $105,638.20. 2.5 Public Works P o'ects Financed from the Public Works Lot Le Reserve Fund Through Aonroved 1995 Capital Budget Shown on Attachment No. 1 are projects, including Church Street, that ere financed, fully or partially, from the Public Works Lit Levy Reserve Fund. Attachment No. 1 also compares the budgeted costs and the actual costs to be drawn from the Public Works Lot Levy Reserve Fund. With the exception of Church Street, all the other 1995 Capital Budget project costs, which identified Public Works Lot Levy financing, were on or under budget and resulted in a savings of approximately $95,210 from the Public Works Lot Levy Reserve Fund. 2.6 No Provision in 1995 Budget The money allocated in the 1995 Budget for Contract CL94-13 was based on the tender works carried over into the 1995 construction season and not inclusive of the costs associated with the unresolved work. 1004 REPORT NO.: PAGE 5 2.7 It would hav been difficult (and perhaps misleading to Council) to present individual reports for Council's consideration following the resolution of each unresolved issue. Accordingly, it was concluded by Public Works staff to delay the presentation of these issues to Council until the total "as constructed" costs scenario for the project were available. 3.0 RECOMI'~NDATIONS 3.1 It is, therefore, recommended that Council approve the funding of $105,638.20 from the Public Works Lot Levy Reserve Fund to cover the additional costs already incurred in completing the Church Street Contract CL94-13. Respectfully submitked, Steph/~ oke~ng. Director of Public Works ASC*ph April 29, 1996 Reviewed by, W.- Stockwell A_fChief Administrative Officer Attachment 1005 O W Z U 2 Q 2 LL J J 7 W Q ~ ~Z J ~LL F W 2Q aW N =w H~ 3~ ~ J W ~ SN a~ ~O Q3 J Um ~~ ma ~ W a~ 0 o°i W w O ,~ V/ o^ o~ N N o o ~ ~ O 0 0 c ~ yg {tl ... l0 m N N r y ~ O O Q N O U ~ ~ > ~ a~ U Y Q J E 0 LL ° ° o o , an p y . N y O O' Q U d ° 2 a v a ~ ~ ~ rn~ J 7 m E 0 ti n N I c o U N O ~o i7 iq I cn •c o 0 ' ¢ °' $ c U m o H m ~ ti O U ~ a 7 ~ r U o U U a o^ o~ o ~ o~ o~ o L o a a '~ o ~ o "~ o ~ ~ ~ c c N W ~ c n OD v fA ~ c O p 7 a o c O O 7 o c r 7 of ~ r~ o n N ~ ~ ~ ~tl m GO O o O O O O O p p d T N ~ °~ N ~ p t, y N ~ N ~ ~ O ¢ M ~ U yr ~ cy ~ M > io EPr V ~ Q J E 0 °o °o °o o °o O y > r O q O o° ~[I V O a , O o uj a _ w O N ~ N ~ V ¢ m > ~ m~ 7 J m E 0 ~i s y c m r c o m m ~ o c ~ n E o E o w ~ o # m o L o ° 0 v 0 0 ~I « N ~ ~ I ~ I a v ~ I > O •c y o0 o ~ 00 ° o m~ ao co ~o 0 - Ern U~ n •"m `a°rn ~O rnW o .' a~ 3N ¢°o ~o ~° H d N^ :p ^ Q^ C N N ` ~~ ~~ ~ m ~ ~ a d .. N ~„ ~ ~ ~ ~ N 'a. C V/ ~ ~ ~ ~ C y 7 _ C C ~ ~ Q Q Q Q w Q lO"L ~° O O1 zl Z ~ w~ ~ I 2 U ~ Q E 0 0 ` U a ., N C •O c a U N Y •~ m ay d.. L C •• N O N c a 0 d w L Q- °c ~ o t• a U a m c R 3 ~ 0 0 L J f/1 +y. Y y O U ~ U a ~a' a~ 7 COL