HomeMy WebLinkAboutCSD-019-08
Cl![-!ll-glOn
REPORT
COMMUNITY SERVICES DEPARTMENT
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date:
July 7,2008
Resolution #:flf R - ~ 4-9 - og
Report #: CSD-019-08
File#:
By-law #:
Subject:
NEWCASTLE & DISTRICT RECREATION COMPLEX - FACILITY
UPDATE
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report CSD-019-08 be received for information.
Submitted by:
J s . arua
i ctor of Community Services
Reviewed bY:cJ~-!:: ~
Franklin Wu
Chief Administrative Officer
JPC/SM/GAlJM/wg
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-5506
REPORT NO.: CSD-019-o8
PAGE 2
1.0 BACKGROUND
1.1 At the September 25, 2006 meeting, Council awarded the construction of the
Newcastle & District Recreation Complex to Aquicon Construction Company Ltd.
in the amount of $15,065,884.00. Construction of the facility, designed by Shore
Tilbe Irwin & Partners, commenced in October 2006.
2.0 CONSTRUCTION UPDATE
2.1 Since construction began the project has progressed steadily, although the
schedule did encounter labour disputes during spring 2007 that resulted in a
schedule delay. At the time of this report, the project is approximately 95%
complete.
2.2 Based on the current progress of construction, staff are anticipating the building
to be substantially complete on July 18, 2008. At this point staff will have access
to the building and the contractor will continue to complete deficiencies and other
minor items. Subsequently, the facility should be fully completed by August 15.
2.3 At the time of preparation of this report, the pool tanks are full and pool
mechanical systems operational. The gymnasium flooring is currently being
installed.
2.4 The completion of the exterior grading and landscaping is ongoing and will be
completed during the summer months.
2.5 Separate to the facility construction, the Engineering Department will be
constructing a sidewalk along the west side of Rudell Road, from Highway #2 to
the Edward Street entrance to the facility. The project has recently been
awarded and work is expected to be completed in advance of the opening of the
building.
3.0 POST CONSTRUCTION ACTIVITIES
3.1 Upon access to the facility on July 18th staff will undertake a six week
program to prepare the facility for public use. The program will include the
completion of operational equipment commissioning and training, inspection and
approval to open the pools and water slide by Durham Region Public Health
and Technical Standards & Safety Authority (TSSA), facilities and aquatic staff
training, data/phone system installation and the delivery and set up of office
furnishings and equipment, program and aquatic supplies.
3.2 Based on accessing the facility July 18th, staff are planning to have the facility
unofficially open to the public on September 2nd At that time an abbreviated
schedule of public programs will be offered. Full programming in recreation,
REPORT NO.: CSD-019-08
PAGE 3
aquatics and fitness will commence with the fall program schedule on September
20th
3.3 During this post construction period, the department will be finalizing all staffing
requirements for the facility operations and recreation services with the goal of
being fully staffed and trained in time for public use of the building.
4.0 PROJECT BUDGET
4.1 The approved project budget is as follows:
Construction
Consulting
Contingency
Disbursements
Furnishings/Equipment
$15,000,000.00
$ 950,000.00
$ 750,000.00
$ 100,000.00
$ 355.000.00
$17,155,000.00
Project Total
4.2 As previously advised, we experienced a number of challenges that had an
impact on the project budget. These included the design and installation of
sanitary sewer services to the facility, saturated native soil conditions identified
during the excavation for foundation walls and during the preparation of parking
lot base, remediation in the pool basement area for groundwater conditions and
water and sewer frontage fees due to Durham Region. The costs of these items
are funded from the project contingency.
5.0 RECREATION PROGRAMMING AND FACILITY SCHEDULES
5.1 At this time it is expected that the facility will be fully operational for the fall
session of departmental recreation programs. Registration for the fall session of
programs will commence on August 6th for general recreation programs and
aquatic leadership classes and August 23rd for children's swim lessons.
Departmental program registration can occur through the "Eazy Reg" telephone
line (905-623-3299), on-line www.c1arinatoneazvreg.ca or in person at the
Community Services Department administration office or any existing recreation
centre. (Note: registration will not be available at the Newcastle & District
Recreation Complex until September 2nd).
5.2 The fall session of recreation programs will be promoted through the Clarington
Community Recreation and Leisure Guide (Fall 2008) which will be delivered to
homes in Clarington in their Clarington This Week, on August 6th.
5.3 The programs currently planned for the Newcastle & District Recreation Complex
cover a wide range of activities; some examples would include: swimming
lessons, youth sports (basketball, floor hockey, badminton, dodgeball), general
REPORT NO.: CSD-019-08
PAGE 4
youth programs (after-school, crafts), adult sports (basketball, volleyball,
badminton, floor hockey), birthday parties, aquafit and group fitness classes.
5.4 The Community Services Department is currently consulting with existing
recreation partners to pursue opportunities to provide additional recreation
activities for older adults and pre-schoolers/parent and tot programs.
5.5 Pool schedules have also been included in the Fall Recreation and Leisure
Guide and have been developed on the same basis as existing schedules at the
Courtice Community Complex and Clarington Fitness Centre. The schedule
includes public swims (general public - all ages), adult swims (18+ years), lane
swims (all ages - swimmers must be continuously swimming lengths) and
adult/lane swims (2 lanes for swimming lengths, 1 open lane - youth may attend
but must swim lengths). For the fall session this facility will also offer an older
adult swim (50+ yrs) which is a new swim not currently offered at either of the
existing two pools. The pool schedules will commence with the opening of the
facility on September 2nd.
5.6 From the facility opening through to the start of programs there will be a number
of opportunities for the community to view the facility and try a class at no cost.
From September 6th to September 18th the Community Services Department will
be promoting a sampling of fall programs to encourage participation in the fall
session.
6.0 OFFICIAL OPENING
6.1 The facility's Grand Opening will be held on Saturday, October 4, 2008. As
details regarding the official ceremonies and the day's program and activities are
confirmed, Council will be advised.
6.2 Staff will be working with the Newcastle BIA to coordinate activities to
complement Newcastle's Fall Festival that same weekend, which attracts up to
4,000 people annually. Staff look forward to planning a great community event,
which will surely be well attended with the added volume of people in the area for
the Newcastle Fall Festival.
7.0 COMMENTS
7.1 Prior to the opening of the building to the public, a site tour will be scheduled for
members of Council. Details will be forwarded when they are confirmed.
7.2 Although the project has been challenged by a number of factors, staff continue
to work diligently to stay within the approved project budget.