HomeMy WebLinkAboutTR-16-98
UNFINISHED BUSINESS
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
REPORT
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
AI90L
File # F" ~'i5. Q\ ^-
o p - l':~?3..::-g"l\"'-
Res.# 6~A -/50 -q~
Date:
MONDAY, MARCH 2, 1998
Report #:
TR-16 - 98 File #:
By-Law #
Subject:
TENDER CL98-1, OLDER ADULTS CENTRE
Recommendations:
It is respectfully recommended that the General Purpose and
Administration Committee recommend to Council the following
FORTHWITH:
1. THAT Report TR-16-98 be received;
2. THAT Gerr Construction Limited, Bowmanville, Ontario,
with a total bid in the amount of $859,500.00 (plus
G. S. T. pending determination of applicability) , being the
lowest responsible bidder meeting all terms, conditions
and specifications of Tender CL98-1, be awarded the
contract for the construction of the Older Adults Centre;
3. THAT total funds required in the amount of $955,500.00
($859,500.00 contract + $6,000.00 asbestos removal +
$90,000.00 consulting) be provided as follows:
$912,000.00 - 1997 Capital Budget, Impact Escrow Reserve
Fund, Account #5001-00050-0000;
$ 65,000.00 - Additional Funds, Impact Escrow Reserve
Fund, Account #5001-00050-0000.
4. THAT approval be given for staff to negotiate and draft a
leasehold improvement agreement and funding arrangement;
5. THAT the attached By-law marked Schedule "A" be approved;
and
6. THAT the leasehold improvements totalling approximately
$31,000.00 be interim financed from the Impact Escrow Account,
included in the lease cost, and repaid to that account over
the initial term of the lease agreement.
BACKGROUND AND COMMENT:
Tenders were publicly advertised and issued for the renovation of
the existing Lions Club building to accommodate the Older Adults
Centre, as provided for in the 1997 Capital Budget.
REPORT NO.: TR-16-98
PAGE 2
Subsequently, bids were received and tabulated as follows:
..'1'O'1'A.t......SID.......UOUN'!'...
Corzam Construction Limited $1,189,000.00
Concord, Ontario
Frank Pellegrino General Contracting Limited $1,211,374.50
Toronto, Ontario
Gerr Construction $1,236,000.00
Bowmanville, Ontario
Snyder Construction $1,323,120.00
Whitby, Ontario
Pegdon Construction Limited $1,420,300.00
Mississauga, Ontario
A.G. Reat Construction Limited $1,420,300.00
Concord, Ontario
Richard & B.A. Ryan Limited $1,480,900.00
Toronto, Ontario
Gay Construction Limited Bid Rejected
Oshawa, Ontario
As all of the tenders were over the total budget allocation, in
accordance with the process recommended by the Durham Construction
Association, two post tender addendums were issued to the three low
bidders.
Based on acceptance of the deletions as well as suggestions by each
of the bidders, the revised tender amounts are as follows:
TOTAL BID AMOUNT.
Gerr Construction Limited $865,975.00
Bowmanville, Ontario
Frank Pellegrino General Contracting Limited $918,722.50
Toronto, Ontario
Corzam Construction Limited $966,088.00
Concord, Ontario
REPORT NO.: TR-16-98
PAGE 3
As the revised bid amount of the low bidder, Gerr Construction, was
now within 7% of the total budget allocations, negotiations were
entered into with the low bidder to further reduce the total cost.
Subsequently, the negotiated revised total bid amount is now
$859,500.00. A FORTHWITH approval will allow the contract award
paperwork to commence, however the By-law will not be approved
until the Council meeting of March 9, 1998.
The reductions included are outlined in the attached letter, marked
Schedule "B", from the consultant, Barry Bryan Associates.
Note, for the information of Council, the original tender documents
included in the stipulated price, the cost of a new elevator shaft
located in the centre of the building and up to the underside of
the first floor roof. The elevator shaft was located to satisfy
the wish of the Building Committee that ultimately the elevator
would access all floors of the building. The cost of the elevator
shaft and associated mechanical and electrical services has not
been included in the revised tender amount which resulted in a
reduction of $60,000.00. Also, the front entrance, lobby and
lounge area has been deferred to Phase Two which resulted in a
savings of $160,000.00.
Should Council choose to include either or both of these items,
then this report must be referred back to staff for a further
review due to the uncertainty of who would qualify as the low
bidder.
Should the elevator not be included at this time, the cost of
adding it in future phases will be greater than the reduction
achieved by deleting it from the initial construction. In
addition, an alternate location in the building would have to be
found, which would eliminate the initial objective of full access
to the entire building.
REPORT NO.: TR-16-98
PAGE 4
Council expressed at the meeting of July 7, 1997 and as identified
in Admin-49-97, that the main floor of the centre would be the
first stage of development of the Older Adults Centre. A phasing
program was suggested in order to fully incorporate the entire
building to meet the needs of the seniors.
If Council does not include either the front lobby or elevator
structure in Phase One, it would be recommended in a revised Phase
Two as early as 1999, pending Municipal Budget deliberations.
The Municipality will also enter into negotiations with the
Clarington Community Care with respect to their lease and interior
finishes which have been deleted and will be treated as leasehold
space. Staff are recommending that the interior finishes be added
to the contract and that a leasehold improvement cost, estimated to
be $31,000.00, be incorporated in the lease agreement which would
repay the cost over the initial term. It is recommended that these
additional costs be interim financed from the Impact Escrow Account
and repaid to that Reserve Fund when they are received through the
lease paYments.
It is recommended that the total required funds in the amount of
$955,500.00 ($859,500.00 contract + $6,000.00 asbestos removal +
$90,000.00 consulting) be provided as follows:
$912,000.00 - 1997 Capital Budget, Impact Escrow Reserve
Fund, Account #5001-00050-0000;
$ 65,000.00 - Additional Funds, Impact Escrow Reserve
Fund, Account #5001-00050-0000.
The additional $65,000.00 represents a contingency value of
approximately $35,000.00 which will only be expended if
unanticipated problems arise during construction and an additional
$10,000.00 is required for the contract. There are additional
legal costs of approximately $20,000.00 due to the extensive
negotiations, etc. which were not anticipated in the original
budget review.
REPORT NO.: TR-16-98
PAGE 5
The Treasurer has reviewed the funding requirements and concurs
with the recommendation. The additional funds are recommended to
be financed from the interest earned on the original $1.3 million
allocated to the project. The interest of approximately $48,000.00
has been accumulating to the Impact Escrow Fund because the funds
have not yet been required. Therefore, it would be appropriate to
fund the additional requirements from the same account. Note,
there is no G.S.T. component included in the cost as it is the
opinion of staff that 100% Input Tax Credit rebate is applicable,
however, this has not yet been confirmed. If it is not applicable,
then the 57% rebate will apply. Queries with respect to
specifications, etc., should be referred to the representative from
Barry Bryan Associates.
The low bidder has previously provided satisfactory service to the
Municipality of Clarington.
After further review and analysis of the bids by the Consultant,
Barry Bryan Associates, Purchasing, and the Property Manager, it
was mutually agreed that Gerr Construction, Bowmanville, Ontario,
be recommended for the contract for the construction of the Older
Adults Centre.
Re/7fullY
,fj~~
Marie Marano,
Treasurer
submitted,
Reviewed by,
H . BSc . , AMCT . ,
~
W . H. ' ... tockwe, .
Chief Administrative Officer
R.R.F.A.
MM*LB*ld
SCHEDULE "A"
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW NUMBER 98-
Being a By-law to authorize a contract between the Corporation
of the Municipality of Clarington and Gerr Construction
Limited, Bowmanville, Ontario, for the construction of the
Older Adults Centre.
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY
ENACTS AS FOLLOWS:
1. THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington, and seal with the Corporation Seal,
a Contract between Gerr Construction Limited and said Corporation; and
2. THAT this agreement attached hereto as Schedule "A" form part of this By-law.
By-law read a first and second time this day of March, 1998.
By-law read a third time and finally passed this
day of March, 1998.
Mayor
Clerk
FEB.:-26'981THUlI4:19
BARRY-BRYAN ASSOCIATES
SCHEDULE "8"
BARRY. BRYAN
ASSOCIATES (J99Jj LIMITED
" ARCHITECT
· ";NC3INEER
" PROJECT MANAGERS
Municipality of Clarington
40 Temperance Street
Bowmanville, Ontario L 1 C 3E8
Attention:
Ms. Lou Anne Birkett
Purchasing Manager
Re: Clarington Older Adult Centre
Municipality of Clarington
CL98-1
Dear Ms. Birkett:
TEL:9056665256
P. 001
11 Stanley Court
Whl/by, Ontario L1N 8P9
Telephone (005) 866-5252
Fax (905) 666-5256
February 26, 1888
Tenders for the Clanngton Older Adult Centre, Tender CL98-1 were received by the Municipality
of Clarington on February 4, 1998.
Eight Tenders were received. One tender was rejected by the Municipality. The Stipulated Prices
for the seven remaining tenders were as follows:
CORZAM CONSTRUCTION LIMITED
FRANK PELLEGRINO GENERAL CONTRACTING LIMITED
GERR CONSTRUCTION LIMITED
SNYDER CONSTRUCTION
PEG DON CONSTRUCTION LIMITED
A.G. REA T CONSTRUCTION CO. LIMITED
RICHARD & B.A. RYAN LIMITED
$1.189,000.00
$1,211,374.50
$1,236,000.00
$1.323,120.00
$1.420,300.00
$1,430,000.00
$1.480,900.00
All Tender prices include P.S.T. and are exclusive of GS.T.
All Tender prices include cash and contingency allowances in the amount of $50,000.00.
All tenderers acknowledged receipt of Addenda 1 to 3.
Fallowing review of the Stipulated Tender prices, Post Tender Addenda Numbers 1 and 2 were
issued to the three low bidders. The object of the Post Tender Addenda was to identify cost
savings which would bring the Tender Price in line with the amount budgetEj'd by the Municipality
for the first phase of this project.
During this period, Barry Bryan Associates (1981) LimitEd conducted a detailed review of the
Tenders and checked the references of the three low bidders.
,/260'--5.wpd
FEB..-26'98lTHUI 1~:19
BARRY-BRYAN ASSOCIATES
TEL:9056665256
P. 002
Page 2
On February 13 and February 19,1998, Post Tender Addendum Pricing was received from the
invited bidders by the Municipality of Clarington. Pricing included possible cost savings identified
in the Addendum and add-on pricing requested by the Municipal Building Department. Bidders
were also invited to suggest additional cost savings for consideration.
Our findings and recommendations are as follows:
1. REFERENCES:
Detailed reference checks were completed for the three low bidders.
Bidders were required to submit with the Tender, a list of recently completed projects of
similar scope to the Older Adult Centre. We also contacted the Toronto! Peterborough and
Durham Construction Associations. Additionally, inquiries were made within the Bonding
industry.
GERR CONSTRUCTION LIMITeD has prior experience working with the Municipality of
Clarington. Barry Bryan Associates has worked with this contractor on several occasions
and is confident of their ability to perform the work required on the Older Adult Community
Centre.
2. PRICING:
Tender Pricing has been evaluated using a combination of the Stipulated Tender Price,
the Separate and Altemate Price items listed on page 2{R) of the Tender Form and the
Post Tender Addendum pricing received from the three low bidders on February 13 and
19, 1998.
Post tender Addendum items ware evaluated by the Municipality in conjunction with Barry
Bryan Associates and our Consultants with the aim of maintaining the approved budget
for the first phase of the project while getting the best value for the Municipality. Given the
number of options available for selection I a summary of prices was developed to assist In
the evaluation.
Some of these Items it must be noted are "add" costs which are the result of changes
requested by the Municipality of Clarlngton Building Department. These Items are not
optional and must be Included in the price. They are identified separately in the attached
table of prices. Additional add on prices are identified as Alternate Prices in the Tender
Forms.
The three law bidders were invited to suggest additional cost savings for consideration. Not
all items were suggested by all bidders.
Pest Tender Addendum number 2 was issued on February 18, 1998 and Includes items
which duplicate either in whole or in part, items previously identified in the Tender forms
and in Post Tender addendum number 1.
7175L.21lO2.S .wpd
@
BARRY. BRYAN
ASSOCIATES (19911 LIMITeD
FEB..-?'6' 98lTHUl 14:20
BARRY-BRYAN ASSOCIATES
TEL:9056665256
P. 003
Page 3
Additional possible cost saving items have been further identified in the course of our
discussions with the bidders and with the Municipality.
It should also be noted that Post Tender Addendum item number 19 includes the removal
from the project of the entire northerly addition. This part of the work Includes a new exit
stair from the second noor which can not be deferred until future phases of the overall
project. This stair is necessary to ensure safe egress from the second floor of the existing
building and Is a condItion of the Building Department approvals.
FinallY, as you are aware, the deletion of several i~ems from tha current phase of the work
will result in additional costs during futl.lre phases. It is much more cost effective to
complete the6e items during the major reconstruction and alteration phase of the project
than to attempt to retrofit the building later on. In particular, construction of the elevator
shaft as it is currenijy located will resl.Ilt in significant cost Increases and disruptions during
the next or any other phase.
4. RECOMMENDATIONS:
In consultation with the staff of the Municipality of Clarington we have prepared a summary
of recommended or acceptable prices. Based on the items accepted, the revised
Stipulated prices for the three low bidders are:
CORZAM CONSTRUCTION LIMITED
FRANK PELLEGRINO GENERAL CONTRACTING LIMITED
GERR CONSTRUCTION LIMITeD
S98S,088.00
$818.722.50
$865.975.00
On review of the tenders and the supplemental price details, with staff of the Municipality of
Clarington, the Municipality entered into nego~aticns with the low overall tenderer, Gerr
Constn.lction Limited resLlltlng in a revised tender amount of $859,525.00 (The items included in
this price are described in the attached AppendiX A.) and we recommend acceptance.
CME/cb
7176l.2aO~.S.wpd
@
BARRY. BRYAN
ASSOCIATES 119911 LIMITED
FE B, .- 26' 9 8 IT H U l 1 4 : 20
BARRY-BRYAK ASSOCIATES
TEL:9056665256
P. 004
CLARINGTON OLDER ADULT COMMUNITY CENTRE
26 BEECH AVENUE, BOWMANVlLLE
MUNICIPALllY OF CLARlNGTON TENDER CL 98-1
Page 1 of 3
APPENDIX 'A'
I ITEM COMMENTS
TENDER PRiCe
Separate Price 9,O,8 Delete ope,.,.bls partition number 1 and track.
POST TENDER ADDENDUM *1
A.1 Add 2nQ FI renovations Building cede requirement
A.3 Door'# 25 Change swing of door Building code requirement
C,1 Screen SC? Building code requirement
DR.1 Sheet Floor Refinish existing hardwood in lieu of vinyl
DR.2 Carpet 1 Change Allowance to $20/s.yd.
DR.3 Carpet 2 Change Allowance to $26/s.yd.
ORA Vestibule Leave vestibule as is
DR.7 Operable. Partition No, 2 Delete track and bulkhead
DR.S Oelete 2 Windows Activity Room 128. south wall
Oft 9 Oelete 3 Windows Dining Room 118, north wall
DR.10 Bow windows Use standard window In lieu of bow window
DR.12 Frame colour in lieu of custom colours specified
OR.13 Standard Windows in lieLl of custom sizes specified
DR.14 Brickmould Delete
DR.15 Paint Grade Doors in lieLl of stain grade (includes painting)
DR.16 Backfill Reuse existing
DR.17.1 Cabinetwork Change quality of cabinetwork
DR.17.2 Cabinets (130) Delete cabinets on north wall
DR.17.4 Splash backs Change to 4" high.
DR.18 Elevator shaft Delete entire shaft and associated
mechanical/electrical work, to second floor
MECHANICAL
M3. Humidifiers Delete four humidifiers and drains
M9, coa Controls
71751.2802-5 ummllIV.wpd
BARRY. BRYAN
ASSOCIAT!:S (19911 LIMITED
rlA
FEB,. - 2,6' 98 ITHUI 14: 21
BARRY-BRYAN ASSOCIATES
TEL:90S666S256
p, DOS
CLARlNGTON OLDER ADULT COMMUNITY CENTRE
28 BEECH AVENUE, BOWMANVILLE
MUNICIPALITV OF CLARINGTON TENDER CL 98.1
Page 2 of 3
APPENDIX 'A'
ITEM COMMENTS
M 11. Water Cooler Delate drinking fountain, piping and drain
M12. Exist radiator Leave radiator in place
ELECTRICAL
E1. Tennis Ct sarvice Delete new service,
E2. Add Exit l.lght Add light required by Sullding Code.
ES. Water Cooler.
E6. Humidifiers Delete power to humidifier
POST TENDER ADDENDUM '2
DR.19 North Addition Delete north addition including reception and
lobby.
DR.21 Community Care Delete all interior finishing of suite
71715L2IOZ.Summ.ry,wpd
BARRY. BRYAN
ASSOCIATE5 119911 ~IMITED
~
FBB,-26'98rTHUI14:21
BARRY-BRYAN ASSOCIATES
TEL:9056665256
P. 006
.
.
CLARINGTON OLDER ADULT COMMUNITY CENTRE
26 BEECH AveNUE, BOWMANVILLE
MUNICIPAllTV OF CLARINGTON TENDER CL. 98~1
Page 3 of 3
APPENDIX lA'
ITEM COMMENTS
BIDDER SUGGESTIONS
2. Roof warranty 2 year in lieu of 5 year
4. Acoustic tile
. 11. Metsl curb Use wood curbs at roof
14. Del. Ceramics Paint washrooms only
ADDITIONAL ITEMS
1. Region allowance Delete allowance for street connections
2. Sign allowance Delete sign allowance
3. Services Delete new buried services
4. Sheet flooring Change grade of material
5. Delete Asphalt paving
6. Delete sodding Rough grade only
7. Add stairs to second floor Building code requirement
8. Change HRV unit (Activity and Dining Install 25 ton HVAC unit in lieu of specified item.
room 5)
717S1..2l102oSummllry.wpcl
BARRY. BRYAN
ASSOCIATES (19911 LIMITED
@