HomeMy WebLinkAboutCOD-050-07 Addendum
UNFINISHED BUSINESS
Cl~mgron
REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
Council
Date:
October 29, 2007
Resolution #:
Report #: COD-050-07
File#:
By-law #:
Subject:
Addendum to Report COD-050-07
Recommendations:
It is respectfully recommended that Council approve the following:
1. THAT Report COD-050-07 be received as amended by recommendations in
Addendum to Report COD-050;
2. THAT the recommendations outlined in the Addendum to Report COD-050-07 be
approved;
3 THAT the verbal report by Gerry Shoalts, Architect, be received;
4. THAT the tender bids received for Tender CL2007-42 be rejected;
5. THAT Council formally confirm the revised Capital Budget Amount of
$3,450,047.00
6. THAT Council provide direction in the re-issuing of the tender, to design the
Newcastle Library as either a
a) LEED Certified building; or,
b) A green building
7. THAT Council authorize the Newcastle Library Building Committee to re-scope
the Newcastle Library based on Recommendation #4; and to re-issue the tender
in early 2008 to the same seven pre-qualified general contractors;
8. THAT the previously awarded consultant's contract with Shoalts Zaback
Architects Ltd, Kingston, Ontario, be amended to include the additional design
fees of $37,500.00; and,
9. THAT the previously awarded consultants contract with Shoalts Zaback
Architects Ltd, Kingston, Ontario also be amended to include $68,000.00 for
LEED design by sub-consultants' work; plus an amount of $60,000.00 for the
LEED Application and Registration, Energy Modelling and Commissioning,
including work undertaken to date, without impact to the project budget; and,
10. THAT the attached By-law marked Appendix "A" authorizing the Mayor and Clerk
to amend the existing contract agreement between Shoalts Zaback Architects
Ltd. and the Municipality of Clarington be approved.
Submitted by:
Q _ on ~ 1'_
Reviewed b . ~ lA..) (,(.
ranklin Wu
Chief Administrative Officer
rie Marano, H.B.Sc., C.M.O.
Director of Corporate Services
MM/EH/JB/BT/gj
Attachments:
Attachment #1 - Report COD-050-07
Attachment #2 - Report COD-027-07
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-5506
REPORT NO.: Addendum to COD-050-07
PAGE 3
1.0 BACKGROUND
1.1 At the September 24, 2007 Council Meeting, The Newcastle Library Building
Committee brought forward report #COD-050-07 (Attachment #1) with several
recommendations related to the Newcastle Library Capital Project. The
recommendations in report COD-050-07 have been included with some
amendments into this addendum report. The Architect, Gerry Shoalts is in
attendance to provide some background to Council regarding the details of the
market conditions which contributed to the escalated bid prices to the budget.
1.2 At that meeting, Council expressed a number of concerns regarding the tender
prices and directed the Newcastle Library Building Committee to report back
directly to Council with a more detailed explanation as to why the prices were
higher than the Consultant's estimates.
2.0 TENDER PRICING
2.1 The Building Committee has met with the Consultant to review to Council's
concerns. The tender documents were all-inclusive for the construction of the
Newcastle Branch Library. The primary causes of the tenders being in excess of
the construction budget were the extremely unusual market conditions. The
architect hired an independent cost consultant (M. J. Brennan & Associates,
Kingston, ON) to provide construction estimates for the project. This firm is
familiar with costing within the GTA area and provided estimates for each
construction division within the scope of the Library.
2.2 Some of the pre-qualified bidders advised the Municipality they were
experiencing difficulty in obtaining quotes from their suppliers. Of the seven pre-
qualified bidders, 2 submitted their bids on time, 1 was late submitting their bid, 1
was delayed by traffic, 1 could not obtain bids in all divisions, and 2 withdrew
earlier in the process due to commitments to other projects. The Municipality
only deals with the General Contractor and therefore generally does not have
access to their actual bid numbers of the sub-trades. With the lowest bidder, the
following areas were over projections; steel (48% over), painting (136% over),
drywall (112% over), floor finishes (89% over), windows and doors (26% over) as
well as masonry (33%). The combined net impact of these items to the budget is
$376,894.00.
2.3 In addition to reviewing the tender price components with the Consultant, the
Building Committee conducted preliminary exploration with the lowest bidder to
determine the feasibility of reducing the tender price. While the lowest bidder
was prepared to review his tender pricing, he was not sure that he could
establish sufficient reductions without other changes to the design. This caused
concern as we could only negotiate up to 15% of the contract value. The tender
document for this project states if the changes contemplated are in excess of
15% the bid documents may be amended and invitations to re-bid would be
issued. After explorations with the lowest qualified bidder, the Newcastle Library
Building Committee determined that in all likelihood, we would not reach 15%
REPORT NO.: Addendum to COD-OSO-07
PAGE 4
through efficiencies. Therefore structural changes would be required. Those
structural changes would significantly change the building design and would
therefore be greater than the permitted 15% amount.
2.4 The Purchasing Manager requested an opinion from the Town Solicitor in which
we were advised the compliant tenders could be rejected by the Municipality
provided this was done so prior to any negotiations with the lowest compliant
bidder. In doing so, the Municipality may then re-scope the work and invite the
pre-qualified contractors to submit bids in response to revised tender documents
as recommended in Report # COD-050-07.
2.5 The Purchasing Manager also requested an opinion from the Town Solicitor in
regards to the terms of the tender and to re-issue the Tender documents to the
pre-contractors. The tender document states the tender can be re-issued to the
three (3) qualified low bidders. As there were only two (2) qualified low bidders
the Town Solicitor advises the Municipality may re-scope the work and invite the
pre-qualified contractors to submit bids in response to revised tender documents
as recommended in Report COD-050-07.
3.0 CAPITAL BUDGET AMOUNT
3.1 As advised in COD Report #COD-050-07, the 2006 Capital budget provided
funds in the amount of $2,788,604.00. This amount was based on construction
costs of the day and was comparable to other projects at that time. The original
2006 Capital Budget did not include the scope of work for a LEED Certified
Building ($359,000.00) nor did it take the remedy for poor site conditions into
consideration ($100,000.00). In addition, construction costs for labour and
materials have escalated substantially by approximately $202,443.00 and
revisions to the budget were reviewed at the October 2006 Building Committee
meeting. At that meeting these items were reviewed and budget adjustments
were recommended in the additional amount of $661,443.00 as referenced in
Report COD-027-07 (Attachment #2) reviewed by Council on June 25, 2007.
Confirmation of this budget amount is required at this time.
4.0 IMPACT OF LEED
4.1 The overall impact of LEED (Leadership in Energy and Environmental Design) to
this project is estimated at $359,000.00. This amount consists of a differential in
building components ($231,000.00), LEED registration, modeling, commissioning
and point verification ($60,000.00) as well as additional design fees ($68,000.00)
4.2 The amount of $231,000.00 for differential building costs is the difference
between standard construction and LEED design. This amount includes the
following items:
. Storm Water Management (Quantity and Quality Control) $ 50,000.00
. Mechanical Systems $ 75,000.00
. Electrical Systems $ 36,000.00
. Architectural Components (Roofing, Windows,
REPORT NO.: Addendum to COD-050-07
PAGE 5
Building Envelope, Insulation, Green Materials & Finishes)
. Contractor Administration (Additional Contractor Expenses)
$ 60,000.00
$ 10,000.00
4.3 As indicated, the LEED application process requires the Architect to design the
building and its infrastructure to comply with criteria established by the Canada
Green building Council. In order for the application to qualify, the Architect must
prepare energy models, design the building to certain specifications; and,
ultimately prove the building is functioning as designed. A number of these steps
have already been undertaken to create the building specifications. The overall
cost for these steps is in the $60,000.00 range.
4.4 The final component to the LEED program is the additional design fees of
$68,000.00 for sub-consultants work for the inclusion of the LEED program. As
indicated, when hired, LEED was not included in the original Architects RFP.
Since that time, the Building Committee determined LEED was a desirable
program to embrace in the interest of conservation and sustainable buildings. As
such, the Architect and sub-consultants undertook additional time and material to
develop a LEED program for this building and these fees are in addition to the
original Architect's contract.
5.0 LEED VS. GREEN BUILDING
5.1 The Newcastle Library Building Committee is seeking direction from Council
regarding construction of a LEED Certified Building; or to design a green
building. For several reasons, LEED is a very desirable concept in building
construction, sustainability; and for the community as identified in the Corporate
Business Plan developing a Green Community Strategy.
5.2 However, the Architect has indicated the Newcastle Library could be constructed
as a green building, adhering to the principals of LEED, but without the
Certification. By doing so, approximately $50,000 to $60,000 would be saved in
modeling, testing, commissioning and verification costs.
5.3 As such, the Building Committee requests Council direction in this regard. If
Council desires a LEED Certified project, additional design changes will be taken
into consideration. If a green building is acceptable, the savings from not
proceeding with the testing, commissioning and verification could be applied to
the construction budget.
6.0 PROCEDURES TO RE-TENDERING IN EARLY 2008
6.1 The Architect feels that with competitive bidding, the tender prices will more
reflect the construction budget amount.
6.2 In addition, re-tendering at this time is beneficial as contractors will be bidding for
work in the spring; and, all seven pre-qualified bidders are expected to submit
competitive bids. The Architect is proposing to make optional changes to the
REPORT NO.: Addendum to COD-050-07
PAGE 6
construction materials and methods without compromising quality, bearing in
mind that some material costs may escalate by the time we re-tender. These
optional changes will be reviewed by the Building Committee for selection and
approval.
6.3 Significant components such as the pitched roof over the main library space and
clay brick, which is comparable to surrounding structures, will be retained.
7.0 ADDITIONAL CONSULTANTS FEES
7.1 The consultant has reviewed the additional fees associated with the increased
redesign of the building. As indicated in Report COD-050-07, the consultant
estimated an amount $75,000.00, however, the consultant has advised his fee
will be $37,500.00 and he will absorb any additional costs in excess of this
amount.
8.0 FINANCIAL IMPACT
8.1 The Director of Finance has reviewed the options described for a LEED Certified
Building and a green building. The Director of Finance confirms the proposal for
a green building continues to meet the intent of the funding from the Municipal
Government Enterprise Reserve Fund.
8.2 All other funding sources identified in Report COD-050-07 remain as
recommended by the Director of Finance.
9.0 CONCLUSION
9.1 The Building Committee will report back to Council for approval when the project
has been re-tendered.
Attach.#l to Addendum COD50-07
Cl!Jl-/l]glon
REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
Council
Date:
September 24, 2007
Resolution #:
Report #: COD-050-07
File#:
By-law #:
Subject:
Tender CL2007-42 - Newcastle Library Capital Project
Recommendations:
It is respectfully recommended that Council approve the following:
1. THAT Report COD-050-07 be received;
2. THAT the Tender Bids received for Tender CL2007-42 be rejected;
3. THAT Council formally confirm the revised Capital Budget Amount of
$3,450,047.00
4. THAT Council authorize the Newcastle Library Building Committee to re-scope
the Newcastle Library project and to re-issue the tender to the same pre-qualified
general contractors early 2008.
5. THAT the previously awarded consultant's contract with Shoalts Zaback
Architects Ltd, Kingston, Ontario; be amended to reflect the additional design to
an maximum amount of $75,000.00; and, to include LEED design work in the
amount of $68,000.00 plus $60,000.00 for the LEED Application, Energy
Modelling and Commissioning without impact to the project budget; and,
6. THAT the attached By-law marked Appendix "A" authorizing the Mayor and Clerk
to amend the existing contract agreement between Shoalts Zaback Architects Ltd
and the Municipality be approved.
/
Submitted by: ~ll70-0-
Marie Marano, H.RSc., C.M.O.
Director of Corporate Services
C~illJ-~_~~~
fNancy Taylor, B.B.A., CA,
t 'Director of Financerrreasurer
MM/JB/EH/BT Ig]
0'" . #(\~.
/~~ __ --V(.
Reviewed b .' 0
Franklin Wu
Chief Administrative Officer
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-5506
REPORT NO.: COD-050-07
PAGE 3
1.0 BACKGROUND
1.1 In February, the Municipality advertised for; and, pre-qualified seven contractors
to submit bids. Since that time, two firms had advised they were unable to bid
due to other commitments.
1.2 Tender CL2007-42 for the construction for the Newcastle Branch Library was
advertised and issued to pre-qualified contractors with bids being received on
September 6, 2007; as per Schedule "A".
1.3 At the bid opening, only three submissions were received. Two of the bids were
submitted on time; with one bid being rejected as it was submitted late.
1.4 As noted on Schedule "A", the two qualified bids were in excess of the funds
allocated to the construction budget amount $2,648,895.00
2.0 BIDS ANALYSIS
2.1 As indicated, the two qualified bids that were received are in excess of the
construction budget. Following the opening, the Consultant contacted the
remaining pre-qualified bidders to determine why bids were not received. They
both indicated they were experiencing difficulties in obtaining quotes for materials
and one indicated that he missed the closing deadline due to timing and heavy
traffic.
2.2 Other contributing factors to the high bid amounts were costs related to
addressing the soils conditions, increased construction costs since establishing
the original construction budget; and, unexpected costs related to certain
materials required for the project. Steel, drywall, painting and floor finishes were
well in excess of estimates prepared by the Consultant during the pre-
construction cost analysis.
2.3 While the Municipality reserves the right to negotiate with the lowest bidder;
given the projected scope of changes, it was determined this would not be a
prudent course of action in this case as we would not expect to generate the
required reductions.
2.4 The Newcastle Library Building Committee is aware of the financial concerns
within the Municipality as outlined by the Director of Finance; and, for this reason,
recommend that Council reject both bids; and, authorize the Building Committee
work with the Consultant to re-scope the project in order to bring it in-line with the
financial resources allocated to the project.
2.5 The Building Committee is recommending the tender be re-issued in early 2008;
and that the same seven pre-qualified contractors be given the opportunity to bid
on the revised project.
REPORT NO.: COD-050-07
PAGE 4
3.0 SCOPE OF WORK
3.1 In order to bring the project in-line with the financial resources, the Building
Committee has reviewed a number of options. The Committee recommends re-
scoping the project design through a number of changes to the building
components. In order to do so, the Consultant will re-design the building with
staged reductions, possibly including a reduced floor space and changing to a
flat roof.
3.2 In consideration of the above, these adjustments will allow us to re-tender the
project in early 2008 for construction.
4.0 DESIGN
4.1 In order to achieve the desired results, the Consultant will re-scope the project
design within the financial resources. This will require a significant amount of
work by the Consultant including redesign and revisions and to re-issue the
tender documents tender drawings. Accordingly, the Building Committee is
recommending the Consultant's contract be amended to reflect this increased
scope of work to an up set limit amount of $75,000.00 to be drawn from the
existing project account # 110-42-440-85510-7401.
4.2 At the award of the Consultant's Contract to Shoalts Zaback Architects Ltd, the
Municipal Building Committee had not included the LEED (Leadership in Energy
and Environmental Design) green building program. Through the design
concepts prepared by Shoalts Zaback Architects, it was determined by the
Committee; and, presented to Council in December 2006; the Newcastle Branch
Library would qualify as a LEED Certified Building, demonstrating the
Municipality's commitment to conservation and sustainable buildings.
4.3 The initial consultant's contract did not include fees for the additional scope of
work for LEED development; nor did it include fees for the sub-consultants
working with Shoalts Zaback Architects for the preparation of LEED design work
and tender documents as required by the Canada Green Building Council for
approval.
4.4 The revised project budget presented at an October 2006 Building Committee
meeting at which a number of both the Library Board and Council members were
present. At that meeting the Consultant identified the necessary funds for the
LEED application should the Building Committee determine the LEED process
was viable. The budget includes $60,000.00 for LEED application process,
energy modelling and commissioning, $68,000.00 for the Consultant and their
sub-consultants for the design phase, construction and specifications documents
as well as construction administration.
4.5 The Engineering Department is also recommending future project work for the
proposed Newcastle Memorial Park Soccer Field be included within the scope of
REPORT NO.: COD-050-07
PAGE 5
this work however to be funded from a separate account to be approved during
the 2008 Capital Budget deliberations.
5.0 PROJECT BUDGET
5.1 At the referenced October 2006 Building Committee meeting, the project budget
was reviewed. The 2006 Capital budget provided funds in the amount of
$2,788,604.00. At Library Board meeting, a number of items were reviewed and
budget adjustments were recommended in the additional amount of $661,443.00
based on a number funding sources suggested by the Director of Finance
bringing the total project amount to $3,450,047.00. This was referenced in
Report COD-027-07 approved by Council June 25, 2007.
5.2 As the Building Committee had recommended construction of a LEED Certified
Building, funding from the Municipal Government Enterprise Reserve Fund would
be allocated to the capital cost difference in the amount of $285,000.00.
5.3 The Library Development Charges financing was also adjusted to reflect future
capacity requirements in the additional amount of $178,810.43. This is in
addition to the original budgeted amount of $1,405,456 and will result in an
estimated debenture of $1,584,266.43 once the tender is awarded. This is
determined based on the non-replacement square footage cost share at the
mandatory 90% eligibility for development charges funding. However, this is
substantially in excess of the original amount determined in the 2005
development charges background study of $1,210,500. There is no opportunity
to increase this amount further as there will be a shortfall in the Library
Development Charges Reserve Funds in the foreseeable future. Some provision
for this was incorporated in the 2007 budget. This will limit future library growth
related projects until such time as the future Development Charges growth
reflects this capacity.
5.4 Additional funds were also identified from the Capital Works Reserve Fund in the
amount of $98,816.29 and the General Municipal Reserve Fund in the same
amount of $98,816.29 in addition to the original budget amount for the non-
growth share at 10% and the replacement square footage at the existing
Newcastle Branch Library that cannot be attributed to future growth.
5.5 The Director of Finance concurs with these recommendations and funding
sources. However, as noted, there is no opportunity to increase this amount
further from a development charges perspective.
REPORT NO.: COD-050-07
PAGE 6
6.0 CONCLUSION
6.1 The Building Committee will report back to Council for approval when the project
has been re-tendered.
REPORT NO.: COD-OSO-07
PAGE 7
u
Leading the Way
Municipality of Clarington
Schedule "A"
Bid Summary
TENDER CL2007-42
GENERAL CONTRACTOR FOR THE CONSTRUCTION OF
THE NEWCASTLE BRANCH LIBRARY
Bidder Bid Amount
(Excludina GST)
Aecon No Bid
Garritano Bros. Ltd. Bid Rejected
Gerr Construction Ltd. $ 3,025,000.00
J. J. McGuire Ltd., No Bid
Mitren No Bid
Pre-Eng Contracting Ltd. $3,310,000.00
Strut-Con Constructions Ltd. No Bid
*GST Extra
REPORT NO.: COD-050-07
PAGE 8
Appendix "A"
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW 2007-
Being a By-law to authorize an amendment to the contract between the
Corporation of the Municipality of Clarington and Shoalts Zaback
Architects Limited, Kingston, Ontario, to amend the agreement for
Architectural Services for the Newcastle Branch Library.
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY ENACTS
AS FOllOWS:
1. THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington and seal with the Corporation Seal,
an amendment to the contract between Shoalts Zaback Architects Limited,
Kingston ,Ontario, and said Corporation; and,
2. THAT the amended contract attached hereto as Schedule "A" form part of this
By-law
BY-LAW read a first and second time this
24th day of September 2007
24th day of September 2007
BY-LAW read a third time and finally passed this
Jim Abernethy, Mayor
Patti L. Barrie, Municipal Clerk
Attoch.#2 to Addendum COD50-07
Clfll:-!nglOn
REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
General Purpose and Administration Committee
Date:
June 18, 2007
Resolution ,.{lflA- 'Ii/5-0]
Report #: COD-027 -07
File#:
By-law #:
Subject:
Update - Newcastle Library Capital Project
Recommendations:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report COD-027 -07 be received for information.
Submitted by:
. /\( 01 eQ a. ~
Reviewed by:U -----1A...J LC
Franklin Wu
Chief Administrative Officer
Ie arano, H.B.Sc., C.M.O.
Director of Corporate Serv'ces
/~
MM/EH/BT/gj
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-5506
REPORT NO.: COD-027-07
PAGE 2
1.0 BACKGROUND
1.1 Report COD-027-07 is prepared to provide Council with an update for the
Newcastle Library capital construction project. In December 2006, Council was
provided concept and schematic illustrations of the proposed 9,100 square foot
Newcastle Library facility. Included in those discussions was the introduction of a
LEED (Leadership in Energy and Environmental Design) Green building. This
would be the first LEED Certified building to be constructed by the Municipality,
demonstrating the Municipality's commitment to conservation and sustainable
buildings. Since that date, the Building Committee in conjunction with the
Architect have worked to achieve these goals and to remain within the revised
budget of $3,450,047 as presented to a joint meeting of the Library Board and
Councillors October 2, 2006.
1.2 In preparation for the final design, it is a standard practice for the Architect to
undertake a Geotechnical (Soils) Investigation of the site. The final report
received by the Architect indicated that the soils in this area were deficient and
that design alternatives must be taken into consideration for the development of
the final construction specifications. The architect and sub-consultants have
developed suitable specifications to enable us to continue with the project at this
site. During discussions with the soils engineer, he has advised this problem
exists within certain geographical areas of Newcastle.
1.3 The development of these revised specifications has caused a delay in the
preparation of the overall building specifications. This was necessary to ensure
the final design documents address these concerns in order that the selected
general contractor will have all required information for the construction of the
facility, limiting possibilities of additional construction charges once the
specifications are issued and construction has commenced.
1.4 This report will provide specific updates related to the LEED application,
geotechnical investigations and revised milestone dates for Council's information.
2.0 LEED Application
2.1 The Architect is in the process of developing a LEED program submission for this
project. All LEED applications are submitted to the Canada Green Building
Council for approval. The LEED program is a point-based process, with certain
prerequisites for qualification. The points are assigned in six areas;
. Sustainable Sites
. Water Efficiency
. Energy and Atmosphere
. Materials and Resources
. Indoor Environmental Quality
. Innovation and Design Process
REPORT NO.: COD-027-07
PAGE 3
2.2 There are four (4) classifications of LEED Buildings:
. Certified
. Silver
. Gold
. Platinum
Based on the size of this project, point limitations and budget, the Municipality
will be submitting an application for a LEED Certified project. The expenses
related to the LEED application and additional work for the architect and
consultants are included in the revised budget.
3.0 Geotechnicallnvestiaation
3.1 Prior to the development of final drawings, a Geotechnical Investigation is
undertaken to ensure the selected site location will physically support the
building. In this case, the investigation by a qualified soils engineer indicated the
existing site soils were not suitable for normal construction utilizing standard
excavation methods and construction of supporting footings. The soils were
identified as soft clay. Normally, with suitable soils, the contractor would
excavate a trench and construct footings to support the building. In this case,
due to the soft clay soils, there are several alternatives such as driven piles,
augered caissons, or surcharging the site. Any of these three alternatives would
support a building of this size.
3.2 The soils engineer has proposed a process of surcharging the site. This method
is the least expensive and calls for the excavation of the 9,100 square foot
building footprint to the desired depth and dumping granular fill within the
footprint and letting it stand for a period of 4 to 6 weeks. The weight of this fill
would cause the site to settle in advance of the construction. This method has
also been reviewed by the Architect's engineers and they are in agreement with
the process.
3.3 The estimated additional cost to alleviate the unanticipated poor soil condition is
$150,000.00. The Building Committee is bringing this matter to Council's
attention at this time. Once the Municipality receives the construction bids, the
Building Committee will be in a position to make the appropriate recommendation
to Council. In the interim, the Architect has made several revisions to the plans
to reduce overall costs in an effort to absorb these additional costs within the
revised budget and project contingency.
REPORT NO.: COD-027-07
PAGE 4
4.0 Revised Milestone Dates
4.1 As mentioned, the project schedule has been delayed as the Architect, Soils
Engineer and the Architects project engineers developed a suitable process for
the establishment of an affordable building support system (including time
required for the surcharging). The Architect advises the following milestone
dates for the balance of the project:
Completed Construction Drawings and
Tender Documents
July 05, 2007
Tender Submissions from Contractors
August 02, 2007
Report to General Purpose and
Administration Committee
September 04, 2007
Ground Breaking Ceremony
Week of September 24, 2007
Construction
October 2007
Total Performance
August 2008
Library Opening
October 2008
5.0 COMMENTS
5.1 Construction Contractors were pre-qualified by the Committee in March 2007.
Accordingly, the pre-qualified contractors are aware of the project delay and will
be notified of the revised milestone dates. Based on the above dates, the
Building Committee expects to receive Tender Documents in August 2007 and
will strive to work within the project budget. A report recommending a General
Contractor will be submitted to the General Purpose and Administration
Committee on September 04, 2007.