HomeMy WebLinkAbout94-89
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW 94-89
Being a By-law to authorize a contract between
the Corporation of the Municipality of
Clarington and Rutherford Contracting Ltd.,
Gormley, Ontario in respect of Rotary Park -
Phase III.
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY ENACTS AS
FOLLOWS:
1. THAT the Mayor and Clerk are hereby authorized to execute on
behalf of the Corporation of the Municipality of Clarington
wi th the Corporation Seal, a contract between Rutherford
Contracting Ltd. and said Corporation.
2. THAT this agreement attached hereto as Schedule "A" form part
of this By-law.
By-law read a first and second time this 13th day of June, 1994.
By-law read a third and finally passed this 13th day of June, 1994.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ROTARY PARK PHASE 3
MUNICIPAL TY OF CLARINGTON
CONTRACT DOCUMENTS
CL 94-27
Owner:
Corporation of The Municipality of Clarington
40 Temperance Street
Bomanville, Ontario
LIC 3A6
Consultant:
Cosburn Giberson Landscape Architects
7270 Woodbine Avenue, Suite 100
Markham, Ontario
L3R 4B9
Project:
91.803
Date:
July, 1994
CONTRACTOR COpy
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ROTARY PARK PHASE 3
MUNICIPAL TV OF CLARINGTON
CONTRACT DOCUMENTS
CL 94-27
Owner:
Corporation of The Municipality of CIarington
40 Temperance Street
Bomanville, Ontario
LIC 3A6
Consultant:
Cosburn Giberson Landscape Architects
7270 Woodbine Avenue, Suite 100
Markham, Ontario
L3R 4B9
Project:
91.803
Date:
Jl:lly, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TABLE OF CONTENTS
Page 1
Agreement
Instructions to Bidders
, General Conditions
Supplementary Conditions
(green pages)
(blue pages)
(pink pages)
(yellow pages)
DIVISION 1 - GENERAL REQUIREMENTS
I
Section 0 I 005
Section 01020
Section 01050
Section 01060
Section 01070
Section 01200
Section 01300
Section 01400
Section 01500
Section 01600
Section 01700
Section 01710
General Requirements
Allowances
Lines and Levels
Regulatory Requirements
Abbreviations
Site Administration
Submittals
Quality Control
Temporary Facilities
Products and Workmanship
Project Closeout
Cleaning
DIVISION 2 - SITE WORKS
Section 02070
Section 02110
Section 02210
Section 02300
Section 02410
Section 02515
Section 02552
Temporary Control Fencing
Clearing and Grubbing
Earthworks
Sewers and Appurtenances
Masonry
Unit Paving
Asphalt Paving
DIVISION 3 - CONCRETE
Section 03300
Cast in Place Concrete
LIST OF DRAWINGS
Ll - Layout, Grading Services
L2 - Layout, Grading Services
L3 - Details
L4 - Details
L5 - Details
APPENDIX
Soils Survey
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Standard Construction DO'pument-CCDC 4
AGREEMENT BETWEEN OWNER AND CONTRACTOR
for use when unit prices form the basis of payment
and to be used only with the General Conditions
of the Unit Price Contract
This Agreement made this July 07,1994
in the year Nineteen hundred and ninety-four
by and between
THE CORPORTION OF THE MUNICIPALITY OF CLARINGTON
hereinafter called the "Owner"
and
RUTHERFORD CONTRACTING LIMITED
hereinafter called the "Contractor"
witnesses: that the Owner and Contractor agree as follows:
ARTICLE A-I THE WORK
The contractor shall:
(a) perform the Work required by the Contract Documents for The Corporation of the Municioality
of Clarimrton which have been signed by both the parties, and which were prepared by Cosburn
Giberson consultants Incorporated acting as, and hereinafter called, the"Engineer"and lor
"Consultant" and/or "Landscape Architect",
(b) do and fulfill everything indicated by this Agreement, and
(c) commence the work by the 20th day of June, 1994 and substantial performance of the Work,
as certified by the Consultant by the 31 th day of August, 1994.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A-2 CONTRACT DOCUMENTS
The following is an exact list of the Contract Documents referred to in Article A-I this Agreement and as
defined in Item 2 or Dl3FINITIONS. This list is subject to subsequent amendments in accordance with the
provisions of the Contract and agreed upon between the parties. Terms used in the Contract Documents
which are defined in the attached DEFINITIONS shall have the meanings designated in those DEFINITIONS.
(Insert here, attaching additional pages if required, a list identifying the Contract Documents including: The
Agreement, General Conditions, Supplementary Conditions, Definitions, Drawings (giving drawing number), title,
date, revision date of mark, and Specifications, giving a list of contents with section numbers and titles, number
of pages and date of revision marks, Clearly identify modifications to the Contract Documents).
Agreement
Instructions to Bidders
General Conditions
Supplementary Conditions
(green pages)
(blue pages)
(pink pages)
(yellow pages)
DMSION 1 . GENERAL REQUIREMENTS
Section 01005
Section 01020
Section 01050
Section 01060
Section 01070
Section 01200
Section 01300
Section 01400
Section 01500
Section 01600
Section 01700
Section 01710
General Requirements
Allowances
Lines and Levels
Regulatory Requirements
Abbreviations
Site Administration
Submittals
Quality Control
Temporary Facilities
Products and Workmanship
Project Closeout
Cleaning
DMSION 2 - SITE WORKS
Section 02070
Section 02110
Section 02210
Section 02300
Section 02410
Section 02515
Section 02552
Temporary Control Fencing
Clearing and Grubbing
Earthworks
Sewers and Appurtenances
Masonry
Unit Paving
Asphalt Paving
DMSION 3 . CONCRETE
Section 03300
Cast in Place Concrete
LIST OF DRAWINGS
L1 - Layout, Grading Services
L2 - Layout, Grading Services
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A-2 CONTRACT DOCUMENTS
L3 - Details
U - Details
L5 - Details
APPENDIX
Soils Survey
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A~3 CONTRACT PRICES
The quantities shown in the Schedule of Contract Unit Prices are estimated. The Contract Price shall
be the final sum of the products of the actual quantities that are incorporated in, or made necessary by
the Work, as confinned by the count and measurement, and the appropriate Contract Unit Price,
together with any adjustments that are made in accordance with the provisions of the Contract
Documents.
The Estimated Contract Price shall be the sum of the products of the estimated quantities and the
appropriate Contract Unit Prices in the Schedule.
ITEM
NO.
DESCRIPTION
$1,650.
1.0
Demolition work, clearing,
grubbing, topsoil stripping and
stockpiling.
Temporary project control fencing.
Temporary sediment control
fencing.
Rough grading work including
cutting and/or filling and disposal
of surplus material, if necessary.
Gravel access roadway.
Asphalt pavement.
Poured concrete sidewalk.
Poured concrete depressed curb
and gutter.
Poured concrete curb and gutter.
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0 Poured concrete steps (2 sets).
11.0 Electrical conduit.
12.0 Removable bollards.
13.0 100 ~ SDR 35 piping.
14.0 Sanitary service connection, 150mm
PVC SDR-28 S-305 Bedding, all
fittings include plug.
15.0 Sanitary cleanout manhole, S-101,
Bolt-Down Cover, S-120
ESTIMATED
QUANTITY
UNIT
UNIT
PRICE
TOTAL
Lump Sum
140
100
m
. $19.50
$23.00
m
Lump Sum
. 160
67
220
7.5
m2
$8.80
$32.00
$43.50
$56.00
m2
m2
m
42
$54.00
m
2
36
46
Lump Sum
Lump Sum
$230.00
$27.50
$65.00
Ea.
LM
m
2
$1,400.
Ea.
$2,730.
$2,300.
$2,175.
$1,408.
$2,144.
$9,570.
$420.
$2,268.
$6,500.
$3,370.
$460.
$990.
$2,990.
$2,800.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A-3 CONTRACT PRICES
ITEM DESCRIPTION
NO.
16.0 Mak~ connection to existing
sanitary sewer.
17.0 Water service connection, 19mm
Copper "K" soft, S-410 include
bends, cap, fittings.
18.0 Make connection to existing
watermain.
19.0 Abandon existing catchbasin (CB)
20.0 Interceptor swale, sodded
21.0 Catchbasin manhole (CBMH)
, No.1, complete, include grate and
drop connection.
22.0 Replace existing CB with CBMH
No.2, complete.
23.0 CBMH No.3, complete.
24.0 Catchbasins, complete
25.0 Corrugated Steel Pipe CSP, 300mm
diameter gauge 12.
25.1 CB "A" to CBMH 1
25.2 CB "B" to CBMH 1
25.3 CB "e' to CBMH 2
25.4 CBMH 1 to CBMH 2
25.5 CBMH 2 to CBMH 3
25.6 CBMH 3 to elbow coupling
25.7 Chute, complete with stone
bedding, rock fill cover, anchors
and end section.
26.0 Gabions, complete
27.0 Outlet ditch, complete, include rip-
rap.
28.0 Masonry wall small section at
westerly entry to park measuring
approximately 5.6m in length.
ESTIMATED
QUANTITY
38
1
64
1
1
1
3
19
24
16
27
40
7
18
7.5
10
UNIT
m
Ea.
m2
Ea.
Ea.
Ea.
Ea.
m
m
m
m
m
m
m
m3
m2
UNIT
PRICE
TOTAL
Lump Sum
$56.50
Lump Sum
$108.00
$5.50
$3,530.00
$1,850.00
$1,400.00
$760.00
$93.00
$103.00
$64.00
$66.00
$81.00
$130.00
$250.00
$218.00
$54.00
Lump Sum
$1,100.
$2,147.
$220.
$108.
$352.
$3,530.
$1,850.
$1,400.
$2,280.
$1,767.
$2,472.
$1,024.
$1,782.
$3,240.
$910.
$4,500.
$1,635.
$540.
$4,950.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A-3 CONTRACT PRICES
ITEM DESCRIPTION ESTIMATED
NO. QUANTITY
UNIT UNIT
PRICE
TOTAL
29.0 Masonry walls, twin set of walls
located at main entry to parks
approximately 62m in length.
30.0 Cost of Performance Bonding
31.0 Mobilization and demobilization of
the job site of offices,
conveniences, temporary facilities,
construction plant and other items
not required to form part of
requirements of the contract not
specifically related to the preceding
items herein. Include all cost to
cover Division 1 requirements.
Lump Sum
$42,650.
Lump Sum
Lump Sum
$760.
$3,450.
Sub-Total
$124,392.
32.0 Goods and services tax @ 7% for $8,707.44
items 1.0 to 31.0 inclusive.
33.0 Testing allowance $1,250.
34.0 Contingency allowance $7,500.
Total all items
$141,849.44
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A-3 CONTRACT PRICES
ITEM DESCRIPTION ESTIMATED
NO. QUANTITY
UNIT
TOTAL
UNIT
PRICE
$15,455.
1.0 Tender item 7.0 220
Substitute unit paving. Pavers to be
estate paver, colour blend, random
pattern, by UNILOCK, or equal.
2.0 Tender item 7.0 220
Substitute unit paving. Pavers to be
shot blast exposed aggregate
texture, custom colour, holland
stone shape, herring bone pattern,
by Brooklin concrete products Ltd.
or equal.
m2
$70.25
m2
$72.00
$15,840.
3.0 Tender items 28 and 29 masonry
walls.
3.1 Substitute precast concrete coping,
bush hammered finish in place of
milled limestone coping.
3.2 Substitute berea sandstone (grey)
split face, 2%" thick, sawn top and
bottom in place of milled limestone
coping.
3.3 Substitute standard clay masonry
brick, heritage colour, in place of
granite veneer.
3.4 Delete milled limestone coping in
entirety.
Effect on Price $ not including
G.S.T.
Addition
Deduction
$
$10,000.
$
$10,000.
$
$4,000.
$14,000.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A-3 CONTRACT PRICES
The following are our Separate Prices for the work listed hereunder. Such work and amounts are NOT included in our
Estimated Price.
(if not used, bar and initial the space below)
Unit Price Per m3
1.0
Excavate existing soil, dispose off site,
and replace with pit run sand compacted
to 95% Standard Proctor Density.
Excavate existing soil, dispose off site,
and replace with 20mm crusher run
limestone compacted to 95 % standard
Proctor Density.
$70.
$82.
2.0
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A-4 PAYMENT
a) The Owner shall pay the Contractor in Canadian funds for the performance of the Contract,
the amounts being determined by actual measured quantities of the individual work items
contained in the Schedule of Contract Unit Prices in Article A-2 (c) of this Agreement, and
measured in accordance with the methods of measurement given in the Specifications.
b) Subject to applicable legislation and the provisions of the Contract Documents, and in
accordance with legislation and statutory regulations respecting holdback percentages and,
where such legislation or regulations do not exist or apply, subject to a holdback of 10%,
the Owner shall:
I) Make monthly payment to the Contractor on account of the work performed a as
certified by the Engineer, and
2) upon Substantial Performance of the Work as certified by the Engineer pay to the
Contractor the unpaid balance of monies then due.
3) upon total Performance of the Work as certified by the Engineer pay to the
Contactor the unpaid balance of monies then due.
c) In the event of loss or damage occurring where payment becomes due under the Property
and Boiler Insurance policies, payment shall be made to the Contractor in accordance with
the provisions of GC 20- INSURANCE
d) If the Owner fails to make payments to the Contractor as they become due under the terms
of the Contract or in an award by arbitration or court, interest of 18 percent per annum on
such unpaid amounts shall also become due and payable until payment. Such interest shall
be calculated and added to any unpaid amounts monthly.
ARTICLE A-5 RIGHTS AND REMEDIES
a) The duties and obligations imposed by the Contract Documents and the rights and remedies
available thereunder shall be in addition to and not a limitation of any duties, obligations,
rights and remedies otherwise imposed or available by law.
b) No action or failure to act by the Owner, Engineer or Contractor shall constitute a waiver
of any right or duty afforded any of them under the Contract, nor shall any such action or
failure to act constitute an approval of or acquiescence in any breach thereunder, except as
may be specifically agreed in writing.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A~6 RECEIPT OF AND ADDRESS FOR NOTICES
Communications in- 'writing between the parties or between them and the Engineer shall be
considered the have been receive~ by the addressee on the date of delivery if delivered by hand to
the individual or to a member of the firm or to an officer of the Corporation for whom they are
intended or if sent by post or by telegram, to have been delivered within five (5) working days of
. the date of mailing, dispatch or of delivery to the telegraph company when addressed as follows:
Owner 40 Temperance Street
Bowmanville, Ontario
LtC 3A6
The Contractor at 27 Cardico Drive, P.O. Box 747
Gormley, Ontario
LOH I GO
The Landscape Architect at 7270 Woodbine Avenue
Suite # 1 00
Markham, Ontario
L3R 4B9
ARTICLE A-7 LANGUAGE OF THE CONTRACT
When the Contract Documents are prepared in both the English and French languages, it is agreed that in the
event of any apparent discrepancy between the English and French versions, the English language shall
prevail.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ARTICLE A~8 SUCCESSION
The general Conditions of the Unit Price Contract hereto annexed, and the other aforesaid Contract
Documents, are to be read into and form part of this Agreement and the whole shall constitute the
Contract between the parties and subject to law and the provisions of the Contract Documents shall
inure to the benefit of and be binding upon the parties hereto, their respective heirs, legal
representatives, successors and assigns.
In witness whereof the parties hereto have executed this Agreement under their respective corporate
seals and by the hands of their proper officers thereunto duly authorized.
SIGNED, SEALED AND DELIVERED
in the presence of:
OWNER
Name:
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
flu? C4,s/ 191/11/
DATE
CONTRACTOR
Name: RUTHERFORD CONTRACTING LIMITED
Si~Mure: 4# i ~
A'f/C ~#
DATE
I
I
INSTRUCTION TO BIDDERS
Page 1
I
I
I
1.
Scope of Work
1. Your bid shall include a unit price for all labour, materials, equipment and services to
complete the work described in the specifications, drawings, details and addenda (if
issued) .
2. Delivery and Opening of Tenders
I
I
I
I
I
1. Tenders, sealed in envelopes which shall be clearly marked with the project title, will be
received by the clerk before 2:00 pm (Local Time) Thursday, May 19,1994 at the
following address: The Clerk, Municipality of Clarington, 40 Temperance Street,
Bomanville, Ontario LtC 3A6. Tenders will not be accepted unless submitted in the
envelopes provided.
2. Tenders will be opened publicly after all submissions are received.
3. The use of the mails for delivery of a tender will be at the risk of the tenderer and
delivery by the postal agency or the Government of Ontario or employee of the agency
of the Crown, concerned with the reception or distribution of mail, will not be regarded
as delivery unless the envelope comes into the possession of the above mentioned
representative before said closing time.
3.
Preparation of Tenders
I
I
1. All tenders must be made upon the standard construction document CCDC 4, 1982,
tender form, based on unit prices. The tenderer must give the price for the work both
in words and in figures.
4.
Tender Acceptance and Contract Award
I
I
I
1. As soon as practicable after opening the tenders, the owner will act upon them. The
acceptance of a tender will be notice in writing signed by a duly authorized representative
of the owner, and no other act of the owner shall constitute the acceptance of a tender.
Acceptance of a tender shall bind the successful tenderer to execute the contract.
I
I
2. The tenderer whose tender is accepted will be required to execute the contract within
seven days (excepting Sundays and statutory holidays) after mailing of notice that the
contract documents are available for execution. Failure to do so shall constitute a breach
of the agreement effected by the acceptance of his tender. In the event that a tenderer,
whose tender is accepted, fails or refuses to execute the contract as hereinbefore
provided, the owner may at his option, determine that such tenderer has abandoned his
tender and the acceptance thereof shall be null and void, and bid deposit will be due to
owner.
Rejection of Tenders
5.
I
I
1. The owner reserves the right to accept any tender or reject all tenders. Without limiting
the generality of the foregoing, any tender which is incomplete, conditional, illegible or
obscure or which contains additions not called for, reservations, erasures, alterations or
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
INSTRUCTION TO BIDDERS
Page 2
irregularities of any kind may be rejected.
6.
Discrepancies, Omissions, Interpretations
Should a tenderer find discrepancies in or omissions from the contract documents or be in doubt
as to any meaning or have any questions whatsoever in connection with the tender, they should
enquire directly from Mr. Brian Giberson of Cosburn/Giberson Consultants Inc.,telephone No.
(905) 475-6988. No oral interpretations will be effective to modify any provisions of the contract
documents, unless a written addendum has been issued by the landscape architect prior to tender
closing.
7.
Withdrawal Of Qualifying Tenders
1. A tenderer may withdraw or revise his tender at any time up to the official closing time
by submitting a letter bearing his signatures and seal as in his tender to the Municipality
Clerk, who will mark thereon the time and date of receipt and will place the letter in the
.tender box. The tenderer shall show his name and the project title on the envelope
containing such letter. No telegrams or telephone calls will be considered.
8.
Required Information
1. Any Tenderer may be required to supply any or all of the following information prior
to tender award contract execution.
a) Details of the tenderer's experience including details of the work performed, for
whom and the value.
b) Numbers and functions of personnel to be employed on the work.
c) Proposed construction schedule showing clearly, in the stages, the proposed
progress of the work to the time of completion as stated in the tender.
d) List of construction equipment to be provided on the work to enable
construction to progress according the proposed construction schedule.
9.
Bid Deposit
1. A bid deposit is required with this tender. Deposit shall be in the form of a certified
cheque by the bank on which it is drawn, bank draft, money order equal to, or greater
than, the amount shown in the table below, unless otherwise stipulated
Total Amount of Tender
Minimum Deposit ReQuired
$ 20,000.00 or less
$ 20,000.01 to
$ 50,000.01 to
$ 100,000.01 to
$ 250,000.01 to
$ 500,000.01 to
$ 1,000.00
$ 2,000.00
$ 5,000.00
$ 10,000.00
$ 25,000.00
$ 50,000.00
$ 50,000.00
$100,000.00
$250,000.00
$ 500,000.00
$1,000,000.00
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
INSTRUCTION TO BIDDERS
Page 3
$ 1,000,000.01 to
$ 2,000,000.01 to
$ 3,000,000.00 to
$ 4,000,000.01 to
$ 5,000,000.01 to
$ 6,000,000.01 or over
$2,000,000.00
$3,000,000.00
$4,000,000.00
$5,000,000.00
$6,000,000.00
$ 100,000.00
$ 200,000.00
$ 300,000.00
$ 400,000.00
$ 500,000.00
$ 600,000.00
2.
Security deposit will be returned within a reasonable time to all except the low and second low
bidders. Upon execution of the contract by the successful tenderer, the second low bidder's
deposit will be returned. The successful bidder will receive his security deposit after a satisfactory
performance bond has been received and an Agreement or Contract has been signed.
10.
Letter of Performance
A letter from a bonding company acceptable to the owner, agreeing to issue the required
Performance Bond to the tenderer. Said bond shall be one hundred percent (100%) of
the contract sum and shall guarantee the faithful carrying out of the work to satisfactory
completion.
11.
Submissions Required
1. The following documents are required to be submitted prior to signing of contract
documents.
a) Performance Bond
b) Insurance Policies
c) Workers' Compensation Insurance Compliance
Refer to the appropriate sections in the contract documents for the specific information
required of the aforementioned.
2. The bidder agrees to indemnify and save harmless the Municipality of Clarington for all
actions, suits, claims and demands and costs arising by reason of injury and death to any
person from the work of this tender.
3. The bidder shall take out and keep in force, a policy of comprehensive liability and
property damage insurance in an amount of not less than $2,000,000.00 inclusive each
occurrence or such larger amount as may be required by the Town and shall include as
a named insured THE CORPORATION OF THE MUNICIPALITY OF
CLARINGTON. A certified copy of such policy or certificate of such insurance shall be
provided prior to commencement of work.
4. The bidder shall provide the Town with a Certificate of Clearance Form from the
Worker's Compensation Board prior to the commencement of work and prior to any
payment after completion of the works, certifying that all assessments and liabilities
I
I
I
I
I
INSTRUCTION TO BIDDERS
Page 4
payable to the Board have been paid, that the bidder is in good standing with the Board,
and the Municipality will not be liable to the Board for future payments in connection
with the bidder's completion of the project. All of the bidders personnel must be covered
by the Board at the bidder's expense.
Further Certificate of Clearance Forms must be provided as, and when, required by the
Municipality.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
5. The Contractor shall obey all Federal, Provincial and Municipal Laws, Acts, Ordinances,
Regulations, Orders-in-Council and By-Laws, which could in any way pertain to the work
out-lined in the Contract or to the Employees of the Contractor. Without limiting the
generality of the foregoing, the Contractor shall satisfy all statutory requirements
imposed by the Occupational Health and Safety Act and Regulations made thereunder,
on a Contractor, a Constructor and/or Employer with respect to or arising our of the
performance of the Contractor's obligations under this Contract.
12.
Starting Dates
1. The project shall begin June 20,1994.
13.
Completion Dates
1. The project shall be certified substantially complete on or before August 31,1994
2. If the contractor does not successfully complete the project within the time limit, a
penalty will be enforced. The penalty shall be $250.00 (two hundred and fifty dollars)
per day until the project is certified substantially complete by the consultant.
END
I
I
I
I
I
GENERAL CONDITIONS
Page 1
1.0
Governing Documents
1. The following documents shall govern as the general conditions for this project:
I
I
I
Standard Construction Document CCDC 4
File 00530, 00720
1982
Unit Price Contract
Available at:
Toronto Construction Association
Construction Centre
1 Sparks Avenue
Willowdale, Ontario
M2H 2Wl
(416)499-4000
I
I
2.0
Amendments
1. The 1982 Amendment to CCDC 4 shall integrally form part of the General Conditions.
a) GC 14 - Certificates and Payments
I
I
I
I
I
I
I
I
I
Substitute the new 1982 versions of GC 14.12 and GC 14.13. Add a new general
condition as GC 14.14.
b)
GC 19 - Indemnification
Substitute the new 1982 versions of GC 19.1, 19.2 and 19.3. Add a new general
condition as GCI9.14.
c)
GC 20 - Insurance
Substitute the new 1982 version of GC 20.1(a).
END
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Standard Construction Document - CCDC 4 - 1982
DEFINITIONS
The following Definitions shall apply to all Contract Documents.
1.
The Contract
The Contract Documents form the Contract. The Contract is the undertaking by the parties to perform
their respective duties, responsibilities and obligations as prescribed in the Contract Documents and
represents the entire agreement between the parties. The Contract supersedes all prior negotiations,
representations or agreements, either written or oral, including the bidding documents. The Contract may
be amended only as provided in the General Conditions of the Contract.
2.
Contract Documents
The Contract Documents consist of the executed Agreement between the Owner and Contractor, the
General Conditions of the Contract, Supplementary Conditions, Definitions, specifications, drawings and
such other documents as are listed in Article A-2 - CONTRACT DOCUMENTS including amendments
thereto incorporated before the execution of the Contract and subsequent amendments thereto made
pursuant to the provisions of the Contract and agreed upon between the parties.
3.
Owner
The Owner is the person, firm or corporation identified as such in the Agreement and is referred to
throughout the Contract Documents as if singular in number and masculine in gender. The term Owner
means the Owner or his authorized agent or representative as designated to the Contractor in writing but
does not include the Consultant.
4.
Consultant
The Consultant is the person, firm or corporation identified as such in the Agreement, and is an Architect
or Engineer licensed to practice in the province or territory of the Place of the Work, and is referred to
throughout the Contract Documents as if singular in number and masculine in gender.
5.
Contractor
The Contractor is the person, firm or corporation identified as such in the Agreement and is referred to
throughout the Contract Documents as if singular in number and masculine in gender. The term Contrac-
tor means the Contractor or his authorized representative as designated to the Owner in writing.
6. Subcontractor
A Subcontractor is a person, firm or corporation having a direct contract with the Contractor to perform a
part or parts of the Work, or to supply products worked to a special design according to the Contract
Documents, but does not include one who merely supplies products not so worked. The term Subcontrac-
tor is referred to throughout the Contract Documents as if singular in number and masculine in gender.
7.
The Project
The Project means the total construction contemplated of which the Work may be the whole or a part.
8.
The Work
The Work means the total construction and related services required by the Contract Documents.
9.
Products
Products means material, machinery, equipment and fixtures forming the Work but does not include
machinery and equipment used for preparation, fabrication, conveying and erection of the Work and
normally referred to as construction machinery and equipment.
10.
Other Contractor
Other Contractor means a person, firm or corporation employed by or having a separate contract directly
or indirectly with the Owner for work other than that required by the Contract Documents.
CCDC 4 - 1982 File 00530
9
11.
Place of the Work
The Place of the Work is the designated site or location of the Project of which the Work may be the whole
or a part.
12. Time
(a) The Contract Time is the time stipulated in the Contract Documents for Substantial Performance of
the Work.
(b) The date of Substantial Performance of the Work is the date certified as such by the Consultant.
(c) Day means the calendar day.
(d) Working day means days other than Saturdays, Sundays and holidays which are observed by the
construction industry in the area of the Place of the Work.
13.
14.
Substantial Performance of the Work
Substantial Performance of the Work is as defined in the lien legislation applicable to the Place of the
Work. If such legislation is not in force or does not contain such definition, Substantial Performance of the
Work shall have been reached when the Work is ready for use or is being used for the purpose intended
and is so certified by the Consultant.
Total Performance of the Work
Total Performance of the Work means when the entire Work, except those items arising from the provi-
sions of GC 24 - WARRANTY, has been performed to the requirements of the Contract Documents and
is so certified by the Consultant.
15.
Changes in the Work
Changes in the Work means the deletion, extension, increase, decrease or alteration of lines, grades,
dimensions, methods, drawings or materials of the Work or part thereof, within the scope of the Work
contemplated by the Contract Documents.
16.
Extra Work
Extra Work means any work or service, the performance of which is beyond the scope of the Work
contemplated by the Contract Documents.
'10
eeDe 4 - 1982 File 00530
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Standard Construction Document - CCDC 4 -1982
THE GENERAL CONDITIONS OF THE UNIT PRICE CONTRACT
(Hereinafter referred to as the General Conditions.)
GC 1 DOCUMENTS
1.1 The Contract Documents shall be signed in duplicate by the Owner and the Contractor.
1.2 The Contract Documents are complementary, and what is required by anyone shall be as binding as if
required by all.
1.3 The intent of the Contract Documents is to include the labour, products and services necessary for the
performance of the Work in accordance with these documents. It is not intended, however, that the Con-
tractor shall supply products or perform work not consistent with, covered by or properly inferable from
the Contract Documents.
1.4 Words and abbreviations which have well known technical or trade meanings are used in the Contract
Documents in accordance with such recognized meanings.
1.5 References to the masculine or the singular shall be considered to include the feminine and the plural as
the context requires.
1.6
1.7
1.8
1.9
1.10
In the event of conflicts between Contract Documents the following shall apply:
(a) figured dimensions shown on a drawing shall govern even though they may differ from dimensions
scaled on the same drawing,
(b) drawings of larger scale shall govern over those of smaller scale of the same date,
(c) specifications shall govern over drawings,
(d) the General Conditions shall govern over specifications,
(e) Supplementary Conditions shall govern over the General Conditions, and
(f) the executed Agreement between the Owner and Contractor shall govern over all documents.
Notwithstanding the foregoing, documents of later date shall always govern.
Th"e Contractor shall be provided without charge with as many copies of the Contract Documents or parts
thereof as are necessary for the performance of the Work.
The Contractor shall keep one copy of current Contract Documents and shop drawings at the Place of the
Work, in good order and available to the Consultant and his representatives. This requirement shall not be
considered to include the executed set of Contract Documents.
Drawings, specifications, models and copies thereof furnished by the Consultant are and shall remain his
property with the exception of the signed contract sets belonging to each party to this Contract. Such
documents and models are to be used only with respect to the Work and are not to be used on other work.
Such documents and models are not to be copied or revised in any manner without the written authoriza-
tion of the Consultant.
Models furnished by the Contractor at the Owner's expense are the property of the Owner.
ADDITIONAL INSTRUCTIONS
During the progress of the Work the Consultant will furnish to the Contractor such additional instructions
to supplement the Contract Documents as may be necessary for the performance of the Work. Such in-
structions shall be consistent with the intent of the Contract Documents.
Additional instructions may be in the form of specifications, drawings, samples, models or other written
instructions.
2.3 Additional instructions will be issued by the Consultant with reasonable promptness and in accordance
with a schedule agreed upon for such instructions.
GC2
2.1
2.2
CCDC 4 - 1982 File 00720
11
GC3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
12
CONSULTANT
The Consultant will provide administration of this Contract as described in the Contract Documents.
The Consultant will be the Owner's representative during construction and until completion of any
correction of defects under the provisions of GC 24 - WARRANTY, paragraph 24.2, or until the issuance
of the Certificate of Total Performance of the Work, whichever is later. The Owner's instructions to the
Contractor shall be forwarded through the Consultant. The Consultant will have authority to act on behalf
of the Owner only to the extent provided in the Contract Documents, unless otherwise modified by written
agreement in accordance with paragraph 3.13.
The Consultant will not be responsible for and will not have control or charge of construction means,
methods, techniques, sequences or procedures, or for safety precautions and programs required for the
Work in accordance with the applicable construction safety legislation, other regulations or general con-
struction practice. The Consultant will not be responsible for or have control or charge over the acts or
omissions of the Contractor, his Subcontractors, or their agents, employees or other .persons performing
allY of the Work.
The Consultant will visit the site at intervals appropriate to the progress of construction to familiarize
himself with the progress and quality of the Work and to record the data necessary to establish the pay
quantities under the Schedule of Contract Unit Prices.
Based on the Consultant's observations and his evaluation of the Contractor's applications for payment,
the Consultant will determine the amounts owing to the Contractor under the Contract and will issue cer-
tificates for payment in such amounts, as provided in Article A-4 - PAYMENT and GC 14 - CER-
TIFICATES AND PAYMENTS.
The Consultant will be, in the first instance, the interpreter of the requirements of the Contract Documents
and the judge of the performance thereunder by both parties to the Contract. Interpretations and decisions
of the Consultant shall be consistent with the intent of the Contract Documents and in making his deci-
sions he will not show partiality to either party.
Claims, disputes and other matters in question relating to the performance of the Work or the
interpretation of the Contract Documents shall be referred initially to the Consultant in writing for decision
which he will give in writing within a reasonable time.
The Consultant will have authority to reject work which in his opinion does not conform to the
requirements of the Contract Documents. Whenever he considers it necessary or advisable he will have
authority to require special inspection or testing of work whether or not such work be then fabricated, in-
stalled or completed. However, neither the Consultant's authority to act nor any decision made by him
either to exercise or not to exercise such authority shall give rise to any duty or responsibility of the Consul-
tant to the Contractor, his Subcontractors, or their agents, employees or other persons performing any of
the Work.
The Consultant will review and take appropriate action upon the Contractor's submittals such as shop
drawings, product data, and samples, in accordance with the requirements of the Contract Documents.
The Consultant will prepare change orders in accordance with the requirements of GC 11 - CHANGES IN
THE WORK AND EXTRA WORK.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3.14
The Consultant will conduct inspections to ~etermine the date of Substantial Performance of the Work
and Total Performance of the Work in accordance with the requirements of GC 14 - CERTIFICATES
AND PAYMENTS. He will receive and review written warranties and related documents required by the
Contract and provided by the Contractor and will forward such warranties and documents to the Owner
for his acceptance.
If the Owner and the Consultant agree, the Consultant will provide at the site one or more project
representatives to assist the Consultant in carrying out his responsibilities. The duties, responsibilities and
limitations of authority of such project representatives shall be as set forth in writing to the Contractor but
shall in any event provide for the timely recording of the data necessary to establish the pay quantities
under the Schedule of Contract Unit Prices.
The duties, responsibilities and limitations of authority of the Consultant as set forth in the Contract
Documents will not be modified or extended without the written consent of the Owner, the Contractor and
the Consultant.
In the event of the termination of the employment of the Consultant, the Owner shall immediately appoint
a Consultant to whom the Contractor makes no reasonable objection and whose status under the Contract
shall be that of the former Consultant.
I
I
I
I
I
eeDe 4 - 1982 File 00720
I
3.15
I
I
GC4
4.1
I
I
4.2
I
4.3
I
I
I
4.4
I
4.5
I
4.6
I
GC5
5.1
I
5.2
I
I
5.3
I
I
5.4
I
I
Nothing contained in the Contract Documents shall create any contractual relationship between the
Consultant and the Contractor, his Subcontractors, his suppliers, or their agents, employees or other
persons performing any of the Work.
DELAYS
If the Contractor is delayed in the performance of the Work by an act or omission of the Owner,
Consultant, Other Contractor, or anyone employed or engaged by them directly or indirectly, contrary to
the provisions of the Contract Documents, then the Contract Time shall be extended for such reasonable
time as the Consultant may decide in consultation with the Contractor. The Contractor shall be reimbursed
by the Owner for reasonable costs incurred by the Contractor as the result of such delay.
If the Contractor is delayed in the performance of the Work by a stop work order issued by a court or other
public authority and providing that such order was not issued as the result of an act or fault of the Contrac-
tor or anyone employed or engaged by him directly or indirectly, then the Contract Time shall be extended
for such reasonable time as the Consultant may decide in consultation with the Contractor. The Contrac-
tor shall be reimbursed by the Owner for reasonable costs incurred by the Contractor as the result of such
delay.
If the Contractor is delayed in the performance of the Work by labour disputes, strikes, lock-outs
(including lock-outs decreed or recommended for its members by a recognized contractors' association, of
which the Contractor is a member or to which the Contractor is otherwise bound), fire, unusual delay by
common carriers or unavoidable casualties or, without limit to any of the foregoing, by a cause beyond the
Contractor's control, then the Contract Time shall be extended for such reasonable time as the Consultant
may decide in consultation with the Contractor, but in no case shall the extension of time be less than the
time lost as the result of the event causing the delay, unless such shorter extension be agreed to by the
Contractor. The Contractor shall not be entitled to payment for costs incurred as the result of such delays
unless such delays are as the result of actions by the Owner.
No extension shall be made for delay unless written notice of claim is given to the Consultant not later than
fourteen (14) days after the commencement of delay, providing however, that in the case of a continuing
cause of delay only one notice of claim shall be necessary.
If no schedule is made under GC 2 - ADDITIONAL INSTRUCTIONS, no claim for delay shall be allowed
because of failure to furnish instructions until fourteen (14) days after a demand for such instructions has
been made and not then unless such claim is reasonable.
The Consultant will not, except by written notice to the Contractor, stop or delay the Work pending
instructions or proposed changes in the Work.
OWNER'S RIGHT TO PERFORM WORK OR STOP THE WORK OR TERMINATE CONTRACT
If the Contractor should be adjudged bankrupt, or makes a general assignment for the benefit of creditors
because of his insolvency or if a receiver is appointed because of his insolvency, the Owner may, without
prejudice to any other right or remedy he may have, by giving the Contractor or receiver or trustee in
bankruptcy written notice, terminate the Contract.
If the Contractor should neglect to prosecute the Work properly or otherwise fails to comply with the
requirements of the Contract to a substantial degree and if the Consultant has given a written statement to
the Owner and Contractor that sufficient cause exists, the Owner may notify the Contractor in writing that
he is in default of his contractual obligations and instruct him to correct the default in the five (5) working
days immediately following the receipt of such notice.
If the correction of the default cannot be completed in the five (5) working days specified, the Contractor
shall be in compliance with the Owner's instructions if he:
(al commences the correction of the default within the specified time, and
(b) provides the Owner with an acceptable schedule for such correction, and
(c) completes the correction in accordance with such schedule.
If the Contractor fails to correct the default in the time specified or subsequently agreed upon, the Owner,
without prejudice to any other right or remedy he may have, may:
(a) correct such default and deduct the cost thereof from any payment then or thereafter due the Con-
tractor provided the Consultant has certified such cost to the Owner and the Contractor, or
(b) terminate the Contractor's right to continue with the Work in whole or in part or terminate the
Contract.
ceDe 4 - 1982 File 00720
13
5.5
5.6
5.7
GC 6
6.1
6.2
GC 7
. 7.1
If the Owner terminates the Contractor's right to continue with the Work under the conditions set out in
this General Condition, he shall:
(a) be entitled to take possession of the premises and products and utilize the construction machinery
and equipment the whole subject to the rights of third parties, and finish the Work by whatever
method he may consider expedient but without undue delay or expense, and
(b) withhold further payments to the Contractor until the Work is finished, and
(c) upon Total Performance of the Work, charge the Contractor the amount by which the full cost of
finishing the Work as certified by the Consultant, including compensation to the Consultant for his
additional services and a reasonable allowance as determined by the Consultant to cover the cost of
corrections to work performed by the Contractor that may be required under GC 24 - WARRANTY,
exceeds the unpaid balance of the Contract Price; however, if such cost of finishing the Work is less
than the unpaid balance of the Contract Price, he shall pay the Contractor the difference, and
(d) on expiry of the warranty period, charge the Contractor the amount by which the cost of corrections
to his work under GC 24 - WARRANTY exceeds the allowance provided for such corrections, or if
the cost of such corrections is less than the alloiNance, pay the Contractor the difference.
If a performance bond has been provided by the Contractor the provisions of this General Condition shall
be exercised in accordance with the conditions of such performance bond.
The Contractor's obligation under the Contract as to quality, correction and warranty of the work
performed by him up to the time of termination shall continue in force after such termination.
I
I
I
I
I
I
I
6.3
CONTRACTOR'S RIGHT TO STOP THE WORK OR TERMINATE CONTRACT
If the Owner should be adjudged bankrupt or makes a general assignment for the benefit of creditors
because of his insolvency or if a receiver is appointed because of his insolvency, the Contractor may,
without prejudice to any other right or remedy he may have, by giving the Owner or receiver or trustee in
bankr'uptcy written notice, terminate the Contract.
If the Work should be stopped or otherwise delayed for a period of thirty (30) days or more under an order
of a court or other public authority and providing that such order was not issued as the result of an act or
fault of the Contractor or of anyone directly or indirectly employed or engaged by him, the Contractor
may, without prejudice to any other right. or remedy he may have, by giving the Owner written notice,
terminate the Contract.
The Contractor may notify the Owner in writing, with a copy to the Consultant, that the Owner is in default
of his contractual obligations if:
(a) the Consultant fails to issue a certificate in accordance with the provisions of GC 14 - CER-
TIFICA TES AND PA YMENTS, or
(b) the Owner fails to pay the Contractor when due the amounts certified by the Consultant or awarded
by arbitration or court, or
(c) the Owner violates the requirements of the Contract to a substantial degree and the Consultant con-
firms by written statement to the Contractor that sufficient cause exists.
The Contractor's written notice to the Owner shall advise that if the default is not corrected in the five (5)
working days immediately following the receipt of the written notice the Contractor may, without pre-
judice to any other right or remedy he may have, stop the Work or terminate the Contract.
If the Contractor terminates the Contract under the conditions set out above, he shall be entitled to be paid
for all work performed in accordance with the Schedule of Contract Unit Prices and for loss sustained
upon products and construction machinery and equipment and such other damages as the Contractor
may have sustained as a result of the termination of the Contract.
I
I
I
I
I
I
I
6.4
I
I
DISPUTES
I
Differences between the parties to the Contract as to the interpretation, application or administration of
this Contract or any failure to agree where agreement between the parties is called for, herein collectively
called disputes, which are not resolved in the first instance by decision of the Consultant pursuant to the
provisions of GC 3 - CONSULTANT, paragraphs 3.6 and 3.7, shall be settled in accordance with the re-
quirements of this General Condition.
I
14
eeDe 4 - 1982 File 00720
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
OTHER CONTRACTORS
The Owner reserves the right to let separate contracts in connection with the Project of which the Work is
a part, or do certain work by his own forces.
When separate contracts are awarded for different parts of the Project, or work is performed by the
Owner's own forces, the Owner shall:
(a) provide for the co-ordination of the work of his own forces and of each separate contract with the
Work of this Contract, and
(b) ensure that insurance coverage is provided to the same requirements as are called for in GC 20
-INSURANCE. Such insurance shall be co-ordinated with the insurance coverage of this Contractor
as it affects the Work of this Contract.
The Contractor shall co-ordinate the Work of this Contract with the work of Other Contractors and
connect as specified or shown in the Contract Documents. If there is a change in the scope of the work re-
quired for the planning and performance of this co-ordination and connection, the changes shall be
authorized in accordance with GC 11 - CHANGES IN THE WORK AND EXTRA WORK, and the value of
the changes shall be determined in accordance with GC 12 - VALUATION AND CERTIFICATION OF
CHANGES IN THE WORK.
9.4 The Contractor shall report to the Consultant any apparent deficiencies in Other Contractors' work which
would affect the Work of this Contract immediately they come to his attention and shall confirm such
report in writing. Failure by the Contractor to so report shall invalidate any claims against the Owner by
reason of the deficiencies of Other Contractors' work except as to those of which he was not reasonably
aware.
7.4
7.5
7.6
7.7
GC 8
8.1
GC 9
9.1
9.2
9.3
The claimant shall give written notice of such dispute to the other party no later than thirty (30) days after
the receipt of the Consultant's decision given under GC 3 - CONSULTANT, paragraph 3.7. Such notice
shall set forth particulars of the matters in dispute, the probable extent and value of the damage and the
relevant provisions of the Contract Documents. The other party shall reply to such notice no later than
fourteen (14) days after he receives or is considered to have received it, setting out in such reply his
grounds and other relevant provisions of the Contract Documents.
If the matter in dispute is not resolved promptly the Consultant will give such instructions as in his opinion
are necessary for the proper performance of the Work and to prevent delays pending settlement of the
dispute. The parties shall act immediately according to such instructions, it being understood that by so
doing neither party will jeopardize any claim they may have. If'it is subsequently determined that such
instructions were in error or at variance with the Contract Documents, the Owner shall pay the Contractor
costs incurred by the Contractor in carrying out such instructions which he was required to do beyond
what the Contract Documents correctly understood and interpreted would have required him to do,
including costs resulting from interruption of the Work. ..
It is agreed that no act by either party shall be construed as a renunciation or waiver of any of his rights or
recourses, provided he has given the notices in accordance with paragraph 7.2 and has carried out the
instructions as provided in paragraph 7.3.
If the parties have agreed to submit disputes to arbitration pursuant to a Supplementary Condition to the
Contract, or by subsequent agreement, then the dispute shall be submitted to arbitration in accordance
with the provisions of the arbitration legislation of the Place of the Work.
If no provision or agreement is made for arbitration then either party may submit the dispute to such
judicial tribunal as the circumstances may require.
In recognition of the obligation by the Contractor to perform the disputed work as provided in paragraph
7.3, it is agreed that settlement of dispute proceedings may be commenced immediately following the
dispute in accordance with the aforegoing settlement of dispute procedures.
ASSIGNMENT
Neither party to the Contract shall assign the Contract or a portion thereof without the written consent of
the other, which consent shall not be unreasonably withheld.
9.5 The Owner shall take all reasonable precautions to avoid labour disputes or other disputes on the Project
arising from the work of Other Contractors.
CCDC4 - 1982 File 00720
15
GC10 SUBCONTRACTORS
10. 1 The Contractor agrees to preserve and protect the rights of the parties under the Contract with respect to
work to be performed under subcontract and to:
(a) enter into contracts or written agreements with his Subcontractors to require them to perform their
work in accordance with and subject to the terms and conditions of the Contract Documents, and
(b) be as fully responsible to the Owner for acts and omissions of his Subcontractors and of persons
directly or indirectly employed by them as for acts and omissions of persons directly employed by him.
The Contractor therefore agrees that he will incorporate' the terms and conditions of the Contract
Documents into all subcontract agreements he enters into with his Subcontractors.
10.2 The Contractor agrees to employ those Subcontractors proposed by him in writing and accepted by the
Owner at the signing of the Contract.
10.3 The Owner may, for reasonable cause, object to the use of a proposed Subcontractor and require the
Contractor to employ one of the other subcontract bidders.
10.4 In the event that the Owner requires a change from a proposed Subcontractor the Contract Price shall be
adjusted by the difference in cost and mark-up occasioned by such required change.
10.5 The Contractor shall not be required to employ as a Subcontractor a person or firm to whom he may
reasonably object.
10.6 The Consultant may, upon reasonable request and at his discretion, provide to a Subcontractor
information as to the percentage or quantity of the Subcontractor's work which has been certified for
payment.
10.7 Nothing contained in the Contract Documents shall create a contractual relationship between a
Subcontractor and the Owner.
GC11
11.1
11.2
GC12
12.1
12.2
16
CHANGES IN THE WORK AND EXTRA WORK
Changes in the Work:
Except as provided in GC 12 - VALUATION AND CERTIFICATION OF CHANGES IN THE WORK,
paragraph 12.4:
(a) the Owner, through the Consultant, without invalidating the Contract, may make Changes in the
Work with the Contract Price and Contract Time being adjusted accordingly by written order, and
(b) no Changes in the Work shall be proceeded with without a written order signed by the Owner and no
claim for a change in the Contract Price or change in the Contract Time shall be valid unless so .
ordered and at the same time valued or agreed to be valued as provided in GC 12 - VALUATION
AND CERTIFICATION OF CHANGES IN THE WORK.
Extra Work:
(a) The Owner may offer the Contractor Extra Work. If the terms and conditions for the performance of
the Extra Work are agreed upon, the Owner, through the Consultant, shall issue a written change
order amending the Contract Price and Contract Time as appropriate, or a written order to proceed
until a price and change in time are agreed upon by the parties and a change order can be issued.
VALUATION AND CERTIFICATION OF CHANGES IN THE WORK
If the type of work involved in a Change in the Work is included in the items contained in the Schedule of
Contract Unit Prices in Article A-3 - CONTRACT PRICE, paragraph (c), it shall be performed on the same
payment basis as the original Work except as described in paragraphs 12.7 and 12.8, and the Contract
Time shall be extended for such time as the Consultant may decide in consultation with the Contractor.
If the type of work involved in a Change in the Work is not included in the items contained in the Schedule
of Contract Unit Prices in Article A-3 - CONTRACT PRICE, paragraph (c), or is such as to alter the nature
or intent of the work included in this Schedule, the value of such change shall be determined in one or
more of the following methods:
(a) by estimate and acceptance in a lump sum;
(b) by unit prices agreed upon;
(c) by cost and a fixed or percentage fee;
(d) by variation of the Contract Unit Prices.
CCDC4-1982FileOO12O
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
12.3
I
I
12.4
I
12.5
I
I
12.6
I
12.7
I
I
12.8
I
12.9
I
I
12.10
I
GC13
13.1
13.2
I
13.3
I
13.4
I
When a Change in the Work covered by paragraph 12.2 is proposed or required the Contractor shall
present to the Consultant for approval his claim for a change in the Contract Price and change in Contract
Time with appropriate documentation in a form acceptable to the Consultant. The Consultant will satisfy
himself as to the correctness of such claim and, when approved by the Owner, a change order shall be
issued to the Contractor amending the Contract Price and Contract Time as appropriate. The value of
work performed in the change shall be included for payment with the regular certificates for payment.
In the case of Changes in the Work to be paid for under methods (b) and (c) of paragraph 12.2, the form of
presentation of costs and methods of measurement shall be agreed to by the Consultant and Contractor
before proceeding with the change. The Contractor shall keep accurate records, as agreed upon, of
quantities or costs and present an account of the cost of the Change in the Work, together with vouchers
where applicable.
If the method of valuation, measurement, change in Contract Price and change in Contract Time cannot
be promptly agreed upon, and the change is required to be proceeded with then the Consultant in the first
instance will determine the method of valuation, measurement and the change fn Contract Price and
Contract Time subject to final determination in the manner set out in GC 7 - DISPUTES. In this case the
Consultant will, with the consent of the Owner, issue a written authorization for the change setting out the
method of valuation and if by lump sum his valuation of the change in Contract Price and Contract Time.
In the case of a dispute in the valuation of a change authorized in the Work and pending final
determination of such value, the Consultant will certify the value of work performed in accordance with his
own evaluation of the change and include the amount with the regular certificates for payment. The
Contractor shall keep accurate records of quantities and cost of such work.
Should the actual quantity of an item in the Schedule of Contract Unit Prices referred to in Article A-3 _
CONTRACT PRICE, paragraph (c), vary by more than 15% of the estimated quantity, either the Owner or
the Contractor may request a revision to the Contract Unit Price contained in the Schedule. Such a re-
quest for a revision in a Contract Unit Price shall be given as soon as reasonably possible after the party
concerned becomes aware of the circumstances.
If a revision to a Contract Unit Price is negotiated, then:
(a) the revised unit price in the case of a decrease of more than 15% of the estimated quantity will apply
to the actual work performed for that item, and
(b) the revised unit price in the case of an increase of more than 15% of the estimated quantity will apply
to the excess quantity of work for that item only.
If either party requests renegotiation of a Contract Unit Price, both parties agree to act promptly in order to
arrive at an equitable revision of the Contract Unit Price prior to proceeding with the work so affected. If
agreement of such renegotiation cannot be reached, the Contractor shall proceed with the work and the
matter shall be subject to final determination in the manner set out in GC 7 - DISPUTES. Pending such
settlement, payment for the work performed shall be made on the regular certificates for payment on the
basis of the Contract Unit Prices.
It is intended in all matters referred to above that the Owner, the Consultant and Contractor shall act
promptly.
APPLICATIONS FOR PAYMENT
Applications for payment on account may be made monthly as the Work progresses.
Applications for payment shall be dated the last day of the agreed monthly payment period and the
amount claimed shall be for the value of work performed and products delivered to the Place of the Work
at that date.
Applications for payment for products delivered to the Place of the Work but not yet incorporated into the
Work shall be supported by such evidence as the Consultant may reasonably require to establish the value
and delivery of the products.
Applications for release of holdback monies following Substantial Performance of the Work and the
application for final payment shall be made at the time and in the manner set forth in GC 14 _
CERTIFICATES AND PAYMENTS.
GC 14 CERTIFICATES AND PAYMENTS
14.1 The Consultant will, no later than ten (10) days after the receipt of an application for payment from the
Contractor submitted in accordance with GC 13 - APPLICATIONS FOR PAYMENT, issue a certificate for
payment in the amount applied for or in such other amount as he determines to be properly due. If the
Consultant amends the application, he will promptly notify the Contractor in writing giving his reasons for
the amendment.
I
I
I
eeDe 4 - 1982 File 00720
17
14.2 The Owner shall make payment to the Contractor on account in accordance with the provisions of Article
A-4 - PAYMENT no later than fifteen (15) days after the issuance of a certificate for payment by the Con-
su/tant.
14.3 The Consultant will, no later than ten (10) days after the receipt of an application from the Contractor for a
certificate of Substantial Performance of the Work, make an inspection and assessment of the Work to
verify the validity of the application. The Consultant will, no later than seven (7) days after his inspection,
notify the Contractor of his approval or the reasons for his disapproval of the application. When the Con-
sultant finds that Substantial Performance of the Work has been reached he will issue such a certificate.
The date of Substantial Performance of the Work shall be as stated in this certificate. Immediately follow-
ing the issuance of the certificate of Substantial Performance of the Work, the Consultant, in consultation
with the Contractor, will establish a reasonable date for the Total Performance of the Work.
14.4 Immediately following the issuance of the certificate of Substantial Performance of the Work the
Consultant will issue a certificate for payment of holdback monies. The holdback monies authorized by
this certificate shall become due and payable on the day following the expiration of the statutory limitation
period stipulated in the lien legislation applicable to the Place of the Work or where such legislation does
not exist or apply in accordance with such other legislation, industry practice or such other provisions
which may be agreed to between the parties, providing that the Owner may retain out of such holdback
monies any sums required by law to satisfy any liens against the Work or other monetary claims against
the Contractor and enforceable against the Owner and that the Contractor has submitted to the Owner a
sworn statement that all accounts for labour, subcontracts, products, construction machinery and equip-
ment and other indebtedness which may have been incurred by the Contractor in the Substantial
Performance of the Work and for which the Owner might in any way be held responsible have been paid in
full except holdback monies properly retained.
14.5 Where legislation permits and where, upon application by the Contractor, the Consultant has certified that
the work of a Subcontractor has been totally performed to his satisfaction prior to the Substantial Per-
formance of the Work, the Owner shall pay the Contractor the holdback retained for such Subcontractor
on the day following the expiration of the statutory limitation period for such Subcontractor stipulated in
the lien legislation applicable to the Place of the Work.
14.6 Notwithstanding the provisions of paragraph 14.5 and notwithstanding the wording of such certificates
the Contractor shall ensure that such work is protected pending the Total Performance of the Work and be
responsible for the correction of defects in it regardless of whether or not they were apparent when such
certificates were issued. "
14.7 The Consultant will, no later than ten (10) days after the receipt of an application from the Contractor for
payment upon Total Performance of the Work, make an inspection and assessment of the Work to verify
the validity of the application. The Consultant will, no later than seven (7) days after his inspection, notify
the Contractor of his approval or the reasons for his disapproval of the application. When the Consultant
finds that Total Performance of the Work has been reached he will issue a certificate of Total Performance
of the Work and certify for payment the remaining monies due to the Contractor under the Contract less
holdback monies which are required to be retained. The date of Total Performance of the Work shall be as
stated in this certificate. Subject to the provisions of GC 18 - WORKERS' COMPENSATION
INSURANCE, paragraph 18.1 the Owner shall, no later than fifteen (15) days after the issuance of such
certificate, make payment to the Contractor in accordance with the provisions of Article A-4 - PAY-
MENT.
14.8 The release of the remaining holdback monies shall become due and payable on the day following the
expiration of the statutory limitation period stipulated in the lien legislation applicable to the Place of the
Work, or where such legislation does not exist or apply in accordance with such other legislation, industry
practice or such other provisions which may be agreed to between the parties, providing that the Owner
may retain out of such holdback monies any sums required by law to satisfy any liens against the Work or
other monetary claims against the Contractor and enforceable against the Owner and that the Contractor
has submitted to the Owner a sworn statement that all accounts for labour, subcontracts, products,
construction machinery and equipment and other indebtedness which may have been incurred by the
Contractor in the Total Performance of the Work and for which the Owner might in any way be held
responsible have been paid in full except holdback monies properly retained.
14.9 If because of climatic or other conditions reasonably beyond the control of the Contractor there are items
of work that cannot be performed, payment in full for work which has been performed as certified by the
Consultant shall not be withheld or delayed by the Owner on account thereof, but the Owner may
withhold until the remaining work is finished only such monies as the Consultant determines are sufficient
and reasonable to cover the cost of performing such remaining work and to adequately protect the Owner
from claims.
18 eeDe 4 - 1982 File 00720
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
14.10 No payment made by the Owner under this Contract or partial or entire use or occupancy of the Work by
the Owner shall constitute an acceptance of work or products which are not in accordance with the re-
quirements of the Contract Documents.
14.11 All certificates issued by the Consultant shall be to the best of his knowledge, information and belief. By
issuing any certificate the Consultant does not guarantee the correctness or completeness of the Work.
14.12 As of the date of Total Performance of the Work, as set out in the certificate of Total Performance of the
Work, the Owner expressly waives and releases the Contractor from all claims against the Contractor
including without limitation those that might arise from the negligence or breach of contract by the
Contractor except one or more of the following:
(a) those made in writing prior to the date of Total Performance of the Work and still unsettled;
(b) those arising from the provisions of GC 19 - INDEMNIFICATION or GC 24 - WARRANTY;
In the Common Law provinces GC 14. 12(c) shall read as follows:
(c) those made in writing within a period of six years from the date of Substantial Performance of the
Work, as set out in the certificate of Substantial Performance of the Work, or within such shorter
period as may be prescribed by any limitation statute of the province or territory of the Place of the
Work and arising from any liability of the Contractor for damages resulting from his performance of
the Contract with respect to substantial defects or deficiencies in the Work for which the Contractor is
proven responsible.
As used herein "substantial defects or deficiencies" means those defects or deficiencies in the Work
which affect the Work to such an extent or in such manner that a significant part or the whole of the
Work is unfit for the purpose intended by the Contract Documents.
In the Province of Quebec GC 14. 12(c) shall read as follows:
(c) those arising under the provisions of Article 1688 of the Civil Code.
14.13 As of the date of Total Performance of the Work, as set out in the certificate of Total Performance of the
Work, the Contractor expressly waives and releases the Owner from all claims against the Owner including
without limitation those that might arise from the negligence or breach of contract by the Owner except
those made in writing prior to the Contractor's application for payment upon Total Performance of the
Work and still unsettled.
14.14 Notwithstanding GC 1 - DOCUMENTS, paragraph 1.6, in the event of conflict between the provisions of
this General Condition and Article A-5 - RIGHTS AND REMEDIES paragraph (a) or GC 22 - DAMAGES
AND MUTUAL RESPONSIBILITY, the provisions of this General Condition shall govern.
GC 15 TAXES AND DUTIES
15.1 Unless otherwise stated in Supplementary Conditions the Contractor shall pay the government sales
taxes, customs duties and excise taxes with respect to the Contract.
15.2 Where an exemption or recovery of government sales taxes, customs duties or excise taxes is applicable to
the Contract, the procedure shall be as established in the Supplementary Conditions.
15.3 Any increase or decrease in costs to the Contractor due to changes in such taxes and duties after the date
of the tender shall increase or decrease the Contract Price accordingly.
GC16
16.1
16.2
LAWS, NOTICES, PERMITS AND FEES
The laws of the Place of the Work shall govern the Work.
The Contractor shall obtain the permits, licences and certificates and pay the fees required for the
performance of the Work which are in force at the date of tender closing, but this shall not include the
obtaining of permanent easements or rights of servitude.
The Contractor shall give the required notices and comply with the laws, ordinances, rules, regulations,
codes and orders of the authorities having jurisdiction which are or become in force during the
performance of the Work and which relate to the Work, to the preservation of the public health, and to
construction safety.
16.3
eeDe 4 - 1982 File 00720
19
16.4 The Contractor shall not be responsible for verifying that the Contract Documents are in compliance with
the applicable laws, ordinances, rules, regulations and codes relating to the Work. If the Contract
Documents are at variance therewith, or changes which require modification to the Contract Documents
are made to the laws, ordinances, rules, regulations and codes by the authorities having jurisdiction subse-
quent to the date of tender closing, the Contractor shall notify the Consultant in writing requesting direc-
tion immediately such variance or change becomes known to him. The Consultant will make the change~
required to the Contract Documents in accordance with GC 11 - CHANGES IN THE WORK AND
EXTRA WORK and the value of the changes shall be determined in accordance with GC 12 - VALUA-
TION AND CERTIFICATION OF CHANGES IN THE WORK.
16.5 If the Contractor fails to notify the Consultant in writing and obtain his direction as required in paragraph
16.4 and performs work knowing it to be contrary to any laws, ordinances, rules, regulations, codes and
orders of the authorities having jurisdiction, the Contractor shall be responsible for and shall correct the
violations thereof and shall bear the costs, expense and damages attributable to his failure to comply with
the provisions of such laws, ordinances, rules, regulations, codes and orders.
GC 17 PATENT FEES
17.1 The Contractor shall pay the royalties and patent licence fees required for the performance of the
Contract. He shall hold the Owner harmless from and against claims, demands, losses, costs, damages,
actions, suits, or proCeedings arising out of the Contractor's performance of the Contract which are
attributable to an infringement or an alleged infringement of a patent of invention by the Contractor or
anyone for whose acts he may be liable.
17.2 The Owner shall hold the Contractor harmless against claims, demands, losses, costs, damages, actions,
suits, or proceedings arising out of the Contractor's performance of the Contract which are attributable to
an infringement or an alleged infringement of a patent of invention in executing anything for the purpose
of the Contract, the model, plan or design of which was supplied to the Contractor as part of the Contract
Documents.
GC18
18.1
18.2
GC19
19.1
19.2
19.3
19.4
20
WORKERS' COMPENSATION INSURANCE
Prior to commencing the Work and prior to receiving payment on Substantial and Total Performance of
the Work, the Contractor shall provide evidence of compliance with the requirements of the province or
territory of the Place of the Work with respect to workers' compensation insurance including payments
due thereunder.
At any time during the term of the Contract, when requested by the Owner, the Conttactor shall provide
such evidence of compliance by himself and his Subcontractors.
INDEMNIFICATION
The Contractor shall indemnify and hold harmless the Owner and the Consultant, their agents and
employees from and against claims, demands, losses, costs, damages, actions, suits or proceedings by
third parties that arise out of, or are attributable to, the Contractor's performance of the Contract
(hereinafter called "claims"), provided such claims are:
(a) attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible pro-
perty,and
(b) caused by negligent acts or omissions of the Contractor or anyone for whose acts he may be liable,
and
lc) made in writing within a period of six years from the date of Substantial Performance of the Work, as
set out in the certificate of Substantial Performance of the Work, or within such shorter period as may
be prescribed by any limitation statute of the province or territory of the Place of the Work.
The Owner expressly waives the right to indemnity for claims other than those stated above.
The obligation of the Contractor to indemnify hereunder shall be limited to one million dollars per
occurrence from the commencement of the Work until Substantial Performance of the Work and
thereafter to an aggregate limit of one million dollars.
The Owner shall indemnify and hold harmless the Contractor, his agents and employees from and against
claims, demands, losses, costs, damages, actions, suits, or proceedings arising out of the Contractor's
performance of the Contract which are attributable to a lack of or defect in title or an alleged lack of or
defect in title to the Place of the Work.
Notwithstanding GC 1 - DOCUMENTS paragraph 1.6, in the event of conflict between the provisions of
this General Condition and Article A-5 - RIGHTS AND REMEDIES paragraph (a) or GC 22 - DAMAGES
AND MUTUAL RESPONSIBILITY, the provisions of this General Condition shall govern.
eeDe 4 - 1982 Ale 00720
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC20
20.1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
INSURANCE
Without restricting the generality of GC 19 - INDEMNIFICATION, the Contractor shall provide, maintain
and pay for the insurance coverages listed in this General Condition unless otherwise stipulated:
(a) General Liability Insurance:
General liability insurance shall be in the joint names of the Contractor, the Owner, and the Consultant
with limits of not less than one million dollars inclusive per occurrence for bodily injury, death, and
damage to property including loss of use thereof, with a property damage deductible of five hundred
dollars. The form of this insurance shall be the latest edition of CCDC Form 101 and shall be main-
tained continuously from commencement of the Work until twelve (12) months following the date of
Substantial Performance of the Work, as set out in the certificate of Substantial Performance of the
Work, or until the certificate of Total Performance of the Work is issued, whichever is the later, and
with respect to completed operations coverage for a period of not less than twenty-four (24) months
from the date of Total Performance of the Work, as set out in the certificate of Total Performance of
Work, and thereafter to be maintained for a further period of four (4) years. Should the Contractor
decide not to employ Subcontractors for operations requiring the use of explosives for blasting, or pile
driving or caisson work, or removal or weakening of support of property, building or land; CCDC
Form 101 as required shall include Endorsement CCDC Form 101-2.
(b) Automobile Liability Insurance:
Automobile liability insurance in respect of licensed vehicles shall have limits of not less than one
million dollars inclusive per occurrence for bodily injury, death, and damage to property, in the follow-
ing forms endorsed to provide the Owner with not less than fifteen (15) days written notice in advance
of any cancellation, change or amendment restricting coverage:
(1) Standard non-owned automobile policy including standard contractual liability endorsement.
(2) Standard owner's form automobile policy providing third party liability and accident benefits
insurance and covering licensed vehicles owned or operated by or on behalf of the Contractor.
(c) Aircraft and Watercraft Liability Insurance:
Aircraft and watercraft liability insurance with respect to owned or non-owned aircraft and watercraft
if used directly or indirectly in the performance of the Work, including use of additional premises, shall
be subject to limits of not less than one million dollars inclusive per occurrence for bodily injury, death,
and damage to property including loss of use thereof and limits of not less than one million dollars for
aircraft passenger hazard. Such insurance shall be in a form acceptable to the Owner. The policies
shall be endorsed to provide the Owner with not less than fifteen (15) days written notice in advance
of cancellation, change or amendment restricting coverage.
(d) Property and Boiler Insurance:
(1) All risks property insurance shall be in the joint names of the Contractor, the Owner and the Con-
sultant, insuring not less than the sum of the amount of the Estimated Contract Price and the full
value, as stated in the Supplementary Conditions, of products that are specified to be provided
by the Owner for incorporation into the Work, with a deductible not exceeding one percent of the
amount insured a.t the site of the Work. The form of this insurance shall be the latest edition of
CCDC Form 201 and shall be maintained continuously until ten (10) days after the date of Total
Performance of the Work, as set out in the certificate of Total Performance of the Work.
(2) Boiler insurance insuring the interests of the Contractor, the Owner and the Consultant for not
less than the replacement value of boilers and pressure vessels forming part of the Work. The
form of this insurance shall be the latest edition of CCDC Form 301 and shall be maintained con-
tinuously from commencement of use or operation of the property insured and until ten (10) days
after the date of Total Performance of the Work, as set out in the certificate of Total Performance
of the Work.
(3) Should the Owner wish to use or occupy part or all of the Work he shall give thirty (30) days writ-
ten notice to the Contractor of the intended purpose and extent of such use or occupancy. Prior
to such use or occupancy the Contractor shall notify the Owner in writing of the additional
premium cost, if any, to maintain property and boiler insurance, which shall be at the Owner's
expense. If because of such use or occupancy the Contractor is unable to provide coverage, the
Owner upon written notice from the Contractor and prior to such use or occupancy shall provide,
maintain and pay for property and boiler insurance insuring the full value of the Work, as in
subparagraphs (1) and (2), in CCDC Forms 201 and 301, including coverage for such use or
occupancy and shall provide the Contractor with proof of such insurance. The Contractor shall
refund to the Owner the unearned premiums applicable to the Contractor's polices upon termina-
tion of coverage.
eeDe 4 - 1982 Rle 00720
21
(4) The policies shall provide that, in the event of a loss or damage, payment shall be made to the
Owner and the Contractor as their respective interests may appear. The Contractor shall act on
behalf of the Owner and himself for the purpose of adjusting the amount of such loss or damage
payment with the Insurers. When the extent of the loss or damage is determined the Contractor
shall proceed to restore the Work. Loss or damage shall not affect the rights and obligations of
either party under the Contract except that the Contractor shall be entitled to such reasonable
extension of Contract Time relative to the extent of the loss or damage as the Consultant may
decide in consultation with the Contractor.
(5) Payment for loss or damage:
The Contractor shall be entitled to receive from the Owner, in addition to the amount due under
the Contract, the amount at which the Owner's interest in restoration of the Work has been
appraised, such amount to be paid as the restoration of the Work proceeds and in accordance
with the requirements of GC 13 - APPLICATIONS FOR PAYMENT and GC 14 - CER-
TIFICATES AND PAYMENTS. In addition the Contractor shall be entitled to receive from the.
paymen.ts made by the Insurer the amount of the Contractor's interest in the restoration of the
Work.
(6) The Contractor shall be responsible for deductible amounts under the policies except where such
amounts may be excluded from the Contractor's responsibility by the terms of GC 21 -
PROTECTION OF WORK AND PROPERTY and GC 22 - DAMAGES AND MUTUAL
RESPONSIBILITY.
(7) In the event of loss or damage to the Work arising from the work or act of an Other Contractor,
the Owner, in accordance with his obligations under GC 9 - OTHER CONTRACTORS,
paragraph 9.2, shall pay the Contractor the cost of restoring the Work as the restoration of the
Work proceeds and in accordance with the requirements of GC 13 - APPLICATIONS FOR PAY-
MENT and GC 14 - CERTIFICATES AND PAYMENTS.
I
I
I
I
I
I
I
I
(e) Contractors' Equipment Insurance:
All risks contractors' equipment insurance covering construction machinery and equipment used by
the Contractor for the performance of the Work, including boiler insurance on temporary boilers and
pressure vessels, shall be in a form acceptable to the Owner and shall not allow subrogation claims by
the Insurer against the Owner. The policies shall be endorsed to provide the Owner with not less than
fifteen (15) days written notice in advance of cancellation, change or amendment restricting
coverage. Subject to satisfactory proof of financial capability by the Contractor for self-insurance of
his equipment, the Owner agrees to waive the equipment insurance requirement.
20.2 Unless specified otherwise the duration of each insurance policy shall be from the date of commencement
of the Work until the date of Total Performance of the Work, as set out in the certificate of' Total
Performance of the Work.
20.3 The Contractor shall provide the Owner with proof of insurance prior to commencement of the Work and
shall promptly provide the Owner with a certified true copy of each insurance policy exclusive of informa-
tion pertaining to premium or premium bases used by the Insurer to determine the cost of the insurance.
20.4 If the Contractor fails to provide or maintain insurance as required in this General Condition or elsewhere in
the Contract Documents, then the Owner shall have the right to provide and maintain such insurance and
give evidence thereof to the Contractor and the Consultant. The cost thereof shall be payable by the Con-
tractor to the Owner on demand or the Owner may deduct the costs thereof from monies which are due or
may become due to the Contractor.
I
I
I
I
I
GC 21 PROTECTION OF WORK AND PROPERTY
21.1 The Contractor shall protect the Work and the Owner's property and property adjacent to the Place of the
Work from damage and shall be responsible for damage which may arise as the result of his operations
under the Contract except damage which occurs as the result of:
(a) errors in the Contract Documents;
(b) acts or omissions by the Owner, the Consultant, Other Contractors, their agents and employees.
21.2 Should the Contractor in the performance of this Contract damage the Work, the Owner's property or
property adjacent to the Place of the Work, the Contractor shall be responsible for the making good of
such damage at his expense.
21.3 Should damage occur to the Work or Owner's property for which the Contractor is not responsible as
provided in paragraph 21.1 he shall make good such damage to the Work and if the Owner so directs to the
Owner's property and the Contract Price and Contract Time shall be adjusted in accordance with GC 11 -
CHANGES IN THE WORK AND EXTRA WORK and the value of the changes shall be determined in
accordance with GC 12 - VALUATION AND CERTIFICATION OF CHANGES IN THE WORK.
I
I
I
I
I
22
ceDe 4 - 1982 File 00720
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC 22 DAMAGES AND MUTUAL RESPONSIBILITY
22.1 If either party to this Contract should suffer damage in any manner because of any wrongful act or neglect
of the other party or of anyone for whom he is responsible in law, then he shall be reimbursed by the other
party for such damage. The party reimbursing the other party shall be subrogated to the rights of the other
party in respect of such wrongful act or neglect if it be that of a third party.
22.2 Claims under this General Condition shall be made in writing to the party liable within reasonable time after
the first observance of such damage and may be adjusted by agreement or in the manner set out in GC 7
- DISPUTES.
22.3 If the Contractor has caused damage to an Other Contractor on the Work, the Contractor agrees upon due
notice to settle with such Other Contractor by agreement or arbitration, if he will so settle. If such Other
Contractor sues the Owner on account of d~mage alleged to have been so sustained, the Owner shall
notify the Contractor and may require the Contractor to defend the action at the Contractor's expense. If a
final order or judgment against the Owner arises therefrom the Contractor shall payor satisfy it and pay the
costs incurred by the Owner.
22.4 If the Contractor becomes liable to payor satisfy a final order, judgment or award against the Owner then
the Contractor, upon undertaking to indemnify the Owner against any and all liability for costs, shall have
the right to appeal in the name of the Owner such final order or judgment to any and all courts of compe-
tent jurisdiction.
GC23
23.1
23.2
BONDS
The Contractor shall promptly provide to the Owner the surety bonds called for in the tender documents.
Such bonds shall be issued by a duly licensed surety company authorized to transact a business of
suretyship in the province or territory of the Place of the Work and shall be maintained in good standing
until the fulfillment of the Contract. The form of such bonds shall be in accordance with the latest edition
of the CCDC approved bond forms.
GC24 WARRANTY
24.1 The Contractor shall be responsible for the proper performance of the Work only to the extent that the
design and specifications permit such performance.
24.2 Subject to paragraph 24.1 the Contractor agrees to correct promptly, at his own expense, defects or
deficiencies in the Work which appear prior to and during the period of one year from the date of Substan-
tial Performance of the Work, as set out in the certificate of Substantial Performance of the Work, or such
longer periods as may be specified for certain products or work.
24.3 During the period provided in GC 3 - CONSULTANT, paragraph 3.2, the Consultant shall promptly give
the Contractor written notice of observed defects and deficiencies.
24.4 The Contractor agrees to correct or pay for damage resulting from corrections made under the
requirements of paragraph 24.2.
GC 25 CONTRACTOR'S RESPONSIBILITIES AND CONTROL OF THE WORK
25.1 The Contractor shall have complete control of the Work and shall effectively direct and supervise the Work
so as to ensure conformance with the Contract Documents. He shall be solely responsible for construction
means, methods, techniques, sequences and procedures and for co-ordinating the various parts of the
Work under the Contract.
25.2 The Contractor shall be solely responsible for construction safety at the Place of the Work and for
compliance with the rules, regulations and practices required by the applicable construction safety legisla-
tion.
25.3 The Contractor shall have the sole responsibility for the design, erection, operation, maintenance and
removal of temporary structural and other temporary facilities and the design and execution of construc-
tion methods required in their use. The Contractor shall engage and pay for registered professional
engineering personnel skilled in the appropriate disciplines to perform these functions where required by
law or by the Contract Documents and in all cases where such temporary facilities and their method of
construction are of such a nature that professional engineering skill is required to produce safe and
satisfactory results.
25.4 Notwithstanding the provisions of paragraphs 25.1 and 25.3, or provisions to the contrary elsewhere in the
Contract Documents where such Contract Documents include designs for temporary structural and other
temporary facilities or specify a method of construction in whole or in part, such facilities and methods
shall be considered to be part of the design of the Work and the Contractor shall not be held responsible
for that part of the design or the specified method of construction. The Contractor shall, however, be
responsible for the execution of such design or specified method of construction in the same manner that
he is responsible for the execution of the Work.
CCDC4 - 1982 File 00720
23
25.5
The Contractor shall review the Contract Documents and shall promptly report to the Consultant any
error, inconsistency or omission he may discover. Such review by the Contractor shall be to the best of his
knowledge, information and belief and in making such review the Contractor does not assume any respon-
sibility to the Owner or. the Consultantfor the accuracy of the review. The Contractor shall not be liable for
damage or costs resulting from such errors, inconsistencies or omissions in the Contract Documents
which he did not discover. If the Contractor does discover any error, inconsistency or omission in the
Contract Documents he shall not proceed with the work affected until he has received corrected or mis-
sing information from the Consultant.
The Contractor shall prepare and update as required a construction schedule indicating the timing of the
major activities of the Work. The schedule shall be designed to ensure conformance with the required
Contract Time. The schedule shall be submitted to the Owner and the Consultant for their information
within a reasonable time from the date of Contract award. The Contractor shall monitor the progress of the
Work relative to the schedule and advise the Consultant of any revisions required as the result of delays as
provided in GC 4 - DELAYS, indicating the results expected from the resultant change in schedule.
25.6
GC 26 SUPERINTENDENCE
26.1 The Contractor shall employ a competent supervisor and necessary assistants who shall be in attendance
at the Place of the Work while work is being performed.
26.2 The supervisor shall be satisfactory to the Consultant and shall not be changed except for good reason and
only then after consultation with the Consultant.
26.3 The supervisor shall represent the Contractor at the Place of the Work and instructions given to him by the
Consultant shall be held to have been given to the Contractor. Important instructions shall be confirmed to
the Contractor in writing; other instructions shall be so confirmed if requested.
GC 27 LABOUR AND PRODUCTS
27.1 Unless otherwise stipulated elsewhere in the Contract Documents, the Contractor shall provide and pay
for labour, products, tools, construction machinery and equipment, water, heat, light, power, transporta-
tion and other facilities and services necessary for the performance of the Work in accordance with the
Contract.
27.2 Products provided shall be new unless otherwise specified in the Contract Documents. Products which are
not specified shall be of a quality best suited to the purpose required and their use subject to the approval
of the Consultant.
27.3 The Contractor shall maintain good order and discipline among his employees engaged on the Work and
shall not employ on the Work anyone not skilled in the task assigned to him.
GC 28 SUBSURFACE CONDITIONS
28.1 The Contractor shall promptly notify the Consultant in writing if in his opinion the subsurface conditions at
the Place of the Work differ materially from those indicated in the Contract Documents, or a reasonable
assumption of probable conditions based thereon.
28.2 After prompt investigation, should the Consultant determine that conditions do differ materially, he will
issue appropriate instructions for changes in the Work in accordance with GC 11 - CHANGES IN THE
WORK AND EXTRA WORK, and the value of the changes shall be determined in accordance with GC 12
-VALUATION AND CERTIFICATION OF CHANGES IN THE WORK.
GC29
29.1
USE OF THE WORK
The Contractor shall confine his apparatus, the storage of products, and the operations of his employees
to limits indicated by laws, ordinances, permits or the Contract Documents and shall not unreasonably
encumber the premises with his products.
The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will
endanger the safety of the Work.
29.2
24
CCDC4 - 1982 FHeOO720
I
I
I
I
I
I
I
I
I
I
I'
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC30 CLEANUP AND FINAL CLEANING OF THE WORK
30.1 The Contractor shall maintain the Work in a tidy condition and free from the accumulation of waste
products and debris, other than that caused by the Owner, Other Contractors or their employees.
30.2 Upon attaining Substantial Performance of the Work, the Contractor shall remove his surplus products,
tools, construction machinery and equipment not required for the performance of the remaining work. He
shall also remove waste products and debris other than that caused by the Owner, Other Contractors or
their employees, and leave the Work clean and suitable for occupancy by the Owner unless otherwise
specified.
30.3 Total Performance of the Work shall not be attained until the Contractor has removed his surplus
products, tools, construction machinery and equipment. He shall also have removed waste products and
debris, other than that caused by the Owner, Other Contractors or their employees.
GC 31 CUlTlNG AND REMEDIAL WORK
31.1 The Contractor shall do the cutting and remedial work required to make the several parts of the Work
come together properly.
The Contractor shall co-ordinate the Work to ensure that this requirement is kept to a minimum.
Should the Owner, the Consultant, Other Contractors or anyone employed by them be responsible for
ill-timed work necessitating cutting or remedial work to be performed, the cost of such cutting or remedial
work shall be valued as provided in GC 12 - VALUATION AND CERTIFICATION OF CHANGES IN THE
WORK.
31.2
31.3
31.4 Cutting and remedial wflrk shall be performed by specialists familiar with the materials affected and shall
be performed in a manner to neither damage nor endanger the Work.
GC32 INSPECTION OF THE WORK
32.1 The Owner and the Consultant or their authorized agents or representatives shall at all times have access
to the Work. If parts of the Work are in preparation at locations other than the Place of the Work, the
Owner and the Consultant or their authorized agents or representatives shall be given access to such work
whenever it is in progress.
32.2 If work is designated for spec;:ial tests, inspections or approvals in the Contract Documents, or by the
Consultant's instructions, or the laws or ordinances of the Place of the Work, the Contractor shall give the
Consultant timely notice requesting inspection. Inspection by the Consultant shall be made promptly. The
Contractor shall arrange for inspections by other authorities and shall give the Consultant timely notice of
the date and time.
32.3 If the Contractor covers or permits to be covered work that has been designated for special tests,
inspections or approvals before such special tests, inspections or approvals are made, given or completed,
he shall, if so directed, uncover such work, have the inspections or tests satisfactorily completed and make
good such work at his own expense.
32.4 The Consultant may order any part or parts of the Work to be specially examined should he believe that
such work is not in accordance with the requirements of the Contract Documents. If, upon examination
such work be found not in accordance with the requirements of the Contract Documents, the Contractor
shall correct such work and pay the cost of examination and correction. If such work be found in
accordance with the requirements of the Contract Documents, the Owner shall pay the cost of examina-
tion and replacement.
32.5 The Contractor shall furnist1 promptly to the Consultant two (2) copies of certificates and inspection
reports relating to the Work.
GC 33 REJECTED WORK
33.1 Defective work, whether the result of poor workmanship, use of defective products, or damage through
carelessness or other act or omission of the Contractor and whether incorporated in the Work or not,
which has been rejected by the Consultant as failing to conform to the Contract Documents shall be
removed promptly from the Place of the Work by the Contractor and replaced or re-executed promptly in
accordance with the Contract Documents at the Contractor's expense.
33.2 Other Contractors' work destroyed or damaged by such removals or replacements shall be made good
promptly at the Contractor's expense.
33.3 If in the opinion of the Consultant it is not expedient to correct defective work or work not performed in
accordance with the Contract Documents, the Owner may deduct from the monies otherwise due to the
Contractor the difference in value between the work as performed and that called for by the Contract
Documents, the amount of which will be determined in the first instance by the Consultant.
eeDe 4 - 1982 File 00720
25
GC 34 SHOP DRAWINGS
34.1 The term "shop drawings" means drawings, diagrams, illustrations, schedules, performance charts,
brochures and other data which are to be provided by the Contractor to illustrate details of a portion of the
Work.
34.2 The Contractor shall arrange for the preparation of clearly identified shop drawings as called for by the
Contract Documents or as the Consultant may reasonably request.
34.3 Prior to submission to the Consultant the Contractor shall review all shop drawings. By this review the
Contractor represents that he has determined and verified all field measurements, field construction
criteria, materials, catalogue numbers and similar data or will do so and that he has checked and co-
ordinated each shop drawing with the requirements of the Work and of the Contract Documents. The
Contractor's review of each shop drawing shall be indicated by stamp, date, and signature of a responsible
person.
34.4 The Contractor shall submit shop drawings to the Consultant for his review with reasonable promptness
and in orderly sequence so as to cause no delay in the Work or in the work of Other Contractors. If either
the Contractor or the Consultant so requests they shall jointly prepare a schedule fixing the dates for sub-
mission and return of shop drawings. Shop drawings shall be submitted in the form of reproducible
transparencies or prints as the Consultant may direct. At the time of submission the Contractor shall notify
the Consultant in writing of any deviations in the shop drawings from the requirements of the Contract
Documents.
34.5 The Consultant will review and return shop drawings in accordance with any schedule agreed upon, or
otherwise with reasonable promptness so as to cause no delay. The Consultant's review will be for
conformity to the design .concept and for general arrangement only and such review shall not relieve the
Contractor of responsibility for errors or omissions in the shop drawings or of responsibility for meeting all
requirements of the Contract Documents unless a deviation on the shop drawings has been approved in
writing by the Consultant.
34.6 The Contractor shall make any changes in shop drawings which the Consultant may require consistent
with the Contract Documents and resubmit unless otherwise directed by the Coma,:tant. When resubmit-
ting, the Contractor shall notify the Consultant in writing of any revisions other than those requested by
the Consultant.
GC35 CASH ALLOWANCES
35.1 The Estimated Contract Price includes cash allowances stated in the Contract Documents and itemized in
the Schedule of Contract Unit Prices.
35.2 Cash allowances, unless otherwise specified, cover the net cost to the Contractor of services, products,
construction machinery and equipment, freight, unloading, handling, storage, installation and other
authorized expenses incurred in performing the work stipulated under the cash allowances.
35.3 The Contract Unit Prices, and not the cash allowances, include the Contractor's overhead and profit in
connection with such cash allowances.
35.4 Where costs under a cash allowance exceed the amount of the allowance, the Contractor shall be
compensated for any excess incurred and substantiated plus an allowance for overhead and profit as set
out in the Contract Documents.
35.5 The Estimated Contract Price shall be adjusted by written order to provide for any excess or deficit to each
cash allowance.
35.6 Progress payments on account of work authorized under cash allowances shall be included in the
Consultant's monthly certificates for payment.
35.7 A schedule shall be prepared jointly by the Consultant and Contractor to show when items called for under
cash allowances must be authorized by the Consultant for ordering purposes so that the progress of the
Work will not be delayed.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC 36 CONTINGENCY ALLOWANCE
36.1 The Estimated Contract Price includes the contingency allowance, if any, stated in the Contract I
Documents and itemized in the Schedule of Contract Unit Prices.
36.2 Expenditures under the contingency allowance shall be authorized in accordance with GC 11 -
CHANGES IN THE WORK AND EXTRA WORK, and the value shall be determined in accordance with I
GC 12 - VALUATION AND CERTIFICATION OF CHANGES IN THE WORK.
26
ceDe 4 - 1982 File 00720
I
I
I
I
I
I
SUPPLEMENTARY CONDITIONS
Page 1
The Definitions and General Conditions for Unit Price Contract, CCDC No.4, 1982 File 00530 are
amended as follows:
1. DEFINITIONS ITEM NO.2 CONTRACT DOCUMENTS
Add:
I
I
I
I
I
The Contract Documents shall also include the Instructions to Bidders, the completed
tender as submitted by the successful bidder, the Schedule of Unit Prices, and the
completed list of Subcontractors.
DEFINITIONS ITEM NO.4 ENGINEER
Change:
The word "Engineer" shall mean "Landscape Architect".
The words "reviewed", "satisfactory", "directed", "instructed" and similar words, shall be
understood to be followed by "by the Landscape Architect", unless the context clearly
indicates otherwise.
The General Conditions for Unit Price Contract, CCDC No.4,1982 edition, Common
Law Version are amended as follows:
GC DOCUMENTS
I
I
In paragraph 1.1 change "duplicate" to read "quadruplicate".
GC 23 BONDS
I
I
I
I
I
Change paragraph 23.1 to read:
The contractor shall promptly provide and pay for a Performance Bond in the amount
of one hundred (100) percent of the Contract Price covering the performance of the
Contract including the requirements of GC 24- WARRANTY.
GC 26 SUPERINTENDENCE
Add as paragraph 26.4:
The contractor shall provide for specialty supervisors as required in Division 1 - General
Requirements.
GC 36 CONTINGENCY ALLOWANCE
Add as paragraph 26.4:
"The contractor shall refer to Division 1- Contingency Allowances, for dollar amounts to
allowed for in the tender sum.
I
I
I
I
I
I
I
I
I
I
SUPPLEMENTARY CONDITIONS
Page 2
GC 14 CERTIFICATES AND PAYMENT
Change pafagraph 14.2 to read:
The owner shall make payment to the contractor on account in accordance with the
provisions of Article A-4 PAYMENT no later than (30) thirty days after the issuance of
a certificate by the Landscape Architect.
GC 12 VALUATION AND CERTIFICATES OR CHANGES IN THE WORK
Change:
Wherever reference is made to 15% of the estimated quantities, it shall be changed to
mean the owner has the fight to revise or otherwise delete unlimited quantities without
a change in Contract Unit Prices.
I
I
I
I
I
I
I
I
I
Change:
When changes occur by more than 15% of the estimated quantities, the contractor may
. not revise the Contract Unit Price.
GC 24 WARRANTY
Change: 24.2 to read:
Subject to paragraph 24.1 the Contractor agrees to correct promptly, at his own expense,
defects or deficiencies in the Work which appear prior to and during the period of two
years from the date of Substantial Performance of the Work, as set out in the certificate
of Substantial Performance of the Work, or such longer periods as may be specified for
certain products or work.
END
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1.4
1.5
I
I
I
I
>1
GENERAL REQUIREMENTS
Section 1005
Page 1
1.1
General
1. Comply with requirementsof General Conditions and Supplementary General Conditions.
2. Division 1 requirements apply to all sections of work.
3. In case of conflict between General Conditions and Division 1 requirements, General
Conditions shall govern.
1.2
Summary of Work
1. Provide all items, articles, materials, services and incidentals, whether or not expressly
specified or shown on drawings, to make finished work complete and fully operational,
consistent with the intent of the contract documents.
1.3
Examination
1. Examine the site and surrounding areas and be fully informed as to the conditions and
limitations under which the work has to be executed. Oaims for additional costs will not
be entertained with respect to conditions which could reasonably have been ascertained
by an inspection of the site prior to tender closing.
2. Prior to commencement of work, make careful examination of previously executed work,
existing conditions, levels, dimensions and clearances. Promptly advise consultant of
unsatisfactory preparatory work and substrate conditions; commencement of work implies
acceptance of conditions.
Division of Work
1. Work specified in the specification has been divided into technical sections for the
purpose of ready reference. Division of work among subcontractors and suppliers is
solely the contractor's responsibility and consultant assumes no responsibility to act as
an arbiter to establish subcontract limits between sections or divisions of work.
Metric Project
1. This project is based on the International System of Units (SI). Measurements are
expressed in metric (SI) units and depending on the progress made in the various sectors
of the industry are either hard or soft converted units.
2. All metric units specified shall be taken to the minimum acceptable unless otherwise
noted.
3. It is the contractor's responsibility to check and verify with manufacturers and suppliers
on the availability of materials and products in either metric or imperial sizes.
4. Where a material or product cannot be obtained in the metric size specified, provide the
next larger imperial size available.
I
I
GENERAL REQUIREMENTS
Section 1005
Page 2
I
I
5. Where both metric and imperial sizes or dimensions are shown, the metric size or
dimension shall govern.
1.6
Protection
I
I
I
I
I
I
I
!
I
I
I
I
'I
I
I
1. Ensure that no damage is caused to existing structures, buildings, foundations, pavement,
fences, curbs, grounds, plants, property, utilities, services, finishes during the progress of
work. Repair and make good any damage caused at no extra cost to owner to the
complete satisfaction of the respective property owners and authorities having
jurisdiction. Do not proceed with repairs or remedial work without written permission
of the consultant. Only trades specifically capable of performing the work will be allowed
to make remedial or repair work.
2. Keep municipal roads clean of mud and debris resulting from construction traffic.
3. Prevent soiling of pavement due to spillage, mixing of material or any other cause. Make
good any damages caused.
4. Protect new work from damage with suitable protective coverings.
1.7
Safety and Security
1. Be responsible for security of all areas affected by work of this contract until taken over
by owner. Take steps to prevent entry to the work by unauthorized persons and guard
against theft, fire and damage by any cause.
2. A regular full-time watchman is generally not required on site, but if in the opinion of
the consultant, the work is not adequately protected by the contractor, the owner may
demand that a watchman be employed by the contractor at no extra cost to the contract.
3. Maintain fire protection for work. Store paints and volatile substances in a separate and
controlled location and inspect frequently. Inspect temporary wiring, drop cords,
extension cables for defective insulation or connections frequently. Remove combustible
wastes frequently. Prohibit smoking in areas where volatile and flammable substances
are used
1.8
Use of Site and Premises
1. Accept full responsibility for the site from the time of contract award until Substantial
Performance of the work.
2. Check means of access and egress, rights and interests which may be interfered with. Do
not block lanes, roadways, entrances or exits.
3. Where encroachment beyond property limits is necessary make arrangement with
respective property owners.
I
I
GENERAL REQUIREMENTS
Section 1005
Page 3
I
I
1.9
Services and Utilities
1. Consult with utility companies and other authorities having jurisdiction to ascertain the
locations of existing services on or adjacent to site.
I
2.
Information as to the location of existing services, if shown on the drawings, does not
relieve the contractor of his responsibility to determine the exact number and location
of existing services.
I
I
I
3.
Give proper notices for new services as may be required. Make arrangements with
authorities and utilities for service connections required.
4.
Pay any charges levied by utilities or authorities for work carried out by them in
connection with this contract, unless specified otherwise.
5.
Operate and maintain all utility systems affected by work of this contract, until the
project or specific portions thereof have been accepted by the owner.
I
I
I
I
I
I
I
I
6. Report existing unknown services encountered during excavation to consultant for
instructions; cutback and cap or plug unused services. Be responsible for the protection
of all active services encountered and for repair of such services if damaged.
1.10
Site Access
1. Site access to any component of the project is the contractor's full responsibility to review
during the tender stage, and to include the necessary costs accordingly. These costs are
to be included in the miscellaneous section - MobilizationlDemobilization. Upon
completion, restore all access routes to original condition.
2. The project shall be scheduled and fenced off in a manner to provide public access to the
existing staircase.
3. The gravel access road shall be installed as soon as possible to provide public access. Do
not use this road for construction access.
END
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,
I
I
I
I
I
I
1.5
ALLOW ANCES
Section 01020
Page 1
1.1
Related Instructions
1. Comply with requirements of GC 35 Cash Allowances of the General Conditions.
1.2
Authorization
1. Expenditures from allowances included in the contract price must be authorized in
writing by the consultant.
1.3
Allowances
1. Include the following allowances in the Contract.
Testing Allowance
Contingency Allowance
$1,250.00
$7,500.00
1.4
Quotations
1. Should the contractor have to obtain quotations for any work in the Allowance Section,
the time expended for obtaining such quotes is the contractor's cost.
If the owner accepts the quotation, then the cost for time spent bidding is billable as
overhead expense. It may be billed only when that particular product or service is
delivered or installed at the project.
Limitations
1. All work listed in Allowances mayor may not be incorporated in the work. The owner
has full right to delete any or all parts without claim.
END
I
I
I
I
LINES AND LEVELS
Section 01050
Page 1
1.1
Lines and Levels
a
I
I
I
I
I
I
I
I
I
1. Verify all elevations, lines, levels and dimensions as indicated and report any errors,
conflicts, or inconsistencies to the consultant before commencing work or as soon as
discovered.
2. Accurately layout work and establish lines and levels in accordance with requirements
of contract documents.
3. Set up, maintain and protect permanent reference points and provide general dimensions
and elevations for all sections of work.
1.2
Dimensions
1. Check and verify dimensions wherever referring to work. Dimensions, when pertaining
to work of another section, shall be verified with section concerned. Details and
measurements of work which is to fit or conform with work installed shall be taken at
site.
2. Do not scale drawings. If there is ambiguity, lack of information or inconsistency,
immediately consult consultant for directions. Be responsible for extra costs involved
through the disregarding of this notice.
3. While the contractor is responsible for own survey control, the owner reserves the right
to check completed work. Any discrepancy shall be addressed immediately. Fully correct
any work not built per plans.
END
I
I
I
I
I
I
I
I
REGULATORY REQUIREMENTS
Section 01060
Page 1
1.1 Permits, Licenses, Fees
I
1. Where permits, licenses and inspection fees are required by authorities having jurisdiction
for specific trade functions, they shall be obtained and paid for by the particular subtrade
responsible for that work.
,
I
I
I
I
I
1.2
Building Code By-laws, Regulations
1. Carry out work in accordance with requirements of the Ontario Building Code, latest
issue, including all amendments and revisions.
2. Comply with requirements, regulations and ordinances of other authorities having
jurisdiction.
3. Where it is necessary to carry out work outside property lines, such as sidewalks, paving
or concrete curbs, comply with applicable requirements of municipal authorities having
jurisdiction.
4. Promptly submit written notice to consultant of observed variance of Contract
Documents from requirements of Building Code and authorities having jurisdiction.
Assume responsibility for work known to be contrary to such requirements and
performed without notifying consultant.
1.3
Safety Requirements
I
I
I
I
1. Be governed by pertinent safety requirements of Federal or Provincial Governments and
of municipal bodies having authority, particularly the Ontario Construction Safety Act,
and regulations of Ontario Ministry of Labour, and work in conjunction with proper
safety associations operating under the authority of Ontario Workers' Compensation Act.
2. Do not, in the performance of the work, in any manner endanger the safety or unlawfully
interfere with the convenience of the public.
1.4
Fire Protection Requirements
1. Refer to technical Sections of Specifications and Drawings for fire protection
requirements.
I
I,
2.
Test methods used to determine fire hazard classification and fire endurance rating shall
be as required by Ontario Building Code.
Upon request, furnish to consultant with evidence of compliance with project fire
protection requirements.
3.
I
I
I
I
t
I
I
I
1
I
I
I
I
I
I
I
I
I
I
I
I
I
REGULATORY REQUIREMENTS
Section 01060
Page 2
1.5
Safety Regulations
1. The contractor shall ensure that all contract staff are trained under the provision of the
W.H.M.I.S. (Workplace Hazardous Material Information System) regulations.
2. The contractor shall ensure that Material Safety Data Sheets are available for all
chemicals used on site.
3. The contractor shall conform to and enforce strict compliance with the Construction
Safety Act and regulations made under the act.
4. The contractor shall be aware of and conform to Town Health and Safety Policies made
available by the Deputy Director of Community Services and Facilities.
5. For purposes of the Occupational Health and Safety Act, the contractor will be
designated as the constructor for this project and will assume all of the responsibility of
the constructor set out in that Act and its regulations.
6. The contractor shall ensure that all necessary measures are taken to protect Town
employees, general public and workers from injury.
END
I
I,
II
I
I
I
I
I
I
I
I
11
I
I
I
I
I
I
I
ABBREVIATIONS
Section 01070
Page 1
1.
When the following abbreviations are used in the contract documents, they shall have the
meanings shown.
ABBREVIATION
MEANING
AA
ACI
ASTM
AWPA
AWS
CCA
CCRC
CEC
CFUA
CGA
CGSB
CIQS
CISC
CITC
CLA
CMHA
COFI
CPCI
CSA
CSC
CSI
CSPI
CUA
CWB
CWC
IES
LTIC
NBC
NBS .
NLGA
NRCC
PCA
PCI
RAIC
ULC
The Aluminum Association
American Concrete Institute
American Society For Testing And Materials
American Wood Preservers Association
American Welding Society
Canadian Construction Association
Canadian Code For Residential Construction
Canadian Electrical Code
Canadian Fire Underwriters Association
Canadian Gas Association
Canadian General Standards Board
Canadian Institute Of Quantity Surveyors
Canadian Institute Of Steel Construction
Canadian Institute Of Timber Construction
Canadian Lumbermen's Association
Canada Mortgage And Housing Corporation
Council Of Forest Industries Of British Columbia
Canadian Prestressed Concrete Institute
Canadian Standards Association
Construction Specification Canada
Construction Specifications Institute (USA)
Corrugated Steel Pipe Institute
Canadian Underwriters' .Association
Canadian Welding Bureau
Canadian Wood Council
Illuminating Engineering Society
Laminated Timber Institute Of Canada
National Building Code Of Canada
National Bureau Of Standards USDC
National Lumber Grades Authority
National Research Council Of Canada
Portland Cement Association
Prestressed Concrete Institute
Royal Architectural Institute Of Canada
Underwriters' Laboratories Of Canada
END
I
I
I
I
I
I
I
I
I
I
I
I'
,
I
I
I
I
I
I
SITE ADMINISTRATION
Section 01200
Page 1
1.1
Pre-Construction Meeting
1. Immediately prior to construction, upon notification, attend at location of owner's choice
pre-construction meeting along with authoritative representatives of certain ke;
subcontractors as specifically indicated in the conference notice.
2. Purpose of meeting is as follows:
a) Review project communications procedures.
b) Review contract administration requirements including submittals, payment and
change order procedures.
c) Identify all critical points on construction schedule for positive action.
d) Identify any product availability problems and substitution request.
e) Establish site arrangements and temporary facilities.
f) Revise any points which, in owner's, consultant's and contractor's opinion,
require clarification.
1.2
Site Meetings
1. Prior to the commencement of the work the contractor, together with the consultant,
shall mutually agree to a sequence for holding regular "on site meetings".
2. Organize all necessary site meetings. Ensure that persons, whose presence is required,
are present and that relative information is available to allow meetings to be conducted
efficiently.
3. The consultant will record minutes of each meeting and promptly distribute copies to all
participants not later than seven days after the meeting has been held.
1.3
Supervisio-n
1. Employ an experienced and qualified superintendent who shall devote his time exclusively
to the work of this contract and who shall be in complete charge of the work from
commencement to completion. A working foreman will not be acceptable. The
superintendent shall not be changed after commencement of work without the
consultant's approval.
2. Supervise, direct, manage and control the work of all forces carrying out the work,
including subcontractors and suppliers. Carry out daily inspections to ensure compliance
with the contract documents and the maintenance of quality standards. Ensure that the
inspection staff includes personnel competent in supervising the mechanical and electrical
trades.
I
I
I
I
I
I
I
,
I
I
I
I
I
I
SITE ADMINISTRATION
Section 01200
Page 2
1.4
Progress Record
1. Maintain, on site, permanent written record of progress of work. Record shall be open
to inspection by consultant at all times and a copy shall be furnished to consultant upon
request.
2. This record shall show weather conditions, dates of commencement, progress and
completion of various trades and items of work. Particulars pertaining to erection and
removal of forms, pouring of concrete, and other critical or major components as well
as number of employees of various trades and type and quantity of equipment employed
daily shall be noted.
3. Display a copy of the construction schedule on site from start of construction to
completion. Superimpose actual progress of work on schedule at least once each week.
1.5
Record Drawings
1. Obtain and keep on site at all times a complete and separate set of black line white
prints.
2. Note clearly, neatly, accurately and promptly as the work progresses all architectural,
structural mechanical and electrical changes, revisions and additions to the work and
deviations from the contract documents.
3. Accurate location, depth, position, size and type of concealed and underground services,
both inside and outside shall be included as part of these record drawings.
4. Record drawings shall be available for review at each site meeting.
5. Refer to Section 01700 for requirements on submission of record drawings.
1.6
Documents On Site
1. The contractor shall at all times have in his possession a complete set of contract
documents (drawings and specifications) with all addenda, site instructions, change
orders, reviewed shop drawings and samples, colour schedule, paint materials schedules,
hardware list, progress reports and meeting minutes.
I
I
I
J
I
END
I'
I
I
I
I
I
I
I
I
I,
I
I
I
I
I
I
I
I
I
SUBMITI ALS
Section 01300
Page 1
1.1
General
1. Unless specified otherwise, make all submissions to the consultant at his office.
2. Make all submissions required by the contract documents with reasonable promptness
and in orderly sequence so as to cause no delay in the work.
1.2
Related Work
1. Submission of maintenance and record documents: Section 01700 - Project Closeout.
2. Submission of maintenance materials: Section 01700 - Project Ooseout.
1.3
Construction Schedule
1. Within 7 days after award of contract submit, in form approved by consultant,
construction schedule for work of entire contract.
2. Show in schedule start and completion times of each item of work, including erection and
dismantling of temporary services.
1.4
Shop Drawings
1. Submit shop drawings required by contract documents, in accord with requirements of
GC34.
2. Prepare shop drawings in metric measurements only. Shop drawings containing imperial
measurements will be rejected.
3. Unless otherwise directed by the consultant, submit the following number of prints for
each shop drawing required:
a) Landscape Architectural shop drawings: 2 prints
b) Structural shop drawings: 3 prints
4. Shop drawings which require the approval of a legally constituted authority having
jurisdiction shall be submitted by contractor to such authority for approval. Such shop
drawings shall receive final approval of authority having jurisdiction before consultant's
final review.
5. No work requiring a shop drawing submission shall be commenced until the submission
has received consultant's final review.
I
I
I
SUBMITTALS
Section 01300
Page 2
6.
The consultant's review is for the sole purpose of ascertaining conformance with the
general design concept. This review shall not mean that the consultant approves the
detail design which is inherent in the shop drawings, responsibility for which shall remain
with the contractor submitting same, and this review shall not relieve the contractor of
his responsibility for meeting the requirements of the contract documents. The
contractor is responsible for dimensions to be confirmed and correlated at the job site
for information that pertains solely to fabrication processes or to techniques of
construction and installation and for coordination of the work of all subtrades.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1.5
Samples
1. Submit samples required by contract documents and as directed by the consultant.
2. Unless indicated otherwise, submit samples in duplicate.
3. Submit samples with identifying labels bearing material or component description,
manufacturer's name and brand name, contractor's name, project name, location in which
material or component is to be used, and date.
4. Prepay any shipping charges involved for delivering samples to destination point and
returning to point of origin if required.
5. No work requiring a sample submission shall be commenced until the submission has
received consultant's final review.
END
I
I
I
I
I
I
I
I
I
I
I
I
,
I
I
I
I
I
I
QUALITY CONTROL'
Section 01400
Page 1
1.1
General
1. Requirements specified in this section apply to independent inspection and testing
specified under technical specification sections.
2. Requirements specified in this section do not apply to the following:
a) Inspection and testing required by laws, ordinances, rules, regulations and orders
of public authorities.
b) Inspection and testing performed exclusively for contractor's convenience.
3. Failure by independent testing agency to detect defective work or materials shall not in
any way prevent later rejection, when such defect is discovered, nor shall it obligate
consultant for final acceptance.
1.2
Related Instructions
1. Cash allowance for independent inspection and testing: Section 01020
2. Specific inspection and testing requirements: Divisions 2 to 16 inclusive.
1.3
Duties & Authority of Testing Agency
1. Testing agency is expected to do the following:
a) Act on a professional and unprejudiced basis and carry out inspection and
testing functions to establish compliance with requirements of contract
documents.
b) Check work as it progresses and prepare reports stating results of tests and
conditions of work and state in each report whether specimens tested conform
to requirements of contract documents, specifically noting deviations.
c)
Distribute reports as follows:
Consultant - three (3) copies
Contractor - two (2) copies
2. Testing agency is not authorized to amend or release any requirements of contract
documents, nor approve or accept any portion of work.
3. Contractor shall do the following:
a) Notify testing agency minimum 48 hours in advance of operations to allow for
assignment of personnel and scheduling of tests without causing delay in work.
b) Provide testing agency with access to work at all times.
c) Supply material samples for testing.
I
I
I
I
I 4.
I
I
I
I
I
I
1
I
I
I
I
I
I
I
Section 01400
QUALITY CONTROL
Page 2
d) Supply casual labour and other incidental services required by testing agency.
e) Provide facilities for site storage of samples.
When initial inspection and testing indicates non-compliance with contract documents,
any subsequent re-inspection and re-testing occasioned by non-compliance shall be
performed by same testing agency and cost thereof borne by contractor.
END
I
I
I
I
I
TEMPO RAR Y F AClUTIES
Section 01500
Page 1
1.1
General
1. Provide aU temporary facilities and controls required for the proper execution of the
work.
2. Provide and maintain temporary systems in accordance with applicable regulations and
requirements. Arrange for, obtain and pay for any permits required.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3. Location of temporary facilities shall be subject to consultant's approval.
1.2
Temporary Electricity, Lighting and Water
1. Provide temporary electrical lighting and power system and water for use by all sections,
if required.
2. Arrange, obtain and pay for service including meter, if required, of sufficient size to allow
use of required tools and equipment and to ensure adequate lighting levels for the proper
execution of work.
3. Install and maintain temporary electrical systems in accordance with Construction Safety
Association's "Temporary Wiring Standards on Construction Sites", the Ontario Electrical
Code and other authorities having jurisdiction.
1.3
Temporary Heating
1. Furnish equipment, labour and fuel to provide temporary heat as required for proper
execution of work.
1.4
Temporary Telephone
1. Provide telephone service for duration of contract until completion. A mobile phone is
acceptable.
2. Make telephone available to aU sections. Long distance calls shall be paid by party
making call.
1.5
Temporary Sanitary Facilities
1. Provide toilet facilities for all personnel on site.
2. Keep facilities clean and sanitary and provided with required supplies at all times.
3. Except where temporary sanitary facilities are connected to municipal sewer system,
periodically remove wastes from site.
I
I
I
I
I
TEMPORARY FACILITIES
Section 01500
Page 2
1.6
Temporary First-Aid Facilities
1. Provide site equipment and medical facilities necessary to supply first-aid service to
injured personnel in accordance with regulations of the Worker's Compensation Act.
Maintain facilities for duration of contract.
1.7
Temporary Fire Protection
I
I
I
I
'I
I
I
I
I
I
I
I
I
I
1. Provide and maintain in proper working order, fire extinguishers, prominently placed,
until completion of work.
2. Fire extinguishers shall be minimum 3 kg. 4A60BC type.
3. Remove fire extinguishers from site upon completion of work or when directed by
consultant.
4. Where gas welding or cutting is to be done within 3 m or above combustible material,
or above space that may be occupied by persons, interpose shields of non-combustible
material. Tanks supplying gases for welding or cutting shall be placed at no greater
distance from the work than is necessary and shall be securely fastened in an upright
position. Such tanks shall be free from exposure to the sun or high temperature.
1.8
Construction Aids
1. Provide temporary stairs, ladders, ramps required for movement and placing of materials,
equipment and personnel.
2. Provide mechanical hoisting equipment and fully qualified operators as required during
construction.
3. Erect required scaffolding independent of walls, arranged to avoid interference with work
of other sections as much as possible.
4. Provide and maintain required shoring and bracing in accordance with Construction
Safety Act and other applicable regulations.
5. Shoring and all false work over one tier in height shall be designed and shall bear the
stamp of a registered professional engineer having experience in this field.
6. The use of explosive power tools must be approved in writing by the consultant. The use
of explosive power tools will not be permitted under any circumstances unless equipped
with a device which positively prevents free flight of the stud.
1.9
Barriers
1. Protect public and workmen from injury.
I
I
I
I
I
I
I
I
I
'1
I
I
I.
I
I
I
I
I
I
Section 01500
TEMPORARY FACILITIES
Page 3
2. Provide and maintain required barricades, warning signs, guardrails and lightguards in
accordance with applicable regulations.
1.10
Temporary Controls
1. Provide protective coverings to protect work against damage caused by weather including
but not necessarily limited to rain, snow, ice, wind, frost and excessive heat.
2. Provide wind breaks and sun shade to allow proper setting and curing of cementious
materials.
3. Protect excavations and building materials from freezing.
4. Provide and maintain adequate temporary pumping and drainage systems to keep
excavations and structures free of water. Prevent flow of surface water into excavations.
Locate sumps away from foundation elements. Prevent pumped water from carrying soil
in suspension in sufficient quantity to case settlement of adjacent earth. Provide
sufficient standby equipment to ensure continuity of pumping system.
5.
6.
1.11 Signs
1.
2.
3.
Prevent sprayed materials from contaminating air beyond application area by providing
temporary enclosures.
Cover or wet down dry materials and rubbish to prevent blowing dust and debris.
Except as specified here do not erect any signs unless approved by the consultant.
Erect signs relating to safety on the work or mandatory regulation notices.
Erect the consultants' project sign by supplying and setting three steel T-bar stakes. Wire
the sign securely to the stakes. consultant to provide the sign. Return the sign at the
end of the job.
1.12
Field Office and Sheds
1. Provide temporary covers, sheds and platforms of weatherproof construction as may be
required for protection and preservation of materials, small tools, equipment which may
be susceptible to damage.
END
I
I
I
I
I
PRODUcrS AND WORKMANSHIP
Section 01600
Page 1
1.1
Product Quality
1. Products supplied for work shall be new, and as far as possible, and unless otherwise
specified, of Canadian manufacture.
2. Materials used for temporary facilities are not required to be new, provided they are
structurally sound and in suitable and safe operation condition.
I
I
I
I
I
I
I
I
I
1.2
Standards and Terminology
1. Where a standard has been adopted by these specifications, incorporate minimum
requirements of such standard into the work. Where requirements of specifications are
more stringent than those of the standard, follow more stringent requirements.
2. Reference to standards, specifications, handbooks and manufacturer's catalogues, refer
to latest edition thereof and all amendments or revisions applicable at tender closing
date, unless date suffix is included with document number.
3. Wherever words "acceptable", "approved", "satisfactory", "selected", "directed",
"designated", "permitted", "inspected", "instructed", "required", "submit", or similar words
or phrases are used in standards or elsewhere in contract documents, it shall be
understood that "by (to) the consultant" follow, unless context provides otherwise.
4. Where the word "provide" is used in these contract documents, it shall be taken to mean
"supply and install" unless specifically noted otherwise.
1.3
Availability and Substitution
1. Products which are specified by their proprietary names or by part of catalogue number
from the basis for contract. No substitutes for these may be used without consultant's
approval in writing.
2. Where it is found that specified materials have become unavailable for incorporating into
wQrk, notify consultant immediately of proposed substitution.
3. Proposed substitution shall be any top quality product considered by the consultant to
be suitable for purpose intended.
I
I
I
4.
Products proposed as substitutions, and which are considered by consultant to be suitable
for purpose intended, but which are in his opinion of lesser value and quality than those
specified shall only be accepted as substitution if reasonable credits are allowed for their
use.
5.
In order to substantiate equivalency of proposed materials, products or processes, submit
samples, printed product description's test data, installation instructions, standards,
certification, samples, guarantee/Warrantyforms, list of successful products incorporating
such proposals and similar information requested by consultant.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,
I
I
PRODUCTS AND WORKMANSHIP
Section 01600
Page 2
6. Whenever a substitute is proposed, any change to contract price as a result of acceptance
of proposed product shall include any adjustments to adjacent structure or space in order
to accept minor differences in size or weight between proposed items and corresponding
specified items.
7. Prevent any substitution or request for substitution from delaying construction progress
in any way.
8. Requests for substitution resulting from failure to place orders in time will not be
entertained. Be responsible for ordering products in time to ensure their required
delivery; bear all costs for failure to comply with these requirements.
9. Upon consultant's request submit copies of material and equipment purchase orders.
1.4
Product Delivery, Handling & Storage
1. Suitably pack, crate and protect products during transportation to site to preserve their
quality and fitness for purpose intended.
2. Store products in original, undamaged condition with manufacturer's labels and seals
intact until they are being incorporated into completed work.
3. Handle and store materials in accordance with manufacturer's and supplier's
recommendations so as to ensure preservation of their quality, appearance and fitness
for work.
4. Arrange materials so as to facilitate prompt inspection, and remove faulty, damaged or
rejected materials immediately from site.
1.5
Product Delivery Schedule
1. It is the responsibility of the contractor to ensure that the supplier or distributor of
materials specified or alternatives accepted, which he intends to use, has materials on the
site when required. The contractor shall obtain confirmed delivery dates from the
supplier.
2. The contractor shall contact the consultant immediately upon receipt of information
indicating that any material or item will not be available on time, in accordance with the
original schedule, and similarly it shall be the responsibility of all subcontractors and
suppliers to so inform the contractor.
3. The consultant reserves the right to receive from the contractor at any time, upon
request, copies of actual purchase or work orders of any material or products to be
supplied for the work.
1.6
Workmanship
1. All work shall be carried out in accordance with the best trade practice, by mechanics
skilled in the type of work concerned.
I
I
I
I
PRODUCTS AND WORKMANSHIP
Section 01600
Page 3
2.
Products, materials, systems and equipment shall be applied, installed, connected,
erected, used, cleaned and conditioned in accordance with the applicable manufacturer's
printed directions.
I
I
I
I
I
I
I
I
I
I
I
3.
Where specified requirements are in conflict with the manufacturer's written directions,
follow manufacturer's directions. Where specified requirements are more stringent than
manufacturer's directions, comply with specified requirements.
END
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PRODUCTS AND WORKMANSHIP
Section 01600
Page 4
1.1
Record Drawings
1. Upon completion of work, prior to total performance, obtain and pay for one set of
mylar transparencies and transfer record information compiled during construction from
white prints to mylars.
2. Quality of drafting and lettering shall match that of original drawings and shall be
suitable for microfilming.
1.2
Substantial Performance
1. Prior to requesting a substantial performance deficiency inspection, submit the following:
a) Two copies of inspection and acceptance certificates required from regulatory
agencies.
2. Advise the consultant, in writing, when the project has been substantially completed. If
consultant agrees that this stage has been reached, prepare a complete list of deficiencies
and submit one copy of this list to consultant.
3. On receipt of the above deficiency list, in a satisfactory form, the consultant,
accompanied by the subconsultants, the contractor and his project superintendent, and
the owner if deemed desirable, will carry out an inspection of the project.
4. Add to the deficiency list, in accordance with consultant's directions, any additional
deficiencies which are identified during inspection and re-issue updated deficiency list to
all concerned.
1.3
Total Performance
1. Prior to requesting a final inspection, do the following:
a) Submit one complete set of mylar record drawings.
b) Submit one complete set of reviewed shop drawings of mechanical and electrical
items, folded to 81/2" by 11" size, contained in heavy manila envelopes, numbered
and labeled. Follow specification format with no more than one section per
envelope.
c) Submit a final request for payment incorporating all approved changes to the
contract price, including adjustments to the cash allowances listed in Section
01020 - Allowances.
d) Upon completion of all items noted on the deficiency list, clean all areas,
surfaces and components affected by corrections and completion of deficient
items, as directed by the consultant.
e) Ensure that all services, equipment, apparatus are properly tested and adjusted.
I
I
I
I
I
PRODUCTS AND WORKMANSHIP
Section 01600
Page 5
2.
After all deficiencies have been corrected, submit a written request to the consultant for
a final inspection. This inspection shall be carried out by the same parties involved in
the substantial performance deficiency inspection.
3.
If all deficiencies have not been corrected, in the opinion of the consultant, a final
deficiency list will be prepared in the same manner as specified herein for the substantial
performance deficiency inspection and the inspection procedure repeated until all items
have been completed to the satisfaction of the consultant.
I
I
I
I
I
I
I
END
I
I
I,
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Section 01700
PROJECf CLOSEOUT
Page 1
1.1
Record Drawings
1. Upon completion of work, prior to total performance, obtain and pay for one set of
mylar transparencies and transfer record information compiled during construction from
white prints to mylars.
2. Quality of drafting and lettering shall match that of original drawings and shall be
suitable for microfilming.
1.2
Substantial Performance
1. Prior to requesting a substantial performance deficiency inspection, submit the following:
a) Two copies of inspection and acceptance certificates required from regulatory
agencies.
2. Advise the consultant, in writing, when the project has been substantially completed. If
consultant agrees that this stage has been reached, prepare a complete list of deficiencies
and submit one copy of this list to consultant.
3. On receipt of the above deficiency list, in a satisfactory form, the consultant,
accompanied by the subconsultants, the contractor and his project superintendent, and
the owner if deemed desirable, will carry out an inspection of the project.
4. Add to the deficiency list, in accordance with consultant's directions, any additional
deficiencies which are identified during inspection and re-issue updated deficiency list to
all concerned.
1.3
Total Performance
1. Prior to requesting a final inspection, do the following:
a)
Submit one complete set of mylar record drawings.
b)
Submit one complete set of reviewed shop drawings of mechanical and electrical
items, folded to 8%" by 11" size, contained in heavy manila envelopes, numbered
and labeled. Follow specification format with no more than one section per
envelope.
c)
Submit a final request for payment incorporating all approved changes to the
contract price, including adjustments to the cash allowances listed in Section
01020 - Allowances.
d)
Upon completion of all items noted on the deficiency list, clean all areas,
surfaces and components affected by corrections and completion of deficient
items, as directed by the consultant.
e)
Ensure that all services, equipment, apparatus are properly tested and adjusted.
2. After all deficiencies have been corrected, submit a written request to the consultant for
I
I
I
I 3.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Section 01700
PROJECT CLOSEOUT
Page 2
a final inspection. This inspection shall be carried out by the same parties involved in
the substantial performance deficiency inspection.
If all deficiencies have not been corrected, in the opinion of the consultant, a final
deficiency list will be prepared in the same manner as specified herein for the substantial
performance deficiency inspection and the inspection procedure repeated until all items
have been completed to the satisfaction of the consultant.
END
I
Section 01710
I
I
CLEANING
Page 1
I
I
1.1 General
1.
2.
3.
4.
5.
6.
7.
I
I
I
I
I
I
I
I
I
1.2
1.3
I
I
I
I
I
Be responsible for cleanliness of site and structures to satisfaction of consultant.
Maintain work in neat and orderly condition at all times.
Periodically, or when directed by the consultant, remove from site and legally dispose of
rubbish and waste materials.
Burning or burying of rubbish and waste materials on site is not permitted.
Use only cleaning materials recommended by manufacturer of surface to be cleaned.
Use cleaning material only on surfaces recommended by cleaning material manufacturer.
While on the premises, all hazardous waste shall be properly identified and stored so as
not to pose a safety hazard to employees, workers or the general public.
Utilize recycling programs and efforts for material disposal whenever and wherever
possible. Guidance into various recycling efforts can be obtained by contacting the
municipality .
Cleaning During Construction
1. Remove debris, packaging and waste materials frequently.
2. Keep dust and dirt to an acceptable level as directed.
3. Remove oily rags, waste and other hazardous substances from premises at close of each
day, or more often if required.
Final Cleaning
1. Prior to substantial performance, thoroughly clean all surfaces and components. Provide
professional cleaning of all areas and surfaces to allow owner to occupy without further
cleaning.
2.
Remove stains, dirt and smudges from finished surfaces.
END
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TEMPORAR Y CONTROL FENCING
Section 02070
Page 1
PART 1 ~ GENERAL
1.1 General Instructions
1. Comply with the requirements of Division 1.
PART 2 - PRODUCTS
2.1 Fencing
1. Protective fencing shall fence as detailed.
PART 3 - EXECUTION
1. All existing trees, which are to remain, shall be fully protected with the required fencing erected
outside the "drip line" of trees, prior to commencement of construction. Groups of trees and
other existing plantings to be protected shall be done in like manner with snow fencing or other
similar structures around the entire clump(s). Areas within the protective fencing shall remain
undisturbed and shall not be used for the storage of building materials or equipment.
2. No rigging cables shall be wrapped around or installed in trees; surplus soil, equipment, debris
or materials shall not be placed over root systems of the trees within the protective fencing. No
contaminants will be dumped or flushed where feeder roots of trees exist.
3. The contractor shall take every precaution necessary to prevent damage to trees or shrubs to be
retained.
4. Fencing shall remain in place for the duration of the project, and for the duration of phase 4
implementation in 1995. All materials are the property of the Town of Clarington.
5. At completion date of phase 3 works, repair any fence components which have been damaged.
END
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
CLEARING AND GRUBBING
Section 02110
Page 1
PART 1 - GENERAL
1.1 General Instructions
1. Comply with the requirements of Division 1.
1.2 Related Work
1.
Temporary Control Fencing
Section 02070
1.3 Protection
1. Prevent damage to adjacent property and to areas scheduled to remain unchanged.
Make good any damage caused by site clearing operations.
2. Ensure that tree protection is in place prior to commencement of work.
PART 2 - PRODUcrS
Not applicable
PART 3 - EXECUTION
3.1 Examination & Preparation
1. Visit the site and examine existing conditions so as to understand the extent of work
required. No increase in cost will be considered out of failure to know existing
conditions.
3.2 Qearing Operations
1. Notwithstanding requirements specified herein, retain existing items specifically indicated
on drawings to be retained.
2. Where required to accommodate new construction, remove existing elements regardless
whether shown on drawings to be removed or not.
a) Cut down trees specifically indicated on drawings to be removed, if any.
3.3 Disposal of Material
1. Except where specifically indicated otherwise herein, remove from site and legally dispose
of all materials, rubbish and debris resulting from site clearing operations.
END
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
EARTIIWORKS
Section 02210
Page 1
PART 1 - GENERAL
1.1 General Instructions
1. Comply with requirements of Division 1.
1.2 Related Work
1.
2.
Temporary Control Fencing
Clearing and Grubbing
Section 02070
Section 02110
PART 2 - PRODUCTS
Not applicable
PART 3 - EXECUTION
3.1 Existing Site Conditions
1. The contractor must review and make known, the acceptance of the site contour relative
to the graphic contour shown on the plans.
2. Failure to do so will imply acceptance by the contractor of surfaces and conditions, and
no claim made thereafter for damages or extras resulting from such surfaces and
conditions will be accepted.
3.2 Topsoil Stripping
1. The topsoil shall be stripped from the site in a fully dry condition. Stockpile in a
location acceptable to the Consultant. Strip all topsoil. Reuse topsoil as fill material in
future sodded areas only.
3.3 Cut and Fill Balance
1. The plan have not been prepared with an intention to balance cut and fill. The balancing
of cut/fill is the contractor's responsibility.
2. Supply all materials and execute the works as is necessary to bring the grades to the
finished elevations.
3.4 Filling
1. Unless otherwise specified, the contractor shall, where required, supply and spread
sufficient fill materials to raise existing grades to the specified level as indicated on the
drawings.
2. Such fill materials shall be free of any debris subject to rot or corrosion, and shall be
approved by the consultant before placing.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
EARTHWORKS
Section 02210
Page 2
3. Prior to placing fill, the existing grade shall be scarified to a minimum depth of 75mm
to provide a good bond and prevent slipping of fill.
4. Fill materials shall be placed in loose layers not exceeding 250 mm in depth. Each layer
shall be compacted to 95% Standard Proctor Modified Dry Density (S.P.M.D.D.)before
placing subsequent layers.
5. All fill materials shall be compacted when the moisture content, as determined by
laboratory tests, is suitable for obtaining the required density. When the moisture
content is too low, water shall be applied by means of an approved distributor. When
the material is too wet, it shall be thoroughly mixed with dry material, or the wet
material shall be dried by blading, dicing or other approved method.
6. The surface shall be shaped at all times to ensure adequate surface run-off and prevent
ponding and scouring.
3.5
Excavating
1. Before proceeding with excavating work for paving, the areas shall be staked out and
approval obtained from the consultant.
2. All areas for paving shall be excavated to the specified depths as indicated on drawings.
3. The final sub-grade shall be maintained parallel to the finished grade and shall be
thoroughly compacted to 98% S.P.M.D.D. minimum.
4. Submit written evidence that the specified compaction has been realized and obtain
approval from the Consultant before commencing work.
5. All structures such as walks, steps, etc. shall be staked out on the site to the consultant's
approval before commencing excavating work.
6. The excavations for all foundations shall be carried to undisturbed soil, or to a minimum
d~th of 1200mm unless specified otherwise.
7. The bearing capacity of the soil on which the footings are to be founded shall be capable
of supporting the imposed loads.
8. Where the bearing capacity appears to be insufficient, soil investigations shall be carried
out with the approval of the landscape architect. Costs of such investigations shall be
paid for out of the Cash Allowance as stipulated in the Special Conditions.
9. Where it is necessary to carry excavations deeper than specified, until a firm bearing is
obtained, fill extra excavation with concrete and/or granular fill as directed. Under no
circumstances will earth filling under footings be permitted, unless otherwise approved.
10. The cost of extra excavations and extra concrete will be paid for at the unit prices quoted
in the tender. Where such extra costs are the result of the contractor's error or
I
Section 02210
I
I
I
I
I
I
EARTIIWORKS
Page 3
I
I
I
17.
I
I
I
I
I
I
I
I
I
misinterpretation, no extra payment will be made.
11.
All excavations shall be sufficiently shored and braced to prevent caving in and support
existing structures, roads, services, etc.
12.
All shoring shall be done in strict accordance with local regulations and approval
obtained from local authorities.
13.
Warning signs and protective barriers shall be erected in accordance with local
regulations.
14.
Be responsible for all damages and subsequent repairs to underground utilities and
structures resulting from contractor's operations.
15.
All excavations shall be protected from freezing and water. Provide and operate as many
pumps as are necessary to keep excavations free of water at all times.
16.
All surplus excavated material shall be removed and disposed of, unless approved by the
consultant for filling or backfilling. Surplus material and unacceptable materials shall be
removed from the site and disposed of.
All excavated rocks and boulders shall be immediately buried at approved locations to
depths of 1.5 m below finished grade.
END
I
SECTION 02300
I
SPECIFICATION NO.2
G.~1. Sernas
~sSOCiates Ltd.
I
SEWERS AND APPURTENANCES
1. SCOPE OF WORK
I
This work shall consist of constructing sanitary sewers and/or storm sewers. including manholes.
catchbasins. connections and all appurtenances as shown on the contract drawings. The work shall be
constructed in a manner called for by these specifications and to the satisfaction of the Municipality. The
Contractor shall be responsible for familiarizing himself with all of the requirements of the Municipality
and. wherever necessary. obtaining all permits. licenses and other documents necessary to carry out the
work in a substantial and workmanlike manner.
I
I
This work shall include clearing the site. supplying all necessary materials. excavating in any material to
the lines and levels shown on the drawings. protection of trenches according to the Ministry of Labour as
required. dewatering of all excavations. bedding and cover. laying pipe to line and grade as shown on the
drawings, jointing, constructing catchbasins. manholes and connections. backfilling and compacting all
trenches and excavations. removal of all surplus materials to a dump site arranged Cor by the Contractor
and approved by the engineer. and doing all other things necessary to construct and put in complete
working order the sewer systems. house connections. catchbasins. manholes and all appertaining
structures. including surface restoration of the site. as specified in the contract and shown on the drawings,
to a condition satisfactory to the Engineer.
I
I
I
2. CLEARING SITE
I
. The unit price tendered Cor the respective items shall include, unless otherwise specified, all clearing of
the site including removal of unsuitable material and debris required to construct the sewers and its
appurtenances, as directed by the Engineer.
I
3. EXCAVATION
I
The Contractor shall excavate in any material to the lines and levels shown on the drawings. The width
oC the trench at the top of the pipe shall not exceed the Collowing table:
I
Normal Pipe
Diameter (mm)
Less Than
300
375- 750
825-1800
1950-3600
I
Trench Width At
Top of Pipe (mm)
900
0.0. + 600
0.0. + 750
0.0. + 900
I
If the trench width is exceeded. the Contractor shall. at his own expense. supply and install the type of
pipe bedding or class of pipe as directed by the Engineer.
I
All excavation shall be protected according to the Ministry of Labour as required. and be kept Cree of water
at all times. The Contractor shall. at his own expense. provide sufficient shoring. pumping equipment and
piping Cor this purpose.
I
Should bad ground occur at the depth of excavation as shown on the drawings, the Contractor shall. at
his own expense. unless otherwise specified in the Special Conditions oC this contract, excavate to firm
Coundation and backfill to the required lines and elevations with approved material.
I
S2-}
I
I
SECTION 02300
I
SPEC. NO.2- SEWERS A.l....D APPURTENA.....CES (con't...)
G.i\;l. Sernas
&SSOciates Ll(L
I
All excavations in paved roads and where specii1ed on the drawings shall have vertical walls. Included in
the respective tendered unit rates. the Contractor shall saw-cut all pavement areas in straight lines
paralleling the proposed work and provide sufficient trench shoring to protect workmen and property.
I
4. BEDDING OF SEWERS AND CONNECTIONS
I
All pipes shall be bedded as shown on the drawings and in the form of Tender.
I
5. LAYING AND JOINTING PIPES
All pipes shall be carefully laid to line and grade as shown on the drawings. The pipe shall be firmly
supported along its entire length.
I
During cold weather. the Contractor shall. at this own expense. heat such materials and carry out such
instructions as the Engineer may consider necessary.
I
6. BACKFIlI.ING
I
I
Unless otherwise specified on the drawings or in the Special Conditions of this contraCt. bacJdllling of
excavations and trenches shall be made using excavated material. The Contractor shall be responsible for
compacting the backfill material. For the full depth of the excavation to a minimum of 95% Standard
. Proctor Density. The Contractor shall. at his own expense, repair any senlements in the backfill material.
I
The unit price tendered for the respective items shall include backfilling of excavations in existing roadways
and private driveways with granular "C material. Road pavements and driveways shall be reinstated as
soon as practical and, unless otherwise specitled on the drawings or in the Special Conditions. this work
shall be payable under the appropriate roadworks items.
I
The Contractor shall be responsible for separating frozen excavated material and. under no circumstances
will the Contractor be allowed to use such frozen material for backfill.
I
7. FALSEWORK
I
The Contractor shall.prepare and submit drawings of all falsework to the Engineer when required. All
falsework drawin~ shall bear the seal of a professional engineer who shall be responsible for the entire
falsework design.
I
8. EXISTING UNDERGROUND OBJECTS
I
During the construction of the sewer or its appurtenances. the Contractor may encounter existing
underground objects and utilities. The Contractor shall be responsible for locating and supporting such
objects or utilities in a manner satisfactory to the Engineer. or removing and replacing such objects or
utilities at his own expense. Prior to removal of any underground object or utility. the Contractor must
obtain the approval from the Engineer and the Owner or operating authority of such object or utility.
I
I
52-2
I
I
SECTION 02300
I
SPEC. NO.2 - SEWERS AND APPURTENAJ.'lCES (con'L)
G.~l. Sernas
V,\ssociates Lrd.
Ql. .
I
9. MARKER STAKES
I
I
Immediately upon completion of the backfilling of trenches and excavations. the Contractor shall. at his
own expense. supply and erect marker stakes at the end of each connection or to mark the location of any
other installation. as directed by the Engineer. The marker shall consist of 50mm X 100mm lumber and
be no less than two meters in length. It shall be extended one meter above ground level and painted
according to the direction of the Engineer.
I
I
I
I
10. PlACING AND CURING OF CONCRETE
All concrete work shall be carried out in accordance with Ministry of Transportation and communications
Specification Form 9. and to such lines. grades and dimensions as specified on the drawings.
11. OUALI1Y OF FINISHED WORK
The Contractor shall note that any work that does not meet the standards of the Contract Drawings and
these Specifications. as determined by the Engineer. shall be removed and replaced at the expense of the
Contractor, or at the discretion of the Engineer. payment for the faulty item may be reduced or witheld.
12. MATERIAL TESTING
I
The ContraCtor shall, at his own expense, supply sufficient quantity and arrange for testing of material as
directed by the Engineer. including pipe. bedding material. concrete. brick, etc.
I
I
I
13. flUSHING
The Contractor shall flush all sewers at the completion of the work. No sewer will be inspected for
preliminary approval before they are thoroughly cleaned. The contractor shall. at his own expense. provide
all labour. equipment and water required for this work.
14. INSPECTION
I
The Engineer or his representative. will test all sewers for grade. line and leakage. At the discretion of the
Engineer or when required by the Municipality. the sewers may also be inspected by means of a dosed
circuit T.V. camera. The Contractor shall provide. at no additional cost. such unskilled assistance as the
Engineer may require to carry out the inspection.
I
I
I
If defective work is indicated by such inspections. the Contractor shall bear a part of the total cost in the
proportion that the number of defective sections of sewer bears to the total number of sections inspected;
a section being defined as a length of pipe between adjacent manholes.
The Engineer may. at his discretion. test all sewers for leakage by means of infiltration. exfiltration or air
tests.
I
I
52.3
SECTION 02300
I
I
SPEC. :VO. 2 . SEWERS AND APPURTENANCES (con'L)
G.~t. Sernas
&,sSOCiares Lrd.
(a)
Infiltration
The maximum allowable infiltration shall not exceed 30 and 7S litres per M.M.
of pipe diameter per km. per 24 hours for sanitary and storm sewers respectively,
including connections.
I
I
I
(b)
Exfiltration
The maximum allowable exfiltration shall not exceed 45 and 105 litres per mm
of pipe diameter per km per 24 hours tor sanitary and storm sewers respectively,
including connections. The minimum head on the section of sewer being tested
shall be 900mm measured from the crown of the pipe at the highest end.
provided that the maximum head shall not be greater than 4500mm
I
I
I
I
(c)
Air Test
Air shall be introduced into the section of sewer being tested until 24 kPa gauge
pressure has been reached. The time required for the pressure to drop by 7.0
kPa from 20 kPa to 13 kPa shall not be less than shown in the following table:
Nominal Pipe Diameter
(mm)
Minimum Time Loss
(Sec.)
150 . 300
375 . 450
525 . 750
825 . 900
60
120
180
240
I
I
I
I
15. MATERIAL
All material to be used under these specifications and as shown on the drawings shall conform to the
requirements of the Municipality and be in accordance with their approved list of manufacturers. The
Contractor shall be responsible for submitting a list of proposed material to the Engineer prior to
commencing the work and he shall without any extra cost, substitute such material that the Engineer may
require.
All material stored on the site shall be protected from drainage and the Contractor shall. at his own
expense, remove and replace any damaged material as directed by the Engineer.
I
I
17. COMPLETION OF WORK
I
I
The work shall not be considered completed until all work has been done as specified herein and shown
on the drawinp and approved by the Engineer and the Municipality. This shall include the backfilling and
levelling of all trenches. manholes and catchbasins. the removal of all surplus material. the cleaning up of
the entire site. the replacement of all paved and/or gravel roads. ditches. culvertS. under-drains. pavements,
curbs and gutters. sidewalks, driveways and all existing structures damaged by the construction of the
sewers. connections. catchbasins. manholes and appurtenances. and all work necessary to leave the entire
site in a condition satisfactory to the Engineer.
As specified herein, the work must also meet the requirements of the Municipality and is subject to their
inspection and testing prior to the issuing of a completion certificate.
I
I
52.4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
MASONR Y
Section 02410
Page 1
PART 1 - GENERAL
1.1 General Instructions
1. Comply with the requirements of Division 1.
1.2 Related Work
1. Earthworks
Section 02210
PART 2 - PRODUcrS
2.1 Stonework
1. Granite veneer to be split face product at least 150mm thickness. Width and heights of
stones may vary forming a random pattern, Natural stone shall be of grey and brown
colour ranges. Submit sample to landscape architect.
2. Order a sufficient quantity and ensure that the manufacturer sets aside this amount for
the project to ensure that there will be no undue variation in lots.
2.2 Blocks
1. Concrete Block - Block shall be autoclaved, cured and dimensionally to stable sizes
shown on drawings meeting the requirements of the following specification:
Hollow load bearing units - ASTM C90-66T
2. Blocks shall be sound and free from cracks, chips, spawls or other defects.
2.3 General Products
1. Masonry cement - shall comply with C.S.A Specification CAN3 - A8.
2. Aggregate - shall conform to C.S.A Specification A82.56 - M1976.
3. Water - shall be clean, potable and free from deleterious substances.
4. Reinforcement shall be placed as detailed on drawings and in conformance with CSA-
A23-1.
5. Waterproofing admixtures for mixing with mortar, where specified, shall be of approved
manufacture, delivered in standard containers clearly marked with the manufacturer's
name and brand.
6. All bolts, anchors, etc. shall be galvanized or weatherproofed so as to prevent rusting
through the stonework.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
MASONRY
Section 02410
Page 2
7. Drainage tile to be "Big 0" tile with geotextile filter sock, or approved equal.
2.4 Mortar
1. Mortar shall be mixed in quantities which can be used within one (1) hour. Re-tempered
or frozen mortar will not be accepted.
2. Mix mortar according to manufacturer's instructions. Mortar shall be ASTM type "M"
for foundation walls, type "N" for all other work.
3. Adjust consistency of mortar by maximum amount of water addition, consistent with
workability to provide maximum tensile bond strength. Keep air content in mortar to
minimum.
4. Mortar shall be a colour, subject to approval.
5. Conform to CSA Standards, A179, A179M.
PART 3 - EXECUTION
3.1 Inspection
1. All materials required for work described in this section shall be subject to inspection at
the source of manufacture or supply, or upon delivery on the site.
2. Any materials not meeting the requirements of this specification shall immediately be
rejected and removed from the site.
3. Any materials damaged or otherwise not meeting the requirements of the specifications
shall not be incorporated into the work and shall be removed.
4. Arrange for the landscape architect's inspection of all footings, foundations, etc., before
backfilling.
3.2 Permits and Fees
1. The contractor shall be responsible for obtaining all necessary permits prior to
commencing work and shall arrange for and pay for all fees for such permits.
3.3 Laying Up
1. Lay true to line, level accurately space courses in running bond. Keep bond plumb
throughout. Lay comers and reveals, plumb and true.
2. Fill bed and vertical joints evenly and solidly with mortar. Fill vertical, longitudinal joints
and all voids completely by parging, pouring full of grout or by shoving rock closures into
place with head joints thrown against adjacent bricks.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
MASONRY
Section 02410
Page 3
3. Bond interior and exterior corners fully.
4. Concrete block joints where exposed shall be solid filled, unless specified otherwise.
Ensure all joints are of uniform thickness, in straight lines.
5. Do not wet concrete block before laying.
6. Pace stone to be anchored to block back-up with truss ties as detailed.
7. In laying masonry, avoid overplumbing and pounding of corners and jambs after setting
in position. After mortar has set, if adjustment required, remove mortar and replace with
fresh mortar.
8. Where fresh masonry abuts partially or fully set masonry, clean exposed surface and
dampen existing surface to obtain bond.
9. Conform to CSA Standard A371.
3.4
Cleaning
1. Before starting cleaning operations, allow mortar to set and cure thoroughly.
2. Use cleaning agent as recommended by brick manufacturer's recommendations.
3. When directed, use cleaning agent first on sample panel and obtain approval of results
from the landscape architect.
4. When muriatic acid is used for cleaning, wash treated area with water immediately after
use of acid.
5. The temperature of the air shall be maintained at not less than 4.50C from one (1) hour
b~fore commencement until at least forty-eight (48) hours after completion.
6. The use of admixtures to lower the freezing point of the mortar will not be permitted.
7. Provide adequate protection of finished work to prevent damage.
8. Protect all new work from rain or snow with tarpaulin or similar.
3.5
Erection Tolerances
1. Variation from Mean Plane:
Walls shall be constructed as true planes and when tested with a 3,000 mm straight edge,
placed anywhere on wall in any direction shall be true within 5 mm.
2. Variation from the Plumb:
Surfaces of columns and walls shall be plumb within 5 mm in 3,000 mm.
I
I
MASONRY
Section 02410
I
I
Page 4
3.
Variation from the Level:
I
I
I
Variation from the level for any masonry course shall not exceed 5 mm in any bay or
6,000 mm maximum.
3.6
Protection
1. Be responsible for the protection of all work installed as specified hereinafter until
acceptance of the work.
I
I
I
2. Repair, replace or otherwise remedy any defects or damages to work incurred prior to
acceptance, at no additional cost to the owner.
3.
Mortar shall not be used when the temperature of the air is below 4.50C at any time
during the day, unless means are provided to maintain the temperature above 4.50C and
protect the finished work from freezing.
4.
Where required, bricks shall be heated to a minimum temperature of 4.50C, but not more
than 6OoC, and mortar to a temperature of not less than 210C, but not over 50oC.
END
I
I
I
I
I
I
I
I
I
I
I
UNIT PAVING
Section 02515
Page 1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PART 1 - GENERAL
1.1 General Instructions
1. Comply with the requirements of Division 1.
1.2 Related Work
1.
Earthworks
Section 02210
PART 2 - PRODUcrS
2.1 Materials
1. Unit pavers shall be of manufacture and style as listed in the tender form, alternative
price section. Color to be selected upon sample submission.
2. Sand for setting bed shall be clean, natural coarse masonry sand or limestone fines.
3. Granular base shall consist of a clean, crushed stone, or rock, Granular "A" in accordance
with MTO Form No. 1010.
4. Joints shall be a clean natural fine sand.
5. Conform to CSA Specification CAN 3-A231.2-M85.
PART 3 - EXECUTION
3.1 Preparation
1. Stake out all paving to the consultant's approval. Co-ordinate with layout of adjacent
construction.
2. ExOlvate to the specified depth after compaction as detailed.
3. Excavate all soft unstable areas in sub-grade, backfill with approved granular material
and compact.
4. Maintain sub-grade parallel to finished grade and keep excavation free of water at all
times.
5. Compact sub-grade parallel to finished grade and have sub-grade tested.
6. Install granular base and compact to minimum 98% Standard Proctor Modified Dry
Density (S.P.M.D.D.) until the minimum specified depth, as detailed, has been
established.
7. The outside edge of the paving work shall be mortar supported both below and on the
I
I
UNIT PAVING
Section 02515
I
I
Page 2
side where paving stones abut sodded areas.
3.2
Installation
I
1.
Install pavers in sequence as per manufacturer's recommendations.
2.
Mechanically saw cut all pavers as necessary to fit in corners, ends, etc. Do not guillotine
cut.
I
I
3.
All paving pattern layouts shall be symmetrical between the outside fixed points.
4.
No spaces are acceptable between stones, and spacing shall be consistent to obtain a
uniform pattern.
I
5.
Spread sand on paver surface. Tamp and make level the pavers with a vibrating plate
compactor or equal. Sweep sand into joints not yet filled.
I
I
I
3.3
Inspection
1. Unit paving shall receive final inspection by the consultant upon completion of all paving
work.
2. The surface of the finished paving shall be true to grade as shown on drawings and shall
be free of irregularities exceeding 3 mm as measured with A 3000 mm straight-edge
parallel to the centre line of the paving.
I
I
3. Any part of the completed paving not meeting the requirements of the drawings and the
specifications shall be removed and replaced prior to acceptance and at the contractor's
expense.
END
I
I
I
I
I
I
I
I
ASPHALT PAVING
Section 02552
Page 1
I
I
PART 1 - GENERAL
1.1 General Instructions
I
I
I
I
I
I
I
I
I
I
1. Comply with the requirements of Division 1.
2. Comply with Durham Region standard specifications.
1.2 Related Work
1.
Earthworks
Section 02210
PART 2 - PRODUcrS
2.1 Materials
1. The granular base course shall conform to the requirements of OPS Form 1010.
2. Paving mixtures shall be a hot mix, hot laid asphaltic concrete installed to the minimum
compacted thickness shown on the details.
3. The mixture shall be composed of coarse and fine aggregates, mineral filler and asphalt
cement, uniformly mixed and meeting the gradation requirements specified hereinafter.
4. Coarse aggregates shall be a crushed rock, slag or gravel, or combinations thereof, free
of clay, silt or other deleterious materials and meeting the gradation requirements of
OPS Form 1010, latest edition.
5. Fine aggregates shall be composed of clean, hard durable particles of natural sand,
manufactured sand or screenings resulting from the crushing of rock, stone or gravel.
Material shall be free of clay, silt or other objectionable material.
6. The mineral filler shall consist of finely ground particles of limestone, hydrated lime or
other mineral dust approved by the consultant. It shall be free of clay, silt or other
deleterious matter and shall conform to the following gradation requirements.
Sieve Size
Percentae:e Passine:
I
I
I
No. 30
No. 100
100
80
7.
Asphalt cement shall conform in all respects with OPS Form 301-02-1 (See Appendix A).
8.
Where a priming base is required, it shall be a homogenous medium curing liquid
asphalt, MC - 30.
9.
Material for painting the joints shall be slow setting asphalt emulsion, SS - 1, meeting
the requirements as set out in Appendix C.
I
I
I
I
ASPHALT PAVING
Section 02552
Page 2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2.2 Equipment
1. Plants used by the contractor for the preparation of asphalt paving mixtures shall meet
the requirements of the OPS Form 310.06.01 to 310.06.02.
2. All equipment required for work described shall be maintained in satisfactory working
condition for the duration of the work.
3. Spreading equipment and rollers shall meet the requirements of the OPS Form 310.06.01
to 310.06.02.
4. The contractor shall have copies of the above mentioned sub-sections on the site for the
duration of the work.
PART 3 - EXECUTION
3.1 Inspection
1. During construction, the density and thickness of each course shall be carefully controlled
and shall be in full accordance with the drawings and specifications.
2. The average thickness of each course shall at no point vary more than 6 mm from the
specified thickness.
3. The density of the completed pavement shall be equal to or greater than 97% of a
laboratory specimen prepared as specified in Sub-Section 7.
4. Each course shall be inspected and tested for density and thickness to the approval of the
consultant before placing subsequent courses.
5. Asphalt paving shall receive final inspection by the consultant upon completion of all
asphalt work.
6. The surface of the finished paving shall be true to grade as shown on drawings and shall
be free of irregularities exceeding3 mm as measured with 3000 mm straight-edge parallel
to the centre line of the paving.
7. All defective areas shall immediately be remedied by cutting out the course, as required,
and replacing it with fresh, hot mix which shall immediately be compacted to conform
with the surrounding paving and shall be thoroughly bonded to it.
8. Any part of the completed paving not meeting the requirements of the drawings and the
specifications shall be removed and replaced prior to acceptance and at the contractor's
expense.
I
I
I
I
ASPHALT PAVING .
Section 02552
Page 3
3.2
Cleaning
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1. After completion of asphalt work and prior to final inspection, the contractor shall
remove from all concrete walks, curbs, steps, walls and other structures, such
contamination by asphaltic or other materials resulting from the work.
3.3
Testing
1. Laboratory test specimens of the paving mixtures shall be prepared and tested in
accordance with the current procedures of the Ministry of Transportation.
2. When required by the consultant, all coarse and fine aggregates and mineral fillers to be
used in the paving mixture shall be tested to determine conformance with the
requirements of the specifications.
3. The contractor shall notify the consultant when aggregates and fillers are available for
sampling and testing in order to determine the composition of the paving mixture(s).
4. Ample time shall be given to allow a period of not less than three (3) weeks for testing
and designation of paving mixture prior to commencement of production.
5. The costs of such tests shall be charged as provided for in the special conditions.
6. Asphalt cement shall be guaranteed by the supplier to meet the requirements of the
specifications at the time of arrival on the site. When required by the consultant the
asphalt cement shall be sampled and tested, free of charge, in accordance with the latest
edition of ASTM-DI4O. Cost of sampling and testing shall be paid for by the supplier.
7. Liquid asphalts shall be guaranteed by the supplier to meet the requirements of the
specifications at time of arrival on site.
8. Asphalt emulsions shall be guaranteed by the supplier to meet the requirements of the
specifications at time of arrival on site.
9. When required by the consultant, asphalt emulsions shall be tested in accordance with
the latest edition of ASlM-D244. Test samples shall be taken in accordance with
ASTM-DI4O. The costs of samples and testing shall be the responsibility of the supplier.
3.4
Site Preparation
1. All rough grading, filling where required, excavating and preparation of sub-grade under
all asphalt paving, shall be described under Section 02210 Earthworks.
2. The final sub-grade under asphalt paving shall have the approval of the consultant prior
to placing of granular base course(s).
3. Any underground wiring or other utility occurring below a paved area shall be fully
compacted to 100% Standard Proctor Modified Dry Density (S.P.M.D.D.).Do not place
I
I
I
ASPHALT PAVING
Section 02552
Page 4
I
asphalt and later cut for installation of utilities. Fully inspect and duly accept wire
crossings by the electrical contractor.
I
I
I
I
I
I
I
I
I
I
4. Upon approval of sub-grade, the contractor shall spread the approved specified granular
base course materials in accordance with the drawings.
5. Granular materials shall be spread in layers not exceeding four 100 mm in depth, per
layer. The contractor shall take care that granular materials do not become contaminated
by deleterious materials.6.Immediatelyfollowing spreading, each layer shall be compacted
to 98% S.P.M.D.D.. Areas adjacent to curbs, catchbasins, manholes and other areas not
accessible to rollers, shall be properly compacted with approved mechanical or hand
tamping devices.
7. Depth indicated on drawings shall be the minimum depth after proper compaction.
8. All irregularities or depressions resulting from rolling shall be corrected and compacted
until the surface is smooth and uniform and true to line and level.
9. Pinal grade of granular base shall be subject to the approval of the consultant before
placing of asphalt.
10. The contractor shall arrange for compaction tests to be carried out by an independent
testing firm and submit test results to the consultant prior to placement of asphalt. Have
enough work prepared to justify four hours of work by the testing company.
11. The cost for such tests shall be paid for as provided for in the special conditions. Where
re-testing is required, because of insufficient compaction, the cost of re-testing shall be
the responsibility of the contractor.
3.5
Base Preparation
1. The approved granular base shall be proof rolled and inspected by the consultant.
Excavate and re-work all soft areas.
!I
! I
I
2. the surfaces of all existing curbs, gutters, walls, vertical faces of existing pavements and
all structures in actual contract with new asphalt mixes, shall be painted with a complete,
thin coating of asphalt emulsion SS-l, or approved equal, to provide a closely bonded,
water-tight joint.
3.6
Joints
1. All joints made during paving operations shall be straight, clean, vertical and free of
broken or loose material. Where joints occur between new courses and existing
previously laid down courses, the course shall be cut back sufficiently to provide a clean,
vertical surface.
2. Joint with existing asphalt pavement shall be made by burning process.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ASPHALT PAVING
Section 02552
Page 5
3.7
Placing of Asphalt Mixtures
1. All paving courses shall be spread within twelve (12) hours after the previous course has
been spread and compacted.
2. Paving mixture shall not be placed when the temperature surface is less than or steady
at 2 degrees Celsius. The base upon which the mixture is to be laid shall be dry and
weather conditions suitable.
3. The temperature of the mixture shall not be less than 1180 C immediately after spreading
and prior to initial rolling.
4. All courses shall be laid and spread by means of approved equipment. For walkways,
form long smooth edges. Do not create straightline chords on curved edges.
5. Immediately after spreading and screening, the surface shall be checked and all
irregularities corrected before compaction is started.
6. Where hand-spreading is necessary, this shall be done simultaneously with machine-
spreading or immediately afterwards to ensure a good bond.
3.8
Compaction
1. Each paving course shall be compacted with approved rolling equipment to produce a
pavement with a density equal to or greater than 97% of the density of the laboratory
compacted mixture.
2. Rolling shall be started as soon as possible after placing the mixture when it will bear the
roller without checking or undue displacement.
3. Rolling shall be carried out in three (3) operations in close sequence. Each pass of the
roller shall overlap previous passes to ensure a smooth surface free of roller marks.
a)
The first ''breakdown'' rolling shall be carried out as close as possible to the
paver, using either three-wheeled or two wheeled rollers, depending on the width
of paving to be compacted.
I
I
I
I
I
b) The second rolling with pneumatic-tired rollers, shall follow the first rolling as
soon as possible while the paving mix is still warm enough to result in the
maximum specified density.
c) Final rolling shall be done with two-axle or three-axle tandems while the
material is still warm enough for the removal of roller marks.
Hand tamping shall be carried out with hot tampers in all areas not accessible to the
rolling equipment.
4.
END
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
.61)
Soil-Eng CONSULTING SOIL & FOUNDATION ENGINEERS
Limited 100 NUGGET AVENUE. SCARBOROUGH. ONTARIO "'1$ 3A7' TEL: (416) 754-8515' FAX (416) 754.8516
BRANCH OFFices: BARRIE - MISSISSAUGA · BOWMANVILLE . NEWMARKET
A REPORT TO
COSBURN GmERSON LANDSCAPE ARCHITECTS
A SOIL INVES11GAll0N FOR PROPOSED
PARK FACIUI'IES
PARKLAND OF BOWMANVII.LB amEK
SOUIH OF QUEEN STRBBT
TOWN OF BOWMANVII.LB
....
Reference No. 9306-8.57
AUGUST 1993
DISTRIBUTION
3 Copies - Cosbum Giberson Landscape Architects
1 Copy - Soil-Eng Umited
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
II
I
I
.~
Reference No. 9306-S.57
TABLE OF CONTENTS
1.0
INTRODUcnON
1
"..."..........."...... ...."""""""
2.0 SITE AND PROJECf DESCRIPTION . . . . . . . . . . . . . . . . . . . 2
3.0 FIElD WORK """ " " " , . . . . . " . " . " " . . . " . " " " " " . " " " " " " " " 3
4.0 SUBSURFACE CONDmONS . . . . . . . . . . . . . . . . . . . . . . . . . 4
4.1 Earth Fill "..".",,,.......,,..,,,,,,.,,,,,,,,,,,,,,,,,,,,"""" 4
4.2 Topsoil. . . . . . . . . . . . . . . . . . .'. . . . . . . . . . . . . . . . . . . 5
4.3 Sandy Gravel ................................. 5
4.4 Silty Sand Till . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.5 Silty Oay Till ................................. 7
4.6 Sandy Silt ................................ . . . . 9
4.6 Compaction Characteristics of the Revealed Soils ...... 11
5.0 GROUNDWATER CONDmONS ................ ...... 13
6.0 DISCUSSION AND RECOMMENDATIONS.............. 14
6.1
6.2
6.3
6.4
6.5
6.6
Par kette """."......"......""""."""",,""""""""" 15
16
18
18
20
20
Foundations of Gazebo and Stairway . .' . . . . . . . . . . . . . .
Stairway "..".".""..".......".""""",,""""""""""
Pedestrian. Bridge "".."........"""".""",,""""""""
Storm Sewer " " " . " " . " " " . . . . " . . " " " " " " " " " " " " " " " " "
Excavation
........ ........ ......"..".."..".."
I
I
I
,I
I
I
I
I
I
I
I
I
I
I
,I
I
I
I
I
~
Reference No. 9306-5.57
USTOFTABLES
Table 1 ~ Natural Water Content (Sandy Silt) . . . . . . . . . . . . . . . . . . . . . 10
Table 2 - Estimated Water Content for Compaction. . . . . . . . . . . . . . .. 11
Table 3 - Measured Groundwater Level . . . . . . . . . . . . . . . . . . . . . . . . . 13
Table 4 ~ Soil Parameters for Bridge Design. . . . . . . . . . . . . . . . . . . . .. 19
Table S - Classification of Soils for Excavation . . . . . . . . . . . . . . . . . . . . 20
liST OF ENCLOSURES
Borehole wgs ..........................
Grain Size Distribution Graphs .............
Borehole wcation Plans . . . . . . . . . . . . . . . . . . .
Figure&' 1 to 3
Figures 4 to 6
Drawing Nos. 1 and 2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
!I
!I
I
I
I
~
Reference No. 9306-S.57 1
1.0 INTRODUcnON
In accordance with a facsimile transmission dated June 24, 1993 from
Mr. B. Giberson of Cosburn Giberson Landscape Architects, a soil investigation
was carried out in the parkland of Bowmanville Creek, south of Queen Street, for
proposed Park Facilities.
The purpose of the investigation was to reveal the subsurface conditions and to
determine the engineering properties of the occurring soils for the design and
construction. of the proposed project.
The findings and resulting geotechnical recommendations are presented in this
Report.
It should be noted that no tests have been carried out to determine whether
environmental contaminants are present in the soils. Therefore, this report deals
only with a study of the geotechnical aspects of the proposed project.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-5.57
2
2.0 SITE AND FROmer DESCRIPJ10N
Bowmanville is situated on Iroquois Lake plain, where drift has been partly eroded
by the water action of the glacial lake and in places filled with lacustrine clay, silt
and sand.
The project area is adjacent to the Bowmanville Creek valley in the centre of
Bowmanville, south of Queen Street It covers a flat area at the top of the north
bank of the valley, a sector of the northern valley bank, and a sector on the south
bank of the creek.
The project consists of a paved parkette and pathway leading to a gazebo on the
flat land at the top of the north bank; a stairway on the face of the northern bank;
and a pedestrian bridge crossing the creek.
The .sector of the bank on which the stairway will be built slopes at about
1.0 vertical:2.0 horizontal with a height of 16.0 metres.
A site inspection has shown the face of the valley bank is generally wooded and in
a stable conditipn; however, in the sector where the stairway is proposed, snow-
dumping has flattened the trees and in places the subsoil is exposed and has been
eroded by runoff.
I
I
, I
I
I I
II
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-S.57
3
3~0 FIELD WORK
The field work, consisting of three (3) boreholes to depths ranging from 5.0 to
18.7 m, was performed on July 26, 1993, at the locations shown on the Borehole
Location Plans, Drawing Nos. 1 and 2, attached.
The holes were advanced to the sampling depths by a track-mounted, continuous-
flight power-auger machine equipped for soil sampling. Standard Penetration tests,
.,p
using the procedures descnoed on the enclosed "Ust of Abbreviations and Terms",
were performed at frequent intervals of depth. The test results are recorded as the
Standard Penetration Resistance (or 'N' values) of the subsoil. The relative density
of the granular strata, and the consistency of the cohesive strata are inferred from
the 'N' values. Split-spoon samples were recovered for soil classification and
laboratory testing.
The field work was supervised and the findings recorded by a Senior Geotechnical
Technician.
The elevation at each of the borehole locations was determined with reference to
the site bench mark shown on Drawing No.1, which has a geodetic elevation of
108.82 metres.
I
I
I
I
I
,I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-$.57
4
4.0 SUBSURFACE CONDmONS
Detailed descriptions of the encountered subsurface conditions are presented on
the Borehole Logs, comprising Figures 1 to 3, inclusive. The revealed stratigraphy
and the engineering properties of the oc~g soils are briefly discussed herein.
Beneath a layer of earth fill at the top of the valley bank, strata of sandy silt; silty
sand till; and silty clay till were encountered. The latter extends to the toe of the
valley bank. On the south bank of the creek an alluvi'1l deposit was encountered
above a stratum of silty clay till which is laminated with a stratum of sandy silt.
4.1 Earth Fill
The fills consist of silty clay and sandy silt; they are contaminated with bricks,
cinders and glass, showing the fill is mixed with construction debris. They may be
contaminated with environmentally undesirable material and it will need to be
assessed by laboratory testing (chemical). This procedure is not within the terms of
reference for this investigation.
The fill extends to a depth of 2.1 m in Borehole 1, deepening to 4.6 m towards the
top of the banK, as revealed in Borehole 2. The obtained 'N' values are 5 to 16,
with a mean of 8 per 30 em of penetration. This shows that the fill was loosely
placed; however, it has self-consolidated.
The water content of the samples was found to vary from S to 19%, and shows that
the fill at the top of the bank is drier than that in the flat area behind the top of
the bank.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-$.57
5
In using the fill for engineering purposes, it must be sorted free of debris
. contamination and be properly compacted.
4.2 TQPsoil
The topsoil was found beneath the earth fill in Borehole 2; it has a thickness of
40 centimetres. Sample examinations show it contains fine roots and is dark brown
in colour. indicating it has a high humus content. The organics are highly
compressible rendering the topsoil too weak for engineering application.
4.3 Sandy Gravel
The sandy gravel contains a trace of silt with occasional plant debris occurring in
the upper layers. Sample examinations show the particle sizes of the sand fraction
are well graded, and the gravel and sand particles are subangular to rounded in
shape. This shows that the sandy gravel is an alluvial deposit and from the
resistance to augering the presence of cobbles and boulders in the deposit is
inferred.
The obtained '~ values are 32 and 40, indicating the relative density of the deposit
is dense.
The natural water content of the samples was found to be 8 and 9%. The low
value shows that due to the perviousness of the material the water drained out as
the samples were taken.
A grain size analysis was performed on one representative sample and the result is
plotted on Figure 4.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-S.57
6
According to the above findings, the other engineering properties are deduced in
. the following:
Non-frost-susceptible and moderately water erodible.
Pervious, with the estimated coefficient of permeability being 10-1 em/sec.
A frictional soil, its shear strength is derived from internal friction and is soil
density dependent with an estimated internal friction angle of 400.
In steep cuts, the dry and wet gravel will slough to its angle of repose (or its
internal friction angle), will run with water seepage, and boil with a
piezometric head of about 0.8 metre.
4.4 Siltv Sand Till
This deposit was encountered in the deep borehole drilled at the top of the bank.
It consists of a random mixture of particle sizes ranging from clay to gravel, with
sand and silt being the dominant fractions: Its structure is heterogenous, showing
the deposit is a glacial till.
Sample examinations indicated that the till is cemented and the samples slaked
readily when placed in water.
The obtained 'N' value is 100 +. This shows that the relative density of the till is
very dense, suggesting that it has been highly preconsolidated by past glacial
loading.
Intermittent hard resistance to augering was encountered, indicating the presence
of cobbles and boulders in the stratum.
I
I
I
I
1\
I
I
I
I
I
I
I
I
I
I
I
I
I
I
'I)
Reference No. 9306~S.S7
7
The natural water content of the samples was determined and the results are
. plotted on the Borehole Logs. The values range from 5 to 7%, showing the clay is
in a damp condition.
A grain size analysis was performed on a representative sample and the result is
plotted on Figure 4. The gradation shows the till is gravelly.
According to the above findings, the following engineering properties of the silty
sand till are listed below:
Highly frost susceptible and moderately water erodible.
Low permeability, with an estimated coefficient being 10"' em/sec.
A frictional soil, its shear strength is primarily derived from internal friction,
and is augmented by cementation, with an estimated internal friction angle
of over 450.
It will be stable in steep cuts; however, under prolonged exposure local sheet
collapse will likely occur.
4.5 Silty Oay 1ill
The silty clay till consists of a random mixture of soils; the particle sizes range
from clay to gravel, with the clay fraction exerting the dominant influence on the
soil properties.
The structure of the till is heterogenous, indicating it is a glacial till.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-$.57
8
Hard resistance was encountered during augering, showing the till is embedded
with occasional cobbles and boulders.
The consistency of the till was found to be hard. This is confirmed by the eN'
values of 67 and 100 plus.
The Atterberg Limits of one representative sample and the natural water content
of all the samples were determined. The results are plotted on the Borehole Logs
and summarized below:
Liquid Limit
Plastic Limit
Natural Water Content
29%
17%
9 to 19% '(mean 13%)
The results show that the till is a cohesive material with low plasticity. The natural
water content is generally below its plastic limit, confirming the hard consistency
disclosed by the 'N' values.
A grain size analysis was performed on one representative sample and the result is
plotted on Figu!e S.
According to the above findings, the following engineering properties are deduced:
Moderately frost susceptible and water erodlole.
Low permeability, with an estima~d coefficient of about 10-7 em/sec.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I -
~
Reference No. 9306-$.57
9
A cohesive soil, its shear strength is primarily derived from consistency which
is inversely. related to its moisture content. It contains sand; therefore, its
shear strength is augmented by internal fri1fn.
It will generally be stable in a relatively steep cut; however, long exposure
.<\
will allow infiltrating precipitation to wet thf. soil mantle, and this may lead
.,,,"
to local sloughing. },
4.6 Sanqy Silt
The sandy silt was found in Borehole 1 beneath the earth fill and laminated in the
silty clay till in Borehole 3. f
.."
,t.'
..,-,
Sample examinations showed that the silt found beneath the earth fill (Borehole 1)
:J.~
contains silty clay layers. The silt stratum laD\inatCd in the silty clay till occurred in
.;g..
the valley (Borehole 3) and contains occasional clay seams. The laminated
f~
. structure shows that the revealed silts are lacus~, deposits from a different era.
I
.'~
They are generally wet and became highly dllataDt.when shaken.
The obtained ~ values in the silt found on top of the valley bank varied from 8 to
10, with a mean of 9, and in the sandy silt in the valley, the eN' value is 100 +.
The relative density of the silts is thus inferred as loose and very dense.
,.~.
..
',..'
,
The natural water content of the samples was determined; the values are plotted
. ~
on the Borehole Logs and summarized below: . .
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
II
I
I
I
~
Reference No. 9306-5.57
10
Table 1 - Natural Water Content (Sandy Silt)
Soil Type Natural Water Content (%)
Sandy Silt (Borehole 1) ~. 22 to 31
.,
Sandy Silt (Borehole 3) 15 and 19
These values confirm that the silts are wet.
A grain size analysis was performed on one representative sample and the result is
plotted on Figure 6.
According to the above findings, the following engineering properties relating to
the project are given below:
Highly frost susceptible, with high soil adfreizing potential.
Highly water erodible; susceptlDle to migration through small openings under
.-II
seepage pressure. "
'-%
Low permeability, with the estimated coefficient being 10"' em/sec.
Frictional soils, their shear strength is density dependent. Due to their
dilatancy, the strength of the wet silts is susceptlDle to impact disturbance,
i.e. the disturbance will induce a build-up of pore pressure within the soil
mantle, resulting in soil dilation and a reduction in shear strength.
'i: .
In excavation, the moist silts will be stable hi' relatively steep cuts, while the
,"
wet silts will slough and run slowly with seepage bleeding from the cut face.
I,..
They will boil with a piezometric head of 0.4 metre.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
, I
II
I
~
Reference No. 9306-5.57
11
4~6 Compaction Characteristics of the Revealed Solls
The obtainable degree of compaction is primarily dependent on the soil moisture
and, to a lesser extent, on tbe type of compactor used and the effort applied.
As a general guide, the typical water content values of the revealed soils for
Standard Proctor compaction are presented below:
Table 2 . Estimated Water Content for Compaction
I Water Content (%) for Standard
Proctor Compaction
Determined Natural
Soil Type Water Content (%) 100% (optimnm) Range for 95% or +
Earth Fill (flat land 12 to 19 14 10 to 16
behind the bank)
Earth FilI (top of 5 to 8 14 10 to 16
valley bank)
Sandy Silt (top of 22 to 31 13 10 to 17
valley bank)
Sandy Silt (in the 15 and 19 13 10 to 17
valley)
Silty Clay Tllf 9 to 19 13 10 to 16
(mean 13)
Silty Sand Till 5 to 7 10 8to13
Sandy Gravel 8 and 9 10 6 to 15
-
-.-. w._."-
..'
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,I
II
I
I
I
~
Reference No. 9306-5.57
12
The above values show that for 95% or + Standard Proctor compaction the earth
. fill on top of the bank will require aeration or mixing with the drier fill, and the
sandy silt will require aeration. The remaining soils are generally suitable for
structural compaction.
Densification of the sandy silt, earth fill and sandy gravel should be carried out
using a heavy vibratory roller. The intensity of the vibration must be adjusted in
accordance with the soil moisture. The tills must be compacted using a heavy
kneading-type roller.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-5.57 13
5.0 GROUNDWATER CONDmONS
The groundwater level was measured on completion of the boreholes. The data
are plotted on the Borehole Logs and tabulated below:
Table 3 . Measured Qroundwater Level
BH No. Depth (m) BL (m)
1 4.0 103.8
2 Dry 87.4 .
3 1.5 88.5
The groundwater was detected in the loose silt underlying 2.1 m of earth fill and
close to the creek where the pervious sandy gravel was saturated by the water in
the creek. At the top of the bank the borehole was drilled to a depth level with
the bed of the valley; it remained dry on completion. However, the soil became
grey at about EI. 97.6, and from this, together with the soil moisture profile, the
permanent groundwater regime appears to occur below EI. 94.0.
The water measured in Boreholes 1 and 3 is perched in nature, and is
derived from infiltrated precipitation which is trapped in the voids in the loose
sandy silt or is influenced by the water level in the creek.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-5.57
14
6~O DISCUSSION AND RECOMMENDATIONS
The investigation has disclosed that the fiat land behind the top of the north bank
of the valley is underlain by a layer of self-consolidated, earth fill extending onto a
stratum of loose to compact sandy silt till. At the top of the north bank the earth
fill is deeper and beds onto the original topsoil at a depth of 4.6 metres. The
natural soils at the bank consist of compact to very dense silty sand till overlying a
stratum of silty clay till.
At the south bank of the creek an alluvial deposit consisting of dense sandy gravel
was encountered. It extends onto a hard silty clay till which is laminated with very
dense sandy silt.
The groundwater level measured at the fiat land is derived from infiltrated
precipitation which is perched at a depth of 4.0 metres. At the top of the bank, no
groundwater was detected due to the low permeability of the tills; however, the
permanent groundwater level is expected to occur at a depth of 12.0 m (lower
sector of the bank). The groundwater level at the south bank of the creek
generally corresponds with the water level in the creek.
The geotechnical findings and/or constraints which warrant special consideration
are presented below:
1. The land at the top of the bank and behind the top of the bank has been
covered with a layer of fill. The fill extends to a depth of 2.1 m
(Borehole 1) thickening to a depth of 4.2 m (Borehole 2) at the top of the
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-$.57
15
bank (El. 105.7 to 101.5) According to the design drawing (No.1 prepared
by Cosburn Giberson), the proposed paved parkette will generally follow the
existing contours; therefore, it will be built on the existing fill which was
found to contain construction debris and glass. The environmental
parameters of the fill should be tested to ensure that it is suitable for
parkland use. In addition, the fill is a highly frost-susceptible material, and
this should be taken into consideration in the design of the pavement.
2. The foundations of the gazebo and stairway muSt extend at least 1.5 m into
the natural bank below the creep zone generally associated with banks
sloped at 1.0 vertical:less than 2.5 horizontal.
3. For construction of the pedestrian bridge, the excavation for the abutment
should be sheeted to prevent water infiltration.
The recommendations appropriate for the project described in Section 2.0 are
presented herein. One must be aware that the subsurface conditions may vary
between boreholes. Should this become apparent during construction, a
geotechnical engineer must be consulted to determine whether the following
recommendati~ns require revision.
6.1 Parkette
The pavement for the parkette will either consist of paving stone or a concrete slab
and will be sensitive to frost heave. The recommended protective schemes are
given below:
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-5.57
16
Paving Stone
The fill subgrade must be removed to a depth of 1.0 m, replaced with non-
frost~susceptible sand, and should be provided with subdrains to prevent
water ponding in the sand mantle.
Concrete Slab
The slab must be insulated with SO mm Styrofoam or equivalent.
In preparation of the sand base for the paving stones or granular base for the
concrete slab, the fill subgrade must be proof-rolled.
The sand base must be uniformly compacted to at least 95% of its maximum
Standard Proctor dry density.
The concrete slab should be founded on a 15 em granular base which should be
compacted to at least 95% of its maximum Standard Proctor'dry density.
6.2 Foundations o~ rrll7~bo and Stairway
The existing bank consists of very dense silty sand till overlying a hard silty clay till.
The bank slopes at 1.0 vertical:about 2.0 horizontal with a height of 16.0 meters.
The very dense till extends to about El. 94.0; the remaining soil consists of very
hard silty clay till which extends beyond the toe of the bank, EI. 88.7. This shows
. there is no risk of deep-seated failure of the bank and its overall stability is
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
{l)
Reference No. 9306-5.57
17
estimated to be at least 1.4. However, there is creep movement associated with the
. surficial zone which is driven by the weathering process. This zone is generally
confined within 1.2 m from the face of the bank.
The foundations of the gazebo must be extended onto the natural sound soil, Le.
the dense silty sand till. The foundations of the stairway must extend below the
creep zone and be designed to resist the creep. The foundations must extend at
least 3.0 m into the natural soils.
According to the findings of Borehole 2, this level lies either in the very dense silty
sand till or the hard silty clay till.
A Maximum Allowable Soil Pressure of 800 kPa is recommended for normal
foundations and 1,500 kPa for drilled caissons. The ratio of the embedded depth
to the diameter of the caisson should be at least 2.5:1.0.
The recommended soil pressures incorporate a safety factor of three against shear
failure of the underlying soils.
The total and 4ifferential settlements of the footings are estimated to be less than
25 and 15 111m, respectively.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
Reference No. 9306-$.57
18
6.3 Stairway
The stairway will be elevated. In places, the underlying silty sand till and silty clay
till have been exposed on the face of the bank. These soils are susceptible to
water erosion, particularly on a bank; therefore, the face must be well planted to
promote the rooting system and vegetative cover which will protect the face against
runoff erosion.
6.4 Pedestrian Bridge
The foundations of the bridge abutments must be placed beneath the scouring
depth of the creek and be provided with adequate earth cover (1.2 m) for
protection against frost action.
According to the soil data disclosed by Borehole 3, the founding level appears to
lie in the dense sandy gravel or the hard silty clay till. In the dense sandy gravel,
the foundations must be placed at a level where the material is free of plant debris.
The recommended soil bearing pressure for the SLS is 600 kPa for the design of
the foundatio~. The corresponding soil bearing pressure for the ULS is 1,800 kPa.
The total and differential settlements of the foundations designed with the
recommended SLS soil pressure are estimated to be 2S and 15 mm, respectively.
The other soil paramenters for the design of the bridge are given below:
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
{;)
Reference No. 9306-5.57
19
Table 4 . Soil Parameters for Bridge Design
Soil Unit Weieht (kN/m3)
Bulk SubmeTBed
Sandy Gravel 22 13
lateral Earth Pressure Coefficients
Active At Rest Passive
(JCa ) (}Co.) (I<p)
Silty Sand Till
UI.S 0.33 0.40 3.00
SLS 0.50 0.60 2.00
Sandy Gravel
UI.S 0.28 0.35 3.57
SLS 0.42 0.53 2.38
Coefficients of Friction and/or Cohesion Ar;linu Foundation S1idin~
llLS SLS
Silty Clay Till 150 lcPa SO kPa
Sandy Gravel 0.57 0.38
The abutments should be backfilled with free-draining granular material (such as sandy
gravel, fine to coarse sand, etc.) extending to at least 1.0 m from the wall. Lateral
sub drains, consisting of filter-wrapped weepers. should be installed at the bottom of the
walls, or the walls should be provided with weep holes. This is to prevent water ponding
behind the walls, which upon freezing may damage the abutments.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
{;)
Reference No. 9306-5.57
20
The backfill for the abutments should be compacted to 95% of its maximum Standard
. Proctor dry density.
6.5 Storm Sewer
The proposed invert of the storm sewer, located behind the top of the northern bank of
the valley (as shown on Drawing No. 1 submitted by Cosburn Giberson) extends from
El. 101.9 to El. 105.22. This level lies mostly in the fill.
The sewer bedding should consist of 20 mm Crusher-Run limestone; where debris is
encountered at the sewer subgrade, it should be removed and replaced with compacted
bedding material. The sewer trench should be backfilled with the excavated material,
which must be sorted free of construction debris and compacted to 95% of its maximum
Standard Proctor dry density.
6.6 Excavation
Excavation in excess of 1.2 m should be carried out in accordance with the manner
specified in Ontario Regulation 213/91.
Classification o! the soils for excavation purposes is given below:
Table 5 . Cassification of Soils for Excavation
Material Type
Silty Clay Till; Sandy Silt Till and 1
Dense Sandy Silt
Sandy Silt; Sandy Gravel with Water 3
Seepage and Earth Fill
Sandy Silt and Sandy Gravel Below 4
Groundwater
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
{;)
Reference No. 9306-5.57
21
The excavation for the bridge foundations should be carried out within enclosed sheeting
'which should be driven into the underlying silty clay till to control the groundwater
seepage into the excavation.
SOll.J.ENG LIMl1ED
.-
/
~.... ... ..-
-..-
-''''
VSC:rb
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
LIST OF ASBREVIATIONS & oeSCRIPTION OF TERMS
The abbreviations and .rms CDmtnonly empJoytcl on the bor.hol. Io.;s, an
tn. fi~ures and In the text of W /"IpoI1 are .. follows:-
1. S).MPLE TYPES
3. SOIL OeSCRIPT10N
al c"hllionless Soils:-
"N" (bJows/f'tl Relativ. OensitV
o to 4 very 1000se
4 to 10 loose
10 to 3) compact
3J to 50 dense
over 50 very dense
b) c"h.sive Soils:-
Undrained Shur
(Strength (k.s.f.l Consisune'''
Leu than 0.25 very soft
0.25 to 0.50 soft
0.50 to 1.0 firm
1.0 to 2.0 rtlff
2.0 to 4.0 very stiff
over 4.0 hard
AS Auger Sample
es Chunk S.mple
DO Drive open
DS Denison tYpe sam pl.
FS Foil sampl.
RC Roc\( cora with sin It perc:snu;e of /"ICCVlry
ST Slotted Tube
TO Thin'walled. open
TP Thin-walled, pisten
WS Wash Sample
2. PENETRATION RESISTANC! IHN"
Dynamic Cone Pen.uation R.sistance:
A ccntinuous profil. showing the number of
blows for each foot of pen.tration of a 2"
diameter 900 point ccn. driven by a 14Q.pound
hammer falling 30 inches.
Plotted as
c) Methed of Oeurmination of Undrained Shear
Strength of Cohesive Soils:-
x 3.2 - Fi.ld van. tert In borehole.
Th. number denotes the sensitivity to ~-
moulding.
Standard Pen.tration Resisunce or "N" value:
Th. number of blows of a 140 pound hamnw
failing 30 Inches required to advanca I 2-inch
0.0. drlv. open sampl.r one foot Into undbo
tured soli.
Plotted IS "0"
A Laboratory Van. Ten
WH Sampler advanced by rtatic wti;ht
PH Sampler advanced by hydraulic preswre
PM Simpler advanced by manual pressure
C - Compression tart In laboratory.
For a saturated cohesive soil th. undrair.ec!
shear stren;th Is uken as one-half of the
undrair..d cempr.ssive str.n~th.
METRIC CONVERSION FACTORS
1 FT. . 0.3048 .etre.
1 LB. . 0.453 kl
1 inch - 25.4 mm
1 k.s.f.- 47.88 kN/m2
~
Soil.Eng CONSULT/~G SOIL & FOUNOAT/ON fNGINE!RS
Limited 100 Nugg.~'AYGu., Sca=1:)orouc;h, ON, K1S 3A7
&AWI.U PENETRA TION RES 1ST ANeE Iblowo/Q'3 III )
ELEV. SOIL OEn'H 0 210 4.0 60 8,0 WATl:F
DUCFUn'ION I
DEPTH No. . TV'E "N" SCALE rEAR STRENGTH (kN/nl2) LEVEL
. 5,0 '90 150 200
.. I I
107.8 Ground Surface BH 1
0.0 Brown
SILTY CLAY & :m e
1 00 8 co
SANDY SILT, Fill .
f"')
0 c:
with bricks, cinders and .... 0
2 00 8 . -.-I
glass . .j,,)
1'05 7 2 '"" Q)
- C:aJ.-;
2.1 Brown, loose to 0..
3 00 8 <21 e
compact I 0
. u
'""
. c:
SANDY SILT 4 00 9 ~ 0
. ~ .~ \J
with stiff clay layers 4 ...
(varved structure)
Ii S ro- ..
S 00 10 -:~
.. ..-....
m -
102.3
5.5 END OF BOREHOLE .
- . ...
6 .- -
-
-
4. ..
I -.....- .. ...-...
'--'-'
_...-
- -.. ............. ........:..:
- . . :::.. .
.-. .-. .
; -.....
-
.
. -
-
-
'-
-
~ -
..:
---= =::
- ..-
-
ElmEa; .... --
.- .--
. WATER CONT ENT (%)
wp I ~ OWl
,
I l I
. .
I
Bowmanville Creek & Queen
.108 No.: 9306-5.57 LOCATION: Village of Bowmanville
JOB DESCRI,.,.ION: Proposed Park Facilities
METHOD OF BORINO: Flight-Auger
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SoU.EA, u.u...
I
Street
DATE:
Flei No 1
July 26, 1993
10
20
30
40
I
I
I I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Bowmanville Creek & Queen Street
JOB No.: 9306-S. 57 LQC.A.TIQN: Village of Bowmanville FIG No. 2
JOB DESCRIPTION: Proposed Park Facili ties
METHOD OF BOAING: Flight-Auger CATE: July 26, 1993
SAMPLES PENETRATION RES 1ST ANeE Ibl.-.IO'31ll)
ELEV. IOU. DEI'TH 10 2.0 4,0 6,0 8fO WAT'E
DEICJUPTION
DEPTH TV'E ,." SCALE !IHEAR STRENGTH 1"'''/1'12) LEVU
No. . ',0 /90 /50 200
.. , I
101.0 ~11rT::4(",'" BH 2
0.0 Brown . fila
-+1++
SANDY SILT, Fill
1 DO 16
with silty clay inclusions, S
bricks, cinders and 2 DO
2
glass ---'
3 DO 5 Iaoo
-
4 ...
99.4 ... -
4.6 40cm TOPSOIL :! 't:
~ - 4 DO 15 . ....--.
Compact to c
very dense 0
- . ... ....
6 +J
5 DO 00+ Ql
,...j
0..
e
........ .. + 0
SILTY SAND, Till u
c
.....6 DO 00.... ..............- 0
- -.
. ..0.0- .::::: - >-
S \..l
gravelly brown . .- 0
occ. cobbles and ---- .....,.,..
grey ....... -
boulders
-, 00 100i: --- ~
CO 10()-to.. 10i
t-S
~5
91.0 12.
12.0 Grey, hard 9 DO 100+
SILTY CLAY, Till
sandy ~O DO 100... ~ ')
a tr. of gravel 14_
....
occ_ cobbles and .
boulders
11 DO 100+ - --".......
16 .
. WATER CONTENT (%!
W, , ~ wi.
i
I I , 4~
.
SoU-En, Limited
10
20
30
o
....-...... "-' "
JOe No.: 9306-S.57
J08 DESCRIPTION:
METHOD OF aORINO:
Bowmanville Creek & Queen
LOCATIo..: Village of Bowmanville
Proposed Park Facilities
Flight-Auger
Street
I
I
FIG No 2A
DATe:
July 26, 1993
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
IAWU. 'ENETRATlON RESISTANCE (b1_/O,'ItIj \
ELEV. lOlL DEPTHIO 2.0 4,0 6.0 8,0 WATe~
DESCRIPTION
DEPTH TYPE ....'" SCALE ; ~HEAR STRENGTH IllN/rn2) I.EVEL
.... . ~,o '90 I~O 200
. I I i
Continued BH 2 !
16.0 Grey, hard
:
12 DO 00+
SILTY CLAY, Till
sandy, a tr. of gravel 18
occ. cobbles and boulders -- D
84.3 and clay. seams 13 DO 100+
18.7 END OF BOREHOLE
20
-...-...,
....-........... -
-- .
.......
IE
..
-.-
......-t.
-- .
....
mmmi
e
-
u..
.
~~
Imm
...........
. WATER
wp I
CONTENT (%)
! WL
SoU.En, Umiud
I
10
.
20
30
40
I
I
JOe No.: 9306-5.57
JOB DESCRIPTION:
METHOD OF BORING:
Bowmanville Creek & Queen
LOCATION: Village of Bowmanville
Proposed Park Facilities
Flight-Auger
lOlL SAMPLES
ELEV. DESCRlrTlON
DEPTH No. TYPE ..,.-
.
90.0 Ground Sur1'a("~ BH 3
0.0 Brown, dense
sornejlant
S~OYGAA~L _ ~~ 1 00 32
occ. cobbles
(alluvial deposit) 2 00 40
87.9
2.1 Grey, hard Till 3 00 00+
- SILTY CLAY, -
Grey, very dense -4 00 oo+-
SANOY SILT
86.2
3.8 Grey, hard
SILTY CLAY, Till
sandy, a tr. of gravel
85.0 occ. cobbles and boulders 5 00 67
5.0 END OF BOREHOLE
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SoU.En, Umil4Nl
Street
Fie No 3
DATE: July 26, 1993
PENETRA TlON RESISTANCE I bI 0...0 10 '3 '" 1
DI"H 0 210 4,0 6.0 80 WATER
SCALE ~HEAR STRENGTH I k"'/m2) LrvtL
. 5,0 '90 I~O 2~O
--
2
4_
6-5m
Iii
.
w
~
_... r
- ::"
.~... .....
~S!E
-.
--
-- ..:.-::::=-....::.
-..-
~
-"
~....I..."
.-
..:::: t:.:.:::=
................:-
I
--
---
!E - -. .---
. WATER CONTENT ("to)
Wp I ~ w.
I
'0
40
.
20
30
\J
C
o.,n
'M -
.j.J
OJ
~
0-
S
8
c
o
e
10
.
CX)
.... ... co
.........
.
...J
tzJ
...,.+-t. C2J
--
.
...J
.
~
--
..... .....::.
--
-~
---
-------------------
U. S. BUREAU OF SOILS CLASSIFICATION
I GRAVEL
. ~OARS E
~
Soil-Ellg Limited
GRAIN SIZE DISTRIBUTION
I SAND I
FINE COARSEIMEOIUM I FINE I V. FINE
REFERENCE N2 9306-5.57
SIL T
CLAY
FINE
FIN E
SILT 8 CLAY
10
~ 2"IZ- Vi r ~. 111 31/ 4 8 10 16 20 30 40 5060 100 140 200 210 325
. I 1\ I I '\ II . . I I . I , I I
\ ~
"
" "" ,
""""
'\ ~ ......
" . ~
~~ ~ t'....
'" ""l .... B . /S .5
'" """ ~
'" .....
~ ...~ ~
GRAVEL
SAND 1'" BU.3/f. f.2
SILT .....
CLAY r"""-. ~
~
VERY FINE -
SAHO 8 SILT
10
'1
GRAIN SIZE IN MILUMETERS
COEFFICIENT OF UNIFORMITY'
St.
COEFFiCIENT OF CURVATURE'
01
001
100
90
80
70
e 60
z
it
tit
f. SO
..
~ 40
u
~ 30
20
o
100
Proposed Park Facilities
PROJECT'80wmanville Creek & Queen
lOCAT~'Villaqe of Bowmanville
BOREHOLE ~ 1 2 3
SAMPLE N9 : 5 2
DEPTH: (m) 6. 2 1. 7
ELEVATION' (m) 99.9 88.3
Classification of Sample ond Group Symbol'
BH.2/Sa.5 SILTY SAND, Till
gravelly
BH.3/Sa.2 SANDY GRAVEL, a tr. of silt
LIQUID LIMIT 010 ::
PLASTIC LIMIT OlD ::
PLASTICITY INDEX 0/0
MOISTURE CONTENT 0/0
PERMEABILITY (em/sed :;
BH.3/Sa.2
BH.2/Sa.5
"
-
c,
C
Ai
(T\
( Es t. )
10-1
10-6
-------------------
U.S. BUREAU OF SOILS CLASSIFICATION
A EL
o RS E
~
Soil-Eng Limited
GRAIN SIZE DISTRIBUTION
REFERENCE N9 9306-S.57
SIL T
CLAY
10
1 I I , II I I I I I IT
-
- ---
- r-- ~
~
'"
"...
..... ~
~ '"
"
i"o
..... ......
to-.....
GRAVEL K
SAND ~
SILT
CLAY
VERY fiNE
$NC) a SILT
FINE
50 60 100 140 200 Z10 32S
SILT 8 CLAY
100
90
80
70
" 60
z
4;
.,.
f 50
..
Z 40
W
u
~ 30
20
o
tOO
10
.1
GRAIN SIZE IN MILLIMETERS
COEFFICIENT OF UNIFORMITY:
COEFR:IENT OF CURVATURE'
01
001
Proposed Park Facilities
PROJECT' .
Bowmanv1l1e Creek & Queen
LOCATION. Village of Bowmanville
BOREHOLE Nt. 3
SAMPLE Nil : 3
DEPTH: (m) 2.4
ELEVATION: (m) 87.6
Classification af Sample and Group Symbol I
SILTY CLAY, Till
sandy, a tr. of gravel
LIQUID LIMIT 0/0 % 29
PLASTIC LIMIT 0/0 17 .,.
::
C
PLASTICITY INOE>< 0/0 a: 12 c
~
MOISTURE CONTENT 0/0 :: (T,
PERMEABILITY (em./see.) :: 10-7
(Estimated) .'
St.
-------------------
U. S. BUREAU OF SOILS
(t)
Soil-Eng Limited
GRAIN SIZE DISTRIBUTION
REFERENCE Nt
9306-S.S"/
SIL T
CLAY
10
1 1 I . -..... I I .1 1
~
"\
,
~
,
[\
~ \
1\-
'" I
i
GRAVEL "' I
SAND ,
SILT "
.......... i
CLAY .....
r........ ",
VERY FINE -..... ---
SAND 8 SILT
.001
FINE
I"'; 3,.-
10
FINE
50 60 100 140 200 Z10 325
SILT a CLAY
100
90
80
70
" 60
z
it
lit
f 50
....
Z 40
tal
U
r 30
20
o
100
10
'1
GRAIN SIZE IN MILLIMETERS
COEFFICIENT OF UNIFORMITY'
COEFFCIENT OF CURVATURE'
01
Proposed Park Facilities
PROJECT'Bowmanville Creek & Queen St.
LOCAT~,Village of Bowmanville
BOREHOLE Nt. 1
SAMPLE Nt: 3
DEPTH: ( m ) 2 . 4
ELEVATION: (mHOS.4
SANOY SILT
UQUIO LIMIT % =
PLASTIC UM IT % =
PLASTICITY INDEX % =
MOISTURE CONTENT 0/0
PERMEA81L1TY (cm./secJ ~
(Estimated)
...
G
(
::l
[1
Classification of Sample and Group Symbol'
10-6
c
-------------------
I -. I
I
,
!
t8.K. a.. 108.82 ·
CIIt_._~. ..----
-= ~..h.;.l ,i-K--=- <_..:., 1-;,~- ~r;':., '-rl"i""'" -~,.,.~-~~ii 7/T"
-..... . ~Ij, rrt- "v"..;~!.;.i I .1 ..~" .~ J i It......
- ! l~fje~~F"~ t' _-~, ;r~/-3~:~<--',_ e:J ~rl.
-, I '-".. -- - .p- ~.:::::::. Ld
~ r ,'j' : '. '" -~ ,,' ---".'~ ~I I --
- .~ : ''l ' -'.J " (I \I r ~ ~U onO ;: ,..... 'fl._+..
-- I ~I ,',-" BH.)t If-!" .! r- - /-1--<,--
.- Lofl. i KL !IJ:ll. - --1- .....- . --- II J,....-J
""t] . ~q /' I..... ___ ~,o'
~ ~\ ,~' , ~_~ ~,-~~ ~,~~ _ / 1\\ J / -~~---
" J J~ . ./""................ I . _ .'. \ r-.. lJ
..."'~ I j f-' ./', . ." .............. - --....... -" '1
:~ "r~ . . . ~' ~ ~~ ~~~ ' --. ., \ ~j.jl"/ /.~
-, ~ ....~~.~ t . - - ,. \.....) 7L .' . 1'- .
- ~ . t::":~.~_ ~:"~~ ~ \ .'1.1'='1 ,/. / /'
"':_ .,-:. . ~ . ., ..J LI 0 I '. "1 ~ ~ J' . ---
:-:- - -Y-~ '. ~;::.;,,~~_ ",'" .,...,.. 't . L _ " TLYI.. ,
'~~~.~_~.T"". ~~.~.~..~~' l iT: IT VI ..~vr' J. .---
- '01-'--' 't 1 ~ -~"..'. "" .. . I. -. r' . - ..-- ~\\ /""--. /-1./
~. ~-~: -:., .~~ .:.~:.-:.~,~:~...... k - -- ~~] ~~ : / /<./~ i'\t:; .' /.... ,. -.
~ . -:-:7 .. 1 j .~. _ '=-':~<:>:' ":' '.,. .' .\:\. ." "~I !-f 17
- o' 0 . . , I ....., .;.. -...." ..... .0 .. I.. I f'
_ '-....... ." .... ~ J
= ,.. ; -......... '. ~. .... ... . ...:./" ". ~
. , ! -.t "' ::...-"..-~ .. --
.'If .." - - .~..---.-
~
... . .-..
1-
IOIEHOlE LOCATIO" I
au. NO: 9lO6-S.57
DATE: "...,.,.t l~J
DRAW,'" NO: 1
SCALf: HORIZ - 1.400
SOil-EM' Llftll
-
-
-
,,-----,. ,---
-
,~.
1-'
,:;l-
~L_1-:=: _ l.
-
-
-
-
-
-
-
-
-
-
-
-
.........
,.... .. .N1<,..." .... t. .....
I .1
."-,,
;.~ ~ :~:~~-
.- i::-",..~~- ~,.;~!..
.\..".
",.
-.-
. r
-,
..!~,.l~.
. ... . ~ -\...~~.: .#. 1
l;l:~' .:'
~----r--
-
,I,
~I
...i:I'
-.
i
<<;
I
i
.-"i
-
-
BOREHOLE lOC~TIOH P
REf. NO:
IlA TE :
OIU.'U 1IG 1lO:
SCALE: HOlt I Z
SOil-Eli'
9)06-&.51
lWql.Uotl993
2
-h400
l I II I T
_. _.~-----