HomeMy WebLinkAboutCOD-054-07
Cl!Jl-il!gton
REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
General Purpose and Administration Committee
Date:
October 1, 2007
Resolution #: r;, P A . 5 i1 7.. - () I
Report #: COD-054-07
File#:
By-law #:
Subject:
Pay Equity Phase 2 - Change of Consultant
Recommendations:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report COD-054-07 be received;
2. THAT the Purchasing By-law be waived to permit the Chief Administrative
Officer and the Director of Corporate Services to negotiate with a consultant to
complete the phase 2 revised Pay Equity Plan;
3. THAT the additional funds required to complete phase 2, approximately
$15,000, be provided from the unexpended funds in the Unclassified
Administration - Staff Development account #1 00-21-211-X-7203;
4. THAT the CUPE President be advised of Council's decision, and be invited to
participate in the Phase 2 process as required;
5. THAT the Library Executive Director be provided a copy of this report for
information and the opportunity for input into the revision of the Pay Equity
Plans and process, and to advise the Library Board of Council's actions; and
6. THAT the elements of the revised plan and posting requirements remain as
approved under report COD-44-06.
Attachment: COD-44-06
L
///
Submitted by: . ,-
Marie Marano, H,RSc" C.M.O.
Director of Corporate Services
MM/gj
Reviewed by: i) ~ --..;~
Franklin Wu
Chief Administrative Officer
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-5506
REPORT NO.: COD-054-07
PAGE 3
BACKGROUND
1.0 Current Status
1.1 The Phase 2 Pay Equity Plan revision was approved by Council through report
COD-44-06 (Attachment #1) with an estimated funding allocation of $30,000.
The consultant engaged to complete the pay equity plan revision resigned from
the project as he undertook a position which he felt conflicted with his ability to
work with the Municipality. The consultant recommended a firm to complete the
project, however upon review of the submission by this new consultant, Staff
recommended re-issuing the request for proposal in order to ensure the process
was not compromised.
1.2 The RFP was re-issued on an invitational basis in June 2007, with only one
of 6 companies submitting bids. The bid submission is not being recommended
as there is a question of commitment to a sub-contracted proprietary software
that may have the Municipality indirectly connected to two vendors.
2.0 Recommended Consultant to Complete Phase 2
2.1 Staff have consulted with the area municipalities who have undertaken job
evaluation and pay equity reviews. In these discussions a company was
identified who may be able to undertake the Municipality's existing plan and
transition it to a revised tool which will better reflect current pay equity
environment.
2.2 In consideration of the repetitive unresponsive market for completion of the
phase 2 pay equity proposal, it is recommended that the Purchasing By-law be
waived to permit the CAO, in consultation with the Director of Corporate
Services, Purchasing Manager and Human Resources Manager, negotiate an
agreement with a firm who can complete the phase 2 plan. Preliminary
discussions with such a firm suggest that there is an opportunity to negotiate with
a company who is recognized in pay equity and human resource matters,
however until negotiations are completed, it would be advisable not to provide
details. As Senior Staff will assist in the implementation of the plan, it is
anticipated that the additional funding request of approximately $15,000 should
be sufficient to negotiate completion of transition to a revised plan.
2.3 The 2007 budget provided $40,000 for the anticipated cost of the phase 2 plan.
Therefore the net requirement to continue at this point is an additional $15,000.
Due to the importance of the legislated Pay Equity obligations it is recommended
that Unclassified Administration - Staff Development account fund the remaining
$15,000 to complete the project and defer the staff development initiatives to
future budget consideration. The Director of Finance concurs with the
recommendations.
REPORT NO.: COD-054-07
PAGE 4
3.0 Consultation
The Union will be consulted on the plan, in order that they can sign endorsement
of it for their members, as required by the ACT. The Non-Affiliated group do not
have representation to sign off on the revised plan, consequently the ACT
requires their plan be posted to provide an opportunity for comment or concern to
be raised. Once the posted time limits are complete, and any concerns are
addressed, the revised plan will be considered approved in accordance with the
Pay Equity Act.
4.0 Posting of Revised Plan
Report COD-44-06 authorized posting requirements and other elements of the
process which are considered to be still applicable to the phase 2 process and
are recommended to be continued as approved under Report COD-44-06.
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-6506
, .
C[w:mgton
MEMO
TO:
Marie Marano, Director of Corporate Services
FROM:
Anne Greentree, Deputy Clerk
DATE:
September 12, 2006
RE:
PAY EQUITY REVIEW - CONSULTANT'S FINDINGS AND PHASE 2
PAY EQUITY PAY REVISION
At a meeting held on September 11, 2006, the Council of the Municipality of
Clarington passed the following resolution # GPA-323-06:
THAT Report COD-044-06 be received;
THAT the Review Report of the existing Pay Equity Plan by D & G Dudar
Consultants, be received;
THAT the Chief Administrative Officer be authorized to include a pre-
budget approved amount of $30,000 (inclusive of GST), in the 2007
Administration Consulting account, for the purpose of proceeding with the
development and implementation of revised Pay Equity Plans and
Questionnaires, for Union and Non-Affiliated Employees, including the
Library;
THAT the CAO be authorized to engage Consultants to undertake Phase
2 of the Pay Equity review, by developing a revised plan beginning early
2007;
THAT the suspension of the pay equity job review process approved by
report COD-65-05, be lifted;
THAT the existing Pay Equity Plan job review process continue essentially
in its current form with Supervisory Approval Criteria established by the
CAO, until the revised pay equity plan and process is put into effect;
THAT during the transition period until the revised pay equity plan is in
place, any recommendations by the Pay Equity Committees regarding
adjustment to compensation be approved by the CAO;
,
,
(
THAT, the recommendations put forward by the Consultant, essentially as
outlined in the body of this report, be approved for incorporation as
appropriate in the future pay equity maintenance process;
THAT the CUPE President be provided a copy of Report COD-044-06 for
the purpose of reviewing the content with the Union members;
THAT the CAO be authorized to seek input from the Union President, for
the revision of the Pay Equity Plan for Unionized employees, which will be
posted as a revised plan at the conclusion of the review;
THAT the Library Executive Director be provided a copy of Report COD-
044-06 for information and opportunity for input into the revision of the Pay
Equity Plans and process, and to advise the Library Board of Council's
actions; and
THAT, at the conclusion of the review, the CAO be authorized to post the
revised Non-Affiliated Pay Equity Plan as an amended plan for comment
by the Non-Affiliated group as required under the ACT.
#1~
Ahne Greentree
CAG*bmb
cc: Frank Wu, CAO.
Steve Harding, CUPE President
Edith Hopkins, CEO, Clarington Public Library
CORPORATION OF THE MUNICIPALITY OF CLARlNGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T(905)623-3379 F (905)623-6506
Cf!1ril!gtoo
REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date:
Tuesday September 5, 2006
Report #: COD -044-06
File#:
By-law #:
GP4- 3;13 -00
Subject:
Pay Equity Review - Consultant's Findings and Phase 2 Pay Equity Plan
Revision
RECOMMENDATIONS:
1. THAT Report COD-044-06 be received;
2. THAT the Review Report of the existing Pay Equity Plan by D & G Dudar
Consultants, be received;
3. THAT the Chief Administrative Officer be authorized to include a pre-budget
approved amount of $30,000 (inclusive of GST), in the 2007 Administration
Consulting account, for the purpose of proceeding with the development and
implementation of revised Pay Equity Plans and Questionnaires, for Union and
Non-Affiliated Employees, including the Library;
4. THAT the CAO be authorized to engage Consultants to undertake Phase 2 of the
Pay Equity review, by developing a revised plan beginning early 2007;
5. THAT the suspension of the pay equity job review process approved by report COD-
65-05, be lifted;
6. THAT the existing Pay Equity Plan job review process continue essentially in its
current form with Supervisory Approval Criteria established by the CAO, until the
revised pay equity plan and process is put into effect;
7. THAT during the transition period until the revised pay equity plan is in place, any
recommendations by the Pay Equity Committees regarding adjustment to
compensation be approved by the CAO;
REPORT NO.: COD-044-06
PAGE 2
8. THAT, the recommendations put forward by the Consultant, essentially as outlined
in the body of this report, be approved for incorporation as appropriate in the future
pay equity maintenance process;
9. THAT the CUPE President be provided a copy of this report for the purpose of
reviewing the content with the Union members;
10. THAT the CAO be authorized to seek input from the Union President, for the revision
of the Pay Equity Plan for Unionized employees, which will be posted as a revised
plan at the conclusion of the review;
11. THAT the Library Executive Director be provided a copy of this report for information
and opportunity for input into the revision of the Pay Equity Plans and process, and
to advise the Library Board of Council's actions; and
12. THAT, at the conclusion of the review, the CAO be authorized to post the revised
Non-Affiliated Pay Equity Plan as an amended plan for comment by the Non-
Affiliated group as required under the ACT.
8ubm.... bY~
Marie Marano
Director of Corporate Services
Reviewed by :1) ~ ~
Franklin Wu,
Chief Administrative Officer
Attachment:
D & G Dudar Consultants; Municipality of Clarington Pay Equity Review
Report
REPORT NO.: COD-044-GS
PAGE 3
BACKGROUND
1.0 Pay Equity Review Authorized
1.1 Report COD-65-05 authorized the CAO to undertake an independent review of the
Municipality's existing Pay Equity Plan (McDowall Plan) for applicability to today's
work environment, with a report back to Council.
1.2 The review of Pay Equity questionnaires was suspended by report COD-65-05,
awaiting the review of the plan and process.
1.3 Report COD-10-06 provided an in-camera update to the status of the RFP, which
closed on March 1,2006. As advised in report COD-10-06, the RFP submissions
were anticipated to be within the purchasing by-law limits and funding approved by
Council. The selection of the firm of D & G Dudar Consultants was determined by
the CAO in conjunction with the Director of Corporate Services, Purchasing
Manager, and the Human Resources Manager.
2.0 D & G Dudar Consultants Review and Recommendations
2.1 Don Dudar, of D & G Dudar Consultants met with the members of both Pay Equity
Committees, including the Executive Director of the Library, for a comprehensive
review of the issues surrounding the existing McDowall plan and the maintenance
process.
2.2 The report of the Consultant is attached for information and reference. Senior
Management concurs with the results of the review and the recommendations.
2.3 Essentially the following recommendations put forward by the Consultant, are
proposed to be incorporation as appropriate in the future pay equity maintenance
process under the direction of the Chief Administrative Officer:
a. That the McDowall Plan for Pay Equity, and the accompanying questionnaire, be
replaced with an updated tool for continued compliance with the Municipality's
Pay Equity maintenance obligations;
b. That organizational changes continue to be approved by Council through the
annual budget process, and the CAO be authorized to effect pay equity
adjustments provided they are within the approved budget and overall Corporate
goals and objectives;
c. That the two Committee structure remain to evaluate the pay equity review
requests put forward by employees, with recommendations to the CAO for
decision;
REPORT NO.: COD-044-06
PAGE 4
d. That a system be established to formally record decisions and justification for
recommended adjustments including decisions to grandfather or red-circle
employees;
e. That screening criteria be established to assist the employee in determining if a
change in job function constitutes a significant change requiring a pay equity
review;
f. That applicants who have qualified for a review, be advised of the decision and
reasoning of the Committee, by the CAD for Non-Affiliated employees, and by
the Chair of the Union Committee together with a Union Representative from the
Committee for Union employee applicants;
g. That Employees be educated on the revised Pay Equity Plan and
process, with particular emphasis on the job worth changes that require a review;
h. That Supervisors review the workflow attached to review request applications
that have qualified for a pay equity review to assess whether the position is
performing the authorized and appropriate function, prior to approval of the
request to proceed to the Committee for final review;
i. That the CAD prepare a recommendation for alternate forms of recognition to
address temporary or occasional work, for Council's approval.
j. That future updates to the Pay Equity process will be undertaken as deemed
timely by the CAD, within a 10 year period if possible, and any recommendation
of substantive change put forward to Council for approval.
3.0 Next Steps; Phase 2
3.1 Phase 2 of the Pay Equity analysis was not addressed until the review of the existing
McDowall plan was complete with recommendations advising on whether a new plan
and process was appropriate. The recommendation from the Consultant clearly
notes that the existing plan has outlived its usefulness and should be replaced.
Management concurs with this recommendation.
3.2 It is recommended that a new plan and process be developed with the assistance of
consultants, using the 2007 budget funds. Pre-budget approval is requested to
permit the negotiation process to begin as soon as possible in 2007.
3.3 In the interim, it is therefore recommended that the existing Pay Equity review
process continue so as not to impede any employee who feels that their job has
changes substantially thereby warranting a review. The CAD will develop criteria
applicable to the approval process of the review to ensure workflow analysis and
substantial job changes are appropriately reflected;
REPORT NO.: COD-044-D6
PAGE 5
3.4 The consultant recommended that, consistent with the norm in both private industry,
adjustments resulting from the review of pay equity applications be approved by the
CAO. This is also the practice in the Durham area municipalities. It is recommended
that this authority be extended over the existing and future adjustments, provided
that the overall organizational goals are maintained, as approved by Council.
3.5 The intention in developing a new Union pay equity plan and process, in compliance
with the Pay Equity Act, is to provide an opportunity for input by the Union into the
plan applicable to its members. The plan, once agreed upon by the Bargaining Unit
and the Municipality, will be posted in accordance with the ACT. It is not subject to
comment by employees as the Bargaining Unit is empowered to negotiate the plan
on behalf of its members.
3.6 The Non-Affiliated group, according to the ACT, have the opportunity to submit
comments to the employer during the required 90 days when the plan is posted.
The opportunity will be provided for the Executive Director of the Library to have
input into the plans also considering that the Municipality is the Library employer for
Pay Equity purposes.
3.7 It is proposed that the revised plans will incorporate a method to translate the
existing pay equity scores into the new plan such that there will not be an analysis of
each employee under the new criteria. The review may identify some employees
who require adjustment to fit into the new plan, and it is recommended that these
adjustments be approved by the CAO unless the overall adjustment is deemed to be
of significant budgetary impact.
3.8 The Director of Finance concurs with the pre-budget approval recommendations
outlined in this report.
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-6506