HomeMy WebLinkAboutCOD-050-07
REPORT II 2
CJfJ!mglOn
REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
Council
Report #:
COD-050-07
File#:
Resolution#: C-4'fQ-07
By-law #: J 00 1- / <J 0
Date:
September 24, 2007
Subject:
Tender CL2007-42 - Newcastle Library Capital Project
Recommendations:
It is respectfully recommended that Council approve the following:
1. THAT Report COD-050-07 be received;
2. THAT the Tender Bids received for Tender CL2007-42 be rejected;
3. THAT Council formally confirm the revised Capital Budget Amount of
$3,450,047.00
4. THAT Council authorize the Newcastle Library Building Committee to re-scope
the Newcastle Library project and to re-issue the tender to the same pre-qualified
general contractors early 2008.
5. THAT the previously awarded consultant's contract with Shoalts Zaback
Architects Ltd, Kingston, Ontario; be amended to reflect the additional design to
an maximum amount of $75,000.00; and, to include LEED design work in the
amount of $68,000.00 plus $60,000.00 for the LEED Application, Energy
Modelling and Commissioning without impact to the project budget; and,
6. THAT the attached By-law marked Appendix "A" authorizing the Mayor and Clerk
to amend the existing contract agreement between Shoalts Zaback Architects Ltd
and the Municipality be approved.
Submitted by: a~
Marie Marano, H.B.Sc., C.M.O.
Director of Corporate Services
cJ~~
hNanCy Taylor, B.B.A., C.A.,
(J 'Director of FinancefTreasurer
MM/JB/EH/BT/gj
~~-~
Reviewed bh:J .
Franklin Wu
Chief Administrative Officer
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-5506
REPORT NO.: COD-OSO-07
PAGE 3
1.0 BACKGROUND
1.1 In February, the Municipality advertised for; and, pre-qualified seven contractors
to submit bids. Since that time, two firms had advised they were unable to bid
due to other commitments.
1.2 Tender CL2007-42 for the construction for the Newcastle Branch Library was
advertised and issued to pre-qualified contractors with bids being received on
September 6,2007; as per Schedule "A".
1.3 At the bid opening, only three submissions were received. Two of the bids were
submitted on time; with one bid being rejected as it was submitted late.
1.4 As noted on Schedule "A", the two qualified bids were in excess of the funds
allocated to the construction budget amount $2,648,895.00
2.0 BIDS ANALYSIS
2.1 As indicated, the two qualified bids that were received are in excess of the
construction budget. Following the opening, the Consultant contacted the
remaining pre-qualified bidders to determine why bids were not received. They
both indicated they were experiencing difficulties in obtaining quotes for materials
and one indicated that he missed the closing deadline due to timing and heavy
traffic.
2.2 Other contributing factors to the high bid amounts were costs related to
addressing the soils conditions, increased construction costs since establishing
the original construction budget; and, unexpected costs related to certain
materials required for the project. Steel, drywall, painting and floor finishes were
well in excess of estimates prepared by the Consultant during the pre-
construction cost analysis.
2.3 While the Municipality reserves the right to negotiate with the lowest bidder;
given the projected scope of changes, it was determined this would not be a
prudent course of action in this case as we would not expect to generate the
required reductions.
2.4 The Newcastle Library Building Committee is aware of the financial concerns
within the Municipality as outlined by the Director of Finance; and, for this reason,
recommend that Council reject both bids; and, authorize the Building Committee
work with the Consultant to re-scope the project in order to bring it in-line with the
financial resources allocated to the project.
2.5 The Building Committee is recommending the tender be re-issued in early 2008;
and that the same seven pre-qualified contractors be given the opportunity to bid
on the revised project.
REPORT NO.: COD-050-07
PAGE 4
3.0 SCOPE OF WORK
3.1 In order to bring the project in-line with the financial resources, the Building
Committee has reviewed a number of options. The Committee recommends re-
scoping the project design through a number of changes to the building
components. In order to do so, the Consultant will re-design the building with
staged reductions, possibly including a reduced floor space and changing to a
flat roof.
3.2 In consideration of the above, these adjustments will allow us to re-tender the
project in early 2008 for construction.
4.0 DESIGN
4.1 In order to achieve the desired results, the Consultant will re-scope the project
design within the financial resources. This will require a significant amount of
work by the Consultant including redesign and revisions and to re-issue the
tender documents tender drawings. Accordingly, the Building Committee is
recommending the Consultant's contract be amended to reflect this. increased
scope of work to an up set limit amount of $75,000.00 to be drawn from the
existing project account # 110-42-440-85510-7401.
4.2 At the award of the Consultant's Contract to Shoalts Zaback Architects Ltd, the
Municipal Building Committee had not included the LEED (Leadership in Energy
and Environmental Design) green building program. Through the design
concepts prepared by Shoalts Zaback Architects, it was determined by the
Committee;. and, presented to Council in December 2006; the Newcastle Branch
Library would qualify as a LEED Certified Building, demonstrating the
Municipality's commitment to conservation and sustainable buildings.
4.3 The initial consultant's contract did not include fees for the additional scope of
work for LEED development; nor did it include fees for the sub-consultants
working with Shoalts Zaback Architects for the preparation of LEED design work
and tender documents as required by the Canada Green Building Council for
approval.
4.4 The revised project budget presented at an October 2006 Building Committee
meeting at which a number of both the Library Board and Council members were
present. At that meeting the Consultant identified the necessary funds for the
LEED application should the Building Committee determine the LEED process
was viable. The budget includes $60,000.00 for LEED application process,
energy modelling and commissioning, $68,000.00 for the Consultant and their
sub-consultants for the design phase, construction and specifications documents
as well as construction administration.
4.5 The Engineering Department is also recommending future project work for the
proposed Newcastle Memorial Park Soccer Field be included within the scope of
REPORT NO.: COD-050-07
PAGE 5
this work however to be funded from a separate account to be approved during
the 2008 Capital Budget deliberations.
5.0 PROJECT BUDGET
5.1 At the referenced October 2006 Building Committee meeting, the project budget
was reviewed. The 2006 Capital budget provided funds in the amount of
$2,788,604.00. At Library Board meeting, a number of items were reviewed and
budget adjustments were recommended in the additional amount of $661,443.00
based on a number funding sources suggested by the Director of Finance
bringing the total project amount to $3,450,047.00. This was referenced in
Report COD-027 -07 approved by Council June 25, 2007.
5.2 As the Building Committee had recommended construction of a LEED Certified
Building, funding from the Municipal Government Enterprise Reserve Fund would
be allocated to the capital cost difference in the amount of $285,000.00.
5.3 The Library Development Charges financing was also adjusted to reflect future
capacity requirements in the additional amount of $178,810.43. This is in
addition to the original budgeted amount of $1,405,456 and will result in an
estimated debenture of $1,584,266.43 once the tender is awarded. This is
determined based on the non-replacement square footage cost share at the
mandatory 90% eligibility for development charges funding. However, this is
substantially in excess of the original amount determined in the 2005
development charges background study of $1,210,500. There is no opportunity
to increase this amount further as there will be a shortfall in the Library
Development Charges Reserve Funds in the foreseeable future. Some provision
for this was incorporated in the 2007 budget. This will limit future library growth
related projects until such time as the future Development Charges growth
reflects this capacity.
5.4 Additional funds were also identified from the Capital Works Reserve Fund in the
amount of $98,816.29 and the General Municipal Reserve Fund in the same
amount of $98,816.29 in addition to the original budget amount for the non-
growth share at 10% and the replacement square footage at the existing
Newcastle Branch Library that cannot be attributed to future growth.
5.5 The Director of Finance concurs with these recommendations and funding
sources. However, as noted, there is no opportunity to increase this amount
further from a development charges perspective.
REPORT NO.: COD-050-07
PAGE 6
6.0 CONCLUSION
6.1 The Building Committee will report back to Council for approval when the project
has been re-tendered.
REPORT NO.: COD-OSO-07
PAGE 7
~
Leading the Way
Municipality of Clarington
Schedule "A"
Bid Summary
TENDER CL2007-42
GENERAL CONTRACTOR FOR THE CONSTRUCTION OF
THE NEWCASTLE BRANCH LIBRARY
Bidder Bid Amount
(Excludinq GST)
Aecon No Bid
Garritano Bros. Ltd. Bid Rejected
Gerr Construction Ltd. $ 3,025,000.00
J. J. McGuire Ltd., No Bid .
Mitren No Bid
Pre-Eng Contracting Ltd. $3,310,000.00
Strut-Con Constructions Ltd. No Bid
*GST Extra
REPORT NO.: COD-050-07
PAGE 8
Appendix "A"
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW 2007-
Being a By-law to authorize an amendment to the contract between the
Corporation of the Municipality of Clarington and Shoalts Zaback
Architects Limited, Kingston, Ontario, to amend the agreement for
Architectural Services for the Newcastle Branch Library.
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY ENACTS
AS FOLLOWS~
1. THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington and seal with the Corporation Seal,
an amendment to the contract between Shoalts Zaback Architects Limited,
Kingston ,Ontario, and said Corporation; and,
2. THAT the amended contract attached hereto as Schedule "A" form part of this
By-Law
BY-LAW read a third time and finally passed this
24th day of September 2007
24th day of September 2007
BY-LAW read a first and second time this
Jim Abernethy, Mayor
Patti L. Barrie, Municipal Clerk