Report To: Joint General Government and Planning and Development Committee
Date of Meeting: December 10, 2018
Report Number: COD -030-18 Resolution: JC -051-18
File Number: By-law Number:
Report Subject: Contract Awards During Council Election Recess
Recommendation:
1. That Report COD -030-18 be received for information.
Municipality of Clarington
Report COD -030-18 Page 2
Report Overview
To report to Council on the contracts awarded during Council recess.
1. Background
During periods when Council is in recess provision has been made in the Purchasing By -
Law 2015-022 S. 73 for the approval of contract awards in order to continue with business
as usual. The by-law further states that Council shall not vary any action or decision of the
contract awards made while Council is in recess. During the Council Election Recess of
2018 there were 4 contract awards that would normally necessitate a report to Council.
2. Comments
In accordance with Purchasing By -Law 2015-022 S. 73 (2), the following contracts were
awarded during the Council Election Recess:
CL2018-1, Port Darlington Road Neighbourhood Access Road (Attachment 2- Memo
from Engineering — Confidential Cost Apportionment attached).
Note that for the CL2018-1 Tender award the attachment to the Engineering Services'
Memorandum to Finance, Detailed Low Bid Cost Apportionment — CL2018-01, has been
distributed under separate cover as confidential as it contains financial information that
may impact the Municipality's ability to effectively administer the contract.
RFP2018-11, Microsoft Office 365 Migration
CL2016-16, (Year 3 Renewal), 2018 Stormwater Management Pond Cleanout and
Maintenance
CL2018-30, Soper Creek Trail — Phase 2 Construction
A copy of the recommending Purchasing Services Reports for the above noted projects
are attached.
3. Concurrence
Not applicable.
4. Conclusion
The actions taken by Staff as documented in the attached Report Memos be provided for
Council's information.
5. Strategic Plan Application
Not applicable.
Municipality of Clarington
Resort COD -030-18
Submitted by:
Marie Marano, H.B. Sc., C.M.O
Director of Corporate Services
Paae 3
Reviewed by:
Andrew C. Allison, B. Comm, LL.B.
Chief Administrative Officer
Staff Contact: David Ferguson, Purchasing Manager, 2209 or dferguson(o)clarington.net
Attachments:
Attachment 1 PS -016-18 - Soper Creek Trail — Phase 2 Construction
Attachment 2 PS -017-18 - Port Darlington Road Neighbourhood Access Road
Attachment 3 PS -018-18 - (Year 3 Renewal), 2018 Stormwater Management Pond Cleanout
and Maintenance
Attachment 4 PS -020-18 - Microsoft Office 365 Migration
There are no interested parties to be advised of Council's decision.
MM/DF
r �, ri
ap /
Purchasing Services
Date: September 24, 2018
To: Andrew Allison, Chief Administrative Officer
From: David Ferguson, Manager, Purchasing Services
Report #: PS -016-18 File Number: CL2018-30
Subject: Soper Creek Trail - Phase 2 Construction
Council Recess Procedure (Purchasing By -Law 2015-022 S. 73)
Recommendations
It is respectfully recommended to the Chief Administrative Officer the following:
That Royalcrest Paving & Contracting Ltd. being the lowest bidder meeting all
terms, conditions and specifications of CL2018-30 be awarded the completion of the
Soper Creek Trail - Phase 2 Construction; and
2. That the funding required in the amount of $449,043.62 (Net HST Rebate) which
includes the revised construction costs of $419,519.54 (Net HST Rebate) and other
related costs such as materials testing and contingencies of $29,524.08 (Net HST
Rebate) be funded as follows:
Soper Creek Trail — Phase 2 110-32-325-83284-7401 $425,325.20
Pedestrian Link to Camp 30 110-32-330-83284-7401 $23,718.42
Corporation of The Municipality of Clarington
40 Temperance Street, Bowmanville, Ontario L1 C 3A6 T(905)623-3379
Report No: PS -016-18
Recommended bv:
1
r'
r
David Ferguson,
Manager, Purchasing rvices
g � g
Concurrence:
Trevor Pinn, B.Com, CPA, CA
Deputy Treasurer
Anthony S. Cannella,
Director of Engineering
Approved bLr.
Andrew Alli on,
CAO
MM\DF\sm
cc: M. Marano, Director, Corporate Services
Date
ClLO, )g
Date
Date
q�as`lzr,�g
Date
Page 2
Report No: PS -016-18 Page 3
1. Background
1.1 Tender specifications were prepared by the Engineering Services Department
and provided to the Purchasing Services Division. The work involves 1,850m of
trail from the existing trail location on Mearns Ave south of Soper Creek Drive
extending north along the existing trail and creek alignment terminating at the
existing connection to Sprucewood Crescent.
1.2 Tender CL2018-30 was issued by the Purchasing Services Division and
advertised electronically on the Municipality's website. A notification of the
availability of the document was also posted on the Ontario Public Buyer's
Association website.
1.3 Twenty-one (21) Companies downloaded the bid document.
1.4. The tender closed on September 5, 2018.
1.5. In view of the Council Recess, authorization is requested to award the above
contract in accordance with Purchasing By -Law #2015-022 Part 2, Section 73,
Council Recess Procedures.
2. Analysis
2.1. Seven (7) submissions were received in response to the tender call. Bid were
reviewed and all were deemed to be compliant.
2.2. Submissions were tabulated by the Purchasing Services Division (see
Attachment 1).
2.3. The results were forwarded to the Engineering Services Department for their
review and consideration.
2.4. After review and analysis of the submissions by the Engineering Services
Department and the Purchasing Services Division, it was mutually agreed that
the low bidder, Royalcrest Paving &Contracting Ltd. be recommended for the
award of contract CL2018-30.
2.5. Royalcrest Paving &Contracting Ltd. has successfully completed work for the
Municipality in the past.
3. Financial
3.1 That the funding required in the amount of. $449,043.62 (Net HST Rebate) which
includes the revised construction costs of $419,519.54 (Net HST Rebate) and
other related costs such as materials testing and contingencies of $29,524.08
(Net HST Rebate) be funded as follows:
Soper Creek Trail —Phase 2 110-32-325-83284-7401 $425,325.20
Pedestrian Link to Camp 30 110-32-330-83284-7401 $23,718.42
Report No: PS -016-18
Page 4
3.2 Queries with respect to the department needs, specifications, etc. should be
referred to the Director of Engineering Services.
4. Conclusion
4.1 It is respectfully recommended that Royalcrest Paving &Contracting Ltd. being
the only compliant bid be awarded the contract for work required for the
completion of Soper Creek Trail -Phase 2 Construction in the amount of
$419,519.54 (Net HST Rebate) as per the terms, conditions and specifications of
CL2018-30.
Strategic Plan Application
The recommendations contained in this report conform to the Strategic Plan.
Attachments: Attachment 1 — Bid Tabulation
Report No: PS -016-18
Attachment #1
Municipality of Clarington
Summary of Bid Results
Page 5
BIDDER
Bid
(Including HST)
Total Bid
(Net HST Rebate)
Royalcrest Paving &Contracting Ltd.
$465,857.98
$419,519.54
TDI International AG Inc. DBA Eco
Blue Systems
$554,875.51
$499.682.58
Melfer Construction Inc.
$663,239.94
$597,268.11
CSL Group Ltd.
$663,551.26
$597,548.46
Forest Ridge Landscaping Inc.
$707,662.50*
$637,272.00
Epic Paving &Contracting Ltd.
$867,099.85
$7807850.27
Dig -Con International Ltd.
$931,501.38
$838,845.84
$WWDFRHQWWR
5HSRUWN
ciffftwil Report
Purchasing Services
Date: November 22, 2018
To: Andrew Allison, Chief Administrative Officer
From: David Ferguson, Manager, Purchasing Services
Report #: PS -017-18 File Number: CL2018-1
Subject: Port Darlington Road Neighbourhood Access Road
Council Recess Procedure (Purchasina By -Law 2015-022 S. 73
Recommendations
It is respectfully recommended to the Chief Administrative Officer the following:
1. That Eagleson Construction being the lowest bidder meeting all terms, conditions
and specifications of CL2018-1 be awarded the completion of the Port Darlington
Road Neighbourhood Access Road; and
2. That the total funding required for the overall project in the amount of $2,491,002.10
(Blended HST) which includes the revised construction costs of $1,541,013.94
(Blended HST) and other related costs such as land purchase, consulting costs for
municipal class environmental assessment, contract administration and inspection,
material testing, detailed design, utility relocations, permits and contingencies of
$1,012,523.64 (Blended HST) be funded as follows:
Port Darlington Road Extension
to Subdivision (2016) 110-32-330-83442-7401
Port Darlington Road Extension
to Subdivision (2017) 110-32-330-83442-7401
Developer Contribution 110-32-330-83442-7403
Transfer of DC Funding from Concession Street
East Project (2017) 110-32-340-83453-7401
$ 144,050.00
$ 722,400.00
$1,047,244.76
$ 577,307.34
$2,491,002.10
Corporation of The Municipality of Clarington
40 Temperance Street, Bowmanville, Ontario L1 C 3A6 T(905)623-3379
Report No: PS -017-18
Recommended bv:
David Ferguson, _:
Manager, Purchasing'�Iices
Concurrence:
Trevor Pinn, B.Com, CPA, CA
Deputy Treasurer
Anthony S. Cannella,
Director of Engineering
Approved b
.Z000;
Andr Allison,
Chief Administrative Officer
M M\D F\s m
cc: M. Marano, Director, Corporate Services
Page 2
�2
ew zo
Date
II lZz!l�5
Date
2 2�1 g;ee-
Date
bafe
Report No: PS -017-18 Page 3
1. Background
1.1 Tender specifications were prepared by the Engineering Services Department
and CIMA and provided to the Purchasing Services Division. The work is for the
construction of a new road section to facilitate traffic movement from a new
subdivision. This work will reduce the impact on the older section of road along
our Port Darlington East Beach waterfront park. The provision of this road is a
requirement of the Conditions of Draft Approval of the subdivision and of the
Ontario Municipal Board decision of June 2015. Funding for this road is provided
through Development Charges and directly from the developer.
1.2 Tender CL2018-1 was issued by the Purchasing Services Division and
advertised FD® -I[0 X(QFLSDWVLZ -EVW. A notification of the
D)DL(m MVR [CPAJ--I-FXP HQ/E DIDmR SRANG -I[2 Q5 E-3 XEQF-O/GK HUV
Association website.
1.3 Twenty-nine (29) Companies downloaded the bid document.
1.4. The tender closed on August 29, 2018.
1.5. In view of the Council Recess, authorization is requested to award the above
contract in accordance with Purchasing By -Law # 2015-022, Section 73, Council
Recess Procedures.
2. Analysis
2.1. Six (6) submissions were received in response to the tender call. Bids were
reviewed and all were deemed to be compliant.
2.2. Submissions were tabulated by the Purchasing Services Division (see
Attachment 1).
2.3. The results were forwarded to the Engineering Services Department for their
review and consideration.
2.4. Upon reviewing the submissions, Engineering Services recommended removing
item A59- Decommissioning of the Existing Groundwater Monitoring Well as
Clarington had to have the work completed no later than October 31, 2018 under
the terms of our agreement with Hydro One. As a result of this deadline, the
services of a separate contractor were retained to decommission the well before
the October 31 deadline. The cost for the work is included in the total project
costs noted within the financial section.
2.5. Engineering Services and the Purchasing Services Division mutually agreed
(Attachment 2) that the low bidder, Eagleson Construction be recommended for
the award of contract CL2018-1. Eagleson Construction has successfully
completed work for the Municipality in the past.
Report No: PS -017-18 Page 4
3. Financial
3.1 The total funding required for the overall project in the amount of $2,491,002.10
(Blended HST) which includes the revised construction costs of $1,541,013.94
(Blended HST) and other related costs such as land purchase, consulting costs
for municipal class environmental assessment, contract administration and
inspection, material testing, detailed design, utility relocations, permits and
contingencies of $1,012,523.64 (Blended HST) is to be funded as follows:
Port Darlington Road Extension
to Subdivision (2016) 110-32-330-83442-7401 $ 144,050.00
Port Darlington Road Extension
to Subdivision (2017) 110-32-330-83442-7401 $ 722,400.00
Developer Contribution 110-32-330-83442-7403 $1,047,244.76
Transfer of DC Funding from Concession Street
East Project (2017) 110-32-340-83453-7401 $ 577,307.34
$2,491,002.10
3.2 As a result of Hydro One changing the preferred road alignment part way through
the environmental assessment, some additional design, construction and land
purchase costs were incurred. These unforeseen costs, resulted in an increase
to the overall project costs requiring additional funding. The additional funding is
to be provided through the reallocation of funds from another development
charge project, Concession Street East project, which has been delayed. It is
therefore recommended that funds be transferred from DC Funding F
Concession East Project (110-32-340-83453-7401) to cover the additional costs.
3.3 The contribution from the Developer will be collected prior to the issuance of the
Purchase Order.
3.4 Section 3 of this report has been reviewed by Trevor Pinn, Deputy Treasurer who
concurs with the funding allocation.
3.5 Queries with respect to the department needs, specifications, etc. should be
referred to the Director of Engineering Services.
4. Conclusion
4.1 It is respectfully recommended that Eagleson Construction being the lowest
compliant bid be awarded the contract for work required for the completion of
Port Darlington Road Neighbourhood Access Road in the revised amount of
$1,541,013.94 (Blended HST) as per the terms, conditions and specifications of
CI_2018-1.
Attachments: Attachment 1 u Bid Tabulation
Attachment 2- Memo from Engineering F Confidential Cost Apportionment
Report No: PS -017-18 Page 5
Attachment #1
Municipality of Clarington
Summary of Bid Results
BIDDER
Bid
Total Bid
(Including HST)
(Blended HST Rebate)*
Eagleson Construction
$1,632,833.46
$1,549,660.63
Hard -Co Construction Ltd.
$1,636,340.34
$1,553,644.19
Montgomery MacEwen
$1,716,984.89
$1,632,071.81
Contracting
Coco Paving Inc
$1,810,534.76
$1,718,419.87
Aloia Bros. Concrete
$2,099,846.64
$2,205,320.51
Contractors
Dig -Con International Ltd.
$2,982,181.31
$2,839,471.34
Note: Pricing above does not reflect the removal of Item A59 but rather shows the
pricing as received.
* Blended HST represents the Net HST value on the project items which the Municipality
of Clarington is responsible for plus the full HST amount (13%) on the project items which
the developer is responsible for. The two values are added together resulting in a Blended
HST amount.
PS -017-18 $ W W
Memo
If this information is required in an alternate format, please contact the Accessibility
Co-ordinator at 905-623-3379 ext. 2131
To: David Ferguson, Purchasing Manager
From: Ron Albright, Assistant Director, Engineering Services
Date: November 21, 2018
Subject: CL2018-01 — Port Darlington Realignment
The Engineering Services Department has reviewed the low bid by Eagleson
Construction for CL2018-01 and offer the following comments.
The work locations and a brief description are listed below:
Road
Limits
Description
Port Darlington
Intersection of Port Darlington Road
Construction of a new road
Road (East
and West Beach Road to roughly
section to facilitate traffic
Shore Drive)
500 m southeast to East Shore Drive
movement from a new
subdivision to reduce impact
on older section of road and
along our Port Darlington
East Beach waterfront park.
The low bidder on this contract was Eagleson Construction. Based on past experience
with this contractor, we recommend the contract be awarded to Eagleson Construction
in the amount of $1,623,734.71 inclusive of HST, or $1,541,013.94 with blended HST.
Note that the costs include the 1.76% non-recoverable portion of the HST for the
Municipality of Clarington's share of the project, and the full 13% HST for the
Developer's share of the project. This low bid price reflects the deletion of Item A59 —
Decommissioning of Existing Groundwater Monitoring Well as Clarington had to have
this work completed by October 31, 2018 under the terms of our agreement with Hydro
One and staff retained the services of another contractor to complete the work before
the deadline.
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1 C 3A6 1905-623-3379
PS -017-18 $ W W
Memo
A total contingency amount of approximately 8% of construction costs is required for
this project, based on past experience. Therefore, including other costs such as
Municipal Class Environmental Assessment, land purchase, Hydro One agreements,
design, contract administration, inspection, material testing, permits, contingency and
blended HST costs, the Engineering Department advises of the following funding.
Construction Cost, Based on Low Bid
$ 1,436,933.37
net HST at 1.76%
$12,952.72
HST at 13%
$91,127.85
Other Costs
$908,618.59
net HST at 1.76%
$12,017.93
HST at 13%
$29,351.64
Total Project Cost
$2491,002.10
Allocated Financing
Port Darlington Rd. Extension to Subdivision (2016)
110-32-330-83442-7401
$144,050.00
Port Darlington Rd. Extension to Subdivision(2017)
110-32-330-83442 -74 01
$722,400.00
Port Darlington Rd. Extension to Subdivision
Developer Contribution 110-32-330-83442-7403
$1,047,244.76
Transfer of DC funding from Concession Street
East Project (2017)
110-32-340-83453-7401
$577,307.34
Total Allocated Financing
$2,491,002.10
* A more detailed breakdown is to be provided to Finance to provide necessary
information for tracking of Tangible Capital Assets (TCA).
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1 C 3A6 1905-623-3379
PS -017-18 $ W W
Memo
All funding for this project is provided through Development Charge accounts or directly
from the developer. It should be noted that the provision of this road in the location
identified in CL2018-1 is a requirement of the Conditions of Draft Approval of the
subdivision and of the Ontario Municipal Board decision of June of 2015.
As noted above this project required the Municipality of Clarington to deal with Hydro
One and Infrastructure Ontario in order to complete the necessary Environmental
Assessment works and other studies necessary to complete the purchase of the
necessary land for the new road and multiuse trail. This process resulted in added
costs to the project as in our initial consultations with Hydro One they provided clear
direction where the road had to go as to not compromise their long term plans for
increased distribution towers along the corridor. Staff and our consulting team
proceeded with this direction from Hydro One to the point where Clarington was ready
to post our Notice of Completion for the Environmental Assessment but during Hydro
One's review of the material their senior staff changed Hydro One's position and stated
that the road alignment had to be on the south side of the corridor, opposite to the initial
direction provided. With this change many of the reports and preliminary alignment
design work that was done had to be redone and updated. The other unexpected cost
increase was the purchase of land from Hydro One administered through Infrastructure
Ontario. Infrastructure Ontario requires that an Across the Fence or Industrial Land
Rate method be used to assess the land being purchased from Hydro One. What this
means is that the actual lands and any constraints within it are not assessed but the
best land along hydro corridor is used to assess the value of the land you are seeking.
Originally it was estimated that the land would be less than $100,000 because it is in a
utility corridor and parts of it are environmental protection. But with the Across the
Fence method the final appraisal and eventual cost of the land was $332,927.71,
significantly higher than expected but not contestable as the Infrastructure Ontario
requirements are clearly set out. In addition to the added land costs there were
additional design costs related to the Environmental Assessment and detailed design of
roughly $50,000. The realignment of the road because of Hydro One's change in
position also resulted added construction costs related to having to construct a large
box culvert, provide screening with fending and planting for the resident south of the
corridor because the road was moved adjacent to her house. These added construction
costs amount to roughly $200,000. With these added costs additional funding for the
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1 C 3A6 1905-623-3379
PS -017-18 $ W W
Ciantigton0
Memo
project was required in order to deal with all of these costs. This funding was provided
through the reallocation of funds from another development charge project that will be
delayed as a result of subdivision work not moving forward for another couple of years.
This deferred work will be rebudgeted for once the timing for the subdivisions is
confirmed.
Considering all project costs, there is sufficient funding available and the Engineering
Dept. recommends that the Purchasing Dept. move forward with award of the contract
based on the above apportionments. Should you have any further questions, please
feel free to contact the undersigned.
Regards,
Ron Albright, P. Eng.
Assistant Director, Engineering Services
RA/cv
cc: Trevor Pinn, Acting Director of Finance
E. Watson, Capital Asset Manager
A.S. Cannella, Director of Engineering Services
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1 C 3A6 1905-623-3379
PS -017-18 $ W W
Memo
If this information is required in an alternate format, please contact the Accessibility
Co-ordinator at 905-623-3379 ext. 2131
To: Erika Watson, Capital Asset Manager
From: Ron Albright, Assistant Director, Engineering Services
Date: November 21, 2018
Subject: CL2018-01 — Port Darlington Realignment
Please see the attached Memo to David Ferguson, Purchasing Manager, regarding
award of Contract CL2018-01.
Other commitments associated with this contract are detailed in the attached cost
apportionment and include land purchase, consulting costs for municipal class
environmental assessment, contract administration and inspection, material testing,
detailed design, utility relocations, permits and contingencies. The total project cost,
including other costs and blended HST, is $2,491,002.10. Note that the costs include
the 1.76% non-recoverable portion of the HST for the Municipality of Clarington's share
of the project, and the full 13% HST for the Developer's share of the project.
It should be noted that the provision of this road in the location identified in CL2018-1 is
a requirement of the Conditions of Draft Approval of the subdivision and of the Ontario
Municipal Board decision of June of 2015.
As a result of Hydro One changing the preferred road alignment location part way
through our environmental assessment, there were some additional design,
construction and land purchase costs incurred. Additionally, the way in which
Infrastructure Ontario, who are responsible for real estate transactions for Hydro One,
calculates land costs is much different than is conventionally done and there was a
much higher land purchase cost for this project. As a result of these unforeseen issues,
there were increases in the overall project costs.
In order to accommodate these costs, funding reallocation from another development
charge project, Concession Street East urbanization, in the amount of $577,307.34 (net
of HST) was required to address the funding shortfall. Due to some delays in the
progress in development adjacent to Concession Street East, this project, with the
exception of some design costs, can be deferred and re -budgeted for when the
development is ready to proceed (anticipated sometime in 2020).
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1 C 3A6 1905-623-3379
PS -017-18 $ W W
Memo
As there has been some delays in the developments both north and south of this
section of road, it is recommended that the construction commitments identified in the
2017 budget, Account Number 110-32-330-83453-7401, be released with the exception
of the monies required for the award of the CL2018-01 contract, and $125,000 that
should be retained for detailed design of the road section originally included in the
construction cost.
It is anticipated that both developments should proceed in 2020 or later, at which time
Engineering Services will re -budget for the Concession Street East construction costs.
Should you have any questions regarding this project, please let me know.
Reqards,
Ron Albright, P. Eng.
Assistant Director, Engineering Services
RA/cv
cc: Trevor Pinn, Acting Director of Finance
A.S. Cannella, Director of Engineering Services
The Corporation of the Municipality of Clarington
40 Temperance Street, Bowmanville ON L1 C 3A6 1905-623-3379
Clarington
Report
Purchasing Services
Date: September 27, 2018
To: Andrew Allison, Chief Administrative Officer
From: David Ferguson, Manager, Purchasing Services
Report #: PS -018-18 File Number: CL2016-16 (Year 3 Renewal)
Subject: 2018 Stormwater Management Pond Cleanout and Maintenance
Council Recess Procedure (Purchasing By -Law 2015-022 S. 73
Recommendations
It is respectfully recommended to the Chief Administrative Officer the following.-
That
ollowing:
That Ground Force Environmental Inc., having submitted updated pricing as per the
terms, conditions and specifications, be awarded year 3 of CL2016-16 with a
revised scope of work for the completion of the Stormwater Management Pond
Cleanout work for the Port of Newcastle East Pond; and
2. That the funding required in the amount of $170,000.00 (Net HST Rebate) which
includes the revised construction costs of $129,915.28 (Net HST Rebate) and other
related costs such as design, inspection, contract administration, fish rescue and
contingencies of $40,084.72 (Net HST Rebate) be funded as follows:
2017 Clarington Stormwater Pond Cleanout
110-36-386-83454-7401 $170,000.00
Corporation of The Municipality Of Clarington
40 Temperance Street, Bowmanville, Ontario L1C 3A6 T (905)623-3379 F (905)623-3330
Report No: PS -018-18
Recommended bv:
r
David Ferguson,
Manager, Purchasing S rvices
Concurrence:
Trevor Pinn, B.Com, CPA, CA
Deputy Treasurer
Anthony S. Cannella,
Director of Engineering
Approved by:
An ew Allison,
CAO
MM\DF\sm
cc: M. Marano, Director, Corporate Services
7 2--Oloc"
Date
!i1z:21le
Date
Date
/Cp
Date
2
3
Report No: PS -018-18
1. Background
1.1 The funding application for the Clean Water and Wastewater Funding (CWWF)
program included the completion of the Robert Adams Pond which was tendered
and awarded to Ground Force Environmental Inc. through CL2016-16. The
award of CL2016-16 had a provision to extend the work at the pond over 3 years
provided satisfactory performance by the contractor. The contractor performed
the work satisfactorily in 2016 and 2017.
1.2 Purchase order number 09854 was issued to Ground Force Environmental Inc.
for pond maintenance and sediment removal, outlet structure restoration and
minor erosion repairs for the Robert Adams Storm Pond in Courtice.
1.3 An application from the CWWF was submitted to the Province with the inclusion
of the entire works for Robert Adams Pond to be completed in one year including
additional works at the adjacent quantity pond which have been done. As the
pond work came in under the estimate that was provided as part of the CWWF
funding agreement, staff applied to the CWWF program for a scope change to
include an additional pond cleaning to the funding program. The application was
approved and staff would like to exercise Year 3 of the CL2016-16 term order
with Ground Force Environmental Inc. with an addition to the scope of work. As
noted above, Purchase order number 09854 was issued to Ground Force
Environmental Inc. for year 1 and year 2 in the amount of $317, 292.27 (inclusive
of HST). With the requested change to the scope of work the revised amount will
exceed the dollar threshold that the Chief Administrative Officer is authorized to
approve.
1.4 In view of Council Recess, authorization is requested to award a change in scope
to the above contract in accordance with Purchasing By -Law # 2015-022, Section
73, Council Recess Procedures.
1.5 The pond selected and accepted for the CWWF scope change was the Port of
Newcastle East Pond. As each pond is unique the site preparation, access
route, dewatering and coffer dam work is specific to each pond and therefore
pricing for this work is directly related to the individual site. In reviewing this pond
with Ground Force Environmental Inc. they noted they would be willing to hold
their CL2016-16 pricing with moderate increases to the standard tender items
such as sediment removal and disposal and after reviewing the design prepared
by CIMA provided a price of $127,668.32 exclusive of HST or $129,915.28 net of
HST. Staff have reviewed the price and found the price to be reasonable.
1.6 Based on our experience with pond work over the past 2 years we have been
able to provide a much more efficient design and work program and therefore
can reduce the contingency requirement considerably. The total project costs
including contingency, design, permitting, approvals, fish rescue program,
Report No: PS -018-18
contract administration and net HST costs, is $170,000.00 and is consistent with
funding available through the CWWF program.
1.7 In view of the total award amount (including year 1 and year 2) being over
$250,000 along with a change in the scope, authorization is requested to award
the above contract extension in accordance with Purchasing By -Law # 2015-022,
Section 73, Council Recess Procedures.
2. Analysis
2.1. Ground Force Environmental Inc. were provided the design, specifications and
list of items for pricing for the Port of Newcastle East Pond for review and pricing
based on their original pricing submission in 2016 for CL2016-16.
2.2. The updated pricing was provided to the Engineering Services Department for
their review and consideration and was found to be reasonable and within the
available budget.
2.3. After review and analysis of the submission by the Engineering Services
Department and the Purchasing Services Division, it was mutually agreed that
Ground Force Environmental Inc. be recommended for renewal for year 3 of
contract CL2016-16 including the change to the scope of work.
2.4. Ground Force Environmental Inc. has successfully completed work for the
Municipality in the past, specifically in 2016 and 2017 for year 1 and 2 of this
contract.
3. Financial
3.1 That the funding required in the amount of $170,000.00 (Net HST Rebate) which
includes the construction costs of $129,915.28 (Net HST Rebate) and other
related costs such as design, inspection, contract administration, fish rescue and
contingencies of $40,084.72 (Net HST Rebate) be funded as follows:
2017 Clarington Stormwater Pond Cleanout
110-36-386-83454-7401 $1701000.00
3.2 Queries with respect to the department needs, specifications, etc. should be
referred to the Director of Engineering Services.
4. Conclusion
4.1 It is respectfully recommended that Ground Force Environmental Inc. be
awarded the year 3 contract renewal with a revised scope of work required for
the completion of Stormwater Management Pond Cleanout work for the Port of
5
Report No: PS -018-18
Newcastle East Pond in the amount of $129,915.28 (Net HST Rebate) as per the
terms, conditions and specifications of CL2016-16.
Strategic Plan Application
The recommendations contained in this report conform to the Strategic Plan.
Clarington Report
Purchasing Services
Date: November 6, 2018
To: Andrew Allison, Chief Administrative Officer
From: David Ferguson, Manager, Purchasing Services
Report #: PS -020-18 File Number: RFP2018-11
Subject: Microsoft Office 365 Migration
Council Recess Procedure (Purchasing By -Law 2015-022 S. 73
Recommendations
It is respectfully recommended to the Chief Administrative Officer the following:
1. That the proposal received from Gibraltar Solutions, being the most responsive
bidder meeting all terms, conditions and specifications of RFP2018-11 be awarded
the contract for the Microsoft Office 365 Migration; and
2. That the required funding for this project in the amount of $40,296.96 (Net HST
Rebate) be drawn from the following Account:
IT Computer S/W 110-16-162-81611-7401 $40,296.96
Corporation of The Municipality of Clarington
40 Temperance Street, Bowmanville, Ontario UC 3A6 T(905)623-3379
Report No: PS -020-18
Recommended bv:
David Ferguson,
Manager, Purchasing Se ces
Concurrence:
Trevor Pinn, B.Com, CPA, CA
Deputy Treasurer
Marie Marano, H.B. Sc., C.M.O.
Director, Corporate Services
Approved b�
And ew All son,
Chief Administrative Officer
M M\D F\
Page 2
I 4�e' I
Date
fL'G' zor�
Date
����wiJu/
Date
All�C(1
Date
cc: Rob Van Dyk, Manager, Information and Technology
Report No: PS -020-18 Page 3
1. Background
1.1 Request for Proposal RFP2018-11 was drafted for the purpose of seeking a
qualified company for the Microsoft Office 365 system integration and
implementation. This project was identified in the Information Technology
Strategic Plan as an immediate requirement as the current email system is no
longer viable. The scope of the project is for the migration of the Municipality of
Clarington from an on -premises Exchange 2010 environment to an Office 365
cloud -hosted email services. The scope of the project along with the RFP
specifications were provided by the Information and Technology (IT) Division of
the Corporate Services Department.
1.2 RFP2018-11 was issued by the Purchasing Services Division and advertised
electronically on the Municipality's website. Notification of the availability of the
document was also posted on the Ontario Public Buyer's Association website.
1.3 Twenty-seven (27) Companies downloaded the bid document.
1.4. The request for proposal closed on October 3, 2018.
1.5. In view of Council Recess, authorization is requested to award the above
contract in accordance with Purchasing By -Law #2015-022 Part 2, Section 73,
Council Recess Procedures.
2. Analysis
2.1. Ten (10) submissions were received by the stipulated closing date and time. See
Attachment 1.
2.2. All ten (10) submissions complied with the mandatory submission requirements
and were distributed to the Evaluation Committee for their review and scoring.
2.3. The Technical Proposals were first evaluated and scored independently by the
members of the evaluation committee in accordance with the established criteria
as outlined in the RFP. The evaluation committee was comprised of staff from
the IT Division and the Purchasing Services Division.
2.4. The evaluation committee met to review and agree upon the overall scores for
each proposal. Some of the areas on which submissions were evaluated were as
follows:
• Highlights of services provided within past five (5) years only
• Allocated roles and responsibilities of team members; long timeline for
scope of project and coverage for entire length is essential
• Demonstrated understanding of the Municipality's requirements, the
Project and related issues
• Demonstrated the ability to carry out all aspects of the project.
Report No: PS -020-18
Page 4
2.5. Upon completion of the evaluation, the evaluation committee concluded that the
following four (4) bids met the pre -established threshold of 80% for Phase 1 and
moved on to the second Phase of the process:
• Buchanan Technologies
• Cistel Technology
• Gibraltar Solutions
• Onx Enterprise Solutions
2.6. It was deemed by the evaluation committee that no presentation would be
required to provide further clarification regarding proposals received.
2.7. The Pricing Envelopes for the four (4) pre -qualified companies were opened and
verified and in keeping with the terms of the RFP, the evaluation committee's
recommendation is to award to the lowest bidder, Gibraltar Solutions.
2.8. Staff have reviewed the pricing submitted by Gibraltar Solutions and found it to
be acceptable.
2.9 References provided by Gibraltar Solutions were contacted and they advised that
the level of service has been satisfactory.
3. Financial
3.1 That the funding required in the amount of $40,296.96 (Net HST Rebate) is in the
budget allocation as provided and will be drawn from the following account:
IT Computer SNV 110-16-162-81611-7401 $40,296.96
3.2 Queries with respect to the department needs, specifications, etc. should be
. referred to the Director of Corporate Services.
4. Conclusion
4.1 It is respectfully recommended that Gibraltar Solutions being the lowest
compliant bid be awarded the contract for Microsoft Office 365 Migration in the
amount of $40,296.96 (Net HST Rebate) as per the terms, conditions and
specifications of RFP2018-11.
Attachments: Attachment 1 — Summary of Bid Results
Report No: PS -020-18 Page 5
Attachment #1
Municipality of Clarington
Summary of Bid Results
BIDDER
Buchanan Technologies
ONX Enterprise Solutions
Cistel Technology
Gibraltar Solutions
vNextl Q Inc.
Technology Integration Group
SiRON Technologies Group Inc
COMPAREX Canada Inc
Infront Consulting Group
Alten Calsoft Labs
*Denotes firms who were shortlisted.