HomeMy WebLinkAboutCOD-027-07
Cl!Jlmgron
REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
General Purpose and Administration Committee
Date:
June 18, 2007
Resolution #GfM~ '1lf5-lJ7
Report #: COD-027 -07
File #:
By-law #:
Subject:
Update - Newcastle Library Capital Project
Recommendations:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report COD-027-07 be received for information.
Submitted by:
Ie arano, H.B.Sc., C.M.O.
Director of Corporate Serv'ces
/~ ,
/\~ d. '\7
Reviewed by:U -.l.A...J LC
Franklin Wu
Chief Administrative Officer
MM/EH/BT/gj
CORPORATION OF THE MUNICIPALITY OF ClARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T (905)623-3379 F (905)623-5506
REPORT NO.: COD-027-07
PAGE 2
1.0 BACKGROUND
1.1 Report COD-027 -07 is prepared to provide Council with an update for the
Newcastle Library capital construction project. In December 2006, Council was
provided concept and schematic illustrations of the proposed 9,100 square foot
Newcastle Library facility. Included in those discussions was the introduction of a
LEED (Leadership in Energy and Environmental Design) Green building. This
would be the first LEED Certified building to be constructed by the Municipality,
demonstrating the Municipality's commitment to conservation and sustainable
buildings. Since that date, the Building Committee in conjunction with the
Architect have worked to achieve these goals and to remain within the revised
budget of $3,450,047 as presented to a joint meeting of the Library Board and
Councillors October 2, 2006.
1.2 In preparation for the final design, it is a standard practice for the Architect to
undertake a Geotechnical (Soils) Investigation of the site. The final report
received by the Architect indicated that the soils in this area were deficient and
that design alternatives must be taken into consideration for the development of
the final construction specifications. The architect and sub-consultants have
developed suitable specifications to enable us to continue with the project at this
site. During discussions with the soils engineer, he has advised this problem
exists within certain geographical areas of Newcastle.
1.3 The development of these revised specifications has caused a delay in the
preparation of the overall building specifications. This was necessary to ensure
the final design documents address these concerns in order that the selected
general contractor will have all required information for the construction of the
facility, limiting possibilities of additional construction charges once the
specifications are issued and construction has commenced.
1.4 This report will provide specific updates related to the LEED application,
geotechnical investigations and revised milestone dates for Council's information.
2.0 LEED Application
2.1 The Architect is in the process of developing a LEED program submission for this
project. All LEED applications are submitted to the Canada Green Building
Council for approval. The LEED program is a point-based process, with certain
prerequisites for qualification. The points are assigned in six areas;
. Sustainable Sites
. Water Efficiency
. Energy and Atmosphere
. Materials and Resources
. Indoor Environmental Quality
. Innovation and Design Process
REPORT NO.: COD-027-07
PAGE 3
2.2 There are four (4) classifications of LEED Buildings:
. Certified
. Silver
. Gold
. Platinum
Based on the size of this project, point limitations and budget, the Municipality
will be submitting an application for a LEED Certified project. The expenses
related to the LEED application and additional work for the architect and
consultants are included in the revised budget.
3.0 Geotechnicallnvestiaation
3.1 Prior to the development of final drawings, a Geotechnical Investigation is
undertaken to ensure the selected site location will physically support the
building. In this case, the investigation by a qualified soils engineer indicated the
existing site soils were not suitable for normal construction utilizing standard
excavation methods and construction of supporting footings. The soils were
identified as soft clay. Normally, with suitable soils, the contractor would
excavate a trench and construct footings to support the building. In this case,
due to the soft clay soils, there are several alternatives such as driven piles,
augered caissons, or surcharging the site. Any of these three alternatives would
support a building of this size.
3.2 The soils engineer has proposed a process of surcharging the site. This method
is the least expensive and calls for the excavation of the 9,100 square foot
building footprint to the desired depth and dumping granular fill within the
footprint and letting it stand for a period of 4 to 6 weeks. The weight of this fill
would cause the site to settle in advance of the construction. This method has
also been reviewed by the Architect's engineers and they are in agreement with
the process.
3.3 The estimated additional cost to alleviate the unanticipated poor soil condition is
$150,000.00. The Building Committee is bringing this matter to Council's
attention at this time. Once the Municipality receives the construction bids, the
Building Committee will be in a position to make the appropriate recommendation
to Council. In the interim, the Architect has made several revisions to the plans
to reduce overall costs in an effort to absorb these additional costs within the
revised budget and project contingency.
REPORT NO.: COD-027-07
PAGE 4
4.0 Revised Milestone Dates
4.1 As mentioned, the project schedule has been delayed as the Architect, Soils
Engineer and the Architects project engineers developed a suitable process for
the establishment of an affordable building support system (including time
required for the surcharging). The Architect advises the following milestone
dates for the balance of the project:
Completed Construction Drawings and
Tender Documents
July 05, 2007
Tender Submissions from Contractors
August 02, 2007
Report to General Purpose and
Administration Committee
September 04, 2007
Ground Breaking Ceremony
Week of September 24, 2007
Construction
October 2007
Total Performance
August 2008
Library Opening
October 2008
5.0 COMMENTS
5.1 Construction Contractors were pre-qualified by the Committee in March 2007.
Accordingly, the pre-qualified contractors are aware of the project delay and will
be notified of the revised milestone dates. Based on the above dates, the
Building Committee expects to receive Tender Documents in August 2007 and
will strive to work within the project budget. A report recommending a General
Contractor will be submitted to the General Purpose and Administration
Committee on September 04,2007.