HomeMy WebLinkAboutEGD-024-07
CJ!l.rpn
REPORT
ENGINEERING SERVICES
Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Report #: EGD-024-07
File #:
GPH - oC;fj -0-;
By-law #:
Date: Monday February 5, 2007
Subject:
Mill Street Subway Reconstruction, Newcastle
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report EGD-024-07 be received;
2. THAT Council endorse the Hybrid alternative as the preferred alternative;
3. THAT budget allocations contained in the 2006 Capital Budget, project Mill Street Grade
Separation, account #110 32 330 83263 7401 be reduced from a total project cost of
$6,500,000 to $2,250,000, funded through the DC reserve in the amount of $2,224,533
and from Developer Recovery in the amount of $25,467.
Respectfully by:
AfP41t410 d~-~
Submitted by: Anthony Cannella, C.E.T. Reviewed by: Franklin Wu,
Director of Engineering Services Chief Administrative Officer
ASC/jo
January 29, 2007
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T 905-623-3379 F 905-623-9282
REPORT NO.:EGD-024-07 PAGE 2
1.0 BACKGROUND
1.1 In May of 2006 the Engineering Services Department reported to Council
nd
through report EGD-32-06 on the 2 public meeting held for the
reconstruction of the Mill Street Subway south of Highway 401 in
Newcastle. At that public meeting the preferred option for reconstruction
of the subway was presented to the public and was generally well
received. The preferred option called for the permanent realignment of
the existing railway tracks approximately 10 metres to the south of their
existing location to allow for the staged reconstruction of the new subway
while maintaining high speed rail traffic through the construction zone.
1.2 The preferred alternative was primarily driven by input received from CNR
who firmly indicated no acceptance of a construction approach that would
involve track speed reduction or significant periods of railway closure (i.e.
up to 48 hours), that all railway diversions must be designed for full design
speed operation and only short term (12 to 18 hour) single track closures
would be permitted during the reconstruction. These more stringent
criteria had evolved since 1994 and their inclusion disqualified the option
preferred by staff and project consultants TSH, which was to reconstruct
the subway with the railway tracks temporarily supported in their current
location.
1.3 CNR also indicated that because of the complexity of the project and
potential impacts on its infrastructure that certain aspects of the detailed
design and construction would have to be completed by CN forces or their
designated consultants, UMA Group Ltd. In addition the work would be
tendered as a CN contract with purchase orders issued by Clarington to
cover the majority of design and construction costs.
1.4 On July 26, 2006 the Municipality received a letter addressed to Mayor
Mutton with a petition signed by 50 local residents primarily living south of
REPORT NO.:EGD-024-07 PAGE 3
the railway, expressing concern over the project as proposed. Their
primary issues of concern were the potential for increased noise and
vibration resulting from relocation of the railway tracks closer to their
homes and the environmental impacts resulting from having to widen the
railway embankment to accommodate the new track alignment. Widening
of the railway embankment would result in tree removal and the need to
lengthen culverts at the railway crossing of both Foster and Graham
Creeks. They also expressed concern over noise, dust and vibration
impacts during construction, increased post construction vehicular speeds
and decreased property values and public safety resulting from the tracks
moving closer to their homes. In essence they expressed support for the
“Do Nothing” scenario.
1.5During the fall of 2006 Municipal staff and consultants met with CNR staff
to review project issues and confirm criteria for final design and project
scheduling. Through these meetings CNR staff reinforced the
requirement to maintain high speed train traffic through the construction
zone and the need to relocate the railway southerly to facilitate subway
reconstruction. They would not commit to a construction schedule
because of a severe shortage of flagging personnel and indicated that
even if a flag person was available for the project that person would only
be able to work 8 hour days, including travel time to and from the work
site.
2.0 PROJECT COSTS
2.1 The restricted work day imposed by limited flagging resources will have a
significant impact on project costs. Contractors typically work 10 to 12
hour days during the peak summer construction season. Productivity will
be severely reduced on this project resulting in a cost premium.
REPORT NO.:EGD-024-07 PAGE 4
2.2As CNR forces will be administering the construction contract, the
Municipality will have reduced control over the expenditure of funds and
will be exposed to considerable financial risk.
2.3The needto extend the stone culverts at the railway crossings at both
Foster and Graham Creeks also adds financial liability to the project. Both
extensions will require ”in water works” resulting in the need to provide
fisheries compensation as well as the use of design and construction
methods sensitive to their historic nature.
2.4Based on the above factors it is now estimated that the originally preferred
alternative will cost approximately $11 million to construct. The allocation
in the 2006 capital budget for this project was $6.5 million.
3.0 COST BENEFIT ANALYSIS
3.1 As a result of projected project cost increases noted above, the concerns
raised by residents, and the lack of commitment to the project by CNR, the
Director of Engineering Services requested that previous alternatives for
improving traffic circulation to and from the growing residential community
south of the CNR be re-evaluated.
3.2 Synectics, a subsidiary of TSH specializing in transportation safety, was
retained to review previously evaluated alternatives from a traffic safety
and cost benefit perspective. They submitted a 60 page report (excluding
Appendices) entitled “Operations and Safety Assessment Transportation
Network Improvement Alternatives, Mill Street South, Newcastle” on
January 29, 2007. The report is available for review through the
Engineering Services department. In the report Synectics concludes that
when the costs associated with construction, maintenance, operational
performance and safety are considered, individually, none of the
alternatives considered in the EA process provide a cost effective solution
REPORT NO.:EGD-024-07 PAGE 5
to the problem. When, however, the beneficial components of each
alternative were combined into a “Hybrid” alternative a cost effective
solution was derived. Synectics noted in their report that “These
economic benefits are exclusive of the expected, but unquantifiable,
reduction in collision risk to vulnerable road users travelling along Mill
Street South, in the vicinity of the CN rail underpass.”
3.3 The Hybrid alternative recommended by Synectics is outlined as follows:
?
Retain Mill Street South/Port of Newcastle Drive as the primary access
to development south of the CNR;
?
Make minor improvements to the Mill Street South/CN rail underpass,
to improve sightlines and increase vertical clearance;
?
Upgrade the Mill Street South roadway cross-section to an urban, two-
lane standard, north and south of the CN rail corridor underpass, to
provide cycling lanes and sidewalks;
?
Construct a dedicated pedestrian/cyclist tunnel adjacent to the existing
underpass;
?
Upgrade Toronto Street to a rural two-lane standard with improved
horizontal and vertical geometry, while retaining the existing road/rail
at-grade crossing of the CN rail corridor; and
?
As traffic volumes increase Install traffic control signals at the Mill
Street South @ Toronto Street/Highway 401 South Ramp Terminal
intersection
3.4 The estimated cost to implement the improvements is $2.25 million. While
the solution does not address all project objectives completely it does
address the majority of concerns raised by the resident petition while
reducing overall project costs, collision risk, and limiting the involvement
and cost unpredictability of CNR. Their approvals will still be required for
construction of the pedestrian/cyclist underpass.
3.5 The pedestrian/cyclist tunnel should be designed and construction to
complement the historic nature of the existing Mill Street subway.
REPORT NO.:EGD-024-07 PAGE 6
4.0 CONCLUSIONS
4.1 To properly conclude the public contact component of the project it is
recommended that a final information centre be scheduled for late
February to present the solution noted above. The Environmental Study
Report (ESR) for the project will be completed and on display for public
review.
4.2 The following schedule is proposed for the completion of the project:
Final public contact and completion of the ESR February 28, 2007
Complete construction of Toronto Street improvements September 2007
Tender improvements for Mill Street including sidewalk,
September 2007
pedestrian /cyclist underpass and minor grading
improvements
Complete construction of Mill Street improvements June 2008
Signalization of Mill Street South @ Toronto
Future
Street/Highway 401 South Ramp Terminal intersection
4.3 Based on the cost estimate for the preferred alternative of $2.25 million
and the 2006 Council approved budget allocation of $6.5 million the
Director of Finance and the Director of Engineering Services should
review expenditures to date and reallocate surplus funds as necessary to
reserve accounts.
4.4 This report has been reviewed by the Finance Department and they
concur with the recommendations contained herein.