Report Subject: RFP2017-9 Soper Creek Main and East Branches Subwatershed
Studv
Recommendations:
1. That Report COD -007-18 be received;
2. That the proposal received from Aquafor Beech Limited being the most responsive bidder
meeting all terms, conditions and specifications of RFP2017-9 and subject to a
satisfactory reference check, be awarded the contract for the provision of Soper Creek
Main and East Branches Subwatershed Study, subject to receipt of funding from the
South East Courtice Landowners Group;
3. That the funds required in the amount of $ 391,025.20 (including HST) be drawn from
the following accounts:
Developer Contributions # 100-21-130-00000-1010 $391,025.20
4. That all interested parties listed in Report COD -007-18 and any registered interested
parties will be advised of Council's decision regarding the award by the Corporate
Services Department.
Municipality of Clarington
Report COD- 7 -1
Report Overview
Page 2
To request authorization from Council to award Request for Proposal RFP2017-9 for the
provision of Soper Creek Main and East Branches Subwatershed Study.
1. Background
1.1 A Request for Proposal (RFP) was drafted for the provision of Professional Services as
required for the Subwatershed Study required for Soper Creek Main and East Branches
as per specifications provided by the Planning Services Department.
1.2 The intent of the RFP was to secure the services of a consultant to complete the
Subwatershed Studies for these areas.
1.3 RFP2017-9 was issued by the Purchasing Services Division and advertised electronically
on the Municipality of Clarington's (the Municipality) website. Notification of the
availability of the document was also posted on the Ontario Public Buyer's website. The
RFP was structured on the price — based two envelop RFP system. Thirteen (13)
companies downloaded the document.
1.4 The RFP closed on Thursday, September 14, 2017.
2. Soper Creek Main and East Branches Subwatershed Study
Improvements
As provided for in the Official Plan, the detailed land uses for new greenfield lands will be
determined by the Secondary Planning process. However, in order to detail these land
uses the Subwatershed Study must first be prepared to help balance ecological
protection with land development opportunities, with the goal to protect and maintain a
healthy ecosystem. The Subwatershed Study will provide detailed technical
recommendations that can be implemented through the Secondary Plan.
The RFP stipulated that bidders were to provide a description of Firm/Consulting team,
key qualifications, firm profile, highlight of past service and experience of team members
with projects of similar size, nature and complexity and a demonstrated understanding of
the Municipality's requirements.
Three (3) submissions were received by the closing date and time. See Attachment 1.
Each submission consisted of a comprehensive proposal identifying:
x Qualifications and experience
x Experience of the proponent/sub-consultants with projects of similar nature, size
and complexity
x Understanding of the RFP and proposed solution
x Identification of accessibility design, features and criteria and approach to
methodology of project delivery
Municipality of Clarington
Report COD- 7 -1 Page 3
x Measures that the Proponent has in place to ensure the quality of the deliverables
and that they will meet the needs of the Municipality
All three (3) submissions complied with the mandatory submission requirements and the
Technical Proposals were first evaluated and scored independently in accordance with
the established criteria as outlined in the RFP by an evaluation team consisting of staff
from the Planning Department, Engineering Department, CLOCA and the Purchasing
Services Division. The scores were then jointly reviewed and agreed upon by all
members of the evaluation committee. Some of the areas on which submissions were
evaluated were as follows:
x Highlights of services provided within past five (5) years only
x Allocated roles and responsibilities of team members; long timeline for scope of
project and coverage for entire length is essential
x Proven excellence in this type of study
x Demonstrated understanding of the Municipality's requirements, the Project and
related issues
x Demonstrated ability to carry out all aspects of the RFP
x Value-added services that support and/or enhance the scope of the services were
noted and identified if they were included or available at additional cost to the
Municipality
Upon completion of the evaluation, the evaluation team concluded that two (2) bids met
the established threshold of 85% for Phase 1 and moved on to the second Phase.
It was deemed by the evaluation committee that no presentation would be required to
provide further clarification regarding proposals received.
The Pricing envelope for Aquafor Beech Limited and Amec Foster Wheeler were opened
and verified and in keeping with the terms of the RFP, the evaluation committee's
recommendation is to award to the lowest bidder Aquafor Beech Limited.
Staff have reviewed the price submitted by Aquafor Beech Limited and found it to be
reasonable.
3. Financial and Budget Considerations
As Council is aware all privately initiated secondary plans, including technical studies, are
to be funded 100% by the developers.
This study is to be covered 100% by the Bowmanville Landowners Group. The final
award will be based on confirmation from Bowmanville Landowners group of their
commitment to provide the required funding. Once Council approves the award of the
contract, the Municipality will enter into a funding agreement with the Land Owners
Group. Council has already authorized the Director of Planning Services to enter into
these agreements as per Council resolution PD -183-17.
Municipality of Clarington
Report COD- 7 -1 Page 4
That the funds required in the amount of $ $ 350,329.15 (including HST) be drawn from
the following account:
Developer Contributions # 100-21-130-00000-1010 $391,025.20
Queries with respect to the department needs should be referred to the Director of
Planning.
4. Concurrence
This report has been reviewed by the Director of Planning Services and the Director of
Finance/Treasurer who concur with the recommendations.
5. Conclusion
It is respectfully recommended that Aquafor Beech Limited being the bidder meeting our
threshold and demonstrating the lowest price be awarded the contract for the provision of
Soper Creek Main and East Branches Subwatershed Study Improvements as per the
terms, conditions and specifications of RFP2017-9.
6. Strategic Plan Application
The recommendations contained in this report conform to the Strategic Plan.
Submitted by
Marie Marano, H.B. Sc., C.M.O.,
Director of Corporate Services
Reviewed by:
Andrew Allison, B. Comm., LLB
Chief Administrative Officer
Staff Contact: David Ferguson, Purchasing Manager, 2209 or dferguson@clarington.net
List of interested parties to be notified of Council's decision is on file in the Corporate Services
Department.
Attachment 1 W R 5 H S R U
Municipality of Clarington
Resort COD- 7 -1
Paae 5
Municipality of Clarington
Summary of Submissions Received
RFP2017-9
Soper Creek Main and East Branches
Subwatershed Study
Bidder
I Amec Foster Wheeler. *
II Aquafor Beech Ltd. *
I Candevcon Ltd
*Bidders who were shortlisted.